CN112900464B - Building foundation construction method - Google Patents

Building foundation construction method Download PDF

Info

Publication number
CN112900464B
CN112900464B CN202110075585.3A CN202110075585A CN112900464B CN 112900464 B CN112900464 B CN 112900464B CN 202110075585 A CN202110075585 A CN 202110075585A CN 112900464 B CN112900464 B CN 112900464B
Authority
CN
China
Prior art keywords
hole
pipe
diameter
construction method
explosive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110075585.3A
Other languages
Chinese (zh)
Other versions
CN112900464A (en
Inventor
毛斌峰
沈伟娟
黄国燕
史建锋
马燕
杨少美
朱玲霞
陈学萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Rongcheng Construction Group Co ltd
Original Assignee
Zhejiang Rongcheng Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Rongcheng Construction Group Co ltd filed Critical Zhejiang Rongcheng Construction Group Co ltd
Priority to CN202110075585.3A priority Critical patent/CN112900464B/en
Publication of CN112900464A publication Critical patent/CN112900464A/en
Application granted granted Critical
Publication of CN112900464B publication Critical patent/CN112900464B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Abstract

The invention provides a building foundation construction method, and belongs to the technical field of building construction methods. Drilling a pre-pouring hole with the diameter larger than that of the pipe at the designed position; inserting a hole expanding auxiliary tool into the pre-grouting hole; putting an explosive assembly from an opening at the upper end of the shaped pipe, wherein the explosive assembly comprises a plurality of serially connected explosive bags in a ring shape; igniting a lead of an explosive charge from the top of the molded pipe, and forming a diameter-expanding hole at the bottom of the pre-filling hole; the rotary type pipe is blasted again according to the steps after the position of the spoke piece is adjusted so as to increase the aperture of the diameter expanding hole; after the aperture of the hole with the diameter expanded reaches the designed size, a reinforcement cage is placed in the pre-pouring hole, concrete is poured, the concrete is vibrated to fill the hole with the diameter expanded hole and the inner side and the outer side of the reinforcement cage, and the ground pile of the beam column for connecting the building foundation is formed after the concrete is dried and solidified. The invention has the advantages of high strength, high stability and the like.

Description

Building foundation construction method
Technical Field
The invention belongs to the technical field of building construction methods, and relates to a building foundation construction method.
Background
There are many methods for treating building foundation, among which, concrete pile is a common method for reinforcing foundation, and the bearing capacity and stability of building can be enhanced after receiving the beam column structure of building.
The cast-in-place pile is formed by directly opening a hole at a designed pile position, then adding a reinforcement cage in the hole and then pouring concrete. In order to further enhance the stability and the bearing strength of the cast pile, a construction method of blasting and pile-filling is adopted in the prior art, in the existing construction method of blasting and pile-filling, an explosive charge is firstly put into the bottom of a pile hole, in order to avoid broken stones from splashing out of the pile hole after the explosive charge is detonated and to enable the impact force of the explosion to act on the periphery of the pile hole as much as possible, a certain amount of sand and stone needs to be put into the pile hole after the explosive charge is put in so as to block the pile hole, and the method has the defects that: 1. after blasting, sand and stones can fill partial space at the bottom of the pile hole, so that the reaming effect is influenced, and the reaming size is reduced under the influence of the sand and stones; 2. the secondary blasting cannot be carried out, on one hand, the secondary blasting needs to throw sand again, which further influences the size of the reaming, on the other hand, rock and soil near the reaming after the primary blasting tend to harden and are simultaneously tamped under the action of blasting impact force, on the third hand, the position where the explosive cartridge is thrown again cannot be close to the periphery of the reaming, and the impact force on the rock and soil at the periphery of the reaming in the blasting process can be greatly reduced; 3. under the influence of the peripheral rock-soil environment at the bottom of the pile hole, the existing method cannot ensure that the reaming tends to be uniform, namely the reaming can be caused to be biased relative to the pile hole or irregular quarterly due to the conditions of explosive package position, loose degree of each part of rock-soil, stone distribution and the like, the quality of the cast-in-place pile is influenced, the difficulty of concrete casting and the distribution of concrete after the concrete casting can be increased, and a 'cavity' can be formed between the soil layer and the concrete under partial conditions; 4. pile holes are formed according to design positions, if single blasting cannot achieve ideal effects, secondary blasting is difficult to implement, and the position of a poured pile may need to be changed, so that construction is affected.
Disclosure of Invention
The invention aims to provide a building foundation construction method aiming at the problems in the prior art, and the technical problem to be solved by the invention is how to improve the strength and stability of the building foundation.
The purpose of the invention can be realized by the following technical scheme: a building foundation construction method is characterized in that the construction method depends on a hole-expanding auxiliary tool, the hole-expanding auxiliary tool comprises a shaped pipe, a positioning column and a plurality of radial sheets, each radial sheet is evenly distributed at the lower end of the shaped pipe in the circumferential direction, the upper ends of the radial sheets are fixed on the outer wall of the shaped pipe, the lower ends of the radial sheets are fixed on the outer wall surface of the positioning column, the radial sheets are elastic steel sheets, a protective layer is wrapped outside the radial sheets, the outer diameter of the positioning column is smaller than that of the shaped pipe, a guide cone is arranged at the upper end of the positioning column, a positioning cone is arranged at the lower end of the positioning column, the diameter of the upper end of the guide cone is smaller than that of the lower end of the positioning cone, and the diameter of the lower end of the positioning cone is smaller than that of the upper end of the positioning cone;
the construction method comprises the following steps: A. drilling a pre-pouring hole with the diameter larger than that of the pipe at the designed position; B. inserting the hole expanding auxiliary tool into the pre-pouring hole to enable the positioning column to be located at the bottom of the pre-pouring hole; C. putting an explosion assembly from an opening at the upper end of the shaped pipe, wherein the explosion assembly comprises a plurality of explosive bags which are connected in series to form a ring, the adjacent explosive bags are connected through a soft rope, when the explosion assembly is put in, the upper end of the shaped pipe is pressed, the middle part of each spoke piece is expanded outwards, the upper end of the guide cone is positioned at the opening at the lower end of the shaped pipe, so that the explosion assembly can be sleeved on the guide cone, and the position of the explosion assembly positioned on the guide cone is controlled by controlling the diameter of the explosion assembly, so that the explosion position is controllable; D. igniting a lead of the explosive bags from the top of the pipe, continuously applying downward pressure to the upper end of the pipe, synchronously detonating the explosive bags during blasting, and forming a diameter expanding hole at the bottom of the pre-filling hole; E. after the primary blasting is finished, pulling up the tube to separate the spoke piece from the hole wall of the diameter expanding hole, then rotating the tube, adjusting the position of the spoke piece, and blasting again according to the steps to increase the hole diameter of the diameter expanding hole; F. after the aperture of the diameter-expanded hole reaches the design size, taking out the shaped pipe, pressing down the shaped pipe, and observing the descending depth of the shaped pipe to estimate the aperture of the diameter-expanded hole; G. and placing a reinforcement cage in the pre-pouring hole, pouring concrete, vibrating to fill the diameter-expanding hole and the inner side and the outer side of the reinforcement cage with the concrete, and forming the ground pile of the beam column for connecting the building foundation after the concrete is cured.
Further, the protective layer is a polyurethane layer coated on the spoke piece.
The polyurethane layer is a high-strength plastic material, namely polyurethane elastomer for short and TPU for short, and can protect the spoke pieces from deformation and high temperature caused by the influence of explosion impact force, so that the elastic restoring force of each spoke piece can be maintained.
Further, the width of the middle part of the spoke piece is smaller than the width of the two ends of the spoke piece.
The middle part of the spoke piece is narrower, and the two ends of the spoke piece are wider, so that the impact force of blasting acts on the outer side of the pre-grouting hole as much as possible, the upper side and the lower side of the diameter expanding hole are prevented from being greatly influenced, and the shape and the position of the diameter expanding hole are in a controllable range.
Further, the spokes are helical.
Further, the two ends of the spoke piece form a phase angle of 180 degrees, 360 degrees or 520 degrees.
The two ends of the spiral spoke piece are fixed, and the middle of the spiral spoke piece is narrow, so that the spiral blade-shaped spoke piece is formed in the middle of the spoke piece, the contact area between the spoke piece and the inner side surface of the expanding hole can be reduced, and the impact area to a soil layer during blasting is increased.
Furthermore, in the construction process of the step B, the middle part of the spoke piece is abutted against the peripheral surface of the lower end of the pre-grouting hole through the downward pressing type pipe, and then the rotary type pipe is used for preliminarily expanding the peripheral surface of the lower end of the pre-grouting hole.
Push down the type pipe to make type pipe rotatory, usable spiral helicine spoke piece strikes off the soil layer, preliminary reaming, can not receive preliminary reaming before the high temperature hardening in the soil layer yet on the one hand, improve the effect of blasting, on the other hand can make the degree of depth that type pipe can descend bigger, and the explosive cartridge of being convenient for is laid, also can make when blasting for the first time tentatively carry out incomplete sheltering from to type pipe lower extreme through the guide cone.
Furthermore, the soil taking can be completed by pressing the pipe while rotating the pipe and then pulling the pipe upwards as required.
The pipe is pressed downwards to make the middle parts of the radial sheets protrude outwards, soil slag in the pre-filling hole or the expanding hole can be rolled into a containing cavity surrounded by the radial sheets when the pipe is rotated, after the pipe is pulled upwards, because the auxiliary sheet area is vertical, the distance between the adjacent radial sheets is reduced, the containing cavity area is closed, and the soil slag rolled into the containing cavity can be taken out of the ground.
Furthermore, the shaped pipe is composed of a plurality of splicing pipes, one end of each splicing pipe is provided with a guide splicing part, the other end of each splicing pipe is provided with a guide step corresponding to the guide splicing part, and a return spring is connected between every two adjacent splicing pipes.
Furthermore, two ends of the splicing pipe are respectively provided with a positioning ring groove matched with the return spring.
Furthermore, both ends of the return spring are respectively and fixedly provided with a mounting disc, and the mounting discs can be inserted into the corresponding positioning ring grooves.
The reset spring between the splicing pipes can be used for buffering in the blasting process and buffering when the pipe is rotated, and the mounting disc is fixed in the positioning ring through the bolt, so that the length of the pipe can be controlled according to the number of the splicing pipes, and the construction of ground piles at different depths is adapted.
Compared with the prior art, the scheme has the advantages that:
due to the existence of the guide cone, the placing position of each explosive charge which is connected in series to form a ring can be controlled, namely, each explosive charge is accurately positioned after being thrown through the diameter of each explosive charge formed ring and the cone-column-shaped guide cone;
the positioning cone is used for positioning the expanded diameter auxiliary tool after being inserted into the pre-grouting hole, has larger taper and is not easy to sink in the blasting process;
the positioning cone can guide the explosive charges in the explosive charge feeding process and can be used for partially blocking the lower end opening of the shaped pipe, after the explosive charges are sleeved on the positioning cone, the explosive charges are not positioned at the axis position of the shaped pipe, splashing is less from the upper end of the shaped pipe in the blasting process, and the splashing direction of sand and stone from the bottom of the shaped pipe to the top is not positioned on the axis of the shaped pipe, so that the splashed sand and stone can hardly reach the top of the shaped pipe, and the upper end of the shaped pipe is in a pressing state, namely a blocking state, sand and stone filling is not needed in the blasting process, so that the safety is high;
in the blasting process, part of rock soil on the hole wall of the expanded hole is shielded by the radial sheets, so that the hole wall of the expanded hole forms deep grooves corresponding to gaps between adjacent radial sheets, after concrete is poured, the connection strength between the concrete and the soil layer is higher, and the support strength and reliability of the ground pile are higher;
compared with the prior art, the position and the shape of the diameter expanding hole are more controllable, and the strength of the ground pile is higher.
Drawings
Fig. 1 is a schematic structural diagram of a pre-pouring hole formed in a soil layer in the step A.
FIG. 2 is a schematic view of the construction state in step B.
FIG. 3 is a schematic view showing a state in which the pipe is pressed down during the construction in step C.
FIG. 4 is a schematic view showing the state after the explosive is set during the step C.
Fig. 5 is a schematic view of a state after one reaming.
Fig. 6 is a schematic structural view of the formed ground pile.
FIG. 7 is a top view of the reaming aid after flaring of the spokes.
FIG. 8 is a schematic view of a web construction.
FIG. 9 is a cross-sectional view of a shaped tube.
In the figure, 1, a shaped tube; 11. splicing the tubes; 12. a guide insertion part; 13. a guide step; 14. a return spring; 15. mounting a disc; 2. a positioning column; 3. a web; 4. a guide cone; 5. positioning a cone; 6. pre-filling holes; 7. expanding the diameter hole; 8. a reinforcement cage; 9. and (4) exploding the assembly.
Detailed Description
The following are specific embodiments of the present invention and are further described with reference to the drawings, but the present invention is not limited to these embodiments.
As shown in fig. 2 and 7, the auxiliary reaming tool comprises a tubular tube 1, a positioning column 2 and a plurality of radial sheets 3, wherein each radial sheet 3 is circumferentially and uniformly distributed at the lower end of the tubular tube 1, the upper end of each radial sheet 3 is fixed on the outer wall of the tubular tube 1, the lower end of each radial sheet 3 is fixed on the outer wall surface of the positioning column 2, each radial sheet 3 is a steel sheet with elasticity, a protective layer is wrapped outside each radial sheet, the outer diameter of each positioning column 2 is smaller than the outer diameter of the tubular tube 1, the upper end of each positioning column 2 is provided with a guide cone 4, the lower end of each positioning column 2 is provided with a positioning cone 5, each guide cone 4 is in the shape of a cone with the diameter of the upper end smaller than the diameter of the lower end, and each positioning cone 5 is in the shape of a cone with the diameter of the lower end smaller than the upper end;
the protective layer is a polyurethane layer coated on the spoke 3. The polyurethane layer is a high-strength plastic material, polyurethane elastomer for short, or TPU for short, and can protect the spokes 3 from deformation and high temperature caused by the impact of blasting, so that the elastic restoring force of each spoke 3 can be maintained.
The width of the middle part of the spoke 3 is smaller than the width of the two ends. The middle part of the spoke piece 3 is narrower, and the two ends are wider, so that the impact force of blasting can act on the outer side of the pre-pouring hole 6 as much as possible, the upper side and the lower side of the diameter expanding hole 7 are prevented from being greatly influenced, and the shape and the position of the diameter expanding hole 7 are in a controllable range.
The construction method comprises the following steps: as shown in fig. 1, according to the design diameter and the design depth, at the design position, a pre-pouring hole 6 with the diameter larger than that of the type pipe 1 is punched through a punching machine; as shown in fig. 2, the auxiliary hole-expanding tool is inserted into the pre-filling hole 6, so that the positioning column 2 is located at the bottom of the pre-filling hole 6, and the auxiliary hole-expanding tool is located at the center of the pre-filling hole 6 through the positioning cone 5; as shown in fig. 4, an explosive assembly 9 is thrown from the opening at the upper end of the shaped pipe 1, the explosive assembly 9 comprises a plurality of serially connected explosive charges in a ring shape, adjacent explosive charges are connected through a soft rope, a lead is drawn to the top of the shaped pipe 1, as shown in fig. 3, when the explosive assembly 9 is thrown, the upper end of the shaped pipe 1 is pressed through a punching machine or a hydraulic jack, the middle part of each spoke piece 3 is expanded outwards to improve the stability of the whole auxiliary hole-expanding tool in the pre-filling hole 6, the upper end of the guide cone 4 is positioned at the opening at the lower end of the shaped pipe 1, so that the explosive assembly 9 can be sleeved on the guide cone 4, the position of the explosive assembly 9 when the explosive assembly 9 is positioned on the guide cone 4 is controlled by controlling the diameter of the explosive assembly 9, and the blasting position is controllable; as shown in fig. 5, the lead of the explosive charge is ignited from the top of the type pipe 1, and downward pressure is continuously applied to the upper end of the type pipe 1, the downward pressure is higher than that before the detonation so as to overcome the influence of impact force on the positions of all parts in the detonation process, all the explosive charges are detonated synchronously in the detonation process, and a diameter-expanding hole 7 is formed at the bottom of the pre-filling hole 6; after the primary blasting is finished, the pipe 1 is pulled upwards, the spoke piece 3 is separated from the hole wall of the diameter expanding hole 7, then the pipe 1 is rotated, after the position of the spoke piece 3 is adjusted, the pipe is blasted again according to the steps to increase the hole diameter of the diameter expanding hole 7, and the spoke piece 3 is located in a deep groove formed by the primary blasting as much as possible; as shown in fig. 6, after the bore diameter of the diameter-enlarged hole 7 reaches the design size, the shape tube 1 is taken out, and the bore diameter of the diameter-enlarged hole 7 can be estimated by pressing down the shape tube 1 and observing the depth at which the shape tube 1 can descend; and placing a reinforcement cage 8 in the pre-pouring hole 6, pouring concrete, vibrating to fill the inside and the outside of the diameter-expanding hole 7 and the reinforcement cage 8 with the concrete, and forming a ground pile for connecting a beam column of a building foundation after the concrete is cured.
As a refinement and supplement, the web 3 is helical, as shown in fig. 8, in particular with a phase angle of 180 ° or 360 ° or 520 ° between the two ends of the web 3.
The spiral spoke piece 3 has two fixed ends and a narrower middle part, so that the middle part of the spoke piece 3 forms a spiral blade shape, the contact area between the spoke piece 3 and the inner side surface of the expanding hole 7 can be reduced, and the impact area to the soil layer during blasting is increased.
In the step B, the middle of the spoke piece 3 is abutted against the peripheral surface of the lower end of the pre-filling hole 6 through the pressing-down type pipe 1, and then the type pipe 1 is rotated to preliminarily expand the peripheral surface of the lower end of the pre-filling hole 6. Push down type pipe 1 to make type pipe 1 rotatory, usable spiral helicine spoke piece 3 strikes off the soil layer, preliminary reaming, can not receive preliminary reaming before the high temperature hardening on the one hand at the soil layer, improve the effect of blasting, on the other hand can make the degree of depth that type pipe 1 can descend bigger, and the explosive cartridge bag of being convenient for is laid, can tentatively carry out incomplete sheltering from to type pipe 1 lower extreme through guide cone 4 when also can making the first blasting.
Soil borrowing can be completed by rotating the pipe 1 while pressing the pipe 1 down and then pulling the pipe 1 up as required. The pipe 1 is pressed downwards, the middle parts of the radial plates 3 protrude outwards, soil slag in the pre-filling holes 6 or the expanding holes 7 can be rolled into a containing cavity surrounded by each radial plate 3 when the pipe 1 is rotated, after the pipe 1 is pulled upwards, because the auxiliary plate areas are vertical, the distance between the adjacent radial plates 3 is reduced, the containing cavity areas are closed, and the soil slag rolled into the containing cavity areas can be taken out of the ground.
As shown in fig. 9, the pipe 1 is composed of a plurality of splicing pipes 11, one end of each splicing pipe 11 is provided with a guide splicing part 12, the other end of each splicing pipe 11 is provided with a guide step 13 corresponding to the guide splicing part 12, and a return spring 14 is connected between every two adjacent splicing pipes 11. The splicing tube 11 has a positioning ring groove at each end for fitting the return spring 14. Two ends of the return spring 14 are respectively fixedly provided with a mounting plate 15, and the mounting plates 15 can be inserted into the corresponding positioning ring grooves.
The return spring 14 between the splicing pipes 11 can be used for buffering in the blasting process and buffering when the pipe 1 is rotated, and the mounting disc 15 is fixed in the positioning ring through bolts, so that the length of the pipe 1 can be controlled according to the number of the splicing pipes 11, and the construction of ground piles in different depths is adapted.
The specific embodiments described herein are merely illustrative of the spirit of the invention. Various modifications or additions may be made to the described embodiments or alternatives may be employed by those skilled in the art without departing from the spirit or ambit of the invention as defined in the appended claims.

Claims (7)

1. A construction method of building foundation is characterized by that it utilizes a hole-enlarging auxiliary tool, the auxiliary reaming tool comprises a shaped pipe (1), a positioning column (2) and a plurality of radial sheets (3), wherein the radial sheets (3) are uniformly distributed at the lower end of the shaped pipe (1) in the circumferential direction, the upper end of the spoke piece (3) is fixed on the outer wall of the shaped pipe (1), the lower end of the spoke piece (3) is fixed on the outer wall surface of the positioning column (2), the spoke pieces (3) are steel sheets with elasticity, the spoke pieces are wrapped with protective layers, the outer diameter of the positioning column (2) is smaller than that of the forming tube (1), the upper end of the positioning column (2) is provided with a guide cone (4), the lower end of the positioning column (2) is provided with a positioning cone (5), the guide cone (4) is in a cone column shape, the diameter of the upper end of the guide cone is smaller than that of the lower end of the guide cone, and the diameter of the lower end of the positioning cone (5) is smaller than that of the upper end of the guide cone;
the construction method comprises the following steps: A. drilling a pre-pouring hole (6) with the diameter larger than that of the forming pipe (1) at a design position; B. inserting the auxiliary hole-expanding tool into the pre-filling hole (6) to enable the positioning column (2) to be located at the bottom of the pre-filling hole (6); C. putting an explosion component (9) from an opening at the upper end of the shaped pipe (1), wherein the explosion component (9) comprises a plurality of serially connected ring-shaped explosive bags, the adjacent explosive bags are connected through a soft rope, the upper end of the shaped pipe (1) is pressed when putting the explosion component (9), the middle part of each spoke piece (3) is expanded outwards, the upper end of the guide cone (4) is positioned at the opening at the lower end of the shaped pipe (1), so that the explosion component (9) can be sleeved on the guide cone (4), and the position of the explosion component (9) when being positioned on the guide cone (4) is controlled by controlling the diameter of the explosion component (9), so that the explosion position is controllable; D. igniting a lead of an explosive package from the top of the forming pipe (1), continuously applying downward pressure on the upper end of the forming pipe (1), synchronously detonating the explosive packages during blasting, and forming a diameter expanding hole (7) at the bottom of the pre-filling hole (6); E. after the primary blasting is finished, the pipe (1) is pulled upwards, the spoke piece (3) is separated from the hole wall of the diameter expanding hole (7), then the pipe (1) is rotated, after the position of the spoke piece (3) is adjusted, the pipe is blasted again according to the steps, and the hole diameter of the diameter expanding hole (7) is increased; F. after the aperture of the diameter-expanded hole (7) reaches the designed size, taking out the shaped pipe (1), pressing down the shaped pipe (1), and observing the descending depth of the shaped pipe (1) to estimate the aperture of the diameter-expanded hole (7); G. placing a reinforcement cage (8) in the pre-pouring hole (6), pouring concrete, vibrating to fill the inside and the outside of the diameter-expanding hole (7) and the reinforcement cage (8), and forming a ground pile for connecting a beam column of a building foundation after the concrete is dried;
the spoke piece (3) is in a spiral shape, the middle of the spoke piece (3) is abutted against the peripheral surface of the lower end of the pre-pouring hole (6) through the pressing-down type pipe (1) in the construction process of the step B, and then the diameter of the peripheral surface of the lower end of the pre-pouring hole (6) is expanded preliminarily by rotating the type pipe (1);
the soil taking operation can be carried out according to the needs, and the operation mode is as follows: the soil residue is sent to the ground by rotating the pipe (1) while pressing the pipe (1) down and then pulling the pipe (1) up.
2. A method for constructing a foundation for a building as claimed in claim 1, wherein said protective layer is a polyurethane layer coated on a web (3).
3. A building foundation construction method according to claim 1, wherein the width of the web (3) is smaller in the middle than at both ends.
4. A building foundation construction method according to claim 3, characterized in that the web (3) is set at a phase angle of 180 ° or 360 ° or 520 ° between its ends.
5. The building foundation construction method according to claim 1, 2, 3 or 4, wherein the pipe (1) is composed of a plurality of splicing pipes (11), one end of each splicing pipe (11) is provided with a guide insertion part (12), the other end of each splicing pipe (11) is provided with a guide step (13) corresponding to the guide insertion part (12), and a return spring (14) is connected between every two adjacent splicing pipes (11).
6. The building foundation construction method according to claim 5, wherein both ends of the splicing pipe (11) are respectively provided with a positioning ring groove adapted to the return spring (14).
7. The building foundation construction method according to claim 6, wherein two ends of the return spring (14) are respectively fixedly provided with a mounting plate (15), and the mounting plates (15) can be inserted into the corresponding positioning ring grooves.
CN202110075585.3A 2021-01-20 2021-01-20 Building foundation construction method Active CN112900464B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110075585.3A CN112900464B (en) 2021-01-20 2021-01-20 Building foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110075585.3A CN112900464B (en) 2021-01-20 2021-01-20 Building foundation construction method

Publications (2)

Publication Number Publication Date
CN112900464A CN112900464A (en) 2021-06-04
CN112900464B true CN112900464B (en) 2022-06-07

Family

ID=76116745

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110075585.3A Active CN112900464B (en) 2021-01-20 2021-01-20 Building foundation construction method

Country Status (1)

Country Link
CN (1) CN112900464B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT310094B (en) * 1969-08-18 1973-09-10 Voest Ag Hollow driven pile for the production of an in-situ concrete pile
DE3167401D1 (en) * 1980-05-05 1985-01-10 Travocean Sarl Pyrotechnic device for anchoring piles or similar objects in the soil
CN2202796Y (en) * 1993-08-01 1995-07-05 李长仁 Flexible hole expanding drill
CN1936195A (en) * 2006-10-26 2007-03-28 郭祥山 Structural member for forming enlarged head pouring pile by explosion and construction method
CN212001061U (en) * 2020-01-04 2020-11-24 青岛瑞源工程集团有限公司 Blasting reaming reverse-pushing type grouting pile

Also Published As

Publication number Publication date
CN112900464A (en) 2021-06-04

Similar Documents

Publication Publication Date Title
US9829287B2 (en) Explosive tube having air gap and method of blasting bedrock using same
CN108645300B (en) Composite reflection energy collecting and buffering energy dissipating device and blasting construction method based on same
CN112878307B (en) Foundation pile-connection reinforcing method
CN113279622A (en) Method for demolishing thin-wall reinforced concrete chimney through high-notch blasting
CN112900464B (en) Building foundation construction method
JP5027958B1 (en) Crushed stone pile forming method and crushed stone pile forming apparatus used therefor
JP5407142B2 (en) Smooth blasting method
CN1936195A (en) Structural member for forming enlarged head pouring pile by explosion and construction method
CN110230959B (en) Rock cutting slope controlled blasting method
RU2229684C1 (en) Deep-hole stemming
CN110319739B (en) Blasting dynamic compaction linkage device
CN205444176U (en) Sedimentation pipe stake is prevented in explosion slip casting
US4462716A (en) Pile driving
JP3073277B2 (en) Excavation method for steel tower foundation holes
US3543524A (en) Thin-walled pile with closure plug
CN107726935B (en) Pile foundation construction method for large-angle inclined plane hard rock stratum
CN111707151B (en) One-time blasting excavation forming method for offshore rock-socketed pile foundation
CN210216413U (en) Explosion fracturing formula soil layer stock
EP4206405A1 (en) Method of forming a widened pile base
CN113405420B (en) Boundary control cutter and blasting device and method for nuclear power foundation pit energy-gathered cutting
CN211342779U (en) Reaming drill rod
KR102492406B1 (en) Steel pipe piling method using vibro hammer
CN209991885U (en) Novel nine-hole cut structure
JP2000120066A (en) Execution method for steel pipe pile
CN114991135A (en) High-pressure grouting prestressed pipe pile and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant