CN112475790A - Novel flange production process - Google Patents

Novel flange production process Download PDF

Info

Publication number
CN112475790A
CN112475790A CN202011196362.4A CN202011196362A CN112475790A CN 112475790 A CN112475790 A CN 112475790A CN 202011196362 A CN202011196362 A CN 202011196362A CN 112475790 A CN112475790 A CN 112475790A
Authority
CN
China
Prior art keywords
flange
vod
primary smelting
laying
steel ladle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011196362.4A
Other languages
Chinese (zh)
Inventor
王志超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yixing Lianfeng Heavy Industry Technology Co ltd
Original Assignee
Yixing Lianfeng Heavy Industry Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yixing Lianfeng Heavy Industry Technology Co ltd filed Critical Yixing Lianfeng Heavy Industry Technology Co ltd
Priority to CN202011196362.4A priority Critical patent/CN112475790A/en
Publication of CN112475790A publication Critical patent/CN112475790A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L23/00Flanged joints
    • F16L23/02Flanged joints the flanges being connected by members tensioned axially
    • F16L23/032Flanged joints the flanges being connected by members tensioned axially characterised by the shape or composition of the flanges

Abstract

The invention relates to a novel flange production process, which comprises the steps of (1) sending raw materials into a primary smelting furnace for primary smelting, taking the raw materials out of the furnace after the primary smelting, hoisting a VOD steel ladle into a vacuum chamber, switching on bottom blowing argon to start cover closing and evacuation, adding a deoxidizing agent into the VOD steel ladle under the vacuum condition for deoxidation, and finally hoisting the VOD steel ladle out for pouring; (2) forging the blank; (3) manufacturing the forging material into a plate; (4) cutting the plate by a laser cutting machine to manufacture 1/4 semi-finished flange pieces; (5) laying four 1/4 semi-finished flange sheets on a die of an integrated splicing welding machine, and laying an auxiliary arc plate; (6) starting the integrated splicing welding machine, completing the single-side welding work of the flange, and automatically withdrawing the gun; (7) laying the reverse side of the flange to complete the welding work of the flange, and automatically withdrawing the gun; (8) disassembling the flange, cutting off the auxiliary arc plate, and polishing; (9) and carrying out nondestructive detection on the product. The invention saves working procedures, has less material consumption, saves cost, and is environment-friendly and safe.

Description

Novel flange production process
Technical Field
The invention belongs to the field of flange manufacturing, and particularly relates to a flange manufacturing process.
Background
The flange is an important pipeline connecting piece and is widely applied. At present, in the manufacturing process of a flange, a round rod is generally blanked and then directly machined (lathe machining, milling machine machining and the like), but the machining method has the disadvantages of long turning and milling time, high labor cost and very serious material loss, and accounts for 40% -50%. Due to long-time deep processing, the residual stress of the product is large, the hardness of the material is high, and the mechanical property and the service performance of the material are directly influenced.
Disclosure of Invention
The purpose of the invention is as follows: the invention aims to overcome the defects in the prior art and provide a novel flange production process which is less in working procedure, less in material consumption, cost-saving, environment-friendly and safe.
The technical scheme is as follows: in order to solve the technical problems, the novel flange production process comprises the following steps,
(1) sending the raw materials into a primary smelting furnace for primary smelting, wherein the primary smelting temperature is 1150 ℃ plus, the primary smelting is 60min, lifting a VOD steel ladle into a vacuum chamber after the primary smelting, switching on bottom argon blowing to start cover closing and vacuumizing, when the vacuum degree reaches 20-25kPa, carrying out oxygen blowing decarburization, adjusting the vacuum degree to be 125 plus 150Pa, adding a deoxidizer into the VOD steel ladle under the vacuum condition for deoxidation, finally lifting out the VOD steel ladle for casting, wherein the casting temperature is 1200 plus 1350 ℃, the casting speed is 20-30kg/s, and the casting time is 20s, so as to obtain a blank;
(2) forging the blank, controlling the initial forging temperature at 1100-;
(3) manufacturing the forging material into a plate;
(4) cutting a plate by using a laser cutting machine to manufacture 1/4 semi-finished flange pieces, so that 1/4 semi-finished flange pieces have open holes and smooth inner and outer circles;
(5) laying four 1/4 semi-finished flange sheets on a die of an integrated splicing welding machine, and laying an auxiliary arc plate;
(6) starting the integrated splicing welding machine, completing the single-side welding work of the flange, and automatically withdrawing the gun;
(7) laying the reverse side of the flange to complete the welding work of the flange, and automatically withdrawing the gun;
(8) disassembling the flange, cutting off the auxiliary arc plate, and polishing the excircle bulge of the flange;
(9) and carrying out nondestructive testing on the product, carrying out rust prevention treatment after the product is qualified, obtaining the required qualified product, and then packaging and warehousing the product.
Further, in the step (1), CaO is used as the deoxidizer.
Further, in the step (2), the mold comprises an annular base, and positioning pins are uniformly arranged on the upper part of the annular base.
Has the advantages that: compared with the prior art, the invention has the following remarkable advantages: the invention adopts a VOD smelting process for smelting, because the content of carbon and gas in the molten steel is easily reduced to a very low level under the vacuum condition, the quality of a finished product is ensured, the four-piece welding is adopted, the material yield of raw materials is greatly improved, the cost is saved, the accuracy of the position and the quantity of screw holes can be ensured to be 100 percent by adopting a flange group die, the processes of marking, positioning and the like of the prior flange are saved, the integral precision is effectively improved, the die comprises a full-circle flange, a base and a positioning pin, the manufacture is simple, the size is adjustable, the invention has safe and reliable operation and wide application range.
Detailed Description
The present invention will be further described with reference to the following examples.
Example 1
The novel flange production process comprises the following steps,
(1) sending the raw materials into a primary smelting furnace for primary smelting, wherein the primary smelting temperature is 1110 ℃, the primary smelting is 60min, taking out the raw materials after the primary smelting, hoisting a VOD steel ladle into a vacuum chamber, switching on bottom argon blowing, starting cover closing and vacuumizing, when the vacuum degree reaches 23kPa, carrying out oxygen blowing and decarburization, adjusting the vacuum degree to 140Pa, adding a deoxidizer into the VOD steel ladle for deoxidation under the vacuum condition, finally hoisting the VOD steel ladle out for casting, wherein the casting temperature is 1300 ℃, the casting speed is 29kg/s, and the casting time is 20s, thus obtaining a blank;
(2) forging the blank, controlling the initial forging temperature to be 1130 ℃, controlling the final forging temperature to be 780 ℃, cooling the forged blank to 570 ℃ by air, then placing the forged blank into a heating furnace to heat to 915 ℃, cooling to 450 ℃ by air, and finally cooling to room temperature by water;
(3) manufacturing the forging material into a plate;
(4) cutting a plate by using a laser cutting machine to manufacture 1/4 semi-finished flange pieces, so that 1/4 semi-finished flange pieces have open holes and smooth inner and outer circles;
(5) laying four 1/4 semi-finished flange sheets on a die of an integrated splicing welding machine, and laying an auxiliary arc plate;
(6) starting the integrated splicing welding machine, completing the single-side welding work of the flange, and automatically withdrawing the gun;
(7) laying the reverse side of the flange to complete the welding work of the flange, and automatically withdrawing the gun;
(8) disassembling the flange, cutting off the auxiliary arc plate, and polishing the excircle bulge of the flange;
(9) and carrying out nondestructive testing on the product, carrying out rust prevention treatment after the product is qualified, obtaining the required qualified product, and then packaging and warehousing the product.
In the step (1), CaO is used as the deoxidizer.
In the step (2), the die comprises an annular base, and positioning pins are uniformly arranged on the upper part of the annular base.
Example 2
The novel flange production process comprises the following steps,
(1) sending the raw materials into a primary smelting furnace for primary smelting, wherein the primary smelting temperature is 1050 ℃, the primary smelting is 60min, taking out the raw materials after the primary smelting, hoisting a VOD steel ladle into a vacuum chamber, switching on bottom argon blowing, starting cover closing and vacuumizing, when the vacuum degree reaches 22kPa, carrying out oxygen blowing and decarburization, adjusting the vacuum degree to 130Pa, adding a deoxidizer into the VOD steel ladle for deoxidation under the vacuum condition, finally hoisting the VOD steel ladle out for casting, wherein the casting temperature is 1250 ℃, the casting speed is 24kg/s, and the casting time is 20s, thus obtaining a blank;
(2) forging the blank, controlling the initial forging temperature at 1110 ℃ and the final forging temperature at 760 ℃, air-cooling the forged blank to 540 ℃, then placing the forged blank into a heating furnace to heat to 905 ℃, then air-cooling to 440 ℃, and finally water-cooling to room temperature;
(3) manufacturing the forging material into a plate;
(4) cutting a plate by using a laser cutting machine to manufacture 1/4 semi-finished flange pieces, so that 1/4 semi-finished flange pieces have open holes and smooth inner and outer circles;
(5) laying four 1/4 semi-finished flange sheets on a die of an integrated splicing welding machine, and laying an auxiliary arc plate;
(6) starting the integrated splicing welding machine, completing the single-side welding work of the flange, and automatically withdrawing the gun;
(7) laying the reverse side of the flange to complete the welding work of the flange, and automatically withdrawing the gun;
(8) disassembling the flange, cutting off the auxiliary arc plate, and polishing the excircle bulge of the flange;
(9) and carrying out nondestructive testing on the product, carrying out rust prevention treatment after the product is qualified, obtaining the required qualified product, and then packaging and warehousing the product.
In the step (1), CaO is used as the deoxidizer.
In the step (2), the die comprises an annular base, and positioning pins are uniformly arranged on the upper part of the annular base.
The invention adopts a VOD smelting process for smelting, because the content of carbon and gas in the molten steel is easily reduced to a very low level under the vacuum condition, the quality of a finished product is ensured, the four-piece welding is adopted, the material yield of raw materials is greatly improved, the cost is saved, the accuracy of the position and the quantity of screw holes can be ensured to be 100 percent by adopting a flange group die, the processes of marking, positioning and the like of the prior flange are saved, the integral precision is effectively improved, the die comprises a full-circle flange, a base and a positioning pin, the manufacture is simple, the size is adjustable, the invention has safe and reliable operation and wide application range.
The present invention provides a thought and a method, and a method and a way for implementing the technical scheme are many, the above is only a preferred embodiment of the present invention, it should be noted that, for a person skilled in the art, a plurality of improvements and modifications can be made without departing from the principle of the present invention, and the improvements and modifications should be regarded as the protection scope of the present invention, and each component not explicitly described in the embodiment can be implemented by the prior art.

Claims (3)

1. A novel flange production process is characterized in that: which comprises the following steps of,
(1) sending the raw materials into a primary smelting furnace for primary smelting, wherein the primary smelting temperature is 1150 ℃ plus, the primary smelting is 60min, lifting a VOD steel ladle into a vacuum chamber after the primary smelting, switching on bottom argon blowing to start cover closing and vacuumizing, when the vacuum degree reaches 20-25kPa, carrying out oxygen blowing decarburization, adjusting the vacuum degree to be 125 plus 150Pa, adding a deoxidizer into the VOD steel ladle under the vacuum condition for deoxidation, finally lifting out the VOD steel ladle for casting, wherein the casting temperature is 1200 plus 1350 ℃, the casting speed is 20-30kg/s, and the casting time is 20s, so as to obtain a blank;
(2) forging the blank, controlling the initial forging temperature at 1100-;
(3) manufacturing the forging material into a plate;
(4) cutting a plate by using a laser cutting machine to manufacture 1/4 semi-finished flange pieces, so that 1/4 semi-finished flange pieces have open holes and smooth inner and outer circles;
(5) laying four 1/4 semi-finished flange sheets on a die of an integrated splicing welding machine, and laying an auxiliary arc plate;
(6) starting the integrated splicing welding machine, completing the single-side welding work of the flange, and automatically withdrawing the gun;
(7) laying the reverse side of the flange to complete the welding work of the flange, and automatically withdrawing the gun;
(8) disassembling the flange, cutting off the auxiliary arc plate, and polishing the excircle bulge of the flange;
(9) and carrying out nondestructive testing on the product, carrying out rust prevention treatment after the product is qualified, obtaining the required qualified product, and then packaging and warehousing the product.
2. A novel flange production process according to claim 1, characterized in that: in the step (1), CaO is used as the deoxidizer.
3. A novel flange production process according to claim 1, characterized in that: in the step (2), the die comprises an annular base, and positioning pins are uniformly arranged on the upper part of the annular base.
CN202011196362.4A 2020-10-31 2020-10-31 Novel flange production process Pending CN112475790A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011196362.4A CN112475790A (en) 2020-10-31 2020-10-31 Novel flange production process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011196362.4A CN112475790A (en) 2020-10-31 2020-10-31 Novel flange production process

Publications (1)

Publication Number Publication Date
CN112475790A true CN112475790A (en) 2021-03-12

Family

ID=74927981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011196362.4A Pending CN112475790A (en) 2020-10-31 2020-10-31 Novel flange production process

Country Status (1)

Country Link
CN (1) CN112475790A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014030819A1 (en) * 2012-08-23 2014-02-27 Lee Chun-Hong Method for manufacturing long-neck flange
KR20140116768A (en) * 2013-03-25 2014-10-06 이용붕 The Pipe Type Flange
CN104862615A (en) * 2015-03-31 2015-08-26 无锡市华尔泰机械制造有限公司 S31803 duplex stainless steel flange and production process thereof
CN105331901A (en) * 2015-11-27 2016-02-17 无锡市华尔泰机械制造有限公司 S22253 duplex stainless steel material flange and production process thereof
CN106271446A (en) * 2016-08-30 2017-01-04 江苏协合新能源科技有限公司 A kind of welding production technology of wind-power tower base flange
CN109483157A (en) * 2017-09-13 2019-03-19 南京美克斯精密机械有限公司 A kind of flange processing technology
CN110202327A (en) * 2019-07-01 2019-09-06 宝成重工有限公司 A kind of flange fabrication technology
CN110497158A (en) * 2019-09-04 2019-11-26 南通泰胜蓝岛海洋工程有限公司 A kind of manufacture craft of fragment pylon

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014030819A1 (en) * 2012-08-23 2014-02-27 Lee Chun-Hong Method for manufacturing long-neck flange
KR20140116768A (en) * 2013-03-25 2014-10-06 이용붕 The Pipe Type Flange
CN104862615A (en) * 2015-03-31 2015-08-26 无锡市华尔泰机械制造有限公司 S31803 duplex stainless steel flange and production process thereof
CN105331901A (en) * 2015-11-27 2016-02-17 无锡市华尔泰机械制造有限公司 S22253 duplex stainless steel material flange and production process thereof
CN106271446A (en) * 2016-08-30 2017-01-04 江苏协合新能源科技有限公司 A kind of welding production technology of wind-power tower base flange
CN109483157A (en) * 2017-09-13 2019-03-19 南京美克斯精密机械有限公司 A kind of flange processing technology
CN110202327A (en) * 2019-07-01 2019-09-06 宝成重工有限公司 A kind of flange fabrication technology
CN110497158A (en) * 2019-09-04 2019-11-26 南通泰胜蓝岛海洋工程有限公司 A kind of manufacture craft of fragment pylon

Similar Documents

Publication Publication Date Title
CN102418042B (en) Novel manufacturing process of phi 300 mm-phi 700 mm high-carbon high-chromium cold-working die steel forged round steel
CN100537116C (en) Build-up welding process for low-alloy cast iron valve body sealing surface
CN103352171A (en) High-alloy steel D2 rolling method
CN106591543A (en) Heat treatment method for mold
CN115558860A (en) Welding wire for high-strength steel containing vanadium and niobium, welding wire for high-strength steel and production method of welding wire
CN111394590A (en) Vacuum consumable remelting method for wrought superalloy GH4169
CN105861946A (en) SA387Gr11Cl1 steel plate for petrochemical pipelines and production method thereof
CN112935708A (en) Manufacturing process of ultra-large wheel belt forge piece
CN114438394B (en) Production process of pre-hardened high-polishing plastic mold steel
CN107282854B (en) A kind of manufacturing process of nuclear power retaining ring
CN112475790A (en) Novel flange production process
CN112695248B (en) Wear-resistant hot-rolled seamless steel tube for conveying concrete containing rare earth and production method thereof
CN102517428A (en) Method for producing low compression ratio crack detection thick plate
CN112813243A (en) Heat treatment process for large high-chromium iron casting impeller product in dredging industry
CN110499467A (en) A kind of used in nuclear power station P280GH carbon steel forging and its manufacturing method
CN1160522C (en) Technology for manufacturing large-diameter thick-wall seamless steel pipe
CN111037218A (en) Processing technology of welding neck flange
CN105714062A (en) Production method of high strength extra-thick boiler steam drum steel plate
CN113265575B (en) Preparation method of extra-thick Mn-Cr series die steel
CN112795838B (en) High-speed steel roll collar of profile steel rail beam universal mill and preparation method thereof
CN110819771B (en) Heat treatment process for controlling size of 42CrMo annular forging
CN111926255A (en) High-carbon chromium bearing steel and production method thereof
CN113604733A (en) High-temperature-resistant and high-toughness high-end hot-work die steel and production process thereof
CN103343292B (en) Production method of large explosive pressing mould
KR101341122B1 (en) Apparatus and methods for manufacturing metal ring

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination