CN112801515A - Project resource allocation method, electronic equipment and computer readable storage medium - Google Patents

Project resource allocation method, electronic equipment and computer readable storage medium Download PDF

Info

Publication number
CN112801515A
CN112801515A CN202110134178.5A CN202110134178A CN112801515A CN 112801515 A CN112801515 A CN 112801515A CN 202110134178 A CN202110134178 A CN 202110134178A CN 112801515 A CN112801515 A CN 112801515A
Authority
CN
China
Prior art keywords
resource
project
time node
node
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110134178.5A
Other languages
Chinese (zh)
Inventor
王永刚
全伟雄
张光锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Shipyard International Co Ltd
Original Assignee
Guangzhou Shipyard International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shipyard International Co Ltd filed Critical Guangzhou Shipyard International Co Ltd
Priority to CN202110134178.5A priority Critical patent/CN112801515A/en
Publication of CN112801515A publication Critical patent/CN112801515A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06314Calendaring for a resource

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a project resource allocation method, electronic equipment and a computer readable storage medium capable of avoiding project resource conflict. The invention provides a project resource allocation method, which comprises the following steps: acquiring an input plan sub item and an input resource parameter, wherein the input plan sub item comprises a required resource type, a precondition, a total amount and a single-node maximum amount, and the input resource parameter comprises a resource type and a resource quota; determining the resource supply amount of each time node according to the input resource parameters; assigning a start time node and an end time node to each project based on the input plan sub-items and/or the resource supply amount of each time node; and allocating resources for each time node in the project from the starting time to the ending time in turn according to the sequence of the starting time of the project based on the resource supply amount of each time node and the resource type required by the project.

Description

Project resource allocation method, electronic equipment and computer readable storage medium
Technical Field
The invention belongs to the technical field of production planning, and particularly relates to a project resource allocation method, electronic equipment and a computer-readable storage medium.
Background
In the field of Project management planning, Project planning (Project Plan) is mainly a decision planning performed by a scheduler on a Project according to experience of the Project, and may include various implementation stages of Project division, work emphasis and tasks, resource requirements and time limit for completing tasks, results of stage work, coordination relationships among Project sub-items in the Project, and the like,
at present, the factors considered in the production planning of a company are mainly logical relations, but actually, the development of a plan has the restriction of other factors, and if the factors are not considered in the planning, the scientificity of the planning is low, and the execution deviation is large. The existing production planning has the following technical defects:
1. the existing plan considers key resources mainly according to human experience, and is not accurate and fine enough.
2. The existing plan rarely considers the amount of the planning project per se by taking the construction period as a compiling basis, so that the standard construction period of the plan is not scientific, and meanwhile, the resource cannot be quantitatively evaluated.
3. Existing planning does not consider a solution when different project resources conflict.
4. Existing plans are not sufficiently considered for external influencing factors.
5. Planning is not scientific enough, manual adjustment work is tedious, and efficiency is low.
Disclosure of Invention
In view of the deficiencies of the prior art, the present invention provides a project resource allocation method, an electronic device and a computer-readable storage medium for avoiding project resource conflicts.
The invention provides a project resource allocation method, which comprises the following steps:
acquiring an input plan sub item and an input resource parameter, wherein the input plan sub item comprises a required resource type, a precondition, a total amount and a single-node maximum amount, and the input resource parameter comprises a resource type and a resource quota;
determining the resource supply amount of each time node according to the input resource parameters;
assigning a start time node and an end time node to each project based on the input plan sub-items and/or the resource supply amount of each time node;
and allocating resources for each time node in the project from the starting time to the ending time in turn according to the sequence of the starting time of the project based on the resource supply amount of each time node and the resource type required by the project.
Preferably, assigning a start time node to each project based on the amount of resource offerings entered into the project sub-items and/or each time node comprises: determining a starting time node of the project based on whether a precondition exists, and if the precondition does not exist, giving the starting time node as a first time node; if the precondition exists, the starting time is given as: the precondition ends the time node next to the time node.
Preferably, after the last project allocates resources, the project updates the start time node according to the remaining amount of resources of each time node.
Preferably, after the resource is allocated to the previous project, the project updates the start time node according to the resource remaining amount of each time node, specifically: when the project needs multiple resource types, the time nodes which can be provided by multiple resources are determined according to the residual quantity of the multiple resources of each time node, and therefore the starting time node is updated.
Preferably, assigning an end time node to each project based on the amount of resource offerings entered into the project sub-items and/or each time node comprises: and determining the ending time node of the project based on the total amount and the maximum amount of the single node/the resource residual amount of each time node.
Preferably, the ending time node of the project is determined based on the total amount and the maximum amount of the single node/the resource residual amount of each time node, specifically: when the maximum single-node quantity is less than or equal to the corresponding daily resource residual quantity, counting the maximum single-node quantity; and when the maximum single-node quantity is larger than the corresponding daily resource residual quantity, metering the daily resource residual quantity.
Preferably, the input plan sub-item further includes a weight value, and the resource is sequentially allocated to each time node from the start time to the end time of each project according to the sequence of the start times of the projects and the sequence of the weight values from small to small based on the resource supply amount of each time node and the resource type required by the project.
Preferably, the required resource types include a key resource and a general resource.
The present invention also provides an electronic device, including: one or more processors; a memory for storing one or more programs that, when executed by the one or more processors, cause the one or more processors to implement the project resource allocation method.
The present invention also provides a computer-readable storage medium having stored thereon a computer program, characterized in that the program, when executed by a processor, implements the project resource allocation method.
The project resource allocation method, the electronic device and the computer readable storage medium provided by the invention can better avoid the problem of project resource conflict.
Drawings
The foregoing and other objects, features and advantages of the invention will be apparent from the following more particular description of preferred embodiments of the invention, as illustrated in the accompanying drawings. Like reference numerals refer to like parts throughout the drawings, and the drawings are not intended to be drawn to scale in actual dimensions, emphasis instead being placed upon illustrating the principles of the invention.
FIG. 1 is a flowchart illustrating a project resource allocation method according to an embodiment of the present invention;
FIG. 2 is a block diagram of an embodiment of the present invention;
FIG. 3 is a resource quota usage representation provided by an embodiment of the present invention;
fig. 4 is a resource quota setting presentation provided by an embodiment of the present invention.
Detailed Description
To facilitate an understanding of the invention, the invention will now be described more fully with reference to the accompanying drawings.
It will be understood that when an element is referred to as being "connected" to another element, it can be directly connected to the other element and be integral therewith, or intervening elements may also be present. As used herein, the terms "mounted," "a portion," "another portion," and the like are for illustrative purposes only.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
The embodiment of the invention provides a project resource allocation method, which is suitable for being executed in a production management system or Excel. The project resource allocation method provided by this embodiment may be executed by the resource allocation apparatus provided by this embodiment of the present invention, and the apparatus may be implemented in a software and/or hardware manner and integrated into a device for executing the method, and the device for executing the method in this embodiment may be any device capable of arranging a project plan in a production management system or Excel, such as a tablet computer, a desktop computer, and a notebook computer.
The project resource allocation method provided by the embodiment of the invention comprises the following steps:
(1) the method comprises the steps of obtaining an input plan sub item and input resource parameters, wherein the input plan sub item comprises a required resource type, a precondition, a total amount and a single-node maximum amount, and the input resource parameters comprise a resource type and a resource quota.
The node referred to in this embodiment may be a date, such as No. 1 month 1, No. 1 month 2, No. 1 month 3, etc.; time periods such as 11:00, 12:00, 13 points, etc. are also possible. The required resource types provided by the embodiment include a key resource and a common resource.
Specifically, referring to fig. 2, a worker may pre-design a template in a module table (as in fig. 2) of the Excel in advance, and when the template is used, the specific conditions of the resource type, the precondition, the total amount and the maximum amount of the single node required by the project corresponding to the project are input into the template. Referring to fig. 4, the resource type and the resource quota are input into the resource quota setting table.
(2) And determining the resource supply amount of each time node according to the input resource parameters.
Specifically, referring to fig. 3-4, parameters of each resource are set in a "resource quota setting" table (see, for example, 4) of Excel, and according to the parameters of each resource set in the "resource quota setting" table, the resource supply amount preset for each time node in the resource quota usage table (see, fig. 3) is further obtained. For example, the plane tire position can only provide 2 stations per day, and the resource provision amount of each time node is the corresponding number "2" of the plane tire position.
Referring to fig. 2 and 3, in the embodiment, the required resource type in the module table of Excel can be matched with the resource in the resource quota usage table of Excel. For example, the module table of Excel requires the resource type to have "flat position", and the resource quota usage table of Excel should preset the supply amount of "flat position" of each time node.
(3) Assigning a start time node and an end time node to each project based on the input plan sub-items and/or the resource supply amount of each time node;
a start time node is assigned to each project based on the amount of resource offerings entered into the project sub-items and/or each time node.
The method comprises the following steps: and determining the starting time node of the project based on whether the precondition exists, if the precondition does not exist, the project is an initial project, the implementation of the project does not need to depend on the completion of other projects, and the starting time node is given as a first time node. If the precondition is existed, the implementation of the project needs to depend on the completion of other projects, and needs to be carried out after the completion of other projects, so the project start time should wait until the completion of the dependent preceding project, and the start time is given as: the precondition ends the time node next to the time node. When there are multiple preconditions, the start time is given by: the last precondition finishes the time node next to the time node.
Referring to fig. 2, for example: if the item "a 1 was created in segments" without a precondition, the start time is 1/1(1 month and 1 day). If the preceding item of the item "a 1 segment pre-load" is "a 1 segment creation", and the end time of "a 1 segment creation" is 1/3(1 month and 3 days), the start time of "a 2 segment pre-load" is 1/4(1 month and 4 days).
The project start time node may also be updated. And after the resource is allocated to the previous project, the project updates the starting time node according to the resource residual quantity of each time node.
The method specifically comprises the following steps: when the project needs multiple resource types, the time nodes which can be provided by multiple resources are determined according to the residual quantity of the multiple resources of each time node, and therefore the starting time node is updated.
Referring to fig. 2 and 3, for example: the end time of "a 1 segment creation" was 1/3(1 month, 3 days), the initial start time of "a 1 segment preloading" was 1/4(1 month, 4 days), and then the resource quota usage table of Excel was examined, and the "a 1 segment preloading" project related to the key resource "preloading site" and the "ordinary resource" outfitting "were examined. When the time available for both the key resource and the common resource is checked 1/4(1 month, 4 days) and later, the time is greater, for example, the key resource 1/5(1 month, 5 days) starts to exist, but the common resource does not exist until 1/6(1 month, 6 days), at this time, 1/6(1 month, 6 days) is the start time of the project, and therefore, the update project start time node is 1/6.
An end time node is assigned to each project based on the amount of resource offerings entered into the project sub-items and/or each time node.
The method comprises the following steps: and determining the ending time node of the project based on the total amount and the maximum amount of the single node/the resource residual amount of each time node.
The method specifically comprises the following steps:
let y be the duration (days) of the A task;
m is the total amount of the task A;
n is the maximum daily amount of the task A;
ri is the remaining amount of ordinary resource availability required by task A on the ith day, and ri is retrieved from a resource quota usage table and is not necessarily the same every day.
Then, m ═ min (n, r1) + min (n, r2) + … … + min (n, ri)
y=i
Assuming that the start time of the a task is 1-1(1 month and 1 day), and assuming that y is 3, the end time of the a task is 1 month and 1 day + y-1 is 1 month and 3 days.
For example: the total number of pieces (total amount) of a cutting task is 100, and the maximum number of pieces (maximum amount of single node) of 30 pieces can be cut in one machine day, so that the cutting task can be finished in four days.
Referring to fig. 2 and 3, for example: the starting time of the 'A1 segment preassembly' is 1/4, the total quantity is 23, the maximum quantity of the single nodes is 6, the resource needed is 'outfitting', and a resource quota use table of Excel is checked. Since y is calculated to be 3, the end time node of "a 1 segment pre-load" is 1/7(1 month and 7 days).
(4) And allocating resources for each time node in the project from the starting time to the ending time in turn according to the sequence of the starting time of the project based on the resource supply amount of each time node and the resource type required by the project.
The project resource allocation method provided by the invention has the following advantages:
the plan is arranged according to the required resources, so that the plan is more suitable for practical execution;
the conflict of different project resources can be effectively avoided;
the construction period is used as a compiling basis, the planned standard construction period is scientific, and quantitative evaluation on resources can be better performed.
The planning results of different quantities and resource allocation can be tested, and management decision is convenient to carry out.
The method can be executed based on a production management system or Excel, the automation is stronger, all the steps only need to click a program button, no manual data operation is needed, the accuracy and the rapidness are realized, the efficiency is improved, and the cost is reduced.
In a preferred embodiment, the input plan sub-item further includes a weight value, and the resource is sequentially allocated to each time node from the start time to the end time of each project according to the sequence of the start time of the project and the sequence of the weight value from a substantially small sequence based on the resource supply amount of each time node and the resource type required by the project. The weight factor variable is added, so that a manager can set a priority strategy when facing conflict project resource competition, and the priority consideration of key products is reflected.
In a preferred embodiment, the input schedule sub-item further includes influencing factor variables, so that variables in the schedule operation process can be added, and the scheduling takes into account the changing factors
Referring to fig. 1, a project resource allocation method provided by an embodiment of the present invention includes the following steps:
s101, respectively obtaining the resource supply quantity of the input plan sub item and each time node.
S102, based on whether the precondition exists, the project start time node is given.
And S103, sorting according to the item starting time nodes, the sequence of the item starting time and the weight of the item from small to small.
And S104, endowing the item at the first sequencing point with an end time point according to the total amount and the maximum amount of the single node.
S105, resources are allocated to each time node from the starting time to the ending time of the first item in the sequence.
S106, the start time and the end time of other items are updated.
S107, according to the sequence, allocating resources for each time node from the starting time to the ending time of the next project.
And S108, repeating the steps S106 and S107 until all the items are distributed.
The project resource allocation method provided by the invention can be realized by programming. For example, a plug-in tool is generated and installed onto EXCEL for use. The application steps of the program are as follows:
filling the plan sub-items into a 'module table', wherein six elements including weight, resource type, precondition, key resource, influence factor, total amount and single-day maximum amount are required to be included;
setting parameters of each resource in the resource quota setting table, clicking a parameter changing button, and automatically filling resource elements in the resource quota setting table into corresponding columns in the resource quota using table by a program;
clicking the 'plan generation' button, the program will allocate resources and generate the plan according to the logical relationship and resource attributes of each plan.
In this embodiment, according to the provided Excel plan template, the plan elements are filled into the table as required, and various operations can be automatically realized by clicking the corresponding function buttons (3).
In a further preferred embodiment, a "change parameter" button is provided, after the parameters of each resource are re-input, the "change parameter" button is clicked, and after clicking, the program will automatically fill the resource elements in the "resource quota setting" table into the corresponding columns in the "resource quota usage table" table.
The present invention also provides an electronic device, comprising: one or more processors; a memory for storing one or more programs which, when executed by the one or more processors, cause the one or more processors to implement the project resource allocation method described above.
The present invention also provides a computer-readable storage medium having stored thereon a computer program which, when executed by a processor, implements the project resource allocation method described above.
In this application, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may be directly contacting the first and second features or indirectly contacting the first and second features through intervening media. Also, a first feature "on," "over," and "above" a second feature may be directly or diagonally above the second feature, or may simply indicate that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature may be directly under or obliquely under the first feature, or may simply mean that the first feature is at a lesser elevation than the second feature.
In the description herein, reference to the description of the terms "preferred embodiment," "yet another embodiment," "other embodiments," or "specific examples," etc., means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the application. In this specification, the schematic representations of the terms used above are not necessarily intended to refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, various embodiments or examples and features of different embodiments or examples described in this specification can be combined and combined by one skilled in the art without contradiction.
Although embodiments of the present application have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present application, and that variations, modifications, substitutions and alterations may be made to the above embodiments by those of ordinary skill in the art within the scope of the present application.

Claims (10)

1. A project resource allocation method, comprising the steps of:
acquiring an input plan sub item and an input resource parameter, wherein the input plan sub item comprises a required resource type, a precondition, a total amount and a single-node maximum amount, and the input resource parameter comprises a resource type and a resource quota;
determining the resource supply amount of each time node according to the input resource parameters;
assigning a start time node and an end time node to each project based on the input plan sub-items and/or the resource supply amount of each time node;
and allocating resources for each time node in the project from the starting time to the ending time in turn according to the sequence of the starting time of the project based on the resource supply amount of each time node and the resource type required by the project.
2. The project resource allocation method of claim 1, wherein assigning a start time node to each project based on an input plan sub-project and/or resource supply amount of each time node comprises: determining a starting time node of the project based on whether a precondition exists, and if the precondition does not exist, giving the starting time node as a first time node; if the precondition exists, the starting time is given as: the precondition ends the time node next to the time node.
3. The project resource allocation method of claim 2, wherein when the last project allocates resources, the project updates the start time node according to the remaining amount of resources of each time node.
4. The project resource allocation method of claim 3, wherein after the resource is allocated to the previous project, the project updates the start time node according to the resource remaining amount of each time node, specifically: when the project needs multiple resource types, the time nodes which can be provided by multiple resources are determined according to the residual quantity of the multiple resources of each time node, and therefore the starting time node is updated.
5. The project resource allocation method of claim 1, wherein assigning an end time node to each project based on the input plan sub-items and/or the resource supply amount of each time node comprises: and determining the ending time node of the project based on the total amount and the maximum amount of the single node/the resource residual amount of each time node.
6. The project resource allocation method of claim 4, wherein the end time node of the project is determined based on the total amount and the maximum amount of the single node/amount of resource remaining at each time node, and specifically: when the maximum single-node quantity is less than or equal to the corresponding daily resource residual quantity, counting the maximum single-node quantity; and when the maximum single-node quantity is larger than the corresponding daily resource residual quantity, metering the daily resource residual quantity.
7. The project resource allocation method according to claim 1, wherein the input plan sub-item further includes a weight value, and the resource is allocated to each time node in the time from the start time to the end time of each project in turn in the order of the start time of the project and in the order of the weight value from approximately small, based on the resource supply amount of each time node and the type of the resource required by the project.
8. The project resource allocation method of claim 1, wherein said required resource types include critical resources and common resources.
9. An electronic device, characterized in that the electronic device comprises: one or more processors; memory for storing one or more programs that, when executed by the one or more processors, cause the one or more processors to implement the project resource allocation method of any of claims 1-8.
10. A computer-readable storage medium, on which a computer program is stored, which, when being executed by a processor, carries out a project resource allocation method according to any one of claims 1 to 8.
CN202110134178.5A 2021-01-29 2021-01-29 Project resource allocation method, electronic equipment and computer readable storage medium Pending CN112801515A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110134178.5A CN112801515A (en) 2021-01-29 2021-01-29 Project resource allocation method, electronic equipment and computer readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110134178.5A CN112801515A (en) 2021-01-29 2021-01-29 Project resource allocation method, electronic equipment and computer readable storage medium

Publications (1)

Publication Number Publication Date
CN112801515A true CN112801515A (en) 2021-05-14

Family

ID=75813282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110134178.5A Pending CN112801515A (en) 2021-01-29 2021-01-29 Project resource allocation method, electronic equipment and computer readable storage medium

Country Status (1)

Country Link
CN (1) CN112801515A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113283879A (en) * 2021-06-21 2021-08-20 华电重工股份有限公司 Method and device for determining construction amount, electronic equipment and readable storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101770616A (en) * 2010-02-09 2010-07-07 北京航空航天大学 Multi-level collaborative project plan management method
CN103295100A (en) * 2013-05-28 2013-09-11 机械工业第六设计研究院有限公司 Project management progress arranging method and project management progress arranging system
CN103761614A (en) * 2014-01-20 2014-04-30 北京仿真中心 Project progress management method based on critical chain
CN108985647A (en) * 2018-07-27 2018-12-11 广船国际有限公司 A kind of execution method, apparatus, equipment and the storage medium of the project plan

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101770616A (en) * 2010-02-09 2010-07-07 北京航空航天大学 Multi-level collaborative project plan management method
CN103295100A (en) * 2013-05-28 2013-09-11 机械工业第六设计研究院有限公司 Project management progress arranging method and project management progress arranging system
CN103761614A (en) * 2014-01-20 2014-04-30 北京仿真中心 Project progress management method based on critical chain
CN108985647A (en) * 2018-07-27 2018-12-11 广船国际有限公司 A kind of execution method, apparatus, equipment and the storage medium of the project plan

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭钢;李光锐;邓晓刚;: "有限资源约束的产品开发多项目协同排程", 计算机工程与应用, no. 33, pages 67 - 70 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113283879A (en) * 2021-06-21 2021-08-20 华电重工股份有限公司 Method and device for determining construction amount, electronic equipment and readable storage medium

Similar Documents

Publication Publication Date Title
Vinod et al. Simulation modeling and analysis of due-date assignment methods and scheduling decision rules in a dynamic job shop production system
US5233533A (en) Scheduling method and apparatus
US8417368B2 (en) Method and apparatus for scheduling work orders in a manufacturing process
US5787000A (en) Method and apparatus for scheduling work orders in a manufacturing process
US6023702A (en) Method and apparatus for a process and project management computer system
US11138006B2 (en) Hybrid development systems and methods
MXPA01002771A (en) Computer-implemented product development planning method.
CN110516936B (en) Intelligent production line allocation system
CN112396322A (en) Production plan-based process technology unit productivity assessment method and system
CN110968371A (en) Method and system for configuring workflow in data warehouse
CN112801515A (en) Project resource allocation method, electronic equipment and computer readable storage medium
CN111475137A (en) Method, system and equipment for predicting software development requirements
CN113793203A (en) Order processing method and device
US8296449B2 (en) Systems and methods for calculating a distribution
CN112396323A (en) Production plan-based process sheet distribution method and system
JPH10254962A (en) Group-based work capability correction device and work allocation system
US20040267589A1 (en) System and method for applying human resources to a project plan
Khajehvand et al. Multi-objective and scalable heuristic algorithm for workflow task scheduling in utility grids
CN114648185A (en) Plan scheduling method, plan scheduling device, computer device, and storage medium
Taji et al. Dynamic Scheduling for Event-Driven Embedded Industrial Applications
CN116451976B (en) Automatic production-based production flow configuration method and related equipment
Collart An application of mathematical optimization to autoclave packing and scheduling in a composites manufacturing facility
WO2023228748A1 (en) Scheduling device, scheduling method, and scheduling program
CN116610428A (en) System data migration method, device, equipment and storage medium
Ahmadi et al. Integrated production scheduling in large-scale flexible electronic parts manufacturing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination