CN112686579A - Early warning method and system for settlement control over approximate calculation of engineering project - Google Patents

Early warning method and system for settlement control over approximate calculation of engineering project Download PDF

Info

Publication number
CN112686579A
CN112686579A CN202110132237.5A CN202110132237A CN112686579A CN 112686579 A CN112686579 A CN 112686579A CN 202110132237 A CN202110132237 A CN 202110132237A CN 112686579 A CN112686579 A CN 112686579A
Authority
CN
China
Prior art keywords
node
early warning
project
settlement
amount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110132237.5A
Other languages
Chinese (zh)
Inventor
胡春涛
蒋荣超
韩华银
郑雪松
徐凰耀
王露
李宏
杨仁山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Chongqing Chongqing High Tech Industry Group Co ltd
Original Assignee
Chongqing Chongqing Chongqing High Tech Industry Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Chongqing Chongqing High Tech Industry Group Co ltd filed Critical Chongqing Chongqing Chongqing High Tech Industry Group Co ltd
Priority to CN202110132237.5A priority Critical patent/CN112686579A/en
Publication of CN112686579A publication Critical patent/CN112686579A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention particularly relates to a settlement control over-approximate-calculation early warning method and system for engineering projects. The early warning method divides a construction stage before an engineering project settlement stage into a plurality of project nodes, compares contract amount of each project node with a corresponding node early warning value when the project node occurs, and sends out corresponding over-approximate-calculation early warning when the contract amount of the project node exceeds the corresponding node early warning value. The invention also discloses a corresponding temperature early warning system, which comprises: the project node monitoring unit is used for acquiring the contract amount of the project node when the project node occurs; and the central management unit is used for inputting the contract amount of the project node into the super-probability early warning model and acquiring a corresponding super-probability early warning result. The settlement control super-approximate calculation early warning method and system can perform super-approximate calculation early warning on each construction stage before settlement, so that the super-approximate control effect on project settlement can be improved.

Description

Early warning method and system for settlement control over approximate calculation of engineering project
Technical Field
The invention relates to the technical field of engineering cost management, in particular to a settlement control over-approximate-calculation early warning method and system for engineering projects.
Background
The project budget is the plan for the project to generate revenue and expenditure for a given period of time in the future. The method can evaluate the investment of engineering projects in a currency form and reflect the economic effect of the engineering. The method is the basis for strengthening enterprise management, carrying out economic accounting, assessing engineering cost and compiling construction plan, and is also the main basis for bidding and quotation of engineering tenders and determining engineering cost. The project settlement refers to the final settlement of the project price to a contracting unit after a construction enterprise completes all contracted projects according to the content specified by a contract, the quality of the received projects is qualified, and the contract requirements are met. The project settlement is a summary file of all construction cost, construction achievement and financial condition from the beginning of project completion to the completion delivery of the project by taking the physical quantity and the currency index as measurement units.
The construction period of the project is long, the number of the consumed funds is large, intermediate settlement and annual settlement are needed to be carried out on the project cost for the construction and installation enterprises to compensate the funds consumed in the construction in time, and completion settlement is needed after all project completion acceptance. It can be seen that project settlement is an important task in the contract of project, and for this reason, chinese patent publication No. CN111582915A discloses "a project budget and settlement comparison system" which includes a budget input unit, a settlement input unit, a budget data storage unit, a settlement data storage unit, a calculation unit, a data comparison unit, and an input recording unit. Simultaneously, also discloses the following steps: inputting the project budget of the current month into a budget input unit; the project budget data enters the calculation unit for calculation and then is stored in the budget data storage unit; and then the project settlement data in the current month is input into a settlement input unit.
The project budget and settlement comparison system in the above-mentioned conventional scheme can conveniently compare the project settlement amount (data) with the estimated amount, and further can judge whether the amount of the project cost settlement exceeds the estimated amount (i.e. exceeds the estimated amount). However, in actual research, the applicant has found that before the construction cost is settled, the construction project is subjected to construction stages such as a new start stage, a reconstruction stage and a completion stage, and the construction stages generate corresponding cost. However, the existing scheme only manages the amount of the project cost settlement node, but does not manage the contract amount in the construction stage, so once the amount of the project cost settlement node exceeds the approximate value, the method is difficult to make up, and the existing scheme has a poor effect of the excess control of the project cost settlement node. In addition, after an engineering project is over-approximated, some enterprises need to select 'work stealing and material reduction' in the subsequent construction process to avoid continuing over-approximated calculation, so that the engineering quality is difficult to guarantee. Therefore, the applicant thinks of designing a super-approximate calculation early warning method capable of carrying out super-approximate calculation early warning on each construction stage before the settlement so as to improve the super-approximate management and control effect on the settlement of the engineering project.
Disclosure of Invention
Aiming at the defects of the prior art, the technical problems to be solved by the invention are as follows: how to provide a super-approximate calculation early warning method and system capable of carrying out super-approximate calculation early warning on each construction stage before final settlement, so that the super-approximate control effect on the project final settlement can be improved, and the project quality can be assisted to be improved.
In order to solve the technical problems, the invention adopts the following technical scheme:
a construction stage before an engineering project settlement stage is divided into a plurality of project nodes, contract amount of each project node is compared with a corresponding node early warning value when the project node occurs, and corresponding super-approximate-calculation early warning is sent out when the contract amount of the project node exceeds the corresponding node early warning value.
Preferably, the method specifically comprises the following steps:
s1: correspondingly dividing a construction stage before an engineering project settlement stage into a plurality of project nodes; then, correspondingly generating a node early warning value of each project node and a settlement early warning value in a settlement stage according to the approximate calculation amount of the project;
s2: acquiring contract amount of the project node when the project node occurs, comparing the contract amount of the project node with a corresponding node early warning value, and sending a corresponding over-approximate-calculation early warning signal when the contract amount is larger than the corresponding node early warning value;
s3: and acquiring corresponding contract amount in a settlement stage, comparing the contract amount in the settlement stage with the corresponding settlement early warning value, and sending a corresponding super-approximate-calculation early warning signal when the contract amount is greater than the corresponding settlement early warning value.
Preferably, in step S1, a node risk value corresponding to each project node is generated based on the estimated amount of the project; in step S2, when a project node occurs, the contract amount of the project node is compared with the corresponding node risk value, and a corresponding risk early warning signal is sent when the contract amount is smaller than the corresponding node risk value.
Preferably, in step S1, when the contract amount of the previous project node is smaller than the corresponding node early warning value, the node early warning value of the next project node is adjusted according to the contract amount and the node early warning value of the previous project node.
Preferably, step S3 specifically includes the following steps:
s31: after the submission information of the settlement stage passes, acquiring a first contract audit amount and a second contract audit amount of the settlement stage;
s32: comparing the first-order-of-contract amount with the corresponding settlement early warning value, and if the first-order-of-contract amount is greater than the settlement early warning value, sending a corresponding super-approximate-calculation early warning signal; otherwise, entering the next step;
s33: comparing the second amount of examination of the contract with the corresponding settlement early warning value, and if the second amount of examination of the contract is greater than the settlement early warning value, sending a corresponding super-approximate calculation early warning signal; otherwise, entering the next step;
s34: and entering a final stage.
Preferably, the settlement warning value is ninety percent of the estimated amount of the engineering project.
Preferably, in step S1, the construction phase before the project completion phase is divided into a new construction node, a reconstruction node, and an as-built node.
Preferably, the node early warning value of the new start node is forty percent of the estimated amount, and the node risk value of the new start node is twenty percent of the estimated amount; the node early warning value of the reconstruction node and the reconstruction node is seventy percent of the approximate calculation amount, and the node risk value of the reconstruction node and the reconstruction node is fifty percent of the approximate calculation amount; the node early warning value of the completed node is eighty percent of the approximate amount, and the node risk value of the completed node is sixty percent of the approximate amount.
The invention also discloses a settlement control super-approximate calculation early warning system of the engineering project, which is implemented based on the settlement control super-approximate calculation early warning method and specifically comprises the following steps:
the project phase segmentation unit is used for dividing a construction phase before the project settlement phase into a plurality of project nodes;
the project node monitoring unit is used for acquiring the contract amount of the project node and the approximate calculation amount of the project when the project node occurs;
the central management unit is used for inputting the contract amount of the project node into a pre-established super-probability early warning model and acquiring a super-probability early warning result output by the super-probability early warning model;
and the super-probability early warning model generates a node early warning value corresponding to the project node according to the approximate amount of money, then compares the contract amount of the project node with the corresponding node early warning value, and outputs the corresponding super-probability amount and sends out a super-probability early warning signal as a super-probability early warning result when the contract amount of money is greater than the corresponding node early warning value.
Preferably, the super-probability early warning model is established according to each dimension parameter of the project and historical project information; each dimension parameter of the project comprises a project node, a project node start-stop time, project personnel information, project main content and project approximate calculation amount; and the super-probability early warning model calculates a corresponding node early warning value according to a Monte Carlo analysis method.
Compared with the prior art, the settlement control super-approximate calculation early warning method and the settlement control super-approximate calculation early warning system have the following advantages:
in the invention, the construction stage before the project settlement stage is divided into a plurality of project nodes, and the contract amount of each project node is controlled, so that the project can be prevented from exceeding budget during construction, further the problem of excessive approximate calculation of the project in the settlement stage can be avoided to a certain extent, the control effect of the project settlement can be improved, and the project quality can be assisted to be improved. And secondly, the node early warning value and the settlement early warning value are generated by calculating in advance according to the approximate calculation amount and the historical data or the experience value, so that the cost control effect on each project node and the settlement stage is better, and the control effect on the project settlement can be improved.
Drawings
For purposes of promoting a better understanding of the objects, aspects and advantages of the invention, reference will now be made in detail to the present invention as illustrated in the accompanying drawings, in which:
FIG. 1 is a logic diagram of a decision-making management hyper-approximate-computation early warning method according to an embodiment;
FIG. 2 is a logic diagram of step S3 according to one embodiment;
fig. 3 is a flowchart illustrating a third embodiment of a decision-making management hyper-approximate-computation early warning system;
fig. 4 is a logic block diagram of a decision-making management hyper-approximate-computation early warning system according to a third embodiment.
Detailed Description
The following is further detailed by the specific embodiments:
the first embodiment is as follows:
the embodiment discloses a settlement control over-approximate-calculation early warning method for an engineering project.
A construction stage before an engineering project settlement stage is divided into a plurality of project nodes, contract amount of each project node is compared with a corresponding node early warning value when the project node occurs, and corresponding super-approximate-calculation early warning is sent out when the contract amount of the project node exceeds the corresponding node early warning value. As shown in fig. 1, the method specifically includes the following steps:
s1: correspondingly dividing a construction stage before an engineering project settlement stage into a plurality of project nodes; then, correspondingly generating a node early warning value of each project node and a settlement early warning value in a settlement stage according to the approximate calculation amount of the project;
s2: acquiring contract amount of the project node when the project node occurs, comparing the contract amount of the project node with a corresponding node early warning value, and sending a corresponding over-approximate-calculation early warning signal when the contract amount is larger than the corresponding node early warning value;
s3: and acquiring corresponding contract amount in a settlement stage, comparing the contract amount in the settlement stage with the corresponding settlement early warning value, and sending a corresponding super-approximate-calculation early warning signal when the contract amount is greater than the corresponding settlement early warning value.
In the invention, the construction stage before the project settlement stage is divided into a plurality of project nodes, and the contract amount of each project node is controlled, so that the project can be prevented from exceeding budget during construction, further the problem of excessive approximate calculation of the project in the settlement stage can be avoided to a certain extent, the control effect of the project settlement can be improved, and the project quality can be assisted to be improved. And secondly, the node early warning value and the settlement early warning value are generated by calculating in advance according to the approximate calculation amount and the historical data or the experience value, so that the cost control effect on each project node and the settlement stage is better, and the control effect on the project settlement can be improved.
In a specific implementation process, in step S1, a node risk value corresponding to each project node is generated according to the estimated amount of the engineering project; in step S2, when a project node occurs, the contract amount of the project node is compared with the corresponding node risk value, and a corresponding risk early warning signal is sent when the contract amount is smaller than the corresponding node risk value.
In the actual management and control process, some construction enterprises can purchase some cheap building materials with specifications inconsistent with preset rules in order to avoid over-approximate calculation, so that the quality of engineering projects is difficult to ensure. Therefore, the node risk value is set, and a corresponding risk early warning signal can be sent out when the contract amount is smaller than the corresponding node risk value, namely, a risk early warning can be sent out when the contract amount is obviously inconsistent with the budget amount so as to remind relevant personnel to check, thereby assisting in improving the engineering quality.
In a specific implementation process, as shown in fig. 2, step S3 specifically includes the following steps:
s31: after the submission information of the settlement stage passes, acquiring a first contract audit amount and a second contract audit amount of the settlement stage; the settlement early warning value is ninety percent of the approximate amount;
s32: comparing the first-order-of-contract amount with the corresponding settlement early warning value, and if the first-order-of-contract amount is greater than the settlement early warning value, sending a corresponding super-approximate-calculation early warning signal; otherwise, entering the next step;
s33: comparing the second amount of examination of the contract with the corresponding settlement early warning value, and if the second amount of examination of the contract is greater than the settlement early warning value, sending a corresponding super-approximate calculation early warning signal; otherwise, entering the next step;
s34: and entering a final stage.
In the settlement stage, the invention firstly checks the settlement submission information, controls the amount of money in the settlement stage after the submission information passes, and can send out a corresponding super-approximate calculation early warning signal, thereby improving the control effect on the engineering settlement. And secondly, the invention carries out two different risk control on the contract amount in the settlement stage, which is beneficial to improving the control effect on the project settlement.
In the specific implementation process, in step S1, the construction phase before the engineering project settlement phase is divided into new construction nodes, reconstruction nodes, continued construction nodes and completed construction nodes.
According to the method and the system, each project node is correspondingly divided according to the construction stage of the project, so that the divided project nodes can be adapted to the actual construction process of the project, the control effect on each project node can be improved, and the control effect on the project settlement can be improved.
In the specific implementation process, the node early warning value of the new start node is forty percent of the approximate calculation amount, and the node risk value of the new start node is twenty percent of the approximate calculation amount; the node early warning value of the reconstruction node and the reconstruction node is seventy percent of the approximate calculation amount, and the node risk value of the reconstruction node and the reconstruction node is fifty percent of the approximate calculation amount; the node early warning value of the completed node is eighty percent of the approximate amount, and the node risk value of the completed node is sixty percent of the approximate amount.
According to the invention, through setting the node early warning value and the node risk value of each project node, the cost control effect on each project node and the settlement stage is better, and the risk early warning can be sent out when the contract amount and the budget amount are obviously inconsistent so as to remind related personnel to check the material and cost information, so that the control effect on the project settlement can be improved, and the project quality can be assisted to be improved.
Example two:
on the basis of the first embodiment, the embodiment discloses a method for updating a node early warning value.
In step S1 of this embodiment, when the contract amount of the previous project node is smaller than the corresponding node warning value, the node warning value of the next project node is adjusted according to the contract amount of the previous project node and the corresponding node warning value.
According to the invention, the node early warning value of the next project node can be adjusted according to the difference value between the contract amount of the previous project node and the node early warning value, so that the final settlement amount of the project can be more fit with the approximate calculation amount, thus the cost of each project node can be better controlled, and the control effect of the project settlement can be favorably improved.
For example, the preset node early warning value of the new start node is forty percent of the estimated amount; the node early warning value of the reconstruction node and the reconstruction node is seventy percent of the approximate calculation amount; and the node early warning value of the completed node is eighty percent of the approximate calculation amount. Then, when the contract amount of the new start node is twenty-five percent of the estimated amount, the difference value between the contract amount of the new start node and the node early warning value is fifteen percent, so that the node early warning value of the next project node of the new start node, the rebuilt node and the rebuilt node is adjusted to seventy-five percent of the estimated amount in the embodiment. When the contract amount of the new start node is thirty-eight percent of the approximate amount, the difference value between the contract amount of the new start node and the early warning value of the node is two percent, so that the early warning values of the next project node, the reconstruction node and the reconstruction node of the new start node are adjusted to be sixty-nine percent of the approximate amount.
Specifically, when the difference value between the contract amount of the previous project node and the node early warning value is greater than ten percent, the node early warning value of the next project node is correspondingly adjusted upwards; and when the difference value between the contract amount of the previous project node and the node early warning value is less than five percent, correspondingly adjusting the node early warning value of the next project node downwards. The specific adjustment value is determined according to historical data or corresponding engineering projects. Thus, the final settlement amount of the engineering project can be more matched with the estimated amount.
Example three:
the embodiment further discloses a decision calculation control super-approximate calculation early warning system based on the first embodiment.
With reference to fig. 3 and 4, a decision calculation management and control super-approximate calculation early warning system for engineering projects specifically includes:
the project phase segmentation unit is used for dividing a construction phase before the project settlement phase into a plurality of project nodes;
the project node monitoring unit is used for acquiring the contract amount of the project node and the approximate calculation amount of the project when the project node occurs;
the central management unit is used for inputting the contract amount of the project node into a pre-established super-probability early warning model and acquiring a super-probability early warning result output by the super-probability early warning model;
and the super-probability early warning model generates a node early warning value corresponding to the project node according to the approximate amount of money, then compares the contract amount of the project node with the corresponding node early warning value, and outputs the corresponding super-probability amount and sends out a super-probability early warning signal as a super-probability early warning result when the contract amount of money is greater than the corresponding node early warning value. In the embodiment, the super-probability early warning model is established according to each dimension parameter of the project and historical project information; each dimension parameter of the project comprises a project node, a project node start-stop time, project personnel information, project main content and project approximate calculation amount; and the super-probability early warning model calculates the corresponding node early warning value according to a Monte Carlo analysis method.
According to the invention, the construction stage before the project settlement stage is divided into a plurality of project nodes by the project stage division unit, and the contract money of each project node is controlled by combining the project node monitoring unit and the central management unit, so that the project can be prevented from exceeding budget during construction, and further the problem of overapproximate calculation of the project in the settlement stage can be avoided to a certain extent, thereby improving the control effect of the project settlement and assisting in improving the project quality. Secondly, the hyper-probabilistic early warning model generates corresponding node early warning values and settlement early warning values in advance according to the approximate calculation amount and historical data or experience values, so that the cost control effect of each project node and settlement stage is better, and the control effect of project settlement can be improved.
The foregoing is merely an example of the present invention, and common general knowledge in the field of known specific structures and characteristics is not described herein in any greater extent than that known in the art at the filing date or prior to the priority date of the application, so that those skilled in the art can now appreciate that all of the above-described techniques in this field and have the ability to apply routine experimentation before this date can be combined with one or more of the present teachings to complete and implement the present invention, and that certain typical known structures or known methods do not pose any impediments to the implementation of the present invention by those skilled in the art. It should be noted that, for those skilled in the art, without departing from the structure of the present invention, several changes and modifications can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent. The scope of the claims of the present application shall be determined by the contents of the claims, and the description of the embodiments and the like in the specification shall be used to explain the contents of the claims.

Claims (10)

1. A settlement control over-approximate-calculation early warning method for engineering projects is characterized by comprising the following steps: dividing a construction stage before an engineering project settlement stage into a plurality of project nodes, comparing contract amount of each project node with a corresponding node early warning value when the project node occurs, and sending out a corresponding super-approximate-calculation early warning when the contract amount of the project node exceeds the corresponding node early warning value.
2. The conclusion-computation-management-control hyper-approximate-computation early warning method for engineering projects as claimed in claim 1, specifically comprising the steps of:
s1: correspondingly dividing a construction stage before an engineering project settlement stage into a plurality of project nodes; then, correspondingly generating a node early warning value of each project node and a settlement early warning value in a settlement stage according to the approximate calculation amount of the project;
s2: acquiring contract amount of the project node when the project node occurs, comparing the contract amount of the project node with a corresponding node early warning value, and sending a corresponding over-approximate-calculation early warning signal when the contract amount is larger than the corresponding node early warning value;
s3: and acquiring corresponding contract amount in a settlement stage, comparing the contract amount in the settlement stage with the corresponding settlement early warning value, and sending a corresponding super-approximate-calculation early warning signal when the contract amount is greater than the corresponding settlement early warning value.
3. The settlement control super-approximate-calculation early warning method of engineering project as claimed in claim 2, characterized in that: in step S1, a node risk value corresponding to each project node is generated based on the estimated amount of the project;
in step S2, when a project node occurs, the contract amount of the project node is compared with the corresponding node risk value, and a corresponding risk early warning signal is sent when the contract amount is smaller than the corresponding node risk value.
4. The settlement control super-approximate-calculation early warning method of engineering project as claimed in claim 2, characterized in that: in step S1, when the contract amount of the previous project node is smaller than the corresponding node early warning value, the node early warning value of the next project node is adjusted according to the contract amount and the node early warning value of the previous project node.
5. The method as claimed in claim 2, wherein the step S3 includes the following steps:
s31: after the submission information of the settlement stage passes, acquiring a first contract audit amount and a second contract audit amount of the settlement stage;
s32: comparing the first-order-of-contract amount with the corresponding settlement early warning value, and if the first-order-of-contract amount is greater than the settlement early warning value, sending a corresponding super-approximate-calculation early warning signal; otherwise, entering the next step;
s33: comparing the second amount of examination of the contract with the corresponding settlement early warning value, and if the second amount of examination of the contract is greater than the settlement early warning value, sending a corresponding super-approximate calculation early warning signal; otherwise, entering the next step;
s34: and entering a final stage.
6. The method as claimed in claim 5, wherein the final decision management and control over-estimation early warning method comprises: the settlement warning value is ninety percent of the estimated amount of the engineering project.
7. The settlement control super-approximate-calculation early warning method of engineering project as claimed in claim 3, characterized in that: in step S1, the construction phase before the project settlement phase is divided into new construction nodes, reconstruction nodes and completion nodes.
8. The settlement control super-approximate-calculation early warning method of engineering project as claimed in claim 7, characterized in that: the node early warning value of the new start node is forty percent of the approximate calculation amount, and the node risk value of the new start node is twenty percent of the approximate calculation amount; the node early warning value of the reconstruction node and the reconstruction node is seventy percent of the approximate calculation amount, and the node risk value of the reconstruction node and the reconstruction node is fifty percent of the approximate calculation amount; the node early warning value of the completed node is eighty percent of the approximate amount, and the node risk value of the completed node is sixty percent of the approximate amount.
9. A decision-making management control super-approximate calculation early warning system for engineering projects, which is implemented based on the decision-making management control super-approximate calculation early warning method described in claim 1, and specifically comprises:
the project phase segmentation unit is used for dividing a construction phase before the project settlement phase into a plurality of project nodes;
the project node monitoring unit is used for acquiring the contract amount of the project node and the approximate calculation amount of the project when the project node occurs;
the central management unit is used for inputting the contract amount of the project node into a pre-established super-probability early warning model and acquiring a super-probability early warning result output by the super-probability early warning model;
and the super-probability early warning model generates a node early warning value corresponding to the project node according to the approximate amount of money, then compares the contract amount of the project node with the corresponding node early warning value, and outputs the corresponding super-probability amount and sends out a super-probability early warning signal as a super-probability early warning result when the contract amount of money is greater than the corresponding node early warning value.
10. The settlement management super-approximate-calculation early warning system of engineering project as claimed in claim 9, wherein: the super-probability early warning model is established according to each dimension parameter of the project and historical project information; each dimension parameter of the project comprises a project node, a project node start-stop time, project personnel information, project main content and project approximate calculation amount;
and the super-probability early warning model calculates a corresponding node early warning value according to a Monte Carlo analysis method.
CN202110132237.5A 2021-01-31 2021-01-31 Early warning method and system for settlement control over approximate calculation of engineering project Pending CN112686579A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110132237.5A CN112686579A (en) 2021-01-31 2021-01-31 Early warning method and system for settlement control over approximate calculation of engineering project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110132237.5A CN112686579A (en) 2021-01-31 2021-01-31 Early warning method and system for settlement control over approximate calculation of engineering project

Publications (1)

Publication Number Publication Date
CN112686579A true CN112686579A (en) 2021-04-20

Family

ID=75459543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110132237.5A Pending CN112686579A (en) 2021-01-31 2021-01-31 Early warning method and system for settlement control over approximate calculation of engineering project

Country Status (1)

Country Link
CN (1) CN112686579A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114358734A (en) * 2021-12-29 2022-04-15 深圳供电局有限公司 Project capital budget estimate management and control method and system
CN115577368A (en) * 2022-10-30 2023-01-06 四川通信科研规划设计有限责任公司 Method for improving big data security
CN115983797A (en) * 2023-01-03 2023-04-18 宝钢工程技术集团有限公司 Method for early warning and managing data matching and super-approximate calculation of engineering quantity list of metallurgical engineering project

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10171865A (en) * 1996-12-10 1998-06-26 Maeda Corp System for managing civil engineering work budget
CN104850940A (en) * 2015-04-29 2015-08-19 国网辽宁省电力有限公司鞍山供电公司 Completion settlement making method and completion settlement making system based on project whole-process management
CN105512466A (en) * 2015-11-30 2016-04-20 华北电力大学 Power grid project implementation phase risk early warning method based on extreme value theory
CN106503959A (en) * 2016-09-29 2017-03-15 中工国际工程股份有限公司 The monitoring early-warning system of project information
CN108256821A (en) * 2017-12-14 2018-07-06 中国航空规划设计研究总院有限公司 A kind of management method of construction project overall process various dimensions cost management system
CN109272294A (en) * 2018-09-11 2019-01-25 上海宝冶集团有限公司 A kind of limitation design method of assembled architecture, device, equipment and storage medium
CN109872043A (en) * 2019-01-17 2019-06-11 上海申元工程投资咨询有限公司 A kind of cost process risk management-control method and its system
JP2019197306A (en) * 2018-05-08 2019-11-14 株式会社日立製作所 Settlement management system and settlement management method
JP2019197405A (en) * 2018-05-10 2019-11-14 株式会社野村総合研究所 Project status management device, project status management program, and project status management method
CN110503435A (en) * 2019-07-31 2019-11-26 阿里巴巴集团控股有限公司 Transaction method for early warning, device and equipment based on block chain
CN111401620A (en) * 2020-03-10 2020-07-10 北京泓慧国际能源技术发展有限公司 Spot electricity price prediction method and device
CN111815015A (en) * 2020-05-22 2020-10-23 北京合力信工程投资咨询有限公司 Engineering management optimization method and system
CN112036806A (en) * 2020-07-15 2020-12-04 远光软件股份有限公司 Project full life cycle approximate calculation management method, device, equipment and storage medium
CN112085361A (en) * 2020-08-28 2020-12-15 上海谊逅信息技术有限公司 Construction engineering overall process management method
CN112258050A (en) * 2020-10-26 2021-01-22 厦门海迈科技股份有限公司 Engineering fund control method and equipment based on approximate calculation

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10171865A (en) * 1996-12-10 1998-06-26 Maeda Corp System for managing civil engineering work budget
CN104850940A (en) * 2015-04-29 2015-08-19 国网辽宁省电力有限公司鞍山供电公司 Completion settlement making method and completion settlement making system based on project whole-process management
CN105512466A (en) * 2015-11-30 2016-04-20 华北电力大学 Power grid project implementation phase risk early warning method based on extreme value theory
CN106503959A (en) * 2016-09-29 2017-03-15 中工国际工程股份有限公司 The monitoring early-warning system of project information
CN108256821A (en) * 2017-12-14 2018-07-06 中国航空规划设计研究总院有限公司 A kind of management method of construction project overall process various dimensions cost management system
JP2019197306A (en) * 2018-05-08 2019-11-14 株式会社日立製作所 Settlement management system and settlement management method
JP2019197405A (en) * 2018-05-10 2019-11-14 株式会社野村総合研究所 Project status management device, project status management program, and project status management method
CN109272294A (en) * 2018-09-11 2019-01-25 上海宝冶集团有限公司 A kind of limitation design method of assembled architecture, device, equipment and storage medium
CN109872043A (en) * 2019-01-17 2019-06-11 上海申元工程投资咨询有限公司 A kind of cost process risk management-control method and its system
CN110503435A (en) * 2019-07-31 2019-11-26 阿里巴巴集团控股有限公司 Transaction method for early warning, device and equipment based on block chain
CN111401620A (en) * 2020-03-10 2020-07-10 北京泓慧国际能源技术发展有限公司 Spot electricity price prediction method and device
CN111815015A (en) * 2020-05-22 2020-10-23 北京合力信工程投资咨询有限公司 Engineering management optimization method and system
CN112036806A (en) * 2020-07-15 2020-12-04 远光软件股份有限公司 Project full life cycle approximate calculation management method, device, equipment and storage medium
CN112085361A (en) * 2020-08-28 2020-12-15 上海谊逅信息技术有限公司 Construction engineering overall process management method
CN112258050A (en) * 2020-10-26 2021-01-22 厦门海迈科技股份有限公司 Engineering fund control method and equipment based on approximate calculation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈润生;: "工程项目前期阶段的超概算风险及控制研究", 价值工程 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114358734A (en) * 2021-12-29 2022-04-15 深圳供电局有限公司 Project capital budget estimate management and control method and system
CN115577368A (en) * 2022-10-30 2023-01-06 四川通信科研规划设计有限责任公司 Method for improving big data security
CN115983797A (en) * 2023-01-03 2023-04-18 宝钢工程技术集团有限公司 Method for early warning and managing data matching and super-approximate calculation of engineering quantity list of metallurgical engineering project

Similar Documents

Publication Publication Date Title
CN112686579A (en) Early warning method and system for settlement control over approximate calculation of engineering project
US7945472B2 (en) Business management tool
Mauer et al. Investment under uncertainty: The case of replacement investment decisions
CN110288210B (en) Project level road infrastructure comprehensive maintenance decision method and system
CN108564207B (en) BIM-based construction engineering intelligent bidding decision management system
CN110276682A (en) A kind of information calculates processing method and system
Lesniak et al. Cost calculation of building structures and building works in Polish conditions
CN110310076B (en) Contract management method and device
Feodoria Optimal investment and utility indifference pricing in the presenceof small fixed transaction costs
Hang Evaluating the decision-making on a Public-Private Partnership to finance a road project in Vietnam
KR101187099B1 (en) Accounting treatment system for ifrs financial product using database for mass processing
Floc'h More stochastic expansions for the pricing of vanilla options with cash dividends
Regulator Better regulation. Explanatory statement: Rate of return guideline
Ivory et al. Ireland’s Spending Multipliers
CN111598729A (en) Method for conveniently compiling settlement change list
Kurnianingtyas et al. Financial Strategy Model for Social Health Insurance in Indonesia using Simulation
Shahnazarian A dynamic micro-econometric simulation model for firms
el hédi Arouri et al. Do on/off time series models reproduce emerging stock market comovements?''
Mezak et al. Issues in determining the real value of concession fees when granting concession for commercial use of maritime domain
KR102186235B1 (en) System and Method of Lease Sales Operation of Pre-paid Consumers using Assets Fund
Badaik et al. Impact of fiscal deficit on macroeconomic variables in India
Marović et al. Process approach in modelling Croatian construction contract management practice
Schade et al. Modeling and calibration of large scale system dynamics models: the case of the ASTRA model
Hofstadler In-Depth Bid Assessment for Unit-Priced Contracts
Vaughan The Unearned Premium Reserve for Warranty Insurance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210420