CN112558908B - Comprehensive information presentation system for coal mine - Google Patents
Comprehensive information presentation system for coal mine Download PDFInfo
- Publication number
- CN112558908B CN112558908B CN202011459911.2A CN202011459911A CN112558908B CN 112558908 B CN112558908 B CN 112558908B CN 202011459911 A CN202011459911 A CN 202011459911A CN 112558908 B CN112558908 B CN 112558908B
- Authority
- CN
- China
- Prior art keywords
- display
- data
- coal mine
- display window
- displaying
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000003245 coal Substances 0.000 title claims abstract description 73
- 230000006855 networking Effects 0.000 claims abstract description 12
- 230000005540 biological transmission Effects 0.000 claims abstract description 10
- 238000012545 processing Methods 0.000 claims description 26
- 238000012795 verification Methods 0.000 claims description 24
- 238000004519 manufacturing process Methods 0.000 claims description 14
- 238000012544 monitoring process Methods 0.000 claims description 6
- 238000003860 storage Methods 0.000 claims description 6
- 238000004140 cleaning Methods 0.000 claims description 5
- 239000013589 supplement Substances 0.000 claims description 4
- 238000011835 investigation Methods 0.000 claims description 3
- 230000008447 perception Effects 0.000 claims description 3
- 230000008054 signal transmission Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 5
- 239000000284 extract Substances 0.000 abstract description 2
- 238000007726 management method Methods 0.000 description 13
- 238000010586 diagram Methods 0.000 description 3
- 230000001360 synchronised effect Effects 0.000 description 3
- 238000012549 training Methods 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000013468 resource allocation Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F3/00—Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
- G06F3/14—Digital output to display device ; Cooperation and interconnection of the display device with other functional units
- G06F3/1454—Digital output to display device ; Cooperation and interconnection of the display device with other functional units involving copying of the display data of a local workstation or window to a remote workstation or window so that an actual copy of the data is displayed simultaneously on two or more displays, e.g. teledisplay
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/02—Agriculture; Fishing; Forestry; Mining
Landscapes
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Mining & Mineral Resources (AREA)
- General Health & Medical Sciences (AREA)
- Agronomy & Crop Science (AREA)
- Animal Husbandry (AREA)
- Marine Sciences & Fisheries (AREA)
- General Engineering & Computer Science (AREA)
- Human Computer Interaction (AREA)
- Health & Medical Sciences (AREA)
- Economics (AREA)
- Life Sciences & Earth Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention relates to the technical field of coal mine information, in particular to a comprehensive information display system for a coal mine. The coal mine comprehensive information presentation system provided by the invention consists of software and hardware, wherein the software comprises a data linkage server side and a comprehensive information presentation system; the hardware comprises a control computer, a transmission cable, an LED display screen and a sound. The system cleans, extracts and edits networking data of a coal mine underground operator management system according to related industry specifications and standards by combining a service program with a method for displaying an LED display screen. The name of the leading person with duty, the name of the leading person on duty, the name of the underground operator, the operation position of the underground operator and the department are displayed through an LED screen. Text, tables, databases, images, video, audio, etc. may be displayed simultaneously. The comprehensive display and release of various information of coal mine enterprises at the wellhead are realized.
Description
Technical Field
The invention relates to the technical field of coal mine information, in particular to a method for cleaning, extracting and editing networking data of a coal mine underground operation personnel management system by executing a service program. And the comprehensive information display system is used for displaying the pilot with the shift, the operation position of underground operators and departments to which the underground operators belong at the well head of the coal mine in real time and simultaneously playing the multimedia information content.
Background
The coal industry is one of main industries in the development of energy sources in China. The effective informationized construction is an advantageous change of a coal mine industry hysteresis management method, the perfect informationized construction can protect the driving of coal mine safety production, the circulation and sharing of basic information can more reasonably achieve resource allocation, the cost is saved, and the management efficiency and management level of coal mine enterprises are effectively improved.
At present, basic information of coal mine enterprises is basically disclosed by a billboard or an advertising lamp box, and the disclosed content is single. Audio, video-like content cannot even be realized. According to the document spirit of the national institute notification about further strengthening the enterprise safety production work and the national safety production supervision bureau of the 33 th code of the colliery leader with work and the safety supervision check rule, when a coal mine leader is required to go into the well, its leader name should be shown at a well head apparent location. For a long time, national coal mine enterprises rely on technological progress, attach importance to safety ideological education, strengthen safety technical training and develop various forms of safety propaganda by adhering to the policy of 'safety first, forensic' so as to greatly promote improvement of national coal mine safety production conditions. From the aspect of enterprise management, how to comprehensively display contents such as safety training texts, safety education videos, accident case pictures, lead with duty, real-time information of underground operators and the like at a wellhead is an important problem at present.
Disclosure of Invention
The invention provides a coal mine comprehensive information display system aiming at the problems. The system cleans, extracts and edits networking data of a coal mine underground operator management system according to related industry specifications and standards by combining a service program with a method for displaying an LED display screen. The name of the leading person with duty, the name of the leading person on duty, the name of the underground operator, the operation position of the underground operator and the department are displayed through an LED screen. Text, tables, databases, images, video, audio, etc. may be displayed simultaneously. The comprehensive display and release of various information of coal mine enterprises at the wellhead are realized.
In order to achieve the above purpose, the present invention adopts the following technical scheme:
the invention provides a comprehensive information presentation system for a coal mine, which consists of software and hardware, wherein the software comprises a data linkage server and a comprehensive information presentation system; the hardware comprises a control computer, a transmission cable, an LED display screen and a sound box, and the comprehensive information display system and the data linkage server are flexibly arranged on the control computer.
Further, the data linkage server of the software includes: the system comprises an electronic screen configuration module, a global configuration module, a system authentication module, an area configuration module and a data processing module; the comprehensive information display system of the software comprises a main interface window and a preview window; the LED display screen of the hardware consists of a display unit, a power supply module, a sending card and a receiving card; the sound equipment of the hardware is connected with the control computer through the transmission cable, and the sound is synchronously played.
Further, the electronic screen configuration module of the data linkage server is associated with the comprehensive information presentation system and is used for controlling the starting of the comprehensive information presentation system; the comprehensive information display system is used for controlling the LED screen and editing display contents; the global configuration module of the data linkage server comprises: a basic information configuration item, a data protocol selection item, a default information supplement item and a source data backup item; the system authentication module of the data linkage server is used for registering the data linkage server and authorizing execution of service program operation; the region configuration module of the data linkage service end is used for selecting region display items and department display items; the data processing module of the data linkage server comprises: a data processing service start item and a data processing service stop item; the basic information configuration item is used for setting coal mine codes, approved productivity, approved people who go into the well and duty leaders; the data protocol selection item is used for selecting a protocol or a standard of processed data; the default information supplementary items are used for setting work types or job identification fields defined by coal mine enterprises by themselves except for specifications or standards; the source data backup item comprises a source catalog and a backup catalog; the source directory is used for selecting a storage path of the processed data, the backup directory is used for selecting a storage path when the source data is backed up, and the source directory can be empty, i.e. the backup path can not be selected when the data has no other use requirements.
Furthermore, the coal mine code of the basic information configuration item is used for setting the coal mine enterprise identification code, and is also a unique identification code for judging the enterprise when the system is authenticated; the verification productivity is used for setting approved annual production capacity of coal mine enterprises, storing the annual production capacity in a static2 text under a default path, and displaying the verification productivity; the number of the authorized personnel in the well is set, stored in a static2 text under a default path, and used for showing the number of the authorized personnel in the well; the duty leader is used for setting the ground duty leader of the same day, storing the stored ground duty leader into a static1 text under a default path, and displaying the duty leader of the same day.
The content in the default path display text can also be directly written into the text by the underground coal mine operator management system.
The area display item of the area configuration module is used for selecting the number of people in the display area and the number of people in the display area, and when the number of people in the display area is selected, the display window of the underground operation personnel displays the total number of people in each area at present; when the personnel in the display area are selected, the underground operator display window displays the names of all personnel in each current area; the department display items of the area configuration module are used for selecting and displaying the number of departments and displaying personnel of the departments, and when the number of the departments is selected and displayed, the display window of the underground operation personnel displays the total number of people in the well according to the departments; when the personnel of the department are selected to be displayed, the underground operation personnel display window displays names of all personnel in the well according to the departments.
The data processing service starting item of the data processing module is used for starting an execution service program, cleaning, extracting and editing data in a source directory, writing the data into a display text under a default path, automatically updating text content in real time and displaying current guidance of a well-logging operator and information of the well-logging operator; the data processing service stop item of the data processing module is used for stopping executing the service program and stopping processing the data in the source directory.
The main interface window of the comprehensive information presentation system comprises: the file menu, the control screen menu, the play menu, the setting menu, the debugging menu and the group help menu are used for editing the displayed content; the preview window of the comprehensive information presentation system includes: the system comprises an enterprise/unit name display window, an on-duty/off-duty leading display window, a verification capacity/number of people in the well, a weather condition display window, a clock display window, a database/table/multimedia information display window and an underground operator display window, wherein the enterprise/unit name display window, the on-duty/off-duty leading display window, the verification capacity/number of people in the well, the weather condition display window, the clock display window, the database/table/multimedia information display window and the underground operator display window are used for previewing and adjusting each display window at a control end and synchronously displaying with an LED screen at a well mouth.
Further, the enterprise/unit name display window of the preview window is used for editing and previewing and displaying enterprise/unit names and synchronously displaying the enterprise/unit names and the LED screen; the duty/duty leading display window of the preview window is used for reading static1 and display text content and synchronously displaying the text content and the LED screen; the verification capacity/number of people in the well is displayed in the preview window, and the verification capacity/number of people in the well is used for reading static2 text content and synchronously displaying the text content and the LED screen; the weather condition display window of the preview window is used for displaying weather condition contents and synchronously displaying the weather condition contents and the LED screen; the clock display window of the preview window is used for displaying date and time and synchronously displaying the date and time and the LED screen; the database/table/multimedia information display window of the preview window is used for displaying multimedia contents such as database/table/text/picture/video and the like and synchronously displaying the multimedia contents with the LED screen; and the underground operator display window of the preview window is used for reading the display text content and synchronously displaying the display text content and the LED screen, and displaying the information of the underground operator in real time.
Furthermore, the on-duty/off-duty leading display window of the preview window can also directly read a database table of a coal mine underground operator management system and synchronously display the database table and the LED screen; the underground operator display window of the preview window can also directly read a database table of an underground operator management system of the coal mine, synchronously display the database table and the LED screen, and display the information of the underground operator in real time.
The processed data of the data protocol options are networking data of a coal mine underground operation personnel management system; the protocol or standard of the processed data is "technical standard for data acquisition of coal mine safety supervision law enforcement and decision-making system in Shanxi province", networking data standard DB14/T671.1-2012 for underground worker management of coal mine safety supervision law enforcement and decision-making support system ", general technical requirement and data acquisition standard of online monitoring and networking investigation system for coal mine safety production", coal mine safety monitoring, underground worker and industrial video perception data access rule.
The receiving card of the LED display screen is connected with the display unit through a signal transmission line, receives data from the receiving card and controls the display unit to display; the power supply module is connected with the display unit and the receiving card through a power line and supplies power for the display unit and the receiving card; the transmitting card is arranged on the control computer and is connected with the receiving card through a transmission cable.
Compared with the prior art, the invention has the following advantages:
by adopting the method of displaying by the LED display screen and combining with matched equipment such as sound equipment, the underground coal mine worker can deeply absorb the pain teaching and training of various safety accidents by playing the coal mine safety accident case pictures and videos, thereby being beneficial to improving the responsibility, the mission feeling and the sense of urgency of the safety production of the coal mine worker. The system has an effective warning effect on the lucky mind of part of illegal operators, thereby forming a safe first and foremost operation habit on the consciousness of each employee. By playing the video and audio of the related standard operation under the well, each worker under the well is influenced by the eye dying. The display of audio, image, video and weather content combines with flexible editable window, which is a diversified upgrade for various information of coal mine.
Drawings
FIG. 1 is a schematic diagram of a coal mine comprehensive information presentation system of the present invention.
FIG. 2 is a layout diagram of a preview window of the coal mine comprehensive information display system, wherein 1-7 represent an enterprise/unit name display window, an on-duty/off-duty lead display window, a verification capacity/number of people going into the well display window, a weather condition display window, a clock display window, a database/table/multimedia information display window and a downhole operator display window in sequence.
FIG. 3 is a schematic diagram of the operation of the coal mine comprehensive information presentation system of the present invention.
FIG. 4 is a schematic representation of an electronic screen of the present invention.
Detailed Description
In order to make the objects and technical solutions of the present invention more apparent, the present invention will be further described in detail with reference to the accompanying drawings and examples. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the invention.
Example 1
Coal mine comprehensive information presentation system (fig. 1):
the system consists of software and hardware, wherein the software comprises a data linkage server and a comprehensive information presentation system; the hardware comprises a control computer, a transmission cable, an LED display screen and a sound box, and the comprehensive information display system and the data linkage server are flexibly arranged on the control computer.
The data linkage server comprises: the system comprises an electronic screen configuration module, a global configuration module, a system authentication module, an area configuration module and a data processing module. Wherein:
the electronic screen configuration module is associated with the comprehensive information display system and is used for controlling the starting of the comprehensive information display system, controlling the LED screen and editing display contents.
The global configuration module comprises: basic information configuration items, data protocol selection items, default information supplement items, and source data backup. Wherein,
the basic information configuration item is used for setting coal mine codes, approved productivity, approved underground people and duty leaders. The coal mine code is used for setting a coal mine enterprise identification code and is also a unique identification code for judging the enterprise when the system is authenticated; the verification productivity is used for setting approved annual production capacity of coal mine enterprises, storing the annual production capacity in a static2 text under a default path, and displaying the verification productivity; the number of the authorized personnel in the well is set, stored in a static2 text under a default path, and used for showing the number of the authorized personnel in the well; the duty leader is used for setting the ground duty leader of the same day, storing the stored ground duty leader into a static1 text under a default path, and displaying the duty leader of the same day.
The data protocol selection item is used for selecting a protocol or a standard of processed data; the default information supplement is used to set up job types or job identification fields defined by the coal mine enterprise by itself, except for the specification or standard protocol. The processed data are networking data of a coal mine underground operator management system; the protocol or standard of the processed data is "technical standard for data acquisition of coal mine safety supervision law enforcement and decision-making system in Shanxi province", networking data standard DB14/T671.1-2012 for underground worker management of coal mine safety supervision law enforcement and decision-making support system ", general technical requirement and data acquisition standard of online monitoring and networking investigation system for coal mine safety production", coal mine safety monitoring, underground worker and industrial video perception data access rule.
The source data backup entry contains a source directory and a backup directory. The source directory is used for selecting a storage path of the processed data; the backup catalog is used for selecting a storage path when the source data is backed up, and the item can be empty, namely the backup path can not be selected when the data has no other use requirement.
The system authentication module is used for registering the data linkage server and authorizing the execution of the service program operation.
The region configuration module is used for selecting a region display item and a department display item. The area display item is used for selecting the number of people in the display area and the number of people in the display area, and when the number of people in the display area is selected, the display window of the underground operator displays the total number of people in each area; when the personnel in the display area are selected, the underground operator display window displays the names of all personnel in each current area; the department display item is used for selecting and displaying the number of departments and the personnel of the departments, and when the number of the departments is selected and displayed, the display window of the underground operation personnel displays the total number of people in the well according to the departments; when the personnel of the department are selected to be displayed, the underground operation personnel display window displays names of all personnel in the well according to the departments.
The data processing module comprises: a data processing service start item and a data processing service stop item. The data processing service starting item is used for starting an execution service program, cleaning, extracting and editing data in a source directory, writing the data into a display text under a default path, automatically updating text content in real time and displaying the current pilot and the information of a worker going to the well; the data processing service stop item is used for stopping execution of the service program and terminating processing of the data in the source directory.
The integrated information presentation system includes a main interface window and a preview window. Wherein:
the main interface window includes: the file menu, the control screen menu, the play menu, the setting menu, the debugging menu and the group help menu are used for editing the displayed content;
the preview window includes: the system comprises an enterprise/unit name display window, an on-duty/off-duty leading display window, a verification capacity/number of people in the well, a weather condition display window, a clock display window, a database/table/multimedia information display window and a downhole operator display window, and is used for previewing and adjusting each display window at a control end and synchronously displaying with a wellhead LED screen (figure 2). The enterprise/unit name display window is used for editing and previewing and displaying enterprise/unit names; the duty/duty leading display window is used for reading the text content of static1 and display, and synchronizing the LED screen to display the current duty and duty leading; the verification productivity/well-logging people display window is used for reading static2 text content and synchronously displaying verification productivity and verification well-logging people on the LED screen; the weather condition display window is used for displaying weather condition content and synchronously displaying the weather condition content and the LED screen, and is suspended above the database/table/multimedia information display window and displayed transparently; the clock display window is used for displaying date and time and is synchronous with the LED screen, and the clock display window is suspended above the database/table/multimedia information display window and is displayed transparently; the database/table/multimedia information display window is used for displaying multimedia contents such as database/table/text/picture/video; the underground operator display window is used for reading display text content and synchronizing with the LED screen, and displaying underground operator information in real time.
The LED display screen consists of a display unit, a power supply module, a sending card and a receiving card; the sound equipment is connected with the control computer through the transmission cable, and the sound is synchronously played. The receiving card of the LED display screen is connected with the display unit through a signal transmission line, receives data from the receiving card and controls the display unit to display; the power supply module is connected with the display unit and the receiving card through a power line and supplies power for the display unit and the receiving card; the transmitting card is arranged on the control computer and is connected with the receiving card through a transmission cable.
Example 2
The operation steps of the coal mine comprehensive information presentation system are as follows (figure 3):
step 1, starting data linkage server software;
step 2, setting coal mine codes, duty leaders, capacity verification and well logging verification personnel numbers in a global configuration module according to requirements, and selecting a data protocol, a source catalogue and a backup catalogue;
step 3, selecting an area display item and a part of display items in the area configuration module after the operation is finished;
and 4, saving the setting of the global configuration and the regional configuration.
Step 5, starting an execution service program through a data processing service, cleaning, extracting and editing data in a source directory, writing the data into a display text under a default path, simultaneously reading static1 and display text contents through a duty/duty lead display window of a preview window, and displaying the current duty and duty lead by a synchronous LED screen; the static2 text content is read through the verification productivity/trip number display window, and the verification productivity and the verification trip number are displayed by the synchronous LED screen
Step 6, synchronizing other needed information to the display screen through the preview window, such as: business/unit name, text, pictures, video multimedia information, weather conditions, etc.
Those skilled in the art will appreciate that: the technical solutions described in the foregoing embodiments may be modified or some technical features and fields may be replaced with equivalents, which may not deviate from the method according to the present invention.
Claims (6)
1. The utility model provides a comprehensive information of colliery system of showing which characterized in that: the system consists of software and hardware, wherein the software comprises a data linkage server and a comprehensive information presentation system; the hardware comprises a control computer, a transmission cable, an LED display screen and sound equipment, and the data linkage server and the comprehensive information public system software are installed on the control computer; the data linkage server of the software comprises: the system comprises an electronic screen configuration module, a global configuration module, a system authentication module, an area configuration module and a data processing module; the comprehensive information display system of the software comprises a main interface window and a preview window; the LED display screen of the hardware consists of a display unit, a power supply module, a sending card and a receiving card; the sound equipment of the hardware is connected with the control computer through a transmission cable to synchronously play sound;
the electronic screen configuration module of the data linkage server is associated with the comprehensive information presentation system and is used for controlling the starting of the comprehensive information presentation system; the comprehensive information display system is used for controlling the LED screen and editing display contents; the global configuration module of the data linkage server comprises: a basic information configuration item, a data protocol selection item, a default information supplement item and a source data backup item; the system authentication module of the data linkage server is used for registering the data linkage server and authorizing execution of service program operation; the region configuration module of the data linkage service end is used for selecting region display items and department display items; the data processing module of the data linkage server comprises: a data processing service start item and a data processing service stop item; the basic information configuration item is used for setting coal mine codes, approved productivity, approved people who go into the well and duty leaders; the data protocol selection item is used for selecting a protocol or a standard of processed data; the default information supplementary items are used for setting work types or job identification fields defined by coal mine enterprises by themselves except for specifications or standards; the source data backup item comprises a source catalog and a backup catalog; the source directory is used for selecting a storage path of the processed data, and the backup directory is used for selecting a storage path when the source data is backed up;
the coal mine code of the basic information configuration item is used for setting a coal mine enterprise identification code and is also a unique identification code for judging the enterprise when the system is authenticated; the verification productivity is used for setting approved annual production capacity of coal mine enterprises, storing the annual production capacity in a static2 text under a default path, and displaying the verification productivity; the number of the authorized personnel in the well is set, stored in a static2 text under a default path, and used for showing the number of the authorized personnel in the well; the duty leader is used for setting the ground duty leader of the same day, storing the stored ground duty leader into a static1 text under a default path, and displaying the duty leader of the same day;
the area display item of the area configuration module is used for selecting the number of people in the display area and the number of people in the display area, and when the number of people in the display area is selected, the display window of the underground operation personnel displays the total number of people in each area at present; when the personnel in the display area are selected, the underground operator display window displays the names of all personnel in each current area; the department display items of the area configuration module are used for selecting and displaying the number of departments and displaying personnel of the departments, and when the number of the departments is selected and displayed, the display window of the underground operation personnel displays the total number of people in the well according to the departments; when the personnel of the department are selected and displayed, the names of all personnel in the well are displayed by the underground operation personnel display window according to the departments;
the data processing service starting item of the data processing module is used for starting an execution service program, cleaning, extracting and editing data in a source directory, writing the data into a display text under a default path, automatically updating text content in real time and displaying current guidance of a well-logging operator and information of the well-logging operator; the data processing service stop item of the data processing module is used for stopping executing the service program and stopping processing the data in the source directory;
the processed data of the data protocol options are networking data of a coal mine underground operation personnel management system; the protocol or standard of the processed data is "technical standard for data acquisition of coal mine safety supervision law enforcement and decision-making system in Shanxi province", networking data standard DB14/T671.1-2012 for underground worker management of coal mine safety supervision law enforcement and decision-making support system ", general technical requirement and data acquisition standard of online monitoring and networking investigation system for coal mine safety production", coal mine safety monitoring, underground worker and industrial video perception data access rule.
2. The comprehensive information presentation system for coal mine as claimed in claim 1, wherein: the main interface window of the comprehensive information presentation system comprises: the file menu, the control screen menu, the play menu, the setting menu, the debugging menu and the group help menu are used for editing the displayed content; the preview window of the comprehensive information presentation system includes: the system comprises an enterprise/unit name display window, an on-duty/off-duty leading display window, a verification capacity/number of people in the well, a weather condition display window, a clock display window, a database/table/multimedia information display window and an underground operator display window, wherein the enterprise/unit name display window, the on-duty/off-duty leading display window, the verification capacity/number of people in the well, the weather condition display window, the clock display window, the database/table/multimedia information display window and the underground operator display window are used for previewing and adjusting each display window at a control end and synchronously displaying with an LED screen at a well mouth.
3. The comprehensive information presentation system for coal mine as claimed in claim 2, wherein: the enterprise/unit name display window of the preview window is used for editing and previewing and displaying enterprise/unit names and synchronously displaying the enterprise/unit names and the LED screen; the duty/duty leading display window of the preview window is used for reading static1 and display text content and synchronously displaying the text content and the LED screen; the verification capacity/number of people in the well is displayed in the preview window, and the verification capacity/number of people in the well is used for reading static2 text content and synchronously displaying the text content and the LED screen; the weather condition display window of the preview window is used for displaying weather condition contents and synchronously displaying the weather condition contents and the LED screen; the clock display window of the preview window is used for displaying date and time and synchronously displaying the date and time and the LED screen; the database/table/multimedia information display window of the preview window is used for displaying multimedia contents such as database/table/text/picture/video and the like and synchronously displaying the multimedia contents with the LED screen; and the underground operator display window of the preview window is used for reading the display text content and synchronously displaying the display text content and the LED screen, and displaying the information of the underground operator in real time.
4. The comprehensive information presentation system for coal mine as claimed in claim 2, wherein: the on-duty/off-duty leading display window of the preview window is also used for directly reading a database table of a coal mine underground operation personnel management system and synchronously displaying the database table and the LED screen; the underground operator display window of the preview window is also used for directly reading a database table of the underground operator management system of the coal mine, synchronously displaying the database table and the LED screen, and displaying the information of the underground operator in real time.
5. The comprehensive information presentation system for coal mine as claimed in claim 1, wherein: the content in the default path display text can also be directly written into the text by the underground coal mine operator management system.
6. The comprehensive information presentation system for coal mine as claimed in claim 1, wherein: the receiving card of the LED display screen is connected with the display unit through a signal transmission line, receives data from the receiving card and controls the display unit to display; the power supply module is connected with the display unit and the receiving card through a power line and supplies power for the display unit and the receiving card; the transmitting card is arranged on the control computer and is connected with the receiving card through a transmission cable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011459911.2A CN112558908B (en) | 2020-12-11 | 2020-12-11 | Comprehensive information presentation system for coal mine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011459911.2A CN112558908B (en) | 2020-12-11 | 2020-12-11 | Comprehensive information presentation system for coal mine |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112558908A CN112558908A (en) | 2021-03-26 |
CN112558908B true CN112558908B (en) | 2024-02-06 |
Family
ID=75062432
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011459911.2A Active CN112558908B (en) | 2020-12-11 | 2020-12-11 | Comprehensive information presentation system for coal mine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112558908B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113220770A (en) * | 2021-05-08 | 2021-08-06 | 北京中煤时代科技发展有限公司 | Energy industry decision support system based on big data analysis |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102122461A (en) * | 2010-01-08 | 2011-07-13 | 北京中海锦安高科技有限公司 | Light emitting diode (LED) electronic screen system for fire fighting propaganda educational training and public service announcement |
CN104113563A (en) * | 2013-04-17 | 2014-10-22 | 中煤科工集团常州自动化研究院 | Coal mine multimedia comprehensive information issuing system |
CN104751267A (en) * | 2014-10-24 | 2015-07-01 | 中国矿业大学 | Coal mine training resource could service platform establishing method |
CN109707447A (en) * | 2019-01-07 | 2019-05-03 | 张效春 | Improvement system is analyzed in a kind of coal mine safety management Internet-based and hidden troubles removing |
-
2020
- 2020-12-11 CN CN202011459911.2A patent/CN112558908B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102122461A (en) * | 2010-01-08 | 2011-07-13 | 北京中海锦安高科技有限公司 | Light emitting diode (LED) electronic screen system for fire fighting propaganda educational training and public service announcement |
CN104113563A (en) * | 2013-04-17 | 2014-10-22 | 中煤科工集团常州自动化研究院 | Coal mine multimedia comprehensive information issuing system |
CN104751267A (en) * | 2014-10-24 | 2015-07-01 | 中国矿业大学 | Coal mine training resource could service platform establishing method |
CN109707447A (en) * | 2019-01-07 | 2019-05-03 | 张效春 | Improvement system is analyzed in a kind of coal mine safety management Internet-based and hidden troubles removing |
Also Published As
Publication number | Publication date |
---|---|
CN112558908A (en) | 2021-03-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU758232B2 (en) | Single-document active user interface, method and system for implementing same | |
US20040024662A1 (en) | Equipment documentation management system, method, and software tools | |
EP1577819A1 (en) | Advertising management system and method of operation | |
US20180091568A1 (en) | Digital signage and digital signage content manager | |
CN112001680A (en) | BIM-based highway engineering management system | |
CN101290559A (en) | Information processing apparatus and information processing method | |
CN112558908B (en) | Comprehensive information presentation system for coal mine | |
CN102722507B (en) | content asset manager | |
US8626760B2 (en) | System and method for document management | |
US20030140306A1 (en) | System and method for remotely entering and verifying data capture | |
CN113255879A (en) | Deep learning labeling method, system, computer equipment and storage medium | |
US9489851B1 (en) | Landing signal officer (LSO) information management and trend analysis (IMTA) system | |
CN112669133A (en) | Intelligent cost control reimbursement method capable of automatically matching according to application scenes | |
US20190182259A1 (en) | Refrigeration device, controller thereof, user accessing terminal, mobile terminal, administration terminal and administration system of maintenance data | |
CN113077137B (en) | Intelligent management device for nameplate | |
CN113269536A (en) | Construction log system based on two-dimensional code and use method | |
US20070169193A1 (en) | Data processing system | |
US8103633B2 (en) | Method and system for generic display and use of an object | |
KR100959617B1 (en) | Electric Display Board System Based on Web Browser | |
WO2000067139A1 (en) | System and method for managing film and show production | |
KR100720541B1 (en) | business management system and operation method this system | |
Chaulya et al. | Modernization of Indian coal mining industry: Vision 2025 | |
KR102686542B1 (en) | A banner production management system that can automatically produce and manage product banners | |
JP4927248B2 (en) | Information display system | |
CN116629813A (en) | Constructor management system and method based on intelligent safety helmet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |