CN112412054A - Construction method for cumulating and synchronously lifting different structural systems - Google Patents

Construction method for cumulating and synchronously lifting different structural systems Download PDF

Info

Publication number
CN112412054A
CN112412054A CN202011189587.7A CN202011189587A CN112412054A CN 112412054 A CN112412054 A CN 112412054A CN 202011189587 A CN202011189587 A CN 202011189587A CN 112412054 A CN112412054 A CN 112412054A
Authority
CN
China
Prior art keywords
lifted
lifting
structures
lifter
dismantling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011189587.7A
Other languages
Chinese (zh)
Inventor
何成元
刘宇欣
张福川
蒋国明
年全军
黄文华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Shanghai Steel Structure Technology Co Ltd
Original Assignee
MCC Shanghai Steel Structure Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shanghai Steel Structure Technology Co Ltd filed Critical MCC Shanghai Steel Structure Technology Co Ltd
Priority to CN202011189587.7A priority Critical patent/CN112412054A/en
Publication of CN112412054A publication Critical patent/CN112412054A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a construction method for cumulating and synchronously lifting different structural systems, which comprises the following steps of 1: construction of a lifting structure; step 2: the ground of the lifted structure is preassembled; and step 3: installing lifting equipment; and 4, step 4: fixing the first lifted structure and the lifting structure; and 5: the rest lifter lifts the second lifted structure by a preset height; step 6: installing a supplement rod piece between the lifted structures; and 7: removing the lifting equipment on the first lifted structure; and 8: dismantling the section steel between the first lifted structure and the lifting structure; and step 9: the lifter lifts the lifted structure to a design elevation; step 10: installing and welding rear-mounted rod pieces between the lifted structure and the pre-mounting structure and between the lifted structure and the lifting structure; step 11: and (5) dismantling the lifting equipment. The invention reduces the high-altitude operation amount to the maximum extent, and is beneficial to the control of construction safety, quality and progress.

Description

Construction method for cumulating and synchronously lifting different structural systems
Technical Field
The invention relates to the field of building construction, in particular to a construction method for cumulating and synchronously lifting different structural systems.
Background
The hydraulic lifting technology of the single-form structural system is mature, for example, the grid structure lifting and the truss structure lifting are performed, when one structure is composed of two different structural systems, if the two structural systems are integrally lifted, the high-altitude operation amount can be reduced, the quality control and the safety management are facilitated, the construction period is shortened, but the different structural systems are different in section height and cannot be lifted in place at one time, and the accumulative lifting is required.
Disclosure of Invention
The invention aims to overcome the defects of the prior art, provides a construction method for cumulatively and synchronously lifting different structural systems, and solves the problem of lifting construction of two structural systems with different section heights.
In order to solve the technical problem, the invention is realized as follows:
a construction method for cumulating and synchronously lifting different structural systems is characterized by comprising the following steps:
step 1: constructing all lifting structures;
step 2: assembling and welding the ground of the first and second lifted structures, and installing a pre-assembly structure, wherein the pre-assembly structure comprises an air pipe, a fire-fighting water pipe, a roof purline and a truss auxiliary structure;
and step 3: all lifting supports and lifters are installed: a lifting bracket, a lifter and a steel strand are arranged on the lifting structure and the lifted structure;
and 4, step 4: after a preset force value is applied to part of the lifters, fixing the first lifted structure and the lifting structures on two sides of the first lifted structure, and preventing the first lifted structure from displacing when the steps 5, 6 and 7 are carried out;
and 5: the rest part lifter lifts the second lifted structure by a preset height;
step 6: mounting and welding a supplementary rod piece between the first and second lifted structures;
and 7: unloading and dismantling the lifting support and the lifter on the first lifted structure after the flaw detection of the additional rod piece is qualified;
and 8: removing the section steel temporarily connected between the first lifted structure and the lifting structures on the two sides of the first lifted structure;
and step 9: lifting the first and second lifted structures to a designed elevation by using a lifter;
step 10: mounting and welding rear-mounted rod pieces between the first and second lifted structures and the pre-mounting structure and between the first and second lifted structures and the lifting structures on the two sides of the first and second lifted structures;
step 11: and unloading and dismantling the lifting support and the lifter after the flaw detection of the rear loading rod piece is qualified.
The invention has the beneficial effects that: the high-altitude operation amount is reduced to the maximum extent, the safety control of projects is facilitated, the construction operation efficiency is improved, the construction cost is reduced, and the construction quality is ensured.
Drawings
The invention is described in further detail below with reference to the following figures and embodiments:
FIG. 1 steel structure lifting axonometric drawing
FIG. 2 is a schematic view of a lifting structure;
FIG. 3 is a schematic view of the assembly and welding of the ground of the structure to be lifted, the installation of the auxiliary structures such as air pipes, roof purlins, fire hoses and the like, and the installation of the preassembly structure;
FIG. 4 is a schematic illustration of a lifting installation;
FIG. 5 is a plan view of the first lifting points of the net rack
FIG. 6 is a schematic view showing the first lifted structure and the fixed structure of the lifting structure before the net rack is lifted for the first time
FIG. 7 is a schematic view of the first lifting of the rack;
FIG. 8 is a schematic view of the installation of the supplemental rods between the net rack and the truss;
FIG. 9 is a schematic view of the truss and the net rack being lifted to a designed elevation as a whole;
FIG. 10 is a plan view of the truss and net rack integral lifting points;
FIG. 11 is a schematic view of the remaining rear loading bar installation welding;
fig. 12 is a schematic view of the lifting installation being unloaded and dismantled.
Detailed Description
A construction method for cumulating and synchronously lifting different structural systems comprises the following steps:
as shown in fig. 2: step 1: constructing all the lifting structures 1, 4 and 5;
as shown in fig. 3: step 2: the first and second lifted structures 3 and 6 are assembled and welded on the ground, and the pre-assembly structure 2 is installed and comprises an air pipe, a fire hose 21 and a roof purline 22;
as shown in fig. 4: and step 3: installation of all lifting devices 7, 8, 9, 10, 11, 12, which are installed including lifting brackets 31 and lifters 32: a lifting bracket, a lifter and a steel strand 33 are arranged on the lifting structure and the lifted structure;
as shown in fig. 6: and 4, step 4: after a preset force value is applied to the partial lifting devices 9 and 11, the first lifted structure 6 and the lifting structures 4 and 5 on the two sides of the first lifted structure are fixed by using H-shaped steel 13, so that the first lifted structure 6 is prevented from being displaced when the steps 5, 6 and 7 are carried out;
as shown in fig. 7: and 5: the remaining part of the lifting devices 7, 8, 10, 12 lifts the second structure to be lifted 3 by a predetermined height;
as shown in fig. 8: step 6: mounting and welding a supplement rod 41 between the first and second lifted structures 3 and 6;
and 7: unloading and dismantling the lifting equipment 10 on the first lifted structure 6 after the flaw detection of the supplementing rod piece is qualified;
and 8: removing the section steel temporarily connected between the first lifted structure 6 and the lifting structures 4 and 5 on the two sides of the first lifted structure;
as shown in fig. 9: and step 9: lifting the first and second structures to be lifted 3 and 6 to a design elevation by using lifting devices 7, 8, 9, 11 and 12;
as shown in fig. 11: step 10: installing and welding rear loading rod pieces 42 between the first and second lifted structures 3 and 6 and the preassembly structure 2 and between the first and second lifted structures 3 and 6 and the lifting structures 4 and 5 on the two sides of the first and second lifted structures;
as shown in fig. 12: step 11: and unloading and dismantling the lifting devices 7, 8, 9, 11 and 12 after the flaw detection of the rear loading rod piece is qualified.

Claims (1)

1. A construction method for cumulating and synchronously lifting different structural systems is characterized by comprising the following steps:
step 1: constructing all lifting structures;
step 2: assembling and welding the ground of the first and second lifted structures, and installing a pre-assembly structure, wherein the pre-assembly structure comprises an air pipe, a fire-fighting water pipe, a roof purline and a truss auxiliary structure;
and step 3: all lifting supports and lifters are installed: a lifting bracket, a lifter and a steel strand are arranged on the lifting structure and the lifted structure;
and 4, step 4: after a preset force value is applied to part of the lifters, fixing the first lifted structure and the lifting structures on two sides of the first lifted structure, and preventing the first lifted structure from displacing when the steps 5, 6 and 7 are carried out;
and 5: the rest part lifter lifts the second lifted structure by a preset height;
step 6: mounting and welding a supplementary rod piece between the first and second lifted structures;
and 7: unloading and dismantling the lifting support and the lifter on the first lifted structure after the flaw detection of the additional rod piece is qualified;
and 8: removing the section steel temporarily connected between the first lifted structure and the lifting structures on the two sides of the first lifted structure;
and step 9: lifting the first and second lifted structures to a designed elevation by using a lifter;
step 10: mounting and welding rear-mounted rod pieces between the first and second lifted structures and the pre-mounting structure and between the first and second lifted structures and the lifting structures on the two sides of the first and second lifted structures;
step 11: and unloading and dismantling the lifting support and the lifter after the flaw detection of the rear loading rod piece is qualified.
CN202011189587.7A 2020-10-30 2020-10-30 Construction method for cumulating and synchronously lifting different structural systems Pending CN112412054A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011189587.7A CN112412054A (en) 2020-10-30 2020-10-30 Construction method for cumulating and synchronously lifting different structural systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011189587.7A CN112412054A (en) 2020-10-30 2020-10-30 Construction method for cumulating and synchronously lifting different structural systems

Publications (1)

Publication Number Publication Date
CN112412054A true CN112412054A (en) 2021-02-26

Family

ID=74828051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011189587.7A Pending CN112412054A (en) 2020-10-30 2020-10-30 Construction method for cumulating and synchronously lifting different structural systems

Country Status (1)

Country Link
CN (1) CN112412054A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103835511A (en) * 2014-02-28 2014-06-04 中天建设集团有限公司 Integral lifting method for ultra-long light thin giant steel tube truss
CN111042542A (en) * 2019-12-18 2020-04-21 中建科工集团有限公司 Cumulative lifting method for large-span unequal-height bidirectional curved surface net rack

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103835511A (en) * 2014-02-28 2014-06-04 中天建设集团有限公司 Integral lifting method for ultra-long light thin giant steel tube truss
CN111042542A (en) * 2019-12-18 2020-04-21 中建科工集团有限公司 Cumulative lifting method for large-span unequal-height bidirectional curved surface net rack

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
薛海龙: "大跨度钢网架累积提升结合水平张拉施工技术", 《建筑施工》 *

Similar Documents

Publication Publication Date Title
CN111976917B (en) Method for installing outfitting piece of ship superstructure
CN101759098A (en) Crane beam frame construction method
CN105888229A (en) All-steel attached scaffold mounting method
CN110159057B (en) Mounting and construction method for smoke pipe of technically improved factory building
CN112412054A (en) Construction method for cumulating and synchronously lifting different structural systems
CN217150619U (en) Annular steel structure mounting structure
CN216949308U (en) Shear force wall ventilation shaft inside lining tuber pipe system convenient to installation
CN110924693A (en) Method for mounting large-span steel frame by using temporary support jig
CN113756504B (en) Construction method of right-angle aluminum alloy latticed shell with external corners
CN202954553U (en) Full assembly tool type attachment lifting scaffold
CN113202328A (en) Vertical building prefabricated part reinforcing and adjusting device and reinforcing method
CN210289075U (en) Adjustable elevator shaft operating platform system that can have enough to meet need
CN217201767U (en) Rectangular air pipe hoisting device
CN216864792U (en) Novel steel construction view corridor bridge
CN112647718A (en) Siphon pipeline suspension joint structure of steel structure roof and construction method thereof
CN115492388B (en) Construction method for vertical-surface cable membrane of huge-width outward-inclined cable back-pulling system
CN214274718U (en) Outer outdoor pipe frame structure of large-scale electronic factory building power station
CN219431172U (en) Adopt corner to prop reinforcing H shaped steel purlin roof
CN218643637U (en) Mounting structure of glass curtain wall
CN210153331U (en) Auxiliary jig frame for installation of arc-shaped circular air pipe
CN117166813B (en) Construction method for building curtain wall reconstruction external protection system
CN220414819U (en) Auxiliary wall-attached support is installed in linking bridge on built on stilts layer
CN115676559A (en) Steel construction elevator well
CN219431170U (en) Adopt corner to prop reinforcing C shaped steel purlin roof
CN219326471U (en) Adjustable machine room bearing heightening platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210226