CN112609586A - Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder - Google Patents

Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder Download PDF

Info

Publication number
CN112609586A
CN112609586A CN202011506889.2A CN202011506889A CN112609586A CN 112609586 A CN112609586 A CN 112609586A CN 202011506889 A CN202011506889 A CN 202011506889A CN 112609586 A CN112609586 A CN 112609586A
Authority
CN
China
Prior art keywords
tower
steel box
box girder
bridge
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011506889.2A
Other languages
Chinese (zh)
Other versions
CN112609586B (en
Inventor
李华龙
甄玉杰
代子洲
卢慧忠
罗国龙
刘国栋
郭弘鹏
李钰莹
徐盟
田龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN202011506889.2A priority Critical patent/CN112609586B/en
Publication of CN112609586A publication Critical patent/CN112609586A/en
Application granted granted Critical
Publication of CN112609586B publication Critical patent/CN112609586B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The invention discloses a synchronous construction method of a tower beam of a steel box girder self-anchoring suspension bridge, which is characterized in that the construction of a bridge tower and a main beam is synchronously carried out, and the method comprises the following steps of 1, erecting a steel trestle, and then constructing a foundation below the bridge tower, constructing side piers and steel box girder pushing temporary piers; step 2, assembling a steel box girder forming a main girder on the assembling platform, installing a pushing guide beam, and constructing a tower column under a bridge tower and a tower column cantilever beam; step 3, gradually performing steel box girder pushing construction in turns, and simultaneously performing bridge tower column and connecting beam construction; step 4, after the steel box girder is pushed in place, construction of the steel box girder embedding section is carried out in turns, and meanwhile, the bridge tower is continuously constructed until the construction is finished; and 5, constructing the main cable, the sling and the auxiliary facilities until the bridge construction is finished. The construction progress can be remarkably accelerated, so that the construction period is greatly shortened.

Description

Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder
Technical Field
The invention belongs to the technical field of bridge construction, and particularly relates to a synchronous construction method for a tower beam of a steel box beam self-anchoring suspension bridge.
Background
The suspension bridge is the bridge type structure with the largest spanning capability at present. The traditional ground anchor type suspension bridge generally needs to build a large-size anchor to anchor a main cable, and if the main cable is directly anchored on a stiffening beam in a proper mode, the expensive anchor can be cancelled, so that the traditional ground anchor type suspension bridge evolves into a self-anchored suspension bridge. The self-anchored suspension bridge cancels a huge main cable anchorage, not only can save the cost for constructing the anchorage, but also greatly reduces the requirement on geological conditions and effectively expands the application range of the suspension bridge.
The self-anchored suspension bridge is composed of a main beam, a bridge tower, a cable system and an anchoring system, wherein the main cable is anchored at two ends of the main beam, a sling is pulled, and the main beam is bent to form a self-balanced cable support structure system.
At present, for self-anchored suspension bridges, the traditional construction method is adopted for the construction methods of the bridge tower and the main beam, namely, the main beam is generally constructed firstly and then the bridge tower is constructed, or the bridge tower is constructed firstly and then the main beam is constructed, namely, the construction mode of firstly constructing the bridge tower and then constructing the main beam or firstly constructing the bridge tower and then constructing the bridge tower is adopted, so that the construction period of the bridge is long.
Disclosure of Invention
The invention aims to solve the technical problem of providing a synchronous construction method for a tower beam of a steel box girder self-anchoring suspension bridge, which can remarkably accelerate the construction progress and greatly shorten the construction period.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows:
a synchronous construction method for a tower beam of a steel box girder self-anchoring suspension bridge is characterized in that the construction of a bridge tower and a main beam is carried out synchronously, and comprises the following steps:
step 1, erecting a steel trestle, and then constructing a foundation below a bridge tower, constructing side piers and pushing temporary piers by a steel box girder;
step 2, assembling the steel box girder forming the main girder on an assembling platform formed by pushing the temporary piers by the steel box girder, installing a pushing guide beam, and constructing a tower column under the bridge tower and a tower column cantilever beam;
step 3, gradually performing steel box girder pushing construction in turns, and simultaneously performing bridge tower columns and connecting beams between the tower columns;
step 4, after the steel box girder is pushed in place, construction of the steel box girder embedding section is carried out in turns, and meanwhile, the bridge tower is continuously constructed until the construction is finished;
and 5, constructing the main cable, the sling and the auxiliary facilities until the bridge construction is finished.
In the above technical scheme, in the step 2, the whole steel box girder is divided into two independent steel box girders which are symmetrical along the longitudinal center line of the bridge and assembled, a gap of the steel box girder embedding section is reserved between the two steel box girders, and the width of the steel box girder embedding section is slightly larger than the transverse width of the bridge tower.
In the above technical scheme, in the step 3, a walking type pushing device is adopted for pushing the steel box girder, and the walking type pushing device has the adjusting capability in three directions of vertical, horizontal and horizontal pushing.
In the technical scheme, in the step 3, the bridge tower is formed by butt joint of a plurality of bridge tower sections which are connected end to end in the vertical direction, and the plurality of bridge tower sections are lifted to a designed position by utilizing a tower crane from a gap reserved in the middle of the framing steel box girder.
In the above technical scheme, in the step 3, the same bridge tower is composed of a front bridge tower column and a rear bridge tower column which are symmetrically arranged along a vertical center line, and a connecting beam is arranged between the front bridge tower column and the rear bridge tower column.
In the above technical scheme, in the step 3, the front and rear bridge tower columns are both composed of bridge tower segments; and each bridge tower segment and the connecting cross beam are lifted to a designed position by utilizing a clearance reserved in the middle of the framing steel box girder of the tower crane to be installed.
In the above technical solution, in the step 3, a plurality of connecting beams are arranged at intervals between the front and rear two bridge towers along the vertical direction.
In the above technical scheme, in step 3, the front and rear two bridge towers are arc-shaped columns with the middle parts expanded outwards and the tops contracted outwards, a plurality of connecting beams are arranged between the two arc-shaped columns, and the length of the connecting beam from the middle part to the bottom and the length of the beam from the middle part to the top are both progressively reduced.
In the above technical scheme, in the step 3, a plurality of pylons distributed along the main beam are constructed simultaneously.
In the technical scheme, in the step 4, after the steel box girder is pushed in place, the tower crane is used for assisting with an automobile crane and a flat car to carry out the construction of the steel box girder embedding section.
Therefore, the invention discloses a synchronous construction method for a steel box girder self-anchoring suspension bridge tower girder, which has the following beneficial effects compared with the prior art: because the bridge tower and the main beam are constructed synchronously, the limitation of the traditional construction method of firstly constructing the beam and then constructing the tower or firstly constructing the tower and then constructing the beam is effectively solved, the construction progress is obviously accelerated, and the construction period is greatly shortened.
Drawings
The synchronous construction method of the steel box girder self-anchoring suspension bridge tower girder implemented according to the invention comprises the following six figures.
FIG. 1 is a schematic diagram of step 1 of the synchronous construction method of the steel box girder self-anchoring suspension bridge tower girder;
FIG. 2 is a schematic diagram of step 2 of the synchronous construction method of the steel box girder self-anchoring suspension bridge tower girder of the invention.
FIG. 3 is a schematic diagram of step 3 of the synchronous construction method of the steel box girder self-anchoring suspension bridge tower girder of the invention.
FIG. 4 is a schematic diagram of step 4 of the synchronous construction method of the steel box girder self-anchoring suspension bridge tower girder of the invention.
FIG. 5 is a schematic diagram of step 5 of the synchronous construction method of the steel box girder self-anchoring suspension bridge tower girder of the invention.
FIG. 6 is a schematic view showing the transverse position relationship between the bridge tower and the main beam in the method for the synchronous construction of the steel box girder self-anchoring suspension bridge tower beam.
The reference numbers correspond to the description: 1. a main beam; 11. framing the steel box girder; 12. a steel box girder embedding section; 13. a steel guide beam; 21. side piers; 22. temporarily upsetting; 3. a bridge tower; 31. a tower column cantilever beam; 5. tower crane; 6. a main cable; 7. a sling.
Detailed Description
The present description will be further explained with reference to the drawings and examples.
The synchronous construction method of the tower beam of the steel box beam self-anchoring suspension bridge comprises the following steps.
Step 1: referring to fig. 1, firstly, a steel trestle is erected, and a foundation at the bottom of a bridge tower 3, a construction side pier 21 and a steel box girder pushing temporary pier 22 are constructed through the steel trestle;
step 2: referring to fig. 2 and 6, the framing steel box girder 11 is assembled on an assembling platform formed by a plurality of steel box girder pushing temporary piers 22, a pushing steel guide beam 13 is installed, and a lower tower column and a tower column cantilever beam 31 of the bridge tower 3 are constructed at the same time; the tower column cantilever beam 31 is arranged below the main beam 1; the main beam 1 is divided into a left independent steel box girder and a right independent steel box girder 11 which are symmetrical along the longitudinal central line of the bridge to be assembled, and the width of a steel box girder embedding section 12 reserved in the middle of the two steel box girders 11 is slightly larger than the transverse width of the bridge tower;
and step 3: referring to fig. 3, the incremental launching construction of the steel box girder 11 is performed step by step in turns, and two bridge towers 3 are simultaneously performed (including the tower column sections of the bridge towers 3 and the construction of the connecting beams between the tower column sections (the connecting beams are arranged between two adjacent tower columns of the same bridge tower along the front-back direction)); the steel box girder pushing is performed from one side in the direction of the starting point of the bridge under the influence of external environmental factors on the end point side of the pushing direction; the steel box girder pushing adopts walking type pushing, and the pushing equipment has the adjusting capability in three directions of vertical, horizontal and horizontal pushing; the steel box girder pushing turns are divided into four turns to carry out pushing construction by taking two banks and a main span as boundaries; the tower 3 tower column segment and the connecting cross beam are lifted to a designed position from the middle gap of the framing steel box girder 11 by using a tower crane 5 for installation; in the step 3, the bridge tower is a steel tower, and the bridge tower sections and the connecting beams are all steel structural members.
And 4, step 4: referring to fig. 4 and 6, after the framing steel box girder 11 is pushed to the right position, the construction of the steel box girder embedding section 12 is carried out in turns, and meanwhile, the remaining sections and the beams of the bridge tower 3 are continuously constructed until the construction is finished; after the framing steel box girder 11 is pushed in place, constructing a steel box girder embedding section 12 by using a tower crane 5 and assisting a truck crane and a flat car until the construction of the main girder 1 is finished;
and 5: referring to fig. 5, in the construction of the main cable 6 and the sling 7 and the construction of the auxiliary facilities, the high point of the main cable 6 is anchored on the bridge tower 3, the low point is anchored on the main beam along the sling 7, and the midspan between the high point and the low point is not anchored but is connected with the sling 7; and constructing the auxiliary facilities until the bridge construction is finished.
It should be noted that the above description is only used for illustrating some principles of the method for synchronously constructing the tower beam of the steel box girder self-anchoring suspension bridge according to the present invention, and since it is obvious to those skilled in the art that several modifications and changes can be easily made on the basis of the above principles. Therefore, the present disclosure is not intended to limit the invention to the exact construction and operation shown and described, and all such modifications, equivalents, improvements, and equivalents may be resorted to, falling within the scope of the invention.

Claims (10)

1. A synchronous construction method for a tower beam of a steel box girder self-anchoring suspension bridge is characterized in that the construction of a bridge tower and a main beam is carried out synchronously, and comprises the following steps:
step 1, erecting a steel trestle, and then constructing a foundation below a bridge tower, constructing side piers and pushing temporary piers by a steel box girder;
step 2, assembling the steel box girder forming the main girder on an assembling platform formed by pushing the temporary piers by the steel box girder, installing a pushing guide beam, and constructing a tower column under the bridge tower and a tower column cantilever beam;
step 3, gradually performing steel box girder pushing construction in turns, and simultaneously performing bridge tower columns and cross beams between the tower columns;
step 4, after the steel box girder is pushed in place, construction of the steel box girder embedding section is carried out in turns, and meanwhile, the bridge tower is continuously constructed until the construction is finished;
and 5, constructing the main cable, the sling and the auxiliary facilities until the bridge construction is finished.
2. The synchronous construction method of the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, wherein in the step 2, the whole steel box girder is divided into two independent steel box girders in different widths which are symmetrical along the longitudinal center line of the bridge and assembled, a gap of the steel box girder embedding section is reserved between the two steel box girders in different widths, and the width of the steel box girder embedding section is slightly larger than the transverse width of the bridge tower.
3. The method for synchronously constructing the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, wherein in the step 3, a walking thruster is adopted for steel box girder thrusting, and the walking thruster has the capability of adjusting in three directions of vertical, horizontal and horizontal thrusting.
4. The synchronous construction method of the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, wherein in the step 3, the bridge tower is formed by butt-jointing a plurality of bridge tower segments which are connected end to end in the vertical direction, and the bridge tower segments are lifted to a designed position from a gap reserved in the middle of the framing steel box girder by a tower crane for installation.
5. The method for synchronously constructing the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, wherein in the step 3, the same bridge tower is composed of a front bridge tower column and a rear bridge tower column which are symmetrically arranged along a vertical center line, and a connecting beam is arranged between the front bridge tower column and the rear bridge tower column.
6. The synchronous construction method of the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, wherein in the step 3, the front and rear bridge tower columns are both composed of bridge tower segments; and each bridge tower segment and the connecting cross beam are lifted to a designed position by utilizing a clearance reserved in the middle of the framing steel box girder of the tower crane to be installed.
7. The method for synchronously constructing the tower beam of the steel box girder self-anchoring suspension bridge according to claim 5 or 6, wherein in the step 3, a plurality of connecting cross beams are arranged between the front and rear two bridge towers at intervals along the vertical direction.
8. The method for synchronously constructing the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, 5 or 6, wherein in the step 3, the front and the rear bridge towers are arc-shaped columns with expanded middle parts and contracted bottoms, a plurality of connecting cross beams are arranged between the two arc-shaped columns, and the length of the connecting cross beam from the middle part to the bottom and the length of the cross beam from the middle part to the top are both gradually reduced.
9. The method for synchronously constructing the tower beam of the steel box girder self-anchoring suspension bridge according to claim 1, wherein in the step 3, a plurality of bridge towers distributed along the main beam are constructed simultaneously.
10. The synchronous construction method of the tower beam of the steel box beam self-anchoring suspension bridge according to claim 1, wherein in the step 4, after the steel box beam is pushed in place, a tower crane is used to assist an automobile crane and a flat car to carry out construction of the steel box beam embedding section.
CN202011506889.2A 2020-12-18 2020-12-18 Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder Active CN112609586B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011506889.2A CN112609586B (en) 2020-12-18 2020-12-18 Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011506889.2A CN112609586B (en) 2020-12-18 2020-12-18 Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder

Publications (2)

Publication Number Publication Date
CN112609586A true CN112609586A (en) 2021-04-06
CN112609586B CN112609586B (en) 2021-12-14

Family

ID=75240587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011506889.2A Active CN112609586B (en) 2020-12-18 2020-12-18 Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder

Country Status (1)

Country Link
CN (1) CN112609586B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959919A (en) * 1995-08-21 1997-03-04 Fujisen Kyoryo Doboku Kk Floor slab edge cutting device and floor slab edge cutting method
JP2000008326A (en) * 1998-06-22 2000-01-11 Nkk Corp Bridge girder structure
CN101215819A (en) * 2007-12-27 2008-07-09 上海市政工程设计研究总院 Separated double-layer bridge-floor cable stayed bridge
KR20100109654A (en) * 2009-04-01 2010-10-11 (주)에스앤씨산업 Prestressed concrete girder with plural steel wires disposed at shear surface of tension port, manufacturing method thereof, and assembling bridge construction method using the same
CN102477717A (en) * 2010-11-30 2012-05-30 上海市政工程设计研究总院 Bridge pushing construction method
CN103233427A (en) * 2013-04-27 2013-08-07 长沙理工大学 Sling tensioning and system conversion method for double-tower three-span plane main cable self-anchorage type suspension bridge
CN105568866A (en) * 2015-12-31 2016-05-11 中铁二十局集团第六工程有限公司 Incremental launching construction method for large-span steel box girder spanning constructed road
CN106284074A (en) * 2016-08-30 2017-01-04 中铁大桥勘测设计院集团有限公司 A kind of multiaspect pressure-bearing resistance to plucking combination power transmission main push-towing rope anchor structure and construction method thereof
JP6560774B1 (en) * 2018-02-23 2019-08-14 第一建設工業株式会社 Scaffolding construction method
CN210086024U (en) * 2019-04-16 2020-02-18 安徽省交通规划设计研究总院股份有限公司 Marine large-span ground anchor type suspension cable stayed cooperative system bridge structure
CN211256692U (en) * 2019-11-06 2020-08-14 郑州市市政工程总公司 Transport beam structure of newly-built upper bridge on current bridge

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959919A (en) * 1995-08-21 1997-03-04 Fujisen Kyoryo Doboku Kk Floor slab edge cutting device and floor slab edge cutting method
JP2000008326A (en) * 1998-06-22 2000-01-11 Nkk Corp Bridge girder structure
CN101215819A (en) * 2007-12-27 2008-07-09 上海市政工程设计研究总院 Separated double-layer bridge-floor cable stayed bridge
KR20100109654A (en) * 2009-04-01 2010-10-11 (주)에스앤씨산업 Prestressed concrete girder with plural steel wires disposed at shear surface of tension port, manufacturing method thereof, and assembling bridge construction method using the same
CN102477717A (en) * 2010-11-30 2012-05-30 上海市政工程设计研究总院 Bridge pushing construction method
CN103233427A (en) * 2013-04-27 2013-08-07 长沙理工大学 Sling tensioning and system conversion method for double-tower three-span plane main cable self-anchorage type suspension bridge
CN105568866A (en) * 2015-12-31 2016-05-11 中铁二十局集团第六工程有限公司 Incremental launching construction method for large-span steel box girder spanning constructed road
CN106284074A (en) * 2016-08-30 2017-01-04 中铁大桥勘测设计院集团有限公司 A kind of multiaspect pressure-bearing resistance to plucking combination power transmission main push-towing rope anchor structure and construction method thereof
JP6560774B1 (en) * 2018-02-23 2019-08-14 第一建設工業株式会社 Scaffolding construction method
CN210086024U (en) * 2019-04-16 2020-02-18 安徽省交通规划设计研究总院股份有限公司 Marine large-span ground anchor type suspension cable stayed cooperative system bridge structure
CN211256692U (en) * 2019-11-06 2020-08-14 郑州市市政工程总公司 Transport beam structure of newly-built upper bridge on current bridge

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邓安泰等: "洪都大桥主桥设计", 《城市道桥与防洪》 *

Also Published As

Publication number Publication date
CN112609586B (en) 2021-12-14

Similar Documents

Publication Publication Date Title
CN109235285B (en) Cantilever pouring system and construction method for reinforced concrete arch bridge of large-span railway
CN102121234B (en) Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN110093865B (en) Bridge erecting machine
CN109736206B (en) Cast-in-situ bracket structure for bridge side span closure of corrugated steel web continuous beam and construction method
CN105648924A (en) Construction method of multi-span simply-supported steel truss girder bridge
CN112342917A (en) Combined construction method for pushing beam first and then lifting arch of large-span tied arch bridge
CN112227206A (en) Process design and construction method for ground anchor to self-anchored beam
CN110820582A (en) Method for erecting steel truss girder of cable-stayed bridge
CN104805769B (en) A kind of self-balancing arc beam cast-in-place support and construction method thereof
CN110093862A (en) Vertically and horizontally assembled three working face Bridge Erectors and bent cap can be achieved without sidewalk section assembling engineering method
CN111395186B (en) Method for erecting temporary pier of large-span steel-concrete composite beam cable-stayed bridge
CN103806374B (en) The overall track erection supplying system of assembly type steel bridge on highway and erection push technique
CN112681135A (en) Construction method of n-shaped sea-crossing temporary steel trestle
CN112609586B (en) Synchronous construction method for steel box girder self-anchoring suspension bridge tower girder
CN210315233U (en) Double-working-face integrated bridge girder erection machine without front supporting legs
CN112376440A (en) Construction process for non-closure hoisting of main beam of cable-stayed bridge
CN112160246A (en) Method for mounting combined beam
CN112962455B (en) Cable-first-beam-second segment hoisting self-anchored suspension bridge construction method
CN105696470A (en) Synchronous quick steel box girder in-situ incremental launching and tower column construction method
CN215925692U (en) Overlength multispan assembly type integrated multifunctional bridge girder erection machine
CN214328478U (en) Three-tower self-anchored suspension bridge
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN212561103U (en) Super large span cable-stayed bridge with thrust pier
CN114837059A (en) Mountain rock anchor cable-stayed flexible arch cooperation system bridge and construction method thereof
CN112609578B (en) Method for mounting steel truss girder at top section of bridge pier of cable-stayed bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant