CN112942141A - Segment beam matching prefabrication method - Google Patents

Segment beam matching prefabrication method Download PDF

Info

Publication number
CN112942141A
CN112942141A CN202110366799.6A CN202110366799A CN112942141A CN 112942141 A CN112942141 A CN 112942141A CN 202110366799 A CN202110366799 A CN 202110366799A CN 112942141 A CN112942141 A CN 112942141A
Authority
CN
China
Prior art keywords
post
beams
section
pouring
prefabrication
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110366799.6A
Other languages
Chinese (zh)
Other versions
CN112942141B (en
Inventor
杨磊
蒋朝辉
李向阳
陈仁光
傅新军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
9th Engineering Co Ltd of MBEC
Original Assignee
9th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 9th Engineering Co Ltd of MBEC filed Critical 9th Engineering Co Ltd of MBEC
Priority to CN202110366799.6A priority Critical patent/CN112942141B/en
Publication of CN112942141A publication Critical patent/CN112942141A/en
Application granted granted Critical
Publication of CN112942141B publication Critical patent/CN112942141B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention relates to a matching prefabrication method of a segmental beam, which comprises the following steps: s1, prefabricating two adjacent sections of sectional beams on a prefabricating table according to design sizes, and reserving a post-pouring area at the joint of the two sections of sectional beams, wherein the post-pouring area is reserved at the end part of one section of sectional beam; s2, matching two prefabricated section beams on a matching pedestal, wherein the post-pouring area is positioned between the two section beams, and adjusting the spatial positions of the two section beams by utilizing beam surface characteristic measuring points according to the geometric relative relationship between the two section beams until the deviation meets the requirement; s3, reinforcing and locking two sections of segmental beams, and arranging a pouring template in a post-pouring area; and S4, pouring concrete in the post-pouring area to form a post-pouring belt. The sequence of matching and prefabricating the existing segmental beams is enriched, construction organizations have more optimization options, and the technical problem of long construction period when the segmental beams are prefabricated by the existing construction method is solved.

Description

Segment beam matching prefabrication method
Technical Field
The invention relates to the field of bridge construction, in particular to a section beam matching prefabricating method.
Background
At present, more and more prestressed concrete bridges in China adopt a segmental prefabrication and assembly construction method, and the core of the construction method lies in the prefabrication of segmental beams. The prefabrication by the stub method is a common method for prefabricating bridge sections. For the prefabrication principle of the conventional stub method, referring to fig. 1, a large-span continuous beam is divided into a plurality of segments according to a certain principle, 6 control measurement points are arranged on the top surface of each segment, and the spatial position of each segment can be determined according to the three-dimensional coordinates of the control measurement points under the overall coordinate system. The specific operation is as follows: measuring and lofting each segment on the prefabricated pedestal by using a total station and a level gauge and referring to the fixed end die datum; after the segment is poured, completion measurement is carried out in time, local coordinates and elevations of control points on the top surface of the segment are collected, and then the local coordinates are converted into overall coordinates through reverse conversion, namely the completion line type of the segment. And obtaining target matching data of the segment to be poured in the local coordinate system through the completion coordinate of the previous segment and the theoretical coordinate of the segment to be poured in the global coordinate system. According to the target matching data, the matching beam is accurately measured and positioned, after the pouring of the pouring beam is completed, completion measurement is carried out on the pouring beam and the matching beam, and the local coordinates and elevations of the control points on the top surfaces of the two segments are collected; and then the completion coordinates of the beam to be cast can be calculated according to the overall completion coordinates and the local completion coordinates of the control points of the matched beam sections, and the matched casting of each section is completed by circulating the process.
Namely, when each section of beam is prefabricated by a conventional short-line method, the beam can be prefabricated section by section, the previous section is prefabricated first, the next section is prefabricated by taking the previous section as a reference, and the like, and the process is circulated to finish the matched prefabrication of each section. Therefore, the conventional stub method prefabricated sectional beam has the defects of relatively single pouring sequence and fixation; for the beams with more sections, the defect of long construction period exists.
Disclosure of Invention
The invention aims to change the limitation that the prior segmental beam matching and prefabricating construction must be strictly matched according to a single sequence, so that more options are available in the on-site pouring sequence, and the technical problem of long total construction period in the segmental beam prefabricating construction is solved.
The purpose of the invention is realized by the following technical scheme:
a segment beam matching prefabrication method comprises the following steps:
s1, prefabricating two adjacent sections of sectional beams on a prefabricating table according to design sizes, and reserving a post-pouring area at the joint of the two sections of sectional beams, wherein the post-pouring area is reserved at the end part of one section of sectional beam;
s2, matching two prefabricated section beams on a matching pedestal, wherein the post-pouring area is positioned between the two section beams, and accurately adjusting the space geometric positions of the two section beams by using beam surface characteristic measuring points according to the geometric relative relationship between the two section beams until the deviation meets the requirement;
s3, reinforcing and locking two sections of segmental beams, and arranging a pouring template in a post-pouring area;
and S4, pouring concrete in the post-pouring area to form a post-pouring belt.
As a preferable embodiment of the above, in step S1, the width of the post-cast zone is 15-30 cm.
As a preferred embodiment of the above scheme, the width of the post-cast zone is 20 cm.
In a preferred embodiment of the above scheme, a section beam with a post-cast area reserved is extended into the post-cast area by a steel reinforcement framework inside the section beam, so that a post-cast strip formed by casting can be firmly combined with an original structure.
In step S1, one end of the segment beam, at which the post-cast area is not reserved, is provided with a convex tooth block on its end surface.
As a preferred embodiment of the above scheme, a long hole for laying the prestressed steel strand is reserved in the segment beam.
As a preferred embodiment of the above scheme, in the process of prefabricating the section beam in step S1, a central line and four elevation characteristic measurement points are respectively embedded in the beam surfaces of the two sections of the section beam, the central line measurement points are two and are arranged along the beam axis, and the beam surface characteristic measurement point data is accurately measured after the casting is completed.
In step S2, when the two prefabricated segment beams are matched on the matching pedestal, the relative geometric relationship between the two beams is accurately adjusted and positioned by using the center line and the elevation measurement point of the beam surface according to the data of the measurement calculation, so as to achieve the required deviation and accuracy.
As a preferred embodiment of the above scheme, when step S2 is performed, one of the segmental beams is fixed, and the spatial position of the other segmental beam is adjusted according to the geometric relative relationship between the two segmental beams until the deviation meets the requirement.
As a preferred embodiment of the above solution, before the step S3, the joining surface of the segment beam with the post-cast area is roughened or chiseled.
As a preferred embodiment of the above solution, after the post-cast strip casting of step S4 is completed, completion measurements are taken after the concrete has set to determine the final geometric relationship of the two segment beams.
The invention has the following beneficial effects: the invention provides a segmental beam matching prefabrication method, which is characterized in that during construction, each segmental beam can be prefabricated directly, and a post-cast area is reserved for the matched end part of any two adjacent segmental beams; and then adjusting the space position between two adjacent sections of prefabricated section beams, pouring concrete in a post-pouring area to form a post-pouring belt by taking the end part of the other section as one side of a post-pouring belt pouring template, and realizing the matching between the two sections of section beams after the post-pouring belt is combined with the original section beams. Therefore, by the method, each section of beam can be prefabricated, the post-pouring area reserved at the end part of each section of beam is used as an adjusting and matching area, the space position between two adjacent sections of beams at two ends is adjusted, and the post-pouring area is poured in the post-pouring area to form the post-pouring belt, so that the section beam meeting the design requirement can be obtained. Namely, in this scheme, can prefabricate multistage festival section roof beam simultaneously, can match multistage festival section roof beam simultaneously and carry out pouring of post-cast strip, utilize the mode of multiple spot synchronous construction promptly, can shorten the prefabrication time limit for a project greatly.
Drawings
FIG. 1 is a schematic illustration of a conventional stub-fabricated bridge segment;
FIG. 2 is a schematic structural diagram of the cast-in post-cast strip completed by the scheme;
FIG. 3 is a schematic structural view of a sectional beam according to the present embodiment;
fig. 4 is a schematic structural view of the scheme, wherein the beams are matched with adjacent two end sections and a post-cast strip is poured.
The specific structure in the figure illustrates that: 1-section beam, 11 post-cast areas, 12 steel reinforcement frameworks, 13 tooth blocks, 14 long holes, 2 post-cast strips and 3 matching pedestals.
Detailed Description
The present invention will be described in further detail with reference to the following examples, which are given in the accompanying drawings.
A segment beam matching prefabrication method comprises the following steps:
s1, with reference to FIG. 3, prefabricating two adjacent sections of section beams 1 on a prefabricating platform according to design sizes, respectively embedding central lines and elevation characteristic measurement points on beam surfaces of the two sections of section beams during prefabrication, wherein the central lines are two and are arranged along the axis of the beam, the elevation measurement points are four, and accurately measuring beam surface characteristic measurement point data after pouring is completed; a post-pouring area is reserved at the joint of two sections of the section beams 1, wherein the post-pouring area is reserved at the end part of one section of the section beam; wherein the width of the reserved post-pouring area 11 is 15-30cm, preferably 20 cm. The steel reinforcement framework 12 inside the segmental beam 1 extends into the post-cast area 11, so that the post-cast strip 2 formed by casting can be firmly combined with the original structure;
s2, referring to FIG. 4, matching two sections of prefabricated section beams 1 on a matching pedestal 3, wherein a post-pouring area is located between the two sections of section beams 1, fixing one section of section beam 1, and accurately adjusting the spatial geometric position of the other section beam 1 by using a beam surface characteristic measuring point according to the geometric relative relation between the two sections of section beams 1 until the deviation meets the requirement;
when the two prefabricated section beams 1 are matched on the matching pedestal 3, the relative geometric relationship between the two beams is accurately adjusted and positioned by using the central line and the elevation measurement point of the beam surface according to the data of measurement and calculation to achieve the required deviation and precision;
s3, reinforcing and locking the two sections of the segmental beams 1, performing roughening or chiseling on the joint surface of the segmental beam 1 with the post-pouring area 11, and arranging a pouring template in the post-pouring area 11;
and S4, pouring concrete in the post-pouring area 11 to form a post-pouring strip 2, performing completion measurement after the concrete is solidified, and determining the final geometric relationship of the two sections of segmental beams.
Therefore, in the scheme, during construction, each section of section beam can be directly prefabricated, then the space position between two adjacent sections of prefabricated section beams is adjusted, the end part of the other section is used as one side of a post-cast strip pouring template, concrete is poured in a post-cast area to form a post-cast strip, and the post-cast strip is combined with the original section beam, so that matching between the two sections of section beams can be realized. This scheme can prefabricate multistage festival section roof beam simultaneously, can match multistage festival section roof beam simultaneously and carry out pouring of post-cast strip, utilizes the mode of multiple spot synchronous construction promptly, can shorten the prefabrication time limit for a project greatly.
In step S1, in a preferred embodiment of the above solution, one end of the segment beam 1, which is not reserved with the post-cast area 11, is provided with a convex tooth block 13 on its end surface. Therefore, after the post-cast strip 2 is poured, a groove corresponding to the tooth block 13 is formed in the end face of the post-cast strip 2, and alignment and clamping of each section of beam can be facilitated during later bridge hoisting and installation.
As a preferred embodiment of the above solution, a long hole 14 for laying the prestressed steel strand is reserved in the segment beam 1. The reserved long hole 14 can be used for laying and tensioning prestressed steel strands during bridge hoisting.
The above description is only a preferred embodiment of the present invention, but not intended to limit the scope of the invention, and all simple equivalent changes and modifications made in the claims and the description of the invention are within the scope of the invention.

Claims (10)

1. A segment beam matching prefabrication method is characterized by comprising the following steps:
s1, prefabricating two adjacent sections of sectional beams on a prefabricating table according to design sizes, and reserving a post-pouring area at the joint of the two sections of sectional beams, wherein the post-pouring area is reserved at the end part of one section of sectional beam;
s2, matching two prefabricated section beams on a matching pedestal, wherein the post-pouring area is positioned between the two section beams, and accurately adjusting the space geometric positions of the two section beams by using beam surface characteristic measuring points according to the geometric relative relationship between the two section beams until the deviation meets the requirement;
s3, reinforcing and locking two sections of segmental beams, and arranging a pouring template in a post-pouring area;
and S4, pouring concrete in the post-pouring area to form a post-pouring belt.
2. A method of matched prefabrication of a section beam according to claim 1, including the steps of: in step S1, the width of the post-cast zone is 15-30 cm.
3. A method of matched prefabrication of a section beam according to claim 2, including the steps of: the width of the post-pouring area is 20 cm.
4. A method of matched prefabrication of a section beam according to claim 1, including the steps of: and reserving the section beam with the post-pouring area, wherein the steel reinforcement framework inside the section beam extends into the post-pouring area, so that the post-pouring belt formed by pouring can be firmly combined with the original structure.
5. A method of matched prefabrication of a section beam according to claim 1, including the steps of: in step S1, one end of the segment beam, at which the post-cast region is not reserved, is provided with a convex tooth block on its end surface.
6. A method of matched prefabrication of a section beam according to claim 1, including the steps of: and a long hole for paving the prestressed steel strand is reserved in the segment beam.
7. A method of matched prefabrication of a section beam according to claim 1, including the steps of: in the process of prefabricating the section beams in the step S1, respectively embedding central lines and elevation characteristic measurement points on beam surfaces of two sections of the section beams, wherein the central lines are two and are arranged along the beam axis, the elevation measurement points are four, and the beam surface characteristic measurement point data are accurately measured after the casting is finished;
in step S2, when the two prefabricated segment beams are matched on the matching pedestal, the relative geometric relationship between the two beams is accurately adjusted and positioned by using the center line and the elevation measurement point of the beam surface according to the data of the measurement calculation, so as to achieve the required deviation and accuracy.
8. A method of matched prefabrication of a section beam according to claim 1, including the steps of: before step S3, the joining surfaces of the segment beams with the post-cast sections are roughened or chiseled.
9. A method of matched prefabrication of a section beam according to claim 8, including the steps of: when step S2 is performed, one of the segmental beams is fixed, and the spatial position of the other segmental beam is adjusted according to the geometric relative relationship between the two segmental beams until the deviation meets the requirement.
10. A method of matched prefabrication of a section beam according to claim 1, including the steps of: after the post-cast strip casting in step S4 is completed, completion measurements are performed after the concrete is solidified, and the final geometric relationship of the two segment beams is determined.
CN202110366799.6A 2021-04-06 2021-04-06 Segment beam matching prefabrication method Active CN112942141B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110366799.6A CN112942141B (en) 2021-04-06 2021-04-06 Segment beam matching prefabrication method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110366799.6A CN112942141B (en) 2021-04-06 2021-04-06 Segment beam matching prefabrication method

Publications (2)

Publication Number Publication Date
CN112942141A true CN112942141A (en) 2021-06-11
CN112942141B CN112942141B (en) 2022-11-22

Family

ID=76230688

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110366799.6A Active CN112942141B (en) 2021-04-06 2021-04-06 Segment beam matching prefabrication method

Country Status (1)

Country Link
CN (1) CN112942141B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090064610A1 (en) * 2005-04-13 2009-03-12 Interconstec Co., Ltd. Segments for building spliced prestressed concrete grider and method of manufacturing the segments
CN101476291A (en) * 2009-01-21 2009-07-08 中铁一局集团有限公司 Segment-assembling simply supported box girder movable falsework construction method
CN105625188A (en) * 2016-01-13 2016-06-01 中铁三局集团有限公司 Construction method for 48m sectional beam of passenger railway based on BIM technology
CN108396637A (en) * 2018-04-28 2018-08-14 福州大学 Based on short-line prefabrication assembly girder construction and its construction method
CN109629421A (en) * 2018-11-20 2019-04-16 同济大学 A kind of subsection beam construction method for adding steel pipe and horizontal distribution reinforcing bar
CN109680615A (en) * 2018-12-30 2019-04-26 广东瀚阳轨道信息科技有限公司 The three-dimensional coordinate measurement construction method of short line casting beam sections
CN110777669A (en) * 2019-11-15 2020-02-11 中铁北京工程局集团有限公司 High-speed rail continuous beam short line matching prefabricated cantilever assembly line shape control method
CN112195781A (en) * 2020-09-09 2021-01-08 广州瀚阳工程咨询有限公司 Method for prefabricating section precast bridge by combining long and short line method with bidirectional matching method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090064610A1 (en) * 2005-04-13 2009-03-12 Interconstec Co., Ltd. Segments for building spliced prestressed concrete grider and method of manufacturing the segments
CN101476291A (en) * 2009-01-21 2009-07-08 中铁一局集团有限公司 Segment-assembling simply supported box girder movable falsework construction method
CN105625188A (en) * 2016-01-13 2016-06-01 中铁三局集团有限公司 Construction method for 48m sectional beam of passenger railway based on BIM technology
CN108396637A (en) * 2018-04-28 2018-08-14 福州大学 Based on short-line prefabrication assembly girder construction and its construction method
CN109629421A (en) * 2018-11-20 2019-04-16 同济大学 A kind of subsection beam construction method for adding steel pipe and horizontal distribution reinforcing bar
CN109680615A (en) * 2018-12-30 2019-04-26 广东瀚阳轨道信息科技有限公司 The three-dimensional coordinate measurement construction method of short line casting beam sections
CN110777669A (en) * 2019-11-15 2020-02-11 中铁北京工程局集团有限公司 High-speed rail continuous beam short line matching prefabricated cantilever assembly line shape control method
CN112195781A (en) * 2020-09-09 2021-01-08 广州瀚阳工程咨询有限公司 Method for prefabricating section precast bridge by combining long and short line method with bidirectional matching method

Also Published As

Publication number Publication date
CN112942141B (en) 2022-11-22

Similar Documents

Publication Publication Date Title
WO2016023462A1 (en) Glued joint connecting method for steel-concrete composite beam of cable-stayed bridge
CN108914785B (en) Hanging basket cantilever pouring construction method of multi-chamber corrugated steel web continuous beam bridge
CN106436579A (en) Linear control method and linear control device for sectional beam with specially-shaped cross section through short-line pedestal matching method
CN103410269B (en) Prestressing without bondn cast-in-place reinforced concrete hollow slab constructing structure and construction method
JP2000290933A (en) Method for controlling form of precast segment, and method for erecting bridge by precast segment construction method
CN112195781B (en) Method for prefabricating section precast bridge by combining long and short line method with bidirectional matching method
CN107310025A (en) The fabricated device and method for prefabricating of a kind of Prefabricated bar boots
CN105544887B (en) A kind of construction method of tang style simulation building wing angle cornice
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN107700648A (en) Prefabricated component and cast-in-place post assembled integral concrete frame structure construction
CN112411265A (en) Ballastless track structure suitable for large-span bridge and mounting method
CN107653900A (en) A kind of preparation method of Prefabricated pipe gallery
CN113239429A (en) Method for manufacturing precast assembled bridge of concrete segments
CN112502714A (en) Assembled shaft barrel structure and design and construction method
CN107575023A (en) A kind of sliding formwork component and apply its caisson cutting edge layer slding form operation method
CN114770706A (en) Novel light T-beam prefabricating equipment and prefabricating, installing and constructing method
CN112942141B (en) Segment beam matching prefabrication method
CN113653180A (en) V-shaped steel reinforced concrete inclined column mixed structure and construction method thereof
CN108385527A (en) A kind of superelevation runoff section segment girder precast measures and monitoring method
CN102121312A (en) Construction process for concrete bargeboard in pseudo-classic architecture
CN213572042U (en) Positioning device for semi-prefabricated double-sided overlapped comprehensive pipe gallery side wall with concealed columns
CN213681700U (en) Improved bridge expansion joint width construction structure
CN105648870B (en) The construction method on skid pad washboard road
CN107605156B (en) Method for reinforcing chamfer template
CN108775192B (en) Prestressed concrete tower column structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant