CN112541712A - Electric power construction site safety risk management and control method, device and platform - Google Patents

Electric power construction site safety risk management and control method, device and platform Download PDF

Info

Publication number
CN112541712A
CN112541712A CN202011598200.3A CN202011598200A CN112541712A CN 112541712 A CN112541712 A CN 112541712A CN 202011598200 A CN202011598200 A CN 202011598200A CN 112541712 A CN112541712 A CN 112541712A
Authority
CN
China
Prior art keywords
construction
risk
unit
electric power
hidden danger
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011598200.3A
Other languages
Chinese (zh)
Inventor
陈正茂
周立辉
黄昌跃
陈海平
李日胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhongdian Fangda Technology Co ltd
Huaneng Yangpu Thermal Power Co Ltd
Original Assignee
Beijing Zhongdian Fangda Technology Co ltd
Huaneng Yangpu Thermal Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Zhongdian Fangda Technology Co ltd, Huaneng Yangpu Thermal Power Co Ltd filed Critical Beijing Zhongdian Fangda Technology Co ltd
Priority to CN202011598200.3A priority Critical patent/CN112541712A/en
Publication of CN112541712A publication Critical patent/CN112541712A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a safety risk management and control method for an electric power construction site, which comprises the following steps: acquiring a construction task table uploaded by a construction unit, wherein the construction task table comprises operation tasks; matching danger points corresponding to the operation tasks in a preset operation risk database; analyzing and evaluating the dangerous points to determine a risk level; obtaining preventive measures for preventing accidents from occurring in the operation risk database; and acquiring the implementation situation of the preventive measures, and carrying out hidden danger troubleshooting according to the hidden danger troubleshooting list. According to the electric power construction site safety risk control method in the scheme, the operation risk database can identify the dangerous points in the construction operation task, so that preventive measures for preventing dangerous accidents are obtained and used as a first defense line for safety management; the implementation situation of preventive measures is checked and used as a second defense line for safety management, so that risks of the electric power construction site are effectively controlled, and accidents are reduced.

Description

Electric power construction site safety risk management and control method, device and platform
Technical Field
The invention relates to the field of electric power, in particular to a method, a device and a platform for managing and controlling safety risks of an electric power construction site.
Background
Electric power construction is an important project affecting the nationality of the country. The electric power construction project comprises power generation construction projects such as thermal power, hydroelectric power, nuclear power, wind power and solar power generation, power grid construction projects such as power transmission and power distribution, and other electric power facility construction projects. Because the electric power construction not only involves the building construction, but also involves the installation and the debugging of numerous electric power equipment, very high to the security requirement. The construction safety of the electric power construction project comprises production activities related to construction safety, such as electric power construction, reconnaissance design, construction, supervision units and the like. In order to strengthen the construction safety supervision and management of the electric power construction project and guarantee the life and property safety of people, the state also provides a construction safety supervision and management method of the electric power construction project.
For a general electric power construction project, a construction unit and a supervision unit are responsible for the project. The construction unit is responsible for overall management of construction safety of the electric power construction project, and the construction unit should organize construction according to national laws and regulations and standard standards and be responsible for safety production of the construction site. The supervision unit should implement supervision according to laws and regulations and mandatory standards of engineering construction to fulfill supervision responsibilities of safety production management of power construction engineering. In the electric power construction project, how to perform effective safety management is also important.
Disclosure of Invention
In view of this, the embodiment of the present invention provides a method for managing and controlling a safety risk of an electric power construction site, so as to solve a problem of how to effectively perform safety management in an electric power construction project.
According to a first aspect, an embodiment of the present invention provides a method for managing and controlling safety risks in an electric power construction site, including the following steps:
acquiring a construction task table uploaded by a construction unit, wherein the construction task table comprises operation tasks;
matching danger points corresponding to the operation tasks in a preset operation risk database;
analyzing and evaluating the dangerous points to determine a risk level;
according to the dangerous points and the risk grades, preventive measures for preventing accidents are obtained from the operation risk database;
and acquiring the implementation situation of the preventive measures, and developing hidden danger troubleshooting work according to a hidden danger troubleshooting list, wherein the hidden danger troubleshooting list is generated according to the preventive measures.
According to the electric power construction site safety risk control method in the scheme, the operation risk database is preset, the danger points in the construction operation tasks can be identified through the operation risk database, the danger levels of the danger points are obtained, and therefore the preventive measures for preventing dangerous accidents are obtained and serve as a first line of defense for safety management.
With reference to the first aspect, as an implementation manner, the electric power construction site safety risk management and control method further includes acquiring an emergency event occurring in an operation process; acquiring an emergency plan corresponding to the emergency from the operation risk database; and taking emergency rescue measures according to the emergency plan. In the optional embodiment, an emergency plan is set in advance for an emergency, and when the emergency occurs in the operation process, emergency rescue measures are taken according to the emergency plan to eliminate the accident in a bud state. And as a third defense line for building safety management, safety risk management and control are further enhanced.
With reference to the first aspect and the other embodiments, as a further embodiment, the situation of the preventive measure is extracted by a picture of the scene. The implementation of the pre-control measures is ensured, the working efficiency is improved, the examination and approval time is reduced, the implementation of the pre-control measures of the operation risk is effectively supervised, and the safety risk pre-control capability is improved.
With reference to the first aspect and other embodiments, as a further embodiment, the method further includes that a supervision unit and a construction unit acquire the construction task schedule uploaded by the construction unit and perform approval, so that the working efficiency is improved, and the approval time is reduced.
With reference to the first aspect and the other embodiments, as a further embodiment, the method further includes that the supervision unit and the construction unit approve the implementation situation of the preventive measures through the mobile terminal. The implementation of the pre-control measures is ensured, the working efficiency is improved, the examination and approval time is reduced, the implementation of the pre-control measures of the operation risk is effectively supervised, and the safety risk pre-control capability is improved.
With reference to the first aspect and other embodiments, as a further embodiment, the method further includes acquiring a hidden danger troubleshooting result, and uploading the hidden danger troubleshooting result and the violation condition through the mobile terminal. If the problems are found, the hidden danger and the violation conditions can be directly uploaded by the mobile terminal and fed back to a construction responsibility unit, the construction unit modifies according to requirements and uploads the modified pictures to a supervision or construction party, and the supervision or construction party can check and confirm on-site check and acceptance at the PC terminal or the mobile terminal if necessary and confirms through the mobile terminal. Thereby realizing closed-loop management of hidden troubles and violations.
With reference to the first aspect and the other embodiments, as a further embodiment, the construction task table includes tasks in power generation construction engineering and tasks in power grid construction engineering.
According to a second aspect, an embodiment of the present invention further provides an electric power construction site safety risk management and control apparatus, including:
the construction task obtaining unit is used for obtaining a construction task schedule uploaded by a construction unit, and the construction task schedule comprises operation tasks;
the dangerous point identification unit is used for matching dangerous points corresponding to the operation tasks in a preset operation risk database;
the danger level determining unit is used for analyzing and evaluating the danger points and determining the risk level;
a preventive measure generation unit, configured to obtain a preventive measure for preventing an accident from occurring in the operation risk database according to the risk point and the risk level;
and the troubleshooting unit is used for acquiring the implementation condition of the preventive measures and developing hidden trouble troubleshooting work according to a hidden trouble troubleshooting list, and the hidden trouble troubleshooting list is generated according to the preventive measures.
According to a third aspect, an embodiment of the present invention further provides an electric power construction site safety risk management and control platform, which includes a memory and a processor, where the memory and the processor are communicatively connected to each other, and a computer instruction is stored in the memory, and the processor executes the computer instruction, so as to execute the electric power construction site safety risk management and control method in the first aspect and the optional implementation manner thereof.
According to a fourth aspect, an embodiment of the present invention further provides a computer-readable storage medium, which stores computer instructions for causing a computer to execute the method for managing and controlling the safety risk of the electric power construction site in the first aspect and the optional embodiments thereof.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.
Fig. 1 shows a flowchart of a safety risk management and control method for an electric power construction site in an embodiment of the invention;
fig. 2 is a block diagram of a safety risk management and control device of an electric power construction site according to an embodiment of the present invention;
fig. 3 is a block diagram of a safety risk management and control platform of an electric power construction site according to an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention.
In order to carry out safety risk control on the electric power construction project, an electric power construction site safety risk control platform is constructed, the electric power construction site safety risk control platform is a set of software system, a construction unit and a supervision unit can log in the software platform system, different roles are allocated to three parties, different user permissions are provided, and safety risk control on the electric power construction project is achieved. The platform can log in at a computer PC terminal and also can log in through a mobile terminal.
The electric power construction site safety risk management and control method in this embodiment is executed in a server of the software platform, as shown in fig. 1, and includes the following steps:
s1: and acquiring a construction task table uploaded by a construction unit, wherein the construction task table comprises operation tasks.
The construction unit can input a construction task list through the PC client. The construction task table is formed according to construction tasks, for example, the operation tasks in the construction task table can be tasks in power generation construction projects or tasks in power grid construction projects. The construction is performed by a construction unit according to different construction projects.
Through the software platform, a construction unit can also record the safe work execution condition and the work accountability condition, and the mobile device and the PC are used for uploading to the electric power construction site safety risk management and control platform. The construction unit can also upload documents in the construction process, including a construction task list, through the platform, and the platform can automatically push the documents to corresponding responsible persons and automatically remind auditors; and intelligent management and control are realized.
The supervision unit and the construction unit can log in the platform through the mobile equipment or the PC, all documents before construction can be uploaded to the construction unit through the platform, and documents such as a construction task list uploaded by the construction unit can be acquired through the platform and are approved, so that the working efficiency is improved, and the approval time is reduced.
S2: and matching the dangerous points corresponding to the job tasks in a preset job risk database.
And after receiving the construction task list uploaded by the construction unit, the platform calls a corresponding operation risk database.
The operation risk database is well established in advance, the operation tasks and the corresponding danger points are stored in the risk database, and for example, for hoisting operation, the risk points in which links exist are well set in advance. In this way, the risk points for all tasks in the power engineering construction are pre-established.
For the power generation construction project, the power generation construction project comprises a thermal power part, a gas turbine part, a hydroelectric part, an onshore wind power part, an offshore wind power part and a photovoltaic part, wherein
The thermal power part comprises: management requirements, foundation treatment, soil engineering, boiler installation, steam turbine generator set installation, electrical installation, thermal control installation, chemical installation, coal conveying installation, welding heat treatment and nondestructive detection, corrosion prevention and heat preservation, debugging engineering and special operation;
the combustion engine part includes: management requirements, foundation treatment, civil engineering, waste heat boiler installation, gas turbine installation, steam turbine generator set installation, natural gas pressure regulating station installation, electrical installation, thermal control installation, chemical installation, welding heat treatment and nondestructive testing, corrosion prevention and heat preservation, debugging engineering and special operation;
the hydroelectric portion comprises: management requirements, auxiliary engineering, current conducting and carrying engineering, foundation treatment, water retaining buildings, water delivery buildings, water release buildings, plant junction buildings, other buildings, metal structure manufacturing and installation, electromechanical equipment installation, electrical equipment installation, debugging engineering and special operation;
the onshore wind power part comprises: management requirements, road construction, booster station soil construction, fan foundation construction, wind power foundation construction, wind generating set installation, transmission line installation, debugging and special operation;
the offshore wind power part comprises: management requirements, foundation construction, wind power generation equipment installation, auxiliary facility construction, offshore booster station installation, seabed laying, electrical equipment installation, debugging and special operation;
the photovoltaic part comprises management requirements, civil engineering, installation engineering, debugging and special operation.
Under the task in each part, a plurality of subtasks can be set, and each task corresponds to a dangerous point. And identifying the existence of dangerous points in the process of the operation tasks, determining the distribution condition of the dangerous points, analyzing the characteristics and the hazard degree of the dangerous points, and establishing a database.
After the platform receives the job tasks uploaded by the construction unit, the danger points corresponding to the job tasks are identified in the job risk database, so that each job task corresponds to the danger points, the existing risk can be known in advance for each job task, and the execution of subsequent tasks is guided, thereby improving the working efficiency and ensuring the safety of the job.
S3: and analyzing and evaluating the dangerous points to determine the risk level.
And analyzing and evaluating risks caused by the hazard sources by adopting a scientific method according to the operation tasks and the hazard points, and determining the risk level. The risk classes are classified into major risk, general risk, and low risk. For example, the risk level of the dangerous point can be obtained by presetting the job task and the corresponding relation between the dangerous point and the risk level according to experience in a preset job risk database and by a matching mode. In addition, the current environmental condition parameters during construction can be further input through a construction unit, and the danger level of the dangerous point can be determined by combining the environmental parameters. For example, in construction, these parameters also influence the risk level of the hazard point, taking into account the current environmental weather, such as wind power, temperature, etc. If the installation of an offshore power plant is carried out with particularly high wind forces, the risk level is higher than in the case of low wind forces. And obtaining the risk level of the risk point of the current operation task by analysis according to the information input by the construction unit and the experience information prestored in the operation risk database.
S4: and according to the dangerous points and the risk grades, obtaining preventive measures for preventing accidents from the operation risk database.
And precautionary measures are also preset in the operation risk database, the measures correspond to the risk points and the risk grades, and different precautionary measures are given for different risk points and different risk grades. After the risk points and the risk classes of the job tasks are determined, corresponding preventive measures can be obtained.
And the prevention measures for preventing accidents are made from the aspects of organization, system, technology, emergency and the like. These all belong to the risk management and control category, are the "first line of defense" of building the safety control.
S5: and acquiring the implementation situation of the preventive measures, and developing hidden danger troubleshooting work according to a hidden danger troubleshooting list, wherein the hidden danger troubleshooting list is generated according to the preventive measures.
The implementation of the preventive measures is extracted through the pictures on site. The construction unit serves as an executive party, carries out the pre-control measures of the operation risk library on site, and uploads the photos through the platform, so that the pre-control measures are guaranteed to be implemented and the pre-control measures are guaranteed to be implemented in place. The work efficiency is improved, the examination and approval time is reduced, the implementation of the pre-control measures of the operation risk is effectively supervised, and the capability of safety risk pre-control is improved.
The supervision unit and the construction unit examine and approve the implementation situation of the preventive measures through the mobile end, the supervision unit and the construction unit check pictures of the site risk pre-control implementation situation uploaded by the construction unit through the PC end or the mobile end, and the pictures are examined and confirmed, so that the pre-control measures are ensured to be implemented in place, the working efficiency is improved, the examination and approval time is reduced, the implementation of the pre-control measures for operation risks is effectively supervised, and the safety risk pre-control capacity is improved.
If necessary, the supervision unit and the construction unit can check and confirm the risk pre-control measures on site and ensure the pre-control measures to be in place through examination and approval of the mobile terminal. The work efficiency is improved, the examination and approval time is shortened, the implementation of the pre-control measures of the operation risk is effectively supervised, and the capability of the safety risk pre-control is improved.
According to the precautionary measures, a hidden danger troubleshooting list can be generated, the construction unit can troubleshoot hidden dangers according to the list, most managers of a supervision unit, a construction unit or the construction unit can obtain the hidden danger troubleshooting list on a platform, and the hidden dangers are troubleshooted according to the list. And (4) carrying out hidden danger troubleshooting according to whether the pre-control measures are implemented as main contents, carrying out hidden danger troubleshooting according to a hidden danger troubleshooting list, and eliminating the hidden danger in front of the accident. This is the "second line of defense" line of security management of building firmly.
The construction unit management personnel, the supervision unit and the construction unit personnel can go to the site to check the hidden trouble and the violation condition of site operation, if the problem is found, the hidden trouble and the violation condition can be directly uploaded by the mobile terminal and fed back to the construction unit, the construction unit carries out rectification according to the requirement and uploads the rectified picture to the supervision unit or the construction unit, and the supervision unit or the construction unit can carry out acceptance and confirmation at the PC terminal or the mobile terminal. If necessary, the mobile terminal can also check and accept the information on the spot and confirm the information through the mobile terminal. The closed-loop management of hidden dangers and violation is realized through the platform. The management of the left trace is realized and the trace can be found well. The safety risk and hidden danger big data management is realized, the safety trend analysis and the prediction and early warning of the safety state are realized, the intelligent analysis of the main reasons of the hidden danger problems is realized, the common problems existing in the management are found in time through analysis, the deviation is corrected in time, and the precise management based on the big data is realized.
According to the electric power construction site safety risk control method in the scheme, the operation risk database is preset, the danger points in the construction operation tasks can be identified through the operation risk database, the danger levels of the danger points are obtained, and therefore the preventive measures for preventing dangerous accidents are obtained and serve as a first line of defense for safety management.
In order to improve the emergency handling capacity, the electric power construction site safety risk management and control method further comprises the following steps:
first, an emergency event occurring during the operation process is acquired. Unexpected emergencies may occur during the operation due to uncontrollable operation, and a separate emergency plan may be set at this time.
Secondly, acquiring an emergency plan corresponding to the emergency event in the operation risk database. And setting an emergency plan of the emergency in the operation risk database, and carrying out standardized operation aiming at the handling of the emergency.
Thirdly, taking emergency rescue measures according to the emergency plan.
Because the emergency plan is preset according to advanced experience, the efficiency of processing the emergency event can be improved. In the embodiment, an emergency plan is set in advance for an emergency, and when the emergency occurs in the operation process, emergency rescue measures are taken according to the emergency plan to eliminate the accident in a bud state. And as a third defense line for building safety management, safety risk management and control are further enhanced. The emergency scheme can be acquired and checked by a construction unit, a supervision unit and a construction unit in a platform, and emergency accidents are processed at the first time according to emergency measures.
In addition, an embodiment of the present invention further provides an electric power construction site safety risk management and control apparatus, as shown in fig. 2, including:
the construction task obtaining unit 01 is used for obtaining a construction task schedule uploaded by a construction unit, and the construction task schedule comprises operation tasks; see step S1 for details of the implementation.
A dangerous point identification unit 02 for matching a dangerous point corresponding to the job task in a preset job risk database; see step S2 for details of the implementation.
A risk level determining unit 03, configured to analyze and evaluate the risk points to determine a risk level; see step S3 for details of the implementation.
A preventive measure generation unit 04, configured to obtain a preventive measure for preventing an accident from occurring in the operation risk database according to the risk point and the risk level; see step S4 for details of the implementation.
And the troubleshooting unit 05 is used for acquiring the implementation condition of the preventive measures and developing hidden danger troubleshooting work according to a hidden danger troubleshooting list, wherein the hidden danger troubleshooting list is generated according to the preventive measures. See step S5 for details of the implementation.
The electric power construction scene safety risk management and control device in this scheme, operation risk database has set up in advance, can discern the dangerous point in the construction operation task through this operation risk database, obtain its danger level, thereby obtain the precaution that the prevention dangerous accident takes place, as the first line of defence of safety control, in addition, still investigate to the implementation condition of precaution, as the second line of defence of safety control, through double-deck line of defence, make the risk at electric power construction scene obtain effective management and control, reduce the incidence of accident.
An embodiment of the present invention further provides a security risk management and control platform for an electric power construction site, which can be executed at a PC terminal or a mobile terminal, please refer to fig. 3, where fig. 3 is a schematic structural diagram of a terminal according to an alternative embodiment of the present invention, and as shown in fig. 3, the terminal may include: at least one processor 601, such as a Central Processing Unit (CPU), at least one communication interface 603, memory 604, and at least one communication bus 602. Wherein a communication bus 602 is used to enable the connection communication between these components. The communication interface 603 may include a Display (Display) and a Keyboard (Keyboard), and the optional communication interface 603 may also include a standard wired interface and a standard wireless interface. The Memory 604 may be a Random Access Memory (RAM) or a non-volatile Memory (non-volatile Memory), such as at least one disk Memory. The memory 604 may optionally be at least one storage device located remotely from the processor 601. Wherein the processor 601 may be in connection with the apparatus described in fig. 3, the application program is stored in the memory 604, and the processor 601 calls the program generation stored in the memory 604
The communication bus 602 may be a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus. The communication bus 602 may be divided into an address bus, a data bus, a control bus, etc. For ease of illustration, only one thick line is shown in FIG. 3, but this does not mean only one bus or one type of bus.
The memory 604 may include a volatile memory (RAM), such as a random-access memory (RAM); the memory may also include a non-volatile memory (english: non-volatile memory), such as a flash memory (english: flash memory), a hard disk (english: hard disk drive, abbreviation: HDD) or a solid-state drive (english: SSD); the memory 604 may also comprise a combination of memories of the kind described above.
The processor 601 may be a Central Processing Unit (CPU), a Network Processor (NP), or a combination of a CPU and an NP.
The processor 601 may further include a hardware chip. The hardware chip may be an application-specific integrated circuit (ASIC), a Programmable Logic Device (PLD), or a combination thereof. The PLD may be a Complex Programmable Logic Device (CPLD), a field-programmable gate array (FPGA), a General Array Logic (GAL), or any combination thereof.
Optionally, the memory 604 is also used for storing program instructions. The processor 601 may call a program instruction to implement the electric power construction site security risk management and control method shown in fig. 1 of the present application.
The embodiment of the invention also provides a non-transitory computer storage medium, wherein the computer storage medium stores computer executable instructions, and the computer executable instructions can execute the electric power construction site safety risk management and control method in any method embodiment. The storage medium may be a magnetic Disk, an optical Disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a Flash Memory (Flash Memory), a Hard Disk (Hard Disk Drive, abbreviated as HDD), a Solid State Drive (SSD), or the like; the storage medium may also comprise a combination of memories of the kind described above.
Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the invention, and such modifications and variations fall within the scope defined by the appended claims.

Claims (10)

1. The electric power construction site safety risk management and control method is characterized by comprising the following steps:
acquiring a construction task table uploaded by a construction unit, wherein the construction task table comprises operation tasks;
matching danger points corresponding to the operation tasks in a preset operation risk database;
analyzing and evaluating the dangerous points to determine a risk level;
according to the dangerous points and the risk grades, preventive measures for preventing accidents are obtained from the operation risk database;
and acquiring the implementation situation of the preventive measures, and developing hidden danger troubleshooting work according to a hidden danger troubleshooting list, wherein the hidden danger troubleshooting list is generated according to the preventive measures.
2. The method of claim 1, further comprising:
acquiring an emergency event occurring in the operation process;
acquiring an emergency plan corresponding to the emergency from the operation risk database;
and taking emergency rescue measures according to the emergency plan.
3. Method according to claim 1 or 2, characterized in that the implementation of the preventive measure is extracted by a picture of the scene.
4. The method of claim 3, further comprising a supervision unit and a construction unit acquiring the construction task schedule uploaded by the construction unit and performing an approval.
5. The method of claim 4, further comprising an administrative unit and a construction unit approving the implementation of the preventive measure by the mobile terminal.
6. The method of claim 5, further comprising obtaining hidden danger troubleshooting results and uploading the hidden danger troubleshooting results and violation conditions through the mobile terminal.
7. The method according to any one of claims 1, 2, 4, 5 or 6, wherein the construction task list comprises tasks in power generation construction projects and tasks in power grid construction projects.
8. The utility model provides an electric power construction scene safety risk management and control device which characterized in that includes:
the construction task obtaining unit is used for obtaining a construction task schedule uploaded by a construction unit, and the construction task schedule comprises operation tasks;
the dangerous point identification unit is used for matching dangerous points corresponding to the operation tasks in a preset operation risk database;
the danger level determining unit is used for analyzing and evaluating the danger points and determining the risk level;
a preventive measure generation unit, configured to obtain a preventive measure for preventing an accident from occurring in the operation risk database according to the risk point and the risk level;
and the troubleshooting unit is used for acquiring the implementation condition of the preventive measures and carrying out hidden danger troubleshooting work according to a hidden danger troubleshooting list, and the hidden danger troubleshooting list is generated according to the preventive measures.
9. An electric power construction site safety risk management and control platform, comprising a memory and a processor, wherein the memory and the processor are communicatively connected with each other, the memory stores computer instructions, and the processor executes the computer instructions so as to execute the electric power construction site safety risk management and control method according to any one of claims 1 to 7.
10. A computer-readable storage medium storing computer instructions for causing a computer to execute the electric power construction site safety risk management and control method according to any one of claims 1 to 7.
CN202011598200.3A 2020-12-29 2020-12-29 Electric power construction site safety risk management and control method, device and platform Pending CN112541712A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011598200.3A CN112541712A (en) 2020-12-29 2020-12-29 Electric power construction site safety risk management and control method, device and platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011598200.3A CN112541712A (en) 2020-12-29 2020-12-29 Electric power construction site safety risk management and control method, device and platform

Publications (1)

Publication Number Publication Date
CN112541712A true CN112541712A (en) 2021-03-23

Family

ID=75017865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011598200.3A Pending CN112541712A (en) 2020-12-29 2020-12-29 Electric power construction site safety risk management and control method, device and platform

Country Status (1)

Country Link
CN (1) CN112541712A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113516385A (en) * 2021-07-02 2021-10-19 沈阳风驰软件股份有限公司 Remote video safety management and control method and management and control system
CN113627897A (en) * 2021-08-23 2021-11-09 珠海优特电力科技股份有限公司 Method and device for managing and controlling safety of field operating personnel and storage medium
CN113673959A (en) * 2021-08-23 2021-11-19 珠海优特电力科技股份有限公司 Comprehensive control method and device for field operation safety and storage medium
CN114240386A (en) * 2021-12-22 2022-03-25 重庆至信实业集团有限公司 Risk point management system and method based on quality control
CN116090830A (en) * 2023-02-17 2023-05-09 南方电网调峰调频发电有限公司工程建设管理分公司 Operation risk monitoring method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110428181A (en) * 2019-08-06 2019-11-08 四川省水利干部学校(四川省水利职工中等专业学校) Security risk control and hidden troubles removing administering method
CN111091609A (en) * 2019-12-11 2020-05-01 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling
CN111160684A (en) * 2019-09-18 2020-05-15 中国电建集团华东勘测设计研究院有限公司 Safe production risk dual prevention mechanism construction platform

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110428181A (en) * 2019-08-06 2019-11-08 四川省水利干部学校(四川省水利职工中等专业学校) Security risk control and hidden troubles removing administering method
CN111160684A (en) * 2019-09-18 2020-05-15 中国电建集团华东勘测设计研究院有限公司 Safe production risk dual prevention mechanism construction platform
CN111091609A (en) * 2019-12-11 2020-05-01 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
左志远: "浅谈电网基建安全风险管理", 科技创新导报, vol. 13, no. 33, pages 104 - 105 *
杨文阳: "建设工程施工中的风险管理分析", 科技创新导报, no. 18, pages 89 - 90 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113516385A (en) * 2021-07-02 2021-10-19 沈阳风驰软件股份有限公司 Remote video safety management and control method and management and control system
CN113627897A (en) * 2021-08-23 2021-11-09 珠海优特电力科技股份有限公司 Method and device for managing and controlling safety of field operating personnel and storage medium
CN113673959A (en) * 2021-08-23 2021-11-19 珠海优特电力科技股份有限公司 Comprehensive control method and device for field operation safety and storage medium
CN113673959B (en) * 2021-08-23 2024-03-15 珠海优特电力科技股份有限公司 Comprehensive management and control method and device for site operation safety and storage medium
CN113627897B (en) * 2021-08-23 2024-03-19 珠海优特电力科技股份有限公司 Method and device for controlling safety of field operators and storage medium
CN114240386A (en) * 2021-12-22 2022-03-25 重庆至信实业集团有限公司 Risk point management system and method based on quality control
CN116090830A (en) * 2023-02-17 2023-05-09 南方电网调峰调频发电有限公司工程建设管理分公司 Operation risk monitoring method
CN116090830B (en) * 2023-02-17 2024-02-20 南方电网调峰调频发电有限公司工程建设管理分公司 Operation risk monitoring method

Similar Documents

Publication Publication Date Title
CN112541712A (en) Electric power construction site safety risk management and control method, device and platform
US20210326499A1 (en) Apparatus and method for safety analysis evaluation with data-driven workflow
CN107798479B (en) Knowledge management system based on full life cycle integrated knowledge experience information
CN105184519A (en) Standardized safety operation tracing management system
CN114744769A (en) Service processing method and system for power grid dispatching system
Singh et al. Development of a Sem-Quantitative approach for risk based inspection and maintenance of thermal power plant components
CN106789182B (en) Detection and scoring system and implementation method of automatic evaluation device for power plant grade protection
CN114580877A (en) Engineering supervision safety monitoring method and system
Ng et al. Structural Integrity Management (SIM) via a Digitalized Structural Integrity Compliance System
Kim Feasibility of shared use of alternative AC diesel generator under dual-unit station blackout
Bai et al. Risk assessment of hoisting aboard and installation for offshore wind turbine
Park et al. Application of Probabilistic Risk Assessment to Cyber Security of a Nuclear Power Plant
Fang et al. Research of potential safety hazard investigation and risk control system for mine enterprise
CN116596189A (en) Transformer information management method and device, electronic equipment and storage medium
CN116882738A (en) Nuclear power unit operation risk database, and establishment method and analysis method thereof
CN117236933A (en) Maintenance and verification method, device and equipment for power equipment and storage medium
CN115358563A (en) Nuclear power station work order flow configuration method and device, computer equipment and storage medium
Smith et al. Comparison of a Traditional Probabilistic Risk Assessment Approach with Advanced Safety Analysis
Bensi et al. Integrated Assessment of Flooding Hazards at US Nuclear Power Plants
Greco et al. Multi-hazard security assessment of transmission systems: a data-driven probabilistic framework for cascading failure analysis
CN115658981A (en) Equipment data acquisition method and system, terminal equipment and storage medium
CN117787949A (en) Power distribution network inspection method, system and inspection management platform
Santosa et al. Study of loop heat pipe prototype technology as a passive cooling system in nuclear reactors based on technology audit
CN116995671A (en) Quick power failure maintenance method, device and equipment for power grid and storage medium
CN112883089A (en) Fire information processing method, fire information processing device, computer equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination