CN112734357A - Locking management method and system - Google Patents

Locking management method and system Download PDF

Info

Publication number
CN112734357A
CN112734357A CN202011550629.5A CN202011550629A CN112734357A CN 112734357 A CN112734357 A CN 112734357A CN 202011550629 A CN202011550629 A CN 202011550629A CN 112734357 A CN112734357 A CN 112734357A
Authority
CN
China
Prior art keywords
work order
equipment
information
consistent
unlocking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011550629.5A
Other languages
Chinese (zh)
Inventor
李明
程骥
龚自全
牛耘芜
刘华军
王守全
李先进
黄勉斌
陶辉
曾德鹏
符波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Sino French Water Co ltd
Original Assignee
Chongqing Sino French Water Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Sino French Water Co ltd filed Critical Chongqing Sino French Water Co ltd
Priority to CN202011550629.5A priority Critical patent/CN112734357A/en
Publication of CN112734357A publication Critical patent/CN112734357A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Abstract

A method and a system for managing a lock plate comprise the following specific steps: firstly, the method comprises the following steps: presetting or inputting login information on a mobile terminal, and initiating a work order; II, secondly: the equipment management system triggers the work order, verifies the information and submits the work order if the information is correct; thirdly, the method comprises the following steps: appointing a lockset according to the content of the work order; fourthly, the method comprises the following steps: an operator uploads a picture of the operation area; fifthly: carrying out approval operation, if the approval operation is passed, entering the next step, otherwise, returning to the step one; sixthly, the method comprises the following steps: verifying whether the equipment is consistent with the work order information or not, locking if the equipment is consistent with the work order information, and photographing and uploading; seventhly, the method comprises the following steps: starting operation; eighthly: after the operation is finished, submitting an unlocking application on the mobile terminal and uploading a photo; nine: the approver approves, if the approver approves, the next step is carried out, and if the approver approves, the seventh step is carried out; ten: verifying whether the equipment is consistent with the work order information or not, and unlocking if the equipment is consistent with the work order information; eleven: returning the lockset to the designated area and uploading the photo; twelve: and (6) ending.

Description

Locking management method and system
Technical Field
The invention relates to the technical field of industrial equipment operation management, in particular to a method and a system for managing a lock plate.
Background
In industrial equipment, corresponding to some important switches and valves, locks used in the prior art are mechanical locks which are opened and closed by keys; before locking and unlocking operations, an operator signs a paper work approval sheet to obtain permission. At present, the execution of the locking and listing mechanism mainly depends on the subjective consciousness of operators, the behavior of people plays a leading factor in the whole process, and a plurality of uncontrollable risks exist in the implementation process, for example, the operators do not execute the locking and listing program in an unsafe manner (lazy) in the energy saving process, the operators do unsafe behaviors such as operation before approval in the implementation process, the unauthorized operators have misoperation, mistaken unlocking and the like, so that the probability of accidents is increased, and the risk of the locking and listing operation process is increased. Meanwhile, the traditional locking and listing program is relatively high in operation repeatability every time, along with the increase of operation times, the error rate of an operator is increased under the state of long-term repeated operation, and finally the industrial risk control effect of the traditional locking and listing mechanism is weakened.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a method for distributing monotonous, high-precision and regular work such as information transmission, processing, archiving, authority control, flow guidance, lockset pairing and the like in the upper lock plate flow to computer network processing under the coordination of a computing technology and terminal equipment; the upper lock plate management method and the system have the advantages that research and decision-making work such as permission examination and approval, unlocking sequence setting and the like is distributed to operation personnel for operation, so that the human-machine in the upper lock plate program can be optimally matched from the safety angle, the defect that the human factors of the traditional upper lock plate program participate in too much is changed, and the industrial risk management and control efficiency and effect of the upper lock plate mechanism are improved from the technical aspect, and the specific technical scheme is as follows:
a method for managing upper lock cards comprises the following specific steps:
the method comprises the following steps: presetting or inputting login information on a mobile terminal, and initiating a work order;
step two: the equipment management system triggers the work order, verifies the information and submits the work order if the information is correct;
step three: appointing a lockset according to the content of the work order;
step four: an operator uploads a picture of the operation area;
step five: carrying out approval operation, if the approval operation is passed, entering the next step, otherwise, returning to the step one;
step six: verifying whether the equipment is consistent with the work order information or not, locking if the equipment is consistent with the work order information, and photographing and uploading;
step seven: starting operation;
step eight: after the operation is finished, submitting an unlocking application on the mobile terminal and uploading a photo;
step nine: the approver approves, if the approver approves, the next step is carried out, and if the approver approves, the seventh step is carried out;
step ten: verifying whether the equipment is consistent with the work order information or not, and unlocking if the equipment is consistent with the work order information;
step eleven: returning the lockset to the designated area and uploading the photo;
step twelve: and (6) ending.
Preferably, the method comprises the following steps: the fifth step is also provided with a step 5.1: and after the examination and approval are passed, the information of the maintenance work order is pushed to the operation management personnel.
Preferably, the method comprises the following steps: step seven is also provided with step 7.1: and transferring the unlocking authority to the similar operators.
Preferably, the method comprises the following steps: the ninth step is also provided with the step 9.1: after the unlocking application is submitted, the unlocking information is pushed to the operator.
The system of the lock plate management method is provided with an equipment management system for managing the running state of each running equipment, including the locking state on the equipment;
the mobile terminal is arranged and used for maintaining the hand of an operator, initiating a work order and uploading data;
the electronic lock is used for fixing the state of the running equipment;
be provided with work order status information display screen for maintenance work order personnel, progress and tool to lock real-time status information now.
The invention has the beneficial effects that: 1. the related work of process signature approval, record archiving, uploading/unlocking permission transfer, record inquiry and the like in the traditional locking tablet program needs to invest certain time cost and labor cost, the project is managed in an informationized way, the operation can be completed at the mobile terminal of the mobile phone, the investment of the two cost items is shortened, and compared with the traditional locking tablet program, the efficiency of the locking tablet mechanism in the practical application management process is improved;
2. through the functions of equipment system linkage, electronic lock pairing, unlocking sequence setting, electronic lock authority management, operation flow duplication and the like, the inherent risks of the traditional locking tablet program, such as formal approval, unlocking authority (key) management and control loopholes, first-operation and second-approval, wrong unlocking sequence, wrong locking position and the like, which are objectively existed, are effectively reduced, the inherent safety risk of the traditional locking tablet management mechanism in the implementation process is reduced, and the reliability of the program is improved.
3. Among all equipment maintenance injuries, 80% of reasons are that the equipment is not closed, energy is accidentally released, and the upper locking and listing system and method can effectively avoid maintenance accidents caused by the reasons, can better realize the expected risk control effect of the upper locking and listing, and further avoid economic losses caused by safety production accidents. The system is not directly related to economic benefits, the system is one-time investment from the qualitative perspective, certain economic benefits are indirectly formed by improving the working efficiency of the upper locking and listing program and reducing the occurrence probability of safety production accidents, and the economic benefits are positively related to the service cycle of the system.
Drawings
FIG. 1 is a schematic flow chart of the present invention.
Detailed Description
The following detailed description of the preferred embodiments of the present invention, taken in conjunction with the accompanying drawings, will make the advantages and features of the invention easier to understand by those skilled in the art, and thus will clearly and clearly define the scope of the invention.
As shown in fig. 1: a method for managing upper lock cards comprises the following specific steps:
the method comprises the following steps: presetting or inputting login information on the mobile terminal, wherein the login information comprises information of maintenance personnel, maintenance positions and the like, and initiating a work order;
step two: the equipment management system triggers the work order, verifies the information and submits the work order if the information is correct;
step three: appointing a lockset according to the content of the work order;
step four: an operator uploads a picture of the operation area by using the mobile terminal, and scans the two-dimensional code of the equipment to obtain equipment information;
step five: carrying out approval operation, if the approval operation is passed, entering the next step, otherwise, returning to the step one;
step 5.1: after the examination and approval are passed, the maintenance work order information is pushed to the operation management personnel;
step six: verifying whether the equipment is consistent with the work order information or not, locking if the equipment is consistent with the work order information, and photographing and uploading;
step seven: starting operation;
step 7.1: the unlocking authority is handed over to the similar operators, and the subsequent process can be completed by the operators with the authority;
step eight: after the operation is finished, submitting an unlocking application on the mobile terminal and uploading a photo;
step nine: the approver approves, if the approver approves, the next step is carried out, and if the approver approves, the seventh step is carried out;
step 9.1: after the unlocking application is submitted, the unlocking information is pushed to the operator;
step ten: verifying whether the equipment is consistent with the work order information or not, and unlocking if the equipment is consistent with the work order information;
step eleven: returning the lockset to the designated area and uploading the photo;
step twelve: and (6) ending.
A system of a lock plate management method is provided with an equipment management system, which is used for managing the running state of each running equipment, including the locking state on the equipment;
the mobile terminal is arranged and used for maintaining the hand of an operator, initiating a work order and uploading data;
the electronic lock is used for fixing the state of running equipment and is communicated with the mobile terminal through Bluetooth;
be provided with work order status information display screen for maintenance work order personnel, progress and tool to lock real-time status information now.
The method and the system have the following characteristics:
1. linkage and mobile approval of equipment management system
The system can manage information such as locks, equipment, personnel and the like in a database mode, is in seamless butt joint with an equipment management system, synchronously generates a new flow at a mobile terminal by grabbing key fields pushed by the equipment management system, and pushes a locking application flow to related personnel. The intelligent locking tablet management system client is deployed on an enterprise WeChat platform, a user can check maintenance operation progress information at any time and any place, application and approval operations are executed, data are marked in the whole process, and data storage and query are facilitated.
2. Intelligent authority control of electronic lock
The intelligent electronic lock is used in the project, the Bluetooth communication mode is adopted to communicate with the mobile phone client, and through the intelligent authority control lockset, the system can perform Bluetooth communication with most of Bluetooth electronic locks on the current market, and has market adaptability.
3. Electronic lock and isolation device locking object pairing
The project can directly take the unique two-dimensional code of the existing equipment as the identification code and input into the system. In the application process, a background manager configures the corresponding relationship between a management object (maintenance equipment) and corresponding equipment to be locked (locking position) in the system background in advance. After the locking process is newly established, the system automatically extracts corresponding identification codes in the database according to the configured corresponding relation, field operators scan the field two-dimensional codes through a mobile phone to extract the identification codes, the system judges whether the scanned objects are correct locking objects or not through comparison, and the comparison is successful in issuing locking/unlocking permission.
4. Unlock sequence management and control
When a plurality of locking devices or positions exist on one isolation object, the locking personnel can set an unlocking sequence in advance according to the requirements of the office security key, and the system can issue unlocking permission according to a preset program.
5. Electronic card management
The electronic display screen is installed on the operation site, the system can automatically push the operation information of the locking board to the site electronic display screen, the work order progress and the site locking equipment state are displayed in real time, and related personnel can check and acquire corresponding information.
6. Operation flow recording and replaying disc
In the process of implementing the locking board flow, an operator is required to submit a live important measure line pipe photo as a necessary link for flow process, the system can automatically record the system time of the key operation node, and personnel with authority can inquire participators, important node time and live pictures of each locking flow process in the background.

Claims (5)

1. A method for managing a lock plate is characterized by comprising the following specific steps:
the method comprises the following steps: presetting or inputting login information on a mobile terminal, and initiating a work order;
step two: the equipment management system triggers the work order, verifies the information and submits the work order if the information is correct;
step three: appointing a lockset according to the content of the work order;
step four: an operator uploads a picture of the operation area;
step five: carrying out approval operation, if the approval operation is passed, entering the next step, otherwise, returning to the step one;
step six: verifying whether the equipment is consistent with the work order information or not, locking if the equipment is consistent with the work order information, and photographing and uploading;
step seven: starting operation;
step eight: after the operation is finished, submitting an unlocking application on the mobile terminal and uploading a photo;
step nine: the approver approves, if the approver approves, the next step is carried out, and if the approver approves, the seventh step is carried out;
step ten: verifying whether the equipment is consistent with the work order information or not, and unlocking if the equipment is consistent with the work order information;
step eleven: returning the lockset to the designated area and uploading the photo;
step twelve: and (6) ending.
2. The lock plate management method according to claim 1, characterized in that: the fifth step is also provided with a step 5.1: and after the examination and approval are passed, the information of the maintenance work order is pushed to the operation management personnel.
3. The lock plate management method according to claim 1, characterized in that: step seven is also provided with step 7.1: and transferring the unlocking authority to the similar operators.
4. The lock plate management method according to claim 1, characterized in that: the ninth step is also provided with the step 9.1: after the unlocking application is submitted, the unlocking information is pushed to the operator.
5. The system of the lock management method according to any one of claims 1 to 4, wherein: the system is provided with an equipment management system for managing the running state of each running equipment, including the locking state on the equipment;
the mobile terminal is arranged and used for maintaining the hand of an operator, initiating a work order and uploading data;
the electronic lock is used for fixing the state of the running equipment;
be provided with work order status information display screen for maintenance work order personnel, progress and tool to lock real-time status information now.
CN202011550629.5A 2020-12-24 2020-12-24 Locking management method and system Pending CN112734357A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011550629.5A CN112734357A (en) 2020-12-24 2020-12-24 Locking management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011550629.5A CN112734357A (en) 2020-12-24 2020-12-24 Locking management method and system

Publications (1)

Publication Number Publication Date
CN112734357A true CN112734357A (en) 2021-04-30

Family

ID=75615208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011550629.5A Pending CN112734357A (en) 2020-12-24 2020-12-24 Locking management method and system

Country Status (1)

Country Link
CN (1) CN112734357A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115273284A (en) * 2022-07-27 2022-11-01 中国电信股份有限公司 Permission adaptation method and device, storage medium and electronic equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050222889A1 (en) * 2004-03-31 2005-10-06 Chris Lai Method and system for facility management
CN105279419A (en) * 2014-07-12 2016-01-27 鞍钢股份有限公司 Intrinsic safety type electronic operation plate system
CN108492410A (en) * 2018-03-12 2018-09-04 雅砻江流域水电开发有限公司 A kind of Intelligent locking system based on more people control
CN112116252A (en) * 2020-09-21 2020-12-22 武汉瑞莱保能源技术有限公司 Safety control method for electrical equipment isolation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050222889A1 (en) * 2004-03-31 2005-10-06 Chris Lai Method and system for facility management
CN105279419A (en) * 2014-07-12 2016-01-27 鞍钢股份有限公司 Intrinsic safety type electronic operation plate system
CN108492410A (en) * 2018-03-12 2018-09-04 雅砻江流域水电开发有限公司 A kind of Intelligent locking system based on more people control
CN112116252A (en) * 2020-09-21 2020-12-22 武汉瑞莱保能源技术有限公司 Safety control method for electrical equipment isolation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李昆鹏;项泽强;: "上锁挂牌在项目调试工作中的应用", 水泥, no. 07, pages 65 - 66 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115273284A (en) * 2022-07-27 2022-11-01 中国电信股份有限公司 Permission adaptation method and device, storage medium and electronic equipment

Similar Documents

Publication Publication Date Title
US7861314B2 (en) Interactive key control system and method of managing access to secured locations
CN103389705B (en) Operation supervise and control system and operation supervise and control method
CN111027932A (en) Safety management method for intelligent work ticket
CN201562306U (en) Intelligent door lock control system
CN105279419B (en) A kind of intrinsic safety type electric operates board system
CN110910555A (en) Safety management method for intelligent operation ticket
CN109326034B (en) Intelligent lock work ticket management system for electric cabinet
CN105678924A (en) Automatic book borrowing, returning and exchanging method and automatic book borrowing system
US7840010B2 (en) Interactive security control system with conflict checking
CN101599187A (en) A kind of electronic door lock system and management method thereof
CN111445610B (en) System for managing work ticket isolation key
CN106228632A (en) A kind of building site Work attendance method and system
US11893844B2 (en) Face authentication machine and face authentication method
US7702913B2 (en) Interactive security control system with real time activity reports
CN106066882A (en) A kind of virtualization exhibition system and using method thereof
CN112734357A (en) Locking management method and system
CN107181753B (en) Mobile terminal financial system and method
CN110378803A (en) A kind of industry stops power transmission C2C platform and method
US20060123486A1 (en) Interactive security control system with conflict checking
US20060268758A1 (en) Interactive security control system with audit capabilities
CN111292437A (en) Intelligent access control system of photovoltaic box-type substation and control method thereof
US20070214491A1 (en) Interactive security control system and method with automated order submission and approval process
CN109711677A (en) A kind of anti-human-equation error free isolated operation system of power plant and method
CN110348545A (en) A kind of AR Intelligent switching order method and device based on ERP system
CN116028441A (en) Judicial case handling data analysis platform and application method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination