CN112418700B - 一种电力容量市场需求曲线设计方法、装置及设备 - Google Patents
一种电力容量市场需求曲线设计方法、装置及设备 Download PDFInfo
- Publication number
- CN112418700B CN112418700B CN202011379454.6A CN202011379454A CN112418700B CN 112418700 B CN112418700 B CN 112418700B CN 202011379454 A CN202011379454 A CN 202011379454A CN 112418700 B CN112418700 B CN 112418700B
- Authority
- CN
- China
- Prior art keywords
- capacity
- reliability
- unit
- period
- market demand
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 22
- 238000013461 design Methods 0.000 title claims abstract description 17
- 238000012423 maintenance Methods 0.000 claims abstract description 7
- 238000012360 testing method Methods 0.000 claims description 9
- 238000011156 evaluation Methods 0.000 claims description 8
- 238000012545 processing Methods 0.000 claims description 8
- 238000013507 mapping Methods 0.000 claims description 6
- 238000010586 diagram Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 230000008859 change Effects 0.000 description 3
- 230000007423 decrease Effects 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 2
- 230000006870 function Effects 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 238000000342 Monte Carlo simulation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000033228 biological regulation Effects 0.000 description 1
- 238000012888 cubic function Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 238000010977 unit operation Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0637—Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q30/00—Commerce
- G06Q30/02—Marketing; Price estimation or determination; Fundraising
- G06Q30/0201—Market modelling; Market analysis; Collecting market data
- G06Q30/0202—Market predictions or forecasting for commercial activities
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Development Economics (AREA)
- Physics & Mathematics (AREA)
- Finance (AREA)
- Accounting & Taxation (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Tourism & Hospitality (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Water Supply & Treatment (AREA)
- Public Health (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- General Health & Medical Sciences (AREA)
- Data Mining & Analysis (AREA)
- Primary Health Care (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011379454.6A CN112418700B (zh) | 2020-11-30 | 2020-11-30 | 一种电力容量市场需求曲线设计方法、装置及设备 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011379454.6A CN112418700B (zh) | 2020-11-30 | 2020-11-30 | 一种电力容量市场需求曲线设计方法、装置及设备 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112418700A CN112418700A (zh) | 2021-02-26 |
CN112418700B true CN112418700B (zh) | 2023-10-03 |
Family
ID=74829115
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011379454.6A Active CN112418700B (zh) | 2020-11-30 | 2020-11-30 | 一种电力容量市场需求曲线设计方法、装置及设备 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112418700B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115115352B (zh) * | 2022-08-29 | 2022-11-08 | 山东中鲁实业有限公司 | 基于数字化城市运行管理服务的公共设备运行控制系统 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7698233B1 (en) * | 2007-01-23 | 2010-04-13 | Southern Company Services, Inc. | System and method for determining expected unserved energy to quantify generation reliability risks |
CN105429129A (zh) * | 2015-10-14 | 2016-03-23 | 中国电力科学研究院 | 一种考虑网络约束的间歇性能源发电容量置信度评估方法 |
CN106056305A (zh) * | 2016-06-14 | 2016-10-26 | 中国电力工程顾问集团中南电力设计院有限公司 | 一种基于状态聚类的发电系统可靠性快速评估方法 |
CN106469337A (zh) * | 2016-09-30 | 2017-03-01 | 西安交通大学 | 考虑跨区联络线约束的分区电力容量市场模型设计和定价方法 |
CN109149555A (zh) * | 2017-06-15 | 2019-01-04 | 华北电力大学 | 考虑供电模式的配电网广义电源变电可信容量评价方法 |
CN109428344A (zh) * | 2017-09-01 | 2019-03-05 | 国家电网公司 | 含风电场的多电源投资规划方法和装置 |
CN110648176A (zh) * | 2019-09-20 | 2020-01-03 | 南方电网能源发展研究院有限责任公司 | 一种电力容量市场与电能量市场的衔接方法、装置及设备 |
CN112001531A (zh) * | 2020-08-04 | 2020-11-27 | 南京工程学院 | 基于有效载荷能力的风电短期运行容量可信度评估方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10169726B2 (en) * | 2014-02-06 | 2019-01-01 | Siemens Industry, Inc. | Systems, methods and apparatus for improved operation of electricity markets |
-
2020
- 2020-11-30 CN CN202011379454.6A patent/CN112418700B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7698233B1 (en) * | 2007-01-23 | 2010-04-13 | Southern Company Services, Inc. | System and method for determining expected unserved energy to quantify generation reliability risks |
CN105429129A (zh) * | 2015-10-14 | 2016-03-23 | 中国电力科学研究院 | 一种考虑网络约束的间歇性能源发电容量置信度评估方法 |
CN106056305A (zh) * | 2016-06-14 | 2016-10-26 | 中国电力工程顾问集团中南电力设计院有限公司 | 一种基于状态聚类的发电系统可靠性快速评估方法 |
CN106469337A (zh) * | 2016-09-30 | 2017-03-01 | 西安交通大学 | 考虑跨区联络线约束的分区电力容量市场模型设计和定价方法 |
CN109149555A (zh) * | 2017-06-15 | 2019-01-04 | 华北电力大学 | 考虑供电模式的配电网广义电源变电可信容量评价方法 |
CN109428344A (zh) * | 2017-09-01 | 2019-03-05 | 国家电网公司 | 含风电场的多电源投资规划方法和装置 |
CN110648176A (zh) * | 2019-09-20 | 2020-01-03 | 南方电网能源发展研究院有限责任公司 | 一种电力容量市场与电能量市场的衔接方法、装置及设备 |
CN112001531A (zh) * | 2020-08-04 | 2020-11-27 | 南京工程学院 | 基于有效载荷能力的风电短期运行容量可信度评估方法 |
Non-Patent Citations (7)
Title |
---|
别佩.考虑风电接入的电力系统有功实时调度模型与算法研究.中国博士学位论文全文数据库 (工程科技Ⅱ辑).2019,全文. * |
张妍,陈启鑫,郭鸿业,王一,卢恩.引入投资决策的电力容量市场均衡分析.电力系统自动化.2020,第44卷(第20期),全文. * |
张粒子 ; 许通 ; 宋少群 ; 张枫 ; .电力市场中发电容量充裕性评估方法及保障机制.电力系统自动化.2020,(18),全文. * |
田琳,甘倍瑜,孙谦,季天瑶,盛剑胜等.广东电力现货市场信用风险管理.南方电网技术.2019,第13卷(第6期),全文. * |
蔡霁霖 ; 徐青山 ; 王旭东 ; .基于加速时序蒙特卡洛法的风电场置信容量评估.电力系统自动化.2018,(第05期),全文. * |
郭乐,张丹丹.几种基于可靠性指标的容量支持机制电力市场分析.华电技术.2019,第41卷(第11期),全文. * |
陈新宇.Distributed Piecewise Approximation Economic Dispatch for Regional Power Systems Under Non-Ideal Communication.IEEE.2019,第7卷全文. * |
Also Published As
Publication number | Publication date |
---|---|
CN112418700A (zh) | 2021-02-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Morshed et al. | A probabilistic multi-objective approach for power flow optimization in hybrid wind-PV-PEV systems | |
Wen et al. | A review on reliability assessment for wind power | |
CN108183512B (zh) | 一种接入新能源的电力系统的可靠性评估方法 | |
CN106532688B (zh) | 一种用于评估微电网运行可靠性的方法及系统 | |
CN107403256B (zh) | 一种考虑需求响应不确定性的光伏微网电池储能配置方法 | |
Billinton | Impacts of energy storage on power system reliability performance | |
Huo et al. | Chance-constrained optimization for integrated local energy systems operation considering correlated wind generation | |
CN111898805A (zh) | 一种储能系统容量配置方法、装置、配置设备和存储介质 | |
CN105226650A (zh) | 基于微燃机-储能联合运行策略的微电网可靠性计算方法 | |
CN105279707A (zh) | 一种综合考虑负荷与风电时序特性的随机生产模拟方法 | |
CN109713674A (zh) | 计及电动汽车有序充放电的离网型微电网可靠性评估方法 | |
CN111563637A (zh) | 基于需求响应的多目标概率最优潮流计算方法及装置 | |
CN110112790A (zh) | 有源配电网运行效率的评价方法、装置、设备及存储介质 | |
CN110580538B (zh) | 一种电力系统备用需求的预测方法及装置 | |
CN107506331B (zh) | 基于时间关联性及元件运行时间的微电网可靠性计算方法 | |
CN107359611B (zh) | 考虑多种随机因素的配电网等值方法 | |
CN112418700B (zh) | 一种电力容量市场需求曲线设计方法、装置及设备 | |
CN116470543A (zh) | 一种虚拟电厂的运行控制方法、装置、设备及介质 | |
CN111382518A (zh) | 风储联合系统的置信容量评估方法 | |
CN105870913B (zh) | 考虑供暖约束的时序蒙特卡洛模拟可靠性评估方法及系统 | |
Wang et al. | Source-load scenario generation based on weakly su-pervised adversarial learning and its data-driven appli-cation in energy storage capacity sizing | |
Chen et al. | An evaluation method of distributed generation credible capacity based on island partition | |
CN115577964A (zh) | 基于分布式鲁棒优化的新能源接纳能力评估方法及系统 | |
CN111796143B (zh) | 一种配用电系统节能设备节能量计量方法 | |
CN112398174B (zh) | 发电系统的最大输出功率确定方法、装置、控制器及系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20220530 Address after: 3 / F, Yuedian building, No.6 and 8 shuijungang, Dongfeng East Road, Yuexiu District, Guangzhou, Guangdong 510062 Applicant after: GUANGDONG ELECTRIC POWER TRANSACTION CENTER CO.,LTD. Address before: 3 / F, Yuedian building, No.6 and 8 shuijungang, Dongfeng East Road, Yuexiu District, Guangzhou, Guangdong 510062 Applicant before: GUANGDONG ELECTRIC POWER TRANSACTION CENTER CO.,LTD. Applicant before: Huazhong University of Science and Technology |
|
GR01 | Patent grant | ||
GR01 | Patent grant |