CN112733243A - BIM technology-based pipeline comprehensive optimization method - Google Patents
BIM technology-based pipeline comprehensive optimization method Download PDFInfo
- Publication number
- CN112733243A CN112733243A CN202110068606.9A CN202110068606A CN112733243A CN 112733243 A CN112733243 A CN 112733243A CN 202110068606 A CN202110068606 A CN 202110068606A CN 112733243 A CN112733243 A CN 112733243A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- pipelines
- class
- pipe
- optimization method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F18/00—Pattern recognition
- G06F18/20—Analysing
- G06F18/24—Classification techniques
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/18—Network design, e.g. design based on topological or interconnect aspects of utility systems, piping, heating ventilation air conditioning [HVAC] or cabling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2113/00—Details relating to the application field
- G06F2113/14—Pipes
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- General Physics & Mathematics (AREA)
- Evolutionary Computation (AREA)
- Computer Hardware Design (AREA)
- General Engineering & Computer Science (AREA)
- Mathematical Analysis (AREA)
- Data Mining & Analysis (AREA)
- Pure & Applied Mathematics (AREA)
- Mathematical Optimization (AREA)
- Computational Mathematics (AREA)
- Bioinformatics & Computational Biology (AREA)
- Civil Engineering (AREA)
- Software Systems (AREA)
- Computer Networks & Wireless Communication (AREA)
- Bioinformatics & Cheminformatics (AREA)
- Life Sciences & Earth Sciences (AREA)
- Evolutionary Biology (AREA)
- Computer Vision & Pattern Recognition (AREA)
- Artificial Intelligence (AREA)
- Architecture (AREA)
- Computer Graphics (AREA)
- Structural Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Pipeline Systems (AREA)
Abstract
The invention discloses a pipeline comprehensive optimization method based on a BIM technology, and relates to the technical field of pipeline design and construction equipment. A pipeline comprehensive optimization method based on a BIM technology comprises the following steps: classify the pipeline, functional pipeline sets up to one kind of pipeline, and supply class pipeline sets up to second kind of pipeline, and blowdown class pipeline sets up to three kinds of pipelines, and is managed the district and divide into first area in district, second area in district and third area in district and to respectively with one kind of pipeline, second kind of pipeline and three kinds of pipelines, step two: and performing three-dimensional modeling on the pipeline and the line thereof by using BIM, labeling the material thereof according to the actual use condition, and performing color classification on the material according to the function of the pipeline. According to the collision detection of the BIM, the cross collision and the parallel collision of the pipelines are respectively processed by adopting the pipeline bridging piece and the pipeline parallel auxiliary piece, and the construction problem caused by the fact that the pipelines are not physically crossed is proved.
Description
Technical Field
The invention relates to the technical field of pipeline design and construction equipment, in particular to a comprehensive optimization method of a pipeline based on a BIM technology.
Background
The BIM is a process of uniformly coordinating from planning, designing and constructing to managing stages, and is operating software for converting a standard concept into corresponding data, and the laying of pipelines in the building construction process firstly needs to be designed in the BIM software to determine the installation size, the installation position and relevant material information.
When BIM is used for designing pipelines, due to the fact that pipelines are numerous, the situation of pipeline cross collision can be found during modeling, and if the situation is not processed and found, serious problems can be caused in construction.
Disclosure of Invention
The invention aims to provide a pipeline comprehensive optimization method based on a BIM technology to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the pipeline comprehensive optimization method based on the BIM technology comprises the following specific optimization methods:
the method comprises the following steps: classifying the pipelines according to the use requirements, setting the functional pipelines as first-class pipelines, setting the supply pipelines as second-class pipelines, setting the sewage discharge pipelines as third-class pipelines, dividing the pipeline laying area into a first pipe area, a second pipe area and a third pipe area from top to bottom according to the height, respectively determining the laying rules of the first-class pipelines, the second-class pipelines and the third pipelines according to the BIM comprehensive pipeline optimization principle;
step two: performing three-dimensional modeling on the pipeline and the line thereof by using BIM, labeling the material thereof according to the actual use condition, and performing color classification on the material according to the function of the pipeline;
step three: performing collision detection between pipelines on the three-dimensional model of the BIM pipeline, detecting cross collision and parallel collision between the pipelines, and marking position coordinates of the cross collision and the parallel collision;
step four: processing two pipelines which are in cross collision by utilizing a pipeline bridging piece, connecting the pipeline bridging piece on a pipeline with lower cost by taking a pipeline with low cost and high cost as a processing rule according to the size and the material of the pipeline, and connecting the pipeline bridging piece on the pipeline with lower cost under special conditions;
step five: when two pipelines which are collided in parallel are treated, one pipeline is horizontally deviated, the two pipelines are fixed by using pipeline parallel auxiliary pieces, and the pipeline parallel auxiliary pieces are arranged at the head, the tail and the middle parts of the adjacent pipelines;
step six: the pipelines needing to use equipment or connecting pieces are relatively identical in position, adjacent equipment needing to be overhauled and one position are concentrated, and a plurality of underground maintenance wells are built and included inside the pipelines;
step seven: and outputting the corrected three-dimensional drawing, outputting the three-dimensional drawing as a construction drawing with a specific size, and making an operation animation demonstration when each pipeline is installed by using three-dimensional software.
Further, a special case in the fourth step is that when two cross-collided pipes individually use the pipe bridge, and invade other pipes, both pipes are required to be connected to the adapter bridge, the height of the used adapter bridge is reduced compared to the normal pipe bridge.
Furthermore, the first pipe area, the second pipe area and the third pipe area in the first step are not limited in space height and can be arranged above the building base surface and below the building base surface.
Furthermore, the underground access wells in the sixth step are adapted to the pipeline network below the building base level, the number of the underground access wells is multiple, and each underground access well is marked with the information of the access pipeline.
Furthermore, the first type of pipeline in the first step comprises an electric power pipeline, a steam pipeline and a fire-fighting pipeline, the second type of pipeline comprises a water pipe, a heating pipe and a gas pipe, and the third type of pipeline comprises a drain pipe, a blow-off pipe and a middle water pipe.
Furthermore, the operation in the seventh step is performed with demonstration animation for assisting the workers in the field construction operation.
Compared with the prior art, the invention has the beneficial effects that:
according to the BIM technology-based pipeline comprehensive optimization method, cross collision and parallel collision of pipelines are respectively processed by adopting pipeline bridging pieces and pipeline parallel auxiliary pieces according to collision detection of BIM, and the problem of construction caused by physical cross among the pipelines is proved.
Drawings
FIG. 1 is a schematic view of a piping partition structure according to the present invention;
FIG. 2 is a schematic view of the cross-collision process of the present invention;
FIG. 3 is a schematic view of the parallel crash processing of the present invention;
fig. 4 is a schematic view of the structure of the manhole.
In the figure: 1. a first pipe area; 2. a second tube region; 3. a third tube zone; 4. a type of pipe; 5. a second type of pipeline; 6. three types of pipelines; 7. a conduit bridge; 8. a pipe-parallel auxiliary; 9. an underground manhole; 10. a bridge is fitted.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that in the description of the present invention, the terms "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are only for convenience of description and simplification of description, and do not indicate or imply that the referred device or element must have a specific orientation, be configured in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
Claims (6)
1. The comprehensive pipeline optimization method based on the BIM technology is characterized by comprising the following steps: the specific optimization method comprises the following steps:
the method comprises the following steps: classifying the pipelines according to the use requirements, setting the functional pipelines as first-class pipelines (4), setting the supply-class pipelines as second-class pipelines (5), setting the sewage-discharge-class pipelines as third-class pipelines (6), dividing the pipeline laying area into a first pipe area (1), a second pipe area (2) and a third pipe area (3) from top to bottom according to the height, respectively using the first-class pipelines (4), the second-class pipelines (5) and the third-class pipelines (6), and determining the laying rules according to the BIM comprehensive pipeline optimization principle;
step two: the method comprises the following steps of performing three-dimensional modeling on a pipeline and a line thereof by using IBM, marking materials of the pipeline according to actual use conditions, and classifying colors of the pipeline according to functions of the pipeline;
step three: performing collision detection between pipelines on the three-dimensional model of the IBM pipeline, detecting cross collision and parallel collision existing between the pipelines, and marking position coordinates of the cross collision and the parallel collision;
step four: processing two pipelines which are in cross collision by using a pipeline bridging part (7), connecting the pipeline bridging part (7) on the pipeline with lower cost by using the pipeline with low cost and high cost as a processing rule according to the size and the material of the pipeline, and connecting the pipeline bridging part (7) on the pipeline with lower cost under special conditions;
step five: when two pipelines which are collided in parallel are treated, one pipeline is horizontally deviated, the two pipelines are fixed by using pipeline parallel auxiliary pieces (8), and the pipeline parallel auxiliary pieces (8) are arranged at the head, the tail and the middle parts of the adjacent pipelines;
step six: the pipelines needing to use equipment or connecting pieces are relatively identical in position, adjacent equipment needing to be overhauled and one position are concentrated, and a plurality of underground maintenance wells (9) are built and included inside;
step seven: and outputting the corrected three-dimensional drawing, outputting the three-dimensional drawing as a construction drawing with a specific size, and making an operation animation demonstration when each pipeline is installed by using three-dimensional software.
2. The BIM technology-based pipeline comprehensive optimization method according to claim 1, wherein: the special case in the fourth step is that when two cross-collided pipes individually use the pipe bridge (7) and invade other pipes, both pipes need to be connected with the adapter bridge (10), and the height of the used adapter bridge (10) is reduced compared with the normal pipe bridge (7).
3. The BIM technology-based pipeline comprehensive optimization method according to claim 1, wherein: the first pipe area (1), the second pipe area (2) and the third pipe area (3) in the first step are not limited in space height and can be arranged above a building base surface or below the building base surface.
4. The BIM technology-based pipeline comprehensive optimization method according to claim 1, wherein: and in the sixth step, the underground maintenance wells (9) are adapted to the pipeline network lower than the building base surface, the number of the underground maintenance wells (9) is multiple, and each underground maintenance well (9) is marked with maintenance pipeline information.
5. The BIM technology-based pipeline comprehensive optimization method according to claim 1, wherein: the first-class pipeline (4) in the first step comprises an electric pipeline, a steam pipeline and a fire-fighting pipeline, the second-class pipeline (5) comprises a water pipe, a heating pipe and a gas pipe, and the third-class pipeline (6) comprises a drain pipe, a blow-off pipe and a reclaimed water pipe.
6. The BIM technology-based pipeline comprehensive optimization method according to claim 1, wherein: and operation demonstration animations in the seventh step are used for assisting workers in field construction operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110068606.9A CN112733243B (en) | 2021-01-19 | 2021-01-19 | BIM technology-based pipeline comprehensive optimization method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110068606.9A CN112733243B (en) | 2021-01-19 | 2021-01-19 | BIM technology-based pipeline comprehensive optimization method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112733243A true CN112733243A (en) | 2021-04-30 |
CN112733243B CN112733243B (en) | 2023-02-17 |
Family
ID=75592392
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110068606.9A Active CN112733243B (en) | 2021-01-19 | 2021-01-19 | BIM technology-based pipeline comprehensive optimization method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112733243B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114491883A (en) * | 2021-12-31 | 2022-05-13 | 天津博迈科海洋工程有限公司 | Intelligent installation method for large oil-gas module pipeline parts |
CN118171380A (en) * | 2024-05-15 | 2024-06-11 | 北京市第三建筑工程有限公司 | Deep design method for bridge direction conversion pipe fitting in narrow electric well space |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100252298A1 (en) * | 2009-04-01 | 2010-10-07 | Hubbell Incorporated | Raceway bridge assembly |
CN102867077A (en) * | 2012-07-05 | 2013-01-09 | 西安理工大学 | BIM (Building Information Modeling)-based metro comprehensive pipeline adjustment method |
CN103093061A (en) * | 2013-02-07 | 2013-05-08 | 中铁二十二局集团电气化工程有限公司 | Complex pipeline collision optimization method of subway electromechanical engineering |
CN106202831A (en) * | 2016-08-10 | 2016-12-07 | 中国建筑第八工程局有限公司 | A kind of pipeline layout optimization method based on BIM |
CN107103115A (en) * | 2017-03-24 | 2017-08-29 | 中冶南方城市建设工程技术有限公司 | A kind of town road pipeline optimizing method for disposing based on BIM |
GB2549753A (en) * | 2016-04-27 | 2017-11-01 | Ensign Advanced Systems Ltd | Designing support systems for building services |
CN109614723A (en) * | 2018-12-14 | 2019-04-12 | 中建二局第建筑工程有限公司 | A kind of comprehensive construction method based on BIM technology |
CN209104733U (en) * | 2018-12-26 | 2019-07-12 | 陕西建工第三建设集团有限公司 | A kind of electrical groove box three-dimensional connector of multidirectional intercommunication |
CN110929325A (en) * | 2019-11-30 | 2020-03-27 | 四川鸥鹏建筑工程公司 | Building Information Modeling (BIM) -based comprehensive pipe gallery modeling method |
CN110990983A (en) * | 2019-12-05 | 2020-04-10 | 中建长远建设有限公司 | Water supply pipeline cross arrangement method |
CN111724124A (en) * | 2020-05-27 | 2020-09-29 | 上海宝冶集团有限公司 | BIM technology-based pipeline comprehensive construction method |
CN112182817A (en) * | 2020-09-24 | 2021-01-05 | 中铁八局集团昆明铁路建设有限公司 | BIM model-based pipeline arrangement method |
-
2021
- 2021-01-19 CN CN202110068606.9A patent/CN112733243B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100252298A1 (en) * | 2009-04-01 | 2010-10-07 | Hubbell Incorporated | Raceway bridge assembly |
CN102867077A (en) * | 2012-07-05 | 2013-01-09 | 西安理工大学 | BIM (Building Information Modeling)-based metro comprehensive pipeline adjustment method |
CN103093061A (en) * | 2013-02-07 | 2013-05-08 | 中铁二十二局集团电气化工程有限公司 | Complex pipeline collision optimization method of subway electromechanical engineering |
GB2549753A (en) * | 2016-04-27 | 2017-11-01 | Ensign Advanced Systems Ltd | Designing support systems for building services |
CN106202831A (en) * | 2016-08-10 | 2016-12-07 | 中国建筑第八工程局有限公司 | A kind of pipeline layout optimization method based on BIM |
CN107103115A (en) * | 2017-03-24 | 2017-08-29 | 中冶南方城市建设工程技术有限公司 | A kind of town road pipeline optimizing method for disposing based on BIM |
CN109614723A (en) * | 2018-12-14 | 2019-04-12 | 中建二局第建筑工程有限公司 | A kind of comprehensive construction method based on BIM technology |
CN209104733U (en) * | 2018-12-26 | 2019-07-12 | 陕西建工第三建设集团有限公司 | A kind of electrical groove box three-dimensional connector of multidirectional intercommunication |
CN110929325A (en) * | 2019-11-30 | 2020-03-27 | 四川鸥鹏建筑工程公司 | Building Information Modeling (BIM) -based comprehensive pipe gallery modeling method |
CN110990983A (en) * | 2019-12-05 | 2020-04-10 | 中建长远建设有限公司 | Water supply pipeline cross arrangement method |
CN111724124A (en) * | 2020-05-27 | 2020-09-29 | 上海宝冶集团有限公司 | BIM technology-based pipeline comprehensive construction method |
CN112182817A (en) * | 2020-09-24 | 2021-01-05 | 中铁八局集团昆明铁路建设有限公司 | BIM model-based pipeline arrangement method |
Non-Patent Citations (7)
Title |
---|
PENGFEI LI ET AL.: "Research on optimization design of underground garage comprehensive pipeline based on BIM technology", 《IOP CONFERENCE SERIES: MATERIALS SCIENCE AND ENGINEERING》 * |
廉光伟 等: "基于ArcEngine的管线碰撞分析算法设计与实现", 《城市勘测》 * |
张哲: "工程设计阶段BIM技术应用研究", 《中国优秀硕士学位论文全文数据库工程科技II辑》 * |
李伟等: "基于BIM技术的综合管线设计在地铁中的优化分析", 《沈阳大学学报(自然科学版)》 * |
王咸锋 等: "基于BIM的管线综合技术优化研究与实践", 《能源与环保》 * |
谢焕连: "基于BIM的建筑综合管线优化研究", 《中国优秀硕士学位论文全文数据库工程科技II辑》 * |
马捷: "基于BIM的地铁综合管线设计优化方法研究", 《中国优秀硕士学位论文全文数据库工程科技II辑》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114491883A (en) * | 2021-12-31 | 2022-05-13 | 天津博迈科海洋工程有限公司 | Intelligent installation method for large oil-gas module pipeline parts |
CN114491883B (en) * | 2021-12-31 | 2024-08-02 | 天津博迈科海洋工程有限公司 | Intelligent installation method for large oil and gas module pipeline parts |
CN118171380A (en) * | 2024-05-15 | 2024-06-11 | 北京市第三建筑工程有限公司 | Deep design method for bridge direction conversion pipe fitting in narrow electric well space |
Also Published As
Publication number | Publication date |
---|---|
CN112733243B (en) | 2023-02-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112733243B (en) | BIM technology-based pipeline comprehensive optimization method | |
CN102867077B (en) | BIM (Building Information Modeling)-based metro comprehensive pipeline adjustment method | |
CN107633133B (en) | Construction method of earthquake-resistant support and hanger based on BIM +3D scanning technology | |
CN102867076B (en) | BIM (Building Information Modeling)-based metro comprehensive pipeline clearance detection method | |
CN110763809B (en) | Experimental verification method for optimal arrangement scheme of gas detector | |
CN105701264A (en) | Automatic construction method for underground pipe network | |
CN105046359A (en) | BIM (Building Information Modelling) technology based municipal pipeline factory prefabrication and installation method | |
CN107100645A (en) | Shield tunnel curve section section of jurisdiction preassembling selection designing method based on BIM technology | |
CN103603501B (en) | The discharging method of large-span space structure building operation | |
CN106971046A (en) | A kind of high-order receipts water cooling tower Central Shaft design method | |
CN104200522A (en) | Two-dimensional cable data based three-dimensional cable model generation method | |
CN110990995A (en) | Method and device for positioning water flow abnormity of drainage pipeline | |
CN113392442A (en) | Construction method of pre-embedded lossless connecting component and assembly type branch hanging system | |
CN115587456A (en) | BIM (building information modeling) forward design method and system for outdoor water supply and drainage pipe network | |
CN112257292B (en) | Space safety layout method of large coal gasification plant based on three-dimensional risk | |
CN108121861A (en) | A kind of pipe gallery crosspoint modular design method based on BIM | |
CN109918815A (en) | Detection method and system for preventing external breakage of power cables | |
CN101719288A (en) | Method for inspecting element collision of power generation plant by three-dimensional model | |
Jacobs et al. | Strategy to identify and mitigate hazards in deep-level mine ventilation systems using a calibrated digital twin | |
CN116244807A (en) | BIM (building information modeling) component coding method based on 3DExperience guiding construction | |
WO2019004646A1 (en) | Using simulation method for determining building layout maximising floor area ratio computer | |
CN114493314A (en) | Excel-based quality audit scoring method for drainage pipe network original collected data | |
CN118051983B (en) | Pumped storage power station space topology data and BIM model generation method and device | |
KR102734667B1 (en) | Positioning and Modeling Automation System for Plant Piping Supports | |
Liu et al. | Numerical study on hydrogen flow behavior in two compartments with different connecting pipes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |