CN112526362A - Switching device and method for realizing storage battery charge-discharge test - Google Patents

Switching device and method for realizing storage battery charge-discharge test Download PDF

Info

Publication number
CN112526362A
CN112526362A CN202011335649.0A CN202011335649A CN112526362A CN 112526362 A CN112526362 A CN 112526362A CN 202011335649 A CN202011335649 A CN 202011335649A CN 112526362 A CN112526362 A CN 112526362A
Authority
CN
China
Prior art keywords
storage battery
battery pack
switch
working
discharge test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011335649.0A
Other languages
Chinese (zh)
Inventor
李永增
王明
张学利
王学俊
张志刚
唐红
魏春侠
赵朝
常平
刘昌辉
刘博�
官学刚
尤存
苏国泷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongwei Power Supply Co Of State Grid Ningxia Electric Power Co ltd
Original Assignee
Zhongwei Power Supply Co Of State Grid Ningxia Electric Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongwei Power Supply Co Of State Grid Ningxia Electric Power Co ltd filed Critical Zhongwei Power Supply Co Of State Grid Ningxia Electric Power Co ltd
Priority to CN202011335649.0A priority Critical patent/CN112526362A/en
Publication of CN112526362A publication Critical patent/CN112526362A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/36Arrangements for testing, measuring or monitoring the electrical condition of accumulators or electric batteries, e.g. capacity or state of charge [SoC]
    • G01R31/382Arrangements for monitoring battery or accumulator variables, e.g. SoC
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R1/00Details of instruments or arrangements of the types included in groups G01R5/00 - G01R13/00 and G01R31/00
    • G01R1/02General constructional details
    • G01R1/04Housings; Supporting members; Arrangements of terminals
    • G01R1/0408Test fixtures or contact fields; Connectors or connecting adaptors; Test clips; Test sockets
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/36Arrangements for testing, measuring or monitoring the electrical condition of accumulators or electric batteries, e.g. capacity or state of charge [SoC]
    • G01R31/396Acquisition or processing of data for testing or for monitoring individual cells or groups of cells within a battery

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Secondary Cells (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

The application discloses a switching device and a method for realizing storage battery charge-discharge tests, wherein the device comprises: working storage battery pack and standby storage battery pack; the working storage battery pack is connected to the main circuit through a first switch; the standby storage battery pack is connected to the main circuit through a second switch; the working storage battery pack is connected with the storage battery discharge test circuit through a third switch and is connected with the storage battery charge test circuit through a fourth switch; and the third switch and the fourth switch are both positioned on one side of the first switch close to the working storage battery pack. The structure can ensure that two groups of storage batteries are connected in parallel for a short time in the storage battery switching process of a user, and the direct current bus is ensured to be supplied with power by the storage battery pack all the time, so that the direct current voltage loss risk caused by the loss of a storage battery power supply in the storage battery switching process is avoided, and the power failure probability in a transformer substation is reduced. The switching device for the storage battery charge and discharge test can reduce the direct-current voltage loss risk, improve the switching speed of the storage battery and improve the working efficiency of the charge and discharge test.

Description

Switching device and method for realizing storage battery charge-discharge test
Technical Field
The application relates to the technical field of power grid substations, in particular to a switching device and method for realizing a storage battery charge and discharge test.
Background
The transformer substation is a main intermediate link of power supply, and a plurality of control devices in the transformer substation need direct current power supply, so that each transformer substation is required to be provided with a storage battery, so that the transformer substation can still be supplied with direct current power supplied by the storage battery under the condition of mains supply outage, and a remote control system can continuously monitor the transformer substation remotely. Especially, the existing unattended substation is the main form in the power grid system, and for the substation, the problem of ensuring the state of the substation to be always in the remote monitoring of the control center is very important.
For a substation, a storage battery checking charge and discharge test is the only item of forced periodic inspection for a storage battery pack, and is also the best method for checking whether the storage battery capacity is sufficient. Because the connection between the storage battery and the main circuit needs to be disconnected in the storage battery checking charge-discharge test, a storage battery pack is arranged for a general transformer substation, and a group of storage batteries are used for standby; the problem of direct current voltage loss caused by the loss of a storage battery power supply of a transformer substation can be caused by improper switching between the working storage battery pack and the standby storage battery pack.
The storage battery switching device is convenient and reliable and has short working period and large maintenance amount aiming at the charge-discharge test of the storage battery pack. How to solve the above problems in an effective manner has become an important issue.
Disclosure of Invention
The embodiment of the application provides a switching device and a method for realizing a storage battery charge-discharge test, so as to solve the problem of direct current voltage loss risk caused by the loss of a storage battery power supply in the existing storage battery switching process.
The switching device for realizing the charge-discharge test of the storage battery comprises a working storage battery pack and a standby storage battery pack; the working storage battery pack is connected to the main circuit through a first switch; the standby storage battery pack is connected to the main circuit through a second switch; the working storage battery pack is connected with the storage battery discharge test circuit through a third switch and is connected with the storage battery charge test circuit through a fourth switch; and the third switch and the fourth switch are both positioned on one side of the first switch close to the working storage battery pack.
Optionally, a first voltage or current detection meter is arranged between the first switch and the working battery pack.
Optionally, a second voltage or current detection meter is arranged between the second switch and the working battery pack.
Optionally, the main circuit is provided with a third voltage or current detection meter.
Optionally, the first switch, the second switch, the third switch, and the first voltage or current detection meter, the second voltage or current detection meter, and the third voltage or current detection meter are disposed on a surface of the switching device housing for operation and observation; and the surface of the switching device shell is also provided with a working storage battery terminal, a standby storage battery terminal and a battery output terminal. The working storage battery pack and the standby storage battery pack can be arranged in the switching device shell, and at the moment, the battery output binding post is used for connecting out direct current output by the storage battery pack. The working storage battery pack and the standby storage battery pack can also be arranged outside the shell of the switching device, and only the switch and the detection meter are installed in the shell of the switching device through the connection of the working storage battery terminal and the standby storage battery terminal.
Optionally, a spare storage battery pack and a discharge instrument serving as a discharge test circuit are arranged on the switching device body.
The embodiment of the application further provides a switching method for realizing the storage battery charge and discharge test, and the method comprises the following steps:
when the discharge test operation is carried out on the working storage battery pack, the second switch is closed, the standby storage battery pack is connected with the main circuit, the first switch is disconnected, the working storage battery pack is disconnected with the main circuit, the fourth switch is disconnected, the working storage battery pack is disconnected with the storage battery charge test circuit, the third switch is closed, the working storage battery pack is connected with the storage battery discharge test circuit, and the working storage battery pack discharges to the storage battery discharge test circuit.
When the charging test operation is carried out on the working storage battery pack, the third switch is switched off, the working storage battery pack is disconnected from the storage battery discharging test circuit, the fourth switch is switched on, the working storage battery pack is connected with the storage battery charging test circuit, and the storage battery charging test circuit charges the working storage battery pack.
And if the working storage battery pack is required to be connected with the main circuit, closing the first switch to connect the working storage battery pack with the main circuit, and disconnecting the second switch to disconnect the standby storage battery pack with the main circuit.
Compared with the prior art, the embodiment of the application has the following advantages:
the application provides a switching device for realizing a storage battery charge-discharge test, which comprises a working storage battery pack and a standby storage battery pack; the working storage battery pack is connected to the main circuit through a first switch; the standby storage battery pack is connected to the main circuit through a second switch; the working storage battery pack is connected with the storage battery discharge test circuit through a third switch and is connected with the storage battery charge test circuit through a fourth switch; and the third switch and the fourth switch are both positioned on one side of the first switch close to the working storage battery pack. The structure can ensure that two groups of storage batteries are connected in parallel for a short time in the storage battery switching process of a user, and the direct current bus is ensured to be supplied with power by the storage battery pack all the time, so that the direct current voltage loss risk caused by the loss of a storage battery power supply in the storage battery switching process is avoided, and the power failure probability in a transformer substation is reduced. Therefore, the switching device for the storage battery charge-discharge test can reduce the direct-current voltage loss risk, improve the on-off speed of the storage battery and improve the working efficiency of the charge-discharge test.
Drawings
Fig. 1 is a schematic structural diagram of a switching device for implementing a battery charge-discharge test according to an embodiment of the present application.
Fig. 2 is a schematic circuit diagram of a switching device for implementing a battery charge/discharge test according to an embodiment of the present application.
Detailed Description
The working storage battery pack is used for ensuring that the transformer substation can normally work when alternating current is in power failure, so that direct current voltage loss of the transformer substation caused by the power failure of the alternating current is avoided, a relay protection device of the transformer substation is refused to operate, a motion system cannot realize four remote control (remote measurement, remote signaling, remote control and remote regulation), and the transformer substation is dispatched to lose monitoring and control; therefore, in the process of performing charge and discharge tests on the working storage battery pack, the working storage battery pack needs to be switched to a standby storage battery pack to supply power to the substation system. The application provides a realize experimental auto-change over device of battery charge-discharge and is used for solving this problem.
The switching device for the battery charge/discharge test will be described in detail below.
The embodiment of the present application provides a switching device for implementing a battery charge and discharge test, please refer to fig. 1, where fig. 1 is a schematic structural diagram of the switching device for implementing the battery charge and discharge test provided in the embodiment of the present application; fig. 2 is a schematic circuit diagram of the switching device for realizing the battery charge/discharge test. This realize experimental auto-change over device of battery charge-discharge includes: the secondary battery pack comprises an active battery pack 11, a spare battery pack 12, a first switch QF1, a second switch QF2, a third switch QF3 and a fourth switch QF 4.
In the embodiment of the application, the method comprises the following steps: working battery pack, backup battery pack 12; the working battery pack 11 is connected to the main circuit through a first switch QF 1; the spare battery pack 12 is connected to the main circuit through a second switch QF 2; the main circuit is a direct current circuit for supplying power to substation equipment by a storage battery; the working storage battery pack 11 is connected with a storage battery discharge test circuit through a third switch QF3 and is connected with a storage battery charge test circuit through a fourth switch QF 4; in this embodiment, the battery discharge test circuit is a discharge instrument 13, and the discharge instrument is a device designed for daily maintenance, capacity detection and testing of the load capacity of the dc power supply for the battery pack (24V, 48V, 110V, 220V, 400V, 600V) in the power, telecommunication, railway, battery manufacturing enterprises or other industries, and may be a universal discharge instrument device. The third switch QF3 and the fourth switch QF4 are both located on the side of the first switch QF1 close to the working battery pack 11.
In order to monitor the external power supply of the battery pack, a first voltage or current detection meter 101 is provided between the first switch QF1 and the working battery pack 11. Fig. 1 and 2 show a case where the voltage detection tables are arranged in parallel; the current detection meter can also be arranged in a series connection mode, and the detection meter is used for detecting the external power supply condition of the storage battery no matter what type of detection meter is arranged. The voltage or current detection tables mentioned below are the same and are not described again.
Similarly, a second voltage or current detection meter 102 is provided between the second switch QF2 and the active battery pack 11. Fig. 1 and 2 show a case where a voltage detection table is provided.
Similarly, the main circuit is provided with a third voltage or current detection table 103. Fig. 1 and 2 show a case where a voltage detection table is provided.
The above equipment can be arranged in a chassis to form a complete equipment; one possible solution is that the first switch QF1, the second switch QF2, the third switch QF3, and the first voltage or current detecting table 101, the second voltage or current detecting table 102, and the third voltage or current detecting table 103 are disposed on the housing surface of the switching device chassis for operation and observation; and the surface of the shell is also provided with a working storage battery terminal, a standby storage battery terminal and a battery output terminal. The working storage battery pack 11, the standby storage battery pack 12, the discharging instrument 13 and the like can be arranged in the switching device body, and at the moment, the battery output terminal is used for connecting out direct current output by the storage battery pack. The working battery pack 11 and the standby battery pack 12 can also be arranged outside the switching device body, and are connected through the working battery terminal and the standby battery terminal, and only the switches, the detection meters and the discharge instrument 13 are installed in the switching device body. Another reasonable option is that a spare storage battery pack 12 is arranged in the switching device case, when a substation equipped with a single storage battery pack needs to perform a storage battery charging and discharging test, the switching device is directly carried to the site to perform the test, and meanwhile, the spare storage battery pack 12 is provided.
Specifically, referring to fig. 2, when the working battery pack 11 is connected to the main circuit, the circuit switch QF0 is first turned on, and the main circuit is provided with the third voltage or current detection table 103, so that whether the main circuit is working normally can be determined according to the third voltage or current detection table 103. The working battery pack 11 is connected to the main circuit by closing the first switch QF 1; a first voltage or current detection table 101 is arranged between the first switch QF1 and the working battery pack 11, and whether the working battery pack 11 is normally connected can be judged according to the first voltage or current detection table 101.
Besides the above switching device for realizing the battery charge-discharge test, the embodiment of the present application further provides a switching method for realizing the battery charge-discharge test, which is applied to the above switching device for realizing the battery charge-discharge test, and the method includes:
when the discharge test operation is performed on the working battery pack 11, the second switch QF2 is closed, the spare battery pack 12 is connected to the main circuit, the first switch QF1 is disconnected, the working battery pack 11 is disconnected from the main circuit, the fourth switch QF4 is disconnected, the working battery pack 11 is disconnected from the battery charge test circuit, the third switch QF3 is closed, the working battery pack 11 is connected to the battery discharge test circuit, and the working battery pack 11 discharges to the battery discharge test circuit.
When the charging test operation is performed on the working storage battery pack 11, the third switch QF3 is turned off, so that the working storage battery pack 11 and the storage battery discharging test circuit are disconnected, the fourth switch QF4 is turned on, so that the working storage battery pack 11 and the storage battery charging test circuit are connected, and the storage battery charging test circuit charges the working storage battery pack 11.
If the working battery pack 11 needs to be connected to the main circuit, the first switch QF1 is closed to connect the working battery pack 11 to the main circuit, and the second switch QF2 is opened to disconnect the backup battery pack 12 from the main circuit.
Specifically, when the operating battery pack 11 is subjected to a charge-discharge test, the following process may be executed with reference to fig. 2:
step 1: the spare battery pack 12 is connected to the main circuit by closing the second switch QF 2; a second voltage or current detection table 102 is arranged between the second switch QF2 and the backup battery pack 12, and whether the backup battery pack 12 is normally connected can be determined according to the second voltage or current detection table 102.
Step 2: the working battery pack 11 is disconnected from the main circuit by disconnecting the first switch QF 1;
and step 3: the working storage battery pack 11 disconnects the storage battery charging test circuit by disconnecting the fourth switch QF 4;
and 4, step 4: the working storage battery pack 11 is connected with a storage battery discharge test circuit by closing the third switch QF 3;
and 5: after the discharging is finished, the working storage battery pack 11 disconnects the storage battery discharging test circuit by disconnecting the third switch QF 3; the working storage battery pack 11 is connected with a storage battery charging test circuit by closing the fourth switch QF 4;
step 6: after the working storage battery pack 11 is charged, the working storage battery pack 11 disconnects the storage battery charging test circuit by disconnecting the fourth switch QF 4;
and 7: the working storage battery pack 11 is connected into the main circuit by closing the first switch QF1, and the working storage battery pack 11 is recovered to be connected into the main circuit;
and 8: the backup battery pack 12 is detached from the main circuit by opening the second switch QF 2.
Although the preferred embodiments of the present invention have been disclosed in the foregoing description, the preferred embodiments of the present invention are not limited thereto, and those skilled in the art can make variations and modifications without departing from the spirit and scope of the embodiments of the present invention.

Claims (9)

1. The utility model provides a realize experimental auto-change over device of battery charge-discharge which characterized in that includes: working storage battery pack and standby storage battery pack; the working storage battery pack is connected to the main circuit through a first switch; the standby storage battery pack is connected to the main circuit through a second switch; the working storage battery pack is connected with the storage battery discharge test circuit through a third switch and is connected with the storage battery charge test circuit through a fourth switch; and the third switch and the fourth switch are both positioned on one side of the first switch close to the working storage battery pack.
2. The switching device for realizing the charge-discharge test of the storage battery according to claim 1, wherein a first voltage or current detection meter is arranged between the first switch and the working battery pack.
3. The switching device for realizing the charge-discharge test of the storage battery according to claim 2, wherein a second voltage or current detection meter is arranged between the second switch and the working battery pack.
4. The switching device for realizing the charge-discharge test of the storage battery according to claim 3, wherein the main circuit is provided with a third voltage or current detection meter.
5. The switching device for realizing the charge and discharge test of the storage battery according to claim 4, wherein the first switch, the second switch and the first voltage or current detection meter, the second voltage or current detection meter and the third voltage or current detection meter are arranged on the surface of the shell of the switching device body for operation and observation; and the surface of the shell is also provided with a working storage battery terminal, a standby storage battery terminal and a battery output terminal.
6. The switching device for realizing the charge and discharge test of the storage battery according to claim 4, wherein a spare storage battery pack and a discharge instrument as a discharge test circuit are arranged on the switching device body.
7. A switching method for realizing a storage battery charge-discharge test is applied to the switching device for realizing the storage battery charge-discharge test of any one of claims 1 to 5, and the method comprises the following steps:
when the discharge test operation is carried out on the working storage battery pack, the second switch is closed, the standby storage battery pack is connected with the main circuit, the first switch is disconnected, the working storage battery pack is disconnected with the main circuit, the fourth switch is disconnected, the working storage battery pack is disconnected with the storage battery charge test circuit, the third switch is closed, the working storage battery pack is connected with the storage battery discharge test circuit, and the working storage battery pack discharges to the storage battery discharge test circuit.
8. The switching method for realizing the battery charge-discharge test according to claim 7, further comprising:
when the charging test operation is carried out on the working storage battery pack, the third switch is switched off, the working storage battery pack is disconnected from the storage battery discharging test circuit, the fourth switch is switched on, the working storage battery pack is connected with the storage battery charging test circuit, and the storage battery charging test circuit charges the working storage battery pack.
9. The switching method for realizing the battery charge-discharge test according to claim 7, further comprising:
and if the working storage battery pack is required to be connected with the main circuit, closing the first switch to connect the working storage battery pack with the main circuit, and disconnecting the second switch to disconnect the standby storage battery pack with the main circuit.
CN202011335649.0A 2020-11-24 2020-11-24 Switching device and method for realizing storage battery charge-discharge test Pending CN112526362A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011335649.0A CN112526362A (en) 2020-11-24 2020-11-24 Switching device and method for realizing storage battery charge-discharge test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011335649.0A CN112526362A (en) 2020-11-24 2020-11-24 Switching device and method for realizing storage battery charge-discharge test

Publications (1)

Publication Number Publication Date
CN112526362A true CN112526362A (en) 2021-03-19

Family

ID=74993213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011335649.0A Pending CN112526362A (en) 2020-11-24 2020-11-24 Switching device and method for realizing storage battery charge-discharge test

Country Status (1)

Country Link
CN (1) CN112526362A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113629843A (en) * 2021-08-04 2021-11-09 国网青海省电力公司信息通信公司 Method for testing a battery

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113629843A (en) * 2021-08-04 2021-11-09 国网青海省电力公司信息通信公司 Method for testing a battery

Similar Documents

Publication Publication Date Title
CN101860051B (en) Charge/discharge test device for distributed full online storage battery pack
CN202550664U (en) Direct current power supply system of non-floating charge type transformer substation based on lithium iron battery
CN110224482B (en) Independent power supply and charging system for electric ship main power supply and storage battery grouping
CN110011408B (en) Mobile emergency power supply system and working method thereof
CN109449944B (en) Bidirectional direct-current power supply control system and method for transformer substation
CN103219766B (en) Non-floating charge lithium electricity type station DC power system
CN111864889B (en) Uninterrupted emergency power supply system and power supply method for open-circuit protection of lead-acid storage battery pack
CN115421064A (en) Online inversion capacity checking system and method for storage battery
CN101860050B (en) Discharge test device for distributed full online storage battery pack
CN110752615A (en) Battery energy storage power station field joint debugging device and method
CN110829852A (en) DC power supply open circuit monitoring and output voltage self-healing compensation device
CN214176917U (en) Family energy storage cabinet with universality
CN112526362A (en) Switching device and method for realizing storage battery charge-discharge test
CN201639336U (en) Distributed type full-online storage battery charge-discharge testing equipment
CN113328501B (en) Flexible connection device and framework of energy station direct current screen battery module
CN114884168B (en) Transformer substation direct current system based on lithium iron phosphate storage battery
CN217445031U (en) Storage battery nuclear capacity switching control circuit
CN110441709A (en) A kind of transforming plant DC power-supply system and monitoring method monitoring battery and charging module
CN214122422U (en) Switching device for realizing storage battery charging and discharging test
CN112798970B (en) Remote nuclear capacity system of storage battery of transformer substation
CN113708462A (en) Alternating current-direct current integrated power supply system based on storage battery online management
CN113253124A (en) Safe and energy-saving power storage battery nuclear capacity discharging device and method
CN219978492U (en) Storage battery life testing device for electric power
CN114884167B (en) Transformer substation direct-current control system based on lithium iron phosphate storage battery
CN204290471U (en) Batteries off-line electric discharge free of discontinuities switching device shifter

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination