CN112482366A - 一种适用于淤泥质软土地基的粉喷桩改进施工工艺 - Google Patents
一种适用于淤泥质软土地基的粉喷桩改进施工工艺 Download PDFInfo
- Publication number
- CN112482366A CN112482366A CN202011277004.6A CN202011277004A CN112482366A CN 112482366 A CN112482366 A CN 112482366A CN 202011277004 A CN202011277004 A CN 202011277004A CN 112482366 A CN112482366 A CN 112482366A
- Authority
- CN
- China
- Prior art keywords
- powder
- stirring
- spraying
- drilling
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及一种适用于淤泥质软土地基的粉喷桩改进施工工艺,包括以下步骤:1)钻进喷粉:启动搅拌钻机,钻头为正旋转边钻进同时喷粉,同时通过粉体发射器将加固料喷入被搅拌的土体中,使土体和加固料进行充分拌和;2)提升搅拌:提钻时钻头呈反向,边旋转边提升,控制钻机提升时管道压力,以不堵塞出气孔为原则,预防压力过大对地基产生变形;3)二次搅拌:把土质打散,使土体和加固料充分拌合;4)成桩。本发明可充分利用搅拌机械,增加土体搅拌次数,成桩能够达到相同的无侧限抗压强度和承载力效果,而且桩体均匀性效果更好;减少了喷射压缩空气这道工序,不但保证了不堵管,同时缩短了施工工期。
Description
技术领域
本发明涉及软土地基处理施工领域,具体涉及一种适用于淤泥质软土地基的粉喷桩改进施工工艺。
背景技术
工程地质为淤泥质粉质的黏土,具有触变性、流动性、不均匀性、高压缩性及地层压力较小等特点的软土地基,一般采用粉喷桩处理,施工主要工艺为:
1)预搅下沉至设计加固深度;
2)边喷粉,边搅拌提升直至预定的停灰面;
3)重复搅拌下沉至设计加固深度;
4)根据要求,喷粉或仅搅拌提升直至预定的停灰面;
钻进过程边旋转边钻进,为了不致堵塞喷射口,钻进时喷射压缩空气(不输送加固料),钻进速度小于1.5m/min。但实际施工时发现往往由于空气压力不够,易导致钻进过程中堵管,在此种地质条件下预搅效果不理想,且易扰动土体;在钻进过程中应用空压机送气,增加了施工的繁琐性,同时对空气产生污染。
发明内容
本发明的目的是对于淤泥质软土及地层压力较小地基,为解决其钻进过程易堵管、施工繁琐及扰动土体等不足等问题,针对本地质特殊情况,提供一种适用于淤泥质软土地基的粉喷桩改进施工工艺。
为实现上述目的,本发明提供的技术方案是:
一种适用于淤泥质软土地基的粉喷桩改进施工工艺,包括以下步骤:
1)钻进喷粉
启动搅拌钻机,钻头为正旋转边钻进同时喷粉,钻进速度小于1.5m/min,同时通过粉体发射器将加固料喷入被搅拌的土体中,使土体和加固料进行充分拌和;
2)提升搅拌
提钻时钻头呈反向,以0.5-0.8m/min的速度边旋转边提升,钻机提升时管道压力控制在0.2~0.4MPa,以不堵塞出气孔为原则,预防压力过大对地基产生变形;
3)二次搅拌
为了搅拌均匀,在二次搅拌时钻杆的移动速度要在0.5m/min以下,钻杆的反钻搅拌速度在90转/min以上,把土质打散,使土体和加固料充分拌合;
4)成桩。
步骤1)中,粉体发射器以0.25-0.4MPa的喷粉压力将加固料喷入被搅拌的土体中。
步骤1)中,从桩顶以上500mm开始喷粉,一直钻进喷粉至加固深度。
步骤2)中,当钻头提升至距离地面50cm时,成桩结束。
步骤3)中,二次搅拌长度不得小于5m。
从开始喷粉到提升过程中严禁断喷,保证桩底喷粉量达到要求。
与现有技术相比,本发明的有益效果是:
本发明通过调整施工顺序,即在下钻时喷粉,增加了土体与加固料的搅拌次数一次;同时,减少了喷射压缩空气这道工序,使施工过程无堵管现象。
本发明可充分利用搅拌机械,增加土体搅拌次数,成桩能够达到相同的无侧限抗压强度和承载力效果,而且桩体均匀性效果更好;减少了喷射压缩空气这道工序,不但保证了不堵管,同时缩短了施工工期。
附图说明
图1:本发明的粉喷桩改进施工工艺流程示意图。
图2:本发明的施工过程示意图。图中:a开始钻进喷粉;b钻进过程;c提升搅拌;d成桩。
具体实施方式
下面结合具体实施例对本发明作进一步详细的说明。以下实施例仅用于说明本发明而不用于限制本发明的范围。
1)钻进喷粉
启动搅拌钻机,钻头为正旋转边钻进同时喷粉,钻进速度小于1.5m/min,同时粉体发射器以0.25-0.4MPa的喷粉压力将加固料喷入被搅拌的土体中,使土体和加固料进行充分拌和。
一般从设计桩顶以上500mm开始喷粉,一直钻进喷粉至设计加固深度。开始喷粉到提升过程中严禁断喷,保证桩底喷粉量达到设计要求。
2)提升搅拌
提钻时钻头呈反向以0.5-0.8m/min的速度边旋转边提升,注意钻机提升时管道压力为0.2~0.4MPa,不宜过大(以不堵塞出气孔为原则),预防压力过大对地基产生变形。
当钻头提升至距离地面50cm时,成桩结束。
3)二次搅拌
二次搅拌是否均匀是确定成桩质量的重要因素,二次搅拌长度不得小于5m。为了搅拌均匀在二次搅拌时钻杆的移动速度要在0.5m/min以下,而钻杆的反钻搅拌速度要在90转/min以上,把土质打散,使土体和加固料充分拌合。
4)成桩。
以上所述,仅是本发明的较佳实施例,并非对本发明作任何形式上的限制,任何熟悉本专业的技术人员,在不脱离本发明技术方案范围内,依据本发明的技术实质,对以上实施例所作的任何简单的修改、等同替换与改进等,均仍属于本发明技术方案的保护范围之内。
Claims (6)
1.一种适用于淤泥质软土地基的粉喷桩改进施工工艺,其特征在于:包括以下步骤:
1)钻进喷粉
启动搅拌钻机,钻头为正旋转边钻进同时喷粉,钻进速度小于1.5m/min,同时通过粉体发射器将加固料喷入被搅拌的土体中,使土体和加固料进行充分拌和;
2)提升搅拌
提钻时钻头呈反向,以0.5-0.8m/min的速度边旋转边提升,钻机提升时管道压力控制在0.2~0.4MPa,以不堵塞出气孔为原则,预防压力过大对地基产生变形;
3)二次搅拌
为了搅拌均匀,在二次搅拌时钻杆的移动速度要在0.5m/min以下,钻杆的反钻搅拌速度在90转/min以上,把土质打散,使土体和加固料充分拌合;
4)成桩。
2.根据权利要求1所述的适用于淤泥质软土地基的粉喷桩改进施工工艺,其特征在于:步骤1)中,粉体发射器以0.25-0.4MPa的喷粉压力将加固料喷入被搅拌的土体中。
3.根据权利要求1所述的适用于淤泥质软土地基的粉喷桩改进施工工艺,其特征在于:步骤1)中,从桩顶以上500mm开始喷粉,一直钻进喷粉至加固深度。
4.根据权利要求1所述的适用于淤泥质软土地基的粉喷桩改进施工工艺,其特征在于:步骤2)中,当钻头提升至距离地面50cm时,成桩结束。
5.根据权利要求1所述的适用于淤泥质软土地基的粉喷桩改进施工工艺,其特征在于:步骤3)中,二次搅拌长度不得小于5m。
6.根据权利要求1所述的适用于淤泥质软土地基的粉喷桩改进施工工艺,其特征在于:从开始喷粉到提升过程中严禁断喷,保证桩底喷粉量达到要求。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011277004.6A CN112482366A (zh) | 2020-11-16 | 2020-11-16 | 一种适用于淤泥质软土地基的粉喷桩改进施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011277004.6A CN112482366A (zh) | 2020-11-16 | 2020-11-16 | 一种适用于淤泥质软土地基的粉喷桩改进施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112482366A true CN112482366A (zh) | 2021-03-12 |
Family
ID=74930459
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011277004.6A Pending CN112482366A (zh) | 2020-11-16 | 2020-11-16 | 一种适用于淤泥质软土地基的粉喷桩改进施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112482366A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113502811A (zh) * | 2021-07-07 | 2021-10-15 | 中交一公局集团有限公司 | 一种粉喷桩的施工工艺和设备 |
CN113818429A (zh) * | 2021-11-09 | 2021-12-21 | 樊军让 | 一种改变桩外土体的施工装置及其施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004137670A (ja) * | 2002-10-15 | 2004-05-13 | Geotop Corp | 基礎杭の施工法及びその装置 |
CN101230572A (zh) * | 2008-02-27 | 2008-07-30 | 东南大学 | 双向搅拌粉喷桩成桩操作方法 |
CN103343535A (zh) * | 2013-07-24 | 2013-10-09 | 中铁科工集团有限公司 | 一种双管干喷水泥土成桩方法 |
CN110714453A (zh) * | 2019-09-27 | 2020-01-21 | 浙江科技学院 | 基坑被动区土体加固强度的施工方法 |
-
2020
- 2020-11-16 CN CN202011277004.6A patent/CN112482366A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004137670A (ja) * | 2002-10-15 | 2004-05-13 | Geotop Corp | 基礎杭の施工法及びその装置 |
CN101230572A (zh) * | 2008-02-27 | 2008-07-30 | 东南大学 | 双向搅拌粉喷桩成桩操作方法 |
CN103343535A (zh) * | 2013-07-24 | 2013-10-09 | 中铁科工集团有限公司 | 一种双管干喷水泥土成桩方法 |
CN110714453A (zh) * | 2019-09-27 | 2020-01-21 | 浙江科技学院 | 基坑被动区土体加固强度的施工方法 |
Non-Patent Citations (1)
Title |
---|
汪双杰等: "《高速公路不良地基处理理论与方法》", 31 October 2004, 人民交通出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113502811A (zh) * | 2021-07-07 | 2021-10-15 | 中交一公局集团有限公司 | 一种粉喷桩的施工工艺和设备 |
CN113818429A (zh) * | 2021-11-09 | 2021-12-21 | 樊军让 | 一种改变桩外土体的施工装置及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112482366A (zh) | 一种适用于淤泥质软土地基的粉喷桩改进施工工艺 | |
CN103195363B (zh) | 负压射流式粒子冲击钻井注入装置 | |
CN110616709A (zh) | 三重管三高压旋喷桩施工方法 | |
CN104563099A (zh) | 多孔管法大直径高压旋喷桩施工方法 | |
US8470406B2 (en) | Method of spray application, and spray apparatus, for bentonite material | |
KR101545254B1 (ko) | 중압혼합분사 주입장치 및 이를 이용한 주상형 구조체 시공방법 | |
CN101787693B (zh) | 一种高压粉体喷射方法所使用的高压射粉喷嘴 | |
CN110924385B (zh) | 高压旋喷桩施工工艺 | |
CN211285577U (zh) | 一种加速水泥硬化速度的mjs桩机 | |
CN108775012A (zh) | 一种大直径超深高压喷射注浆装置及其注浆工艺 | |
CN208563316U (zh) | 一种大直径灌注桩桩底虚土沉渣处理装置 | |
CN112030931A (zh) | 一种深层地基软土夹层置换加固方法 | |
CN114352189B (zh) | 旋喷桩施工方法 | |
CN110004924A (zh) | 一种具有消除土体粘结作用的双轴搅拌钻头 | |
CN213625557U (zh) | 一种双液三重管高压旋喷施工装置及系统 | |
CN214530635U (zh) | 大直径水泥搅拌桩搅拌钻头 | |
CN108914939A (zh) | 一种大直径超深高压喷射注浆施工方法 | |
CN107489153B (zh) | 一种用于桩孔混凝土浆注入的浇筑管件 | |
CN107842030B (zh) | 一种围堰防渗墙施工用高压旋喷桩设备及施工方法 | |
JP2011241538A (ja) | 中心孔を取り囲んだ多孔ノズルによる噴射装置を使用した地盤改良工法および地盤改良装置 | |
JP2003286717A (ja) | 高圧噴射注入地盤改良工法 | |
CN215629909U (zh) | 一种提高水泥土搅拌桩水泥浆掺量均匀性的装置 | |
CN108914940A (zh) | 一种超大直径多重超高压喷射注浆施工方法 | |
CN216194693U (zh) | 一种多喷嘴多角度组合式高压旋喷施工装备 | |
CN110172970A (zh) | 一种避免浆液倒灌的旋喷桩供浆管线及其喷浆方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210312 |