CN112663595A - Adjusting and fixing device for first root locking section steel of underground continuous steel wall - Google Patents

Adjusting and fixing device for first root locking section steel of underground continuous steel wall Download PDF

Info

Publication number
CN112663595A
CN112663595A CN202011394074.XA CN202011394074A CN112663595A CN 112663595 A CN112663595 A CN 112663595A CN 202011394074 A CN202011394074 A CN 202011394074A CN 112663595 A CN112663595 A CN 112663595A
Authority
CN
China
Prior art keywords
steel
section steel
section
locking
rotating shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011394074.XA
Other languages
Chinese (zh)
Other versions
CN112663595B (en
Inventor
龚妍
范斌
王海俊
李耀良
钮文敖
丁东强
罗云峰
李吉勇
徐伟
高庆荣
朱德勇
顾蓓瑛
沈豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Foundation Engineering Group Co Ltd
Priority to CN202011394074.XA priority Critical patent/CN112663595B/en
Publication of CN112663595A publication Critical patent/CN112663595A/en
Application granted granted Critical
Publication of CN112663595B publication Critical patent/CN112663595B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to an adjusting and fixing device for a first-root locking-notch profile steel of an underground continuous steel wall, which comprises a rotating shaft fixing base, a rotating shaft, an inclined stay bar and a first-root profile steel special top segment, wherein the first-root locking-notch profile steel special top segment is fixedly connected to the top end of the first-root profile steel through a connecting plate and a bolt and is higher than the ground; the upper surface of the special top section of the first locking section steel is fixedly connected with a rotating shaft fixing base and a rotating shaft; an inclined stay bar is connected between the special top section for the first locking notch section steel and the guide wall, and the perpendicularity of the first section steel is adjusted and fixed through the special top section for the first locking notch section steel. By using the invention, the first section steel can be accurately aligned and fixed, a reliable reference is provided for subsequent construction, and the construction efficiency is improved.

Description

Adjusting and fixing device for first root locking section steel of underground continuous steel wall
Technical Field
The invention relates to a construction device for an underground continuous steel wall, in particular to an adjusting and fixing device for a first locking notch section steel of the underground continuous steel wall.
Background
In the inserting and placing process of the fore-shaft section steel of the underground continuous steel wall, the inserting and positioning and the vertical precision control of the fore-shaft section steel are very important, and the construction quality and the progress control of the whole project are influenced. Therefore, it is necessary to design an adjusting and fixing device for the first locking notch section steel when section steel is inserted in the underground continuous steel wall process.
Disclosure of Invention
The invention aims to provide an adjusting and fixing device for a first locking section steel of an underground continuous steel wall inserted section steel, which ensures the vertical inserting precision and firm fixation of the first section steel in the construction process of inserting the locking section steel of the underground continuous steel wall.
In order to achieve the above object, the present invention provides the following technical solutions:
a device for adjusting and fixing a first-root locking section steel of an underground continuous steel wall comprises a rotating shaft fixing base, a rotating shaft, an inclined stay bar and a first-root special section steel top segment, wherein the first-root special section steel top segment is fixedly connected to the top end of the first-root section steel through a connecting plate and a bolt and is higher than the ground; the upper surface of the special top section of the first locking section steel is fixedly connected with a rotating shaft fixing base and a rotating shaft; an inclined stay bar is connected between the special top section for the first locking notch section steel and the guide wall, and the perpendicularity of the first section steel is adjusted and fixed through the special top section for the first locking notch section steel.
Furthermore, the special top section for the first locked-notch profile steel is also provided with a temporary holding rod seat with adjustable height and a special catch wheel, so that the second profile steel can be conveniently inserted.
Furthermore, the length of the inclined stay bar is adjusted through a screw pair provided with left and right backward and forward screw teeth, a pair of rotating shaft seats is installed at the bottom, one end of each rotating shaft seat is welded with the stay bar, one end of each rotating shaft seat is fixed on the guide wall through a bar-planting screw and is connected with the pin shaft, and the top of each rotating shaft seat is connected with the top end of the top section special for the first locking notch section steel through a cross beam through a bolt.
Furthermore, when the section steel is inserted in place, the inclined stay bar is matched with the rotating shaft and the rotating shaft fixing base for use, and the section steel is straightened, so that the verticality of the first section steel is ensured.
Further, the pivot is installed in the mounting hole of reserving in the fore-root special locking section steel flange plate lower part of locking section steel flange section to it is fixed with shaped steel, pivot unable adjustment base passes through the pinhole position department of round pin axle suit at the pivot both ends.
Further, when the special top segment section of first root fore shaft shaped steel is inserted to first root shaped steel, behind the installation shaped steel connecting plate, wear to adorn the pivot on the pivot unable adjustment base, continue afterwards to insert shaped steel down and contact the guide wall to pivot unable adjustment base's bottom plate and end, it is fixed with pivot unable adjustment base's bottom plate with the planting muscle bolt.
Furthermore, the rotating shaft and the rotating shaft fixing base are matched with the inclined support rod for use, the posture of the section steel is adjusted, and the section steel is fixed on the guide wall after being straightened.
The invention has the beneficial effects that: in the inserting and placing process of the locking section steel of the underground continuous steel wall, the inserting and positioning and vertical precision control of the first locking section steel affect the construction quality and progress of the whole project. By using the invention, the first section steel can be accurately aligned and fixed, a reliable reference is provided for subsequent construction, and the construction efficiency is improved.
Drawings
FIG. 1 is a front sectional view of the first fore-lock section steel adjusting and fixing device of the present invention;
FIG. 2 is a left sectional view of the first fore-shaft section steel adjusting and fixing device of the invention;
FIG. 3 is a front view of the spindle and the spindle fixing base;
FIG. 4 is a left side view of FIG. 3;
FIG. 5 is a top view of FIG. 3;
in the figure: 1-a special top section for the first locking section steel, 2-a height-adjustable holding rod seat, 3-diagonal braces, 4-special catch wheels, 5-rotating shafts and 6-rotating shaft fixing bases.
Detailed Description
The present invention will be described in further detail with reference to the following examples. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1 to 5, the adjusting and fixing device for the first fore-lock section steel of the underground continuous steel wall of the invention comprises a special top section 1 for the first fore-lock section steel, a height-adjustable holding rod seat 2, an inclined stay bar 3, a special catch wheel 4, a rotating shaft 5, a rotating shaft fixing base 6 and the like.
The special top section 1 for the first locking notch section steel is connected to the top end of the first section steel through a connecting plate and a bolt, and the whole section is arranged on the ground; in addition, the upper end of the diagonal brace 3, the rotating shaft 5, the rotating shaft fixing base 6 and other parts of the first section steel adjusting and fixing device are all installed and fixed on the top of the first special locking section steel top segment 1, and the perpendicularity of the first section steel is adjusted and fixed through the first special locking section steel top segment 1.
The top section 1 special for the first locked-notch profile steel is also provided with a temporary laying rod seat 2 and a special catch wheel 4 with adjustable height for facilitating the insertion of the second profile steel.
The length of the inclined stay bar 3 is adjusted by a screw pair provided with left and right backward and forward screw threads, a pair of rotating shaft seats are arranged at the bottom of the inclined stay bar, one end of the inclined stay bar is welded with the stay bar, the other end of the inclined stay bar is fixed on a guide wall by a planting screw and is connected with a pin shaft, the top of the inclined stay bar is connected with the top end of a special top section 1 of the first lock-notch section steel by a bolt through a cross beam, and the section steel is matched with a rotating shaft 5 and a rotating shaft fixing base 6 for; and the requirements of the insertion construction process of the section steel and the fine adjustment of the first section steel during the moving process.
The rotating shaft 5 is arranged in a mounting hole reserved at the lower part of a locking section steel flange plate of the top section 1 special for the first locking section steel and can be fixed with the section steel, and the rotating shaft fixing base 6 is sleeved at pin holes at two ends of the rotating shaft through pin shafts; when the first section steel is inserted into the special top section 1 of the first locking notch section steel, after a section steel connecting plate is installed, a rotating shaft 5 penetrates through the body of the section steel connecting plate, a rotating shaft fixing base 6 is hung on the rotating shaft 5, then the section steel is continuously inserted downwards until a bottom plate of the rotating shaft fixing base 6 contacts a guide wall stop, and the bottom plate of the fixing base 6 is fixed by using a bar planting bolt; through using with the cooperation of diagonal brace, carry out the attitude adjustment to the shaped steel to this straightness that hangs down that guarantees first root shaped steel waits the shaped steel alignment back, and fixes it on leading the wall.
In summary, in the specific implementation of the invention, after the first section steel is straightened through the rotating shaft, the fixing base and the diagonal brace, the section steel is fixed on the guide wall through the welding piece, the embedded steel plate and the like, so that the vertical insertion accuracy and the firm fixation of the first section steel are ensured, and the construction efficiency is improved.

Claims (7)

1. The utility model provides an adjustment fixing device of underground continuous steel wall head root fore shaft shaped steel, includes pivot unable adjustment base, pivot, diagonal brace, the special top segment of head root shaped steel, its characterized in that: the special top section for the first locking notch section steel is fixedly connected to the top end of the first section steel through a connecting plate and a bolt and is higher than the ground; the upper surface of the special top section of the first locking section steel is fixedly connected with a rotating shaft fixing base and a rotating shaft; an inclined stay bar is connected between the special top section for the first locking notch section steel and the guide wall, and the perpendicularity of the first section steel is adjusted and fixed through the special top section for the first locking notch section steel.
2. The adjusting and fixing device for the first locking section steel of the underground continuous steel wall according to claim 1, is characterized in that: the special top section for the first locking notch section steel is also provided with a temporary laying rod seat with adjustable height and a special catch wheel, so that the second section steel can be conveniently inserted.
3. The adjusting and fixing device for the first locking section steel of the underground continuous steel wall according to claim 1, is characterized in that: the length of the inclined stay bar is adjusted through a screw pair provided with left and right backward and forward screw teeth, a pair of rotating shaft seats is arranged at the bottom of the inclined stay bar, one end of the inclined stay bar is welded with the stay bar, the other end of the inclined stay bar is fixed on the guide wall through a bar planting screw and is connected with a pin shaft, and the top of the inclined stay bar is connected with the top end of a top section special for the first lock-notch section steel through.
4. The adjusting and fixing device for the first locking section steel of the underground continuous steel wall according to claim 3, is characterized in that: when the section steel is inserted in place, the inclined stay bar is matched with the rotating shaft and the rotating shaft fixing base for use, and the section steel is straightened, so that the verticality of the first section steel is ensured.
5. The adjusting and fixing device for the first locking section steel of the underground continuous steel wall according to claim 1, is characterized in that: the pivot is installed in the mounting hole of reserving in the fore-root special locking section steel flange plate lower part of lock mouth shaped steel flange section to it is fixed with shaped steel, pivot unable adjustment base passes through the pinhole position department of round pin axle sleeve dress at the pivot both ends.
6. The adjusting and fixing device for the first locking section steel of the underground continuous steel wall according to claim 5, is characterized in that: when the special top segment section of first root fore shaft shaped steel is inserted to first root shaped steel, behind the installation shaped steel connecting plate, wear to adorn the pivot on the pivot unable adjustment base, continue to insert shaped steel down afterwards and touch the guide wall to pivot unable adjustment base's bottom plate and end, it is fixed with pivot unable adjustment base's bottom plate with the planting muscle bolt.
7. The adjusting and fixing device for the first locking section steel of the underground continuous steel wall according to claim 6, is characterized in that: the rotating shaft and the rotating shaft fixing base are matched with the inclined support rod for use, the posture of the section steel is adjusted, and the section steel is fixed on the guide wall after being straightened.
CN202011394074.XA 2020-12-03 2020-12-03 Adjusting and fixing device for first root locking section steel of underground continuous steel wall Active CN112663595B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011394074.XA CN112663595B (en) 2020-12-03 2020-12-03 Adjusting and fixing device for first root locking section steel of underground continuous steel wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011394074.XA CN112663595B (en) 2020-12-03 2020-12-03 Adjusting and fixing device for first root locking section steel of underground continuous steel wall

Publications (2)

Publication Number Publication Date
CN112663595A true CN112663595A (en) 2021-04-16
CN112663595B CN112663595B (en) 2022-05-20

Family

ID=75400917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011394074.XA Active CN112663595B (en) 2020-12-03 2020-12-03 Adjusting and fixing device for first root locking section steel of underground continuous steel wall

Country Status (1)

Country Link
CN (1) CN112663595B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756286A (en) * 2021-08-09 2021-12-07 上海市基础工程集团有限公司 Construction method for implementing underground water soil continuous steel wall by TRD method
CN113846624A (en) * 2021-08-09 2021-12-28 上海市基础工程集团有限公司 Construction method for implementing underground water-soil continuous steel wall by double-wheel slot milling machine

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321249A (en) * 1992-05-22 1993-12-07 Tokyu Constr Co Ltd Method for constructing underground continuous steel wall
US6171030B1 (en) * 1997-05-21 2001-01-09 Hitachi Construction Machinery Co., Ltd. Soil improving machine with excavating means
CN101619573A (en) * 2009-07-24 2010-01-06 徐州文鹏工程机械制造有限公司 Machine for forming underground continuous water-retaining walls by one step
JP2013249703A (en) * 2012-06-04 2013-12-12 Ohbayashi Corp Excavator for continuous underground wall
CN106703014A (en) * 2016-12-14 2017-05-24 上海市基础工程集团有限公司 Underground diaphragm wall pre-buried section steel column fixing and secondary rectifying device and method
WO2018119534A1 (en) * 2016-12-28 2018-07-05 Pontificia Universidad Católica De Chile Combination for anchoring to foundations and energy dissipator for vertical liquid-storage tanks, vertical pressure container, silo or the like with a thin wall and continuous support
CN209958365U (en) * 2019-04-15 2020-01-17 江苏鸿基节能新技术股份有限公司 Triaxial deep mixing pile interpolation tubular pile locator
CN111851468A (en) * 2020-07-28 2020-10-30 上海市基础工程集团有限公司 Underground water soil steel wall continuous inserting verticality control construction method
CN111874843A (en) * 2020-07-27 2020-11-03 山东大学 Segmented reinforcement cage guiding device and method suitable for low space

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321249A (en) * 1992-05-22 1993-12-07 Tokyu Constr Co Ltd Method for constructing underground continuous steel wall
US6171030B1 (en) * 1997-05-21 2001-01-09 Hitachi Construction Machinery Co., Ltd. Soil improving machine with excavating means
CN101619573A (en) * 2009-07-24 2010-01-06 徐州文鹏工程机械制造有限公司 Machine for forming underground continuous water-retaining walls by one step
JP2013249703A (en) * 2012-06-04 2013-12-12 Ohbayashi Corp Excavator for continuous underground wall
CN106703014A (en) * 2016-12-14 2017-05-24 上海市基础工程集团有限公司 Underground diaphragm wall pre-buried section steel column fixing and secondary rectifying device and method
WO2018119534A1 (en) * 2016-12-28 2018-07-05 Pontificia Universidad Católica De Chile Combination for anchoring to foundations and energy dissipator for vertical liquid-storage tanks, vertical pressure container, silo or the like with a thin wall and continuous support
CN209958365U (en) * 2019-04-15 2020-01-17 江苏鸿基节能新技术股份有限公司 Triaxial deep mixing pile interpolation tubular pile locator
CN111874843A (en) * 2020-07-27 2020-11-03 山东大学 Segmented reinforcement cage guiding device and method suitable for low space
CN111851468A (en) * 2020-07-28 2020-10-30 上海市基础工程集团有限公司 Underground water soil steel wall continuous inserting verticality control construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756286A (en) * 2021-08-09 2021-12-07 上海市基础工程集团有限公司 Construction method for implementing underground water soil continuous steel wall by TRD method
CN113846624A (en) * 2021-08-09 2021-12-28 上海市基础工程集团有限公司 Construction method for implementing underground water-soil continuous steel wall by double-wheel slot milling machine

Also Published As

Publication number Publication date
CN112663595B (en) 2022-05-20

Similar Documents

Publication Publication Date Title
CN112663595B (en) Adjusting and fixing device for first root locking section steel of underground continuous steel wall
CN210486720U (en) Measuring apparatu for construction
CN208518352U (en) A kind of positioning device for spatial three-dimensional fine adjusting
CN112211382A (en) Auxiliary construction equipment for fabricated building
CN112504062B (en) Device for measuring dislocation in and between rings of lining segment with high precision
CN215862692U (en) Adjustable land and soil space planning spirit level for topographic survey
CN214549772U (en) Carbon fiber traction frame suitable for femoral head and lower limb orthopedic surgery
CN209737590U (en) Co-location detector
CN214005423U (en) Bridge construction support bracket
DE3703949A1 (en) Articulator
CN216714316U (en) Angle adjusting frame for drilling equipment in slope anchor rod reinforcement
CN214093638U (en) Level gauge for engineering surveying and mapping technology
CN219444980U (en) Steel construction rag bolt mounting tool
CN215331506U (en) Novel formwork support device for building construction
CN211161689U (en) Convenient steel reinforcement cage making devices
CN216707307U (en) Positioning adjustment tool for assembling medium and large pipe bodies
CN107486513B (en) Steel bar straightening positioning machine
CN219348424U (en) Benchmark roof beam telescopic bracket for anchor rod anti-pulling test
CN217612692U (en) Altitude touch machine
CN218822398U (en) Building survey sighting rod
CN215261785U (en) External terrain measuring rod for land reclamation
CN212480568U (en) Total powerstation with leveling mechanism
CN215447934U (en) Measuring device for civil engineering
CN218064127U (en) Total powerstation scanner mount of survey and drawing usefulness
CN210908714U (en) Welding fixture for upper mounting plate assembly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant