CN112365124A - Intelligent construction site construction material rapid distribution working method - Google Patents

Intelligent construction site construction material rapid distribution working method Download PDF

Info

Publication number
CN112365124A
CN112365124A CN202011111332.9A CN202011111332A CN112365124A CN 112365124 A CN112365124 A CN 112365124A CN 202011111332 A CN202011111332 A CN 202011111332A CN 112365124 A CN112365124 A CN 112365124A
Authority
CN
China
Prior art keywords
construction material
distribution
data
material distribution
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202011111332.9A
Other languages
Chinese (zh)
Inventor
熊榆
洪敏�
万里
白金龙
胡宇
唐良艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Hui Hui Information Technology Co ltd
Original Assignee
Chongqing Hui Hui Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Hui Hui Information Technology Co ltd filed Critical Chongqing Hui Hui Information Technology Co ltd
Priority to CN202011111332.9A priority Critical patent/CN112365124A/en
Publication of CN112365124A publication Critical patent/CN112365124A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention provides a construction material rapid distribution working method in an intelligent construction site, which comprises the following steps: acquiring a first execution task of material statistics corresponding to construction material data to be distributed in the construction material data and a second execution task of material work corresponding to the distribution material of the construction material data to be distributed; comparing the difference between the quantity of construction material between the first fulfillment task material statistics and the second fulfillment task allocation material jobs; and when the difference is not in the difference range of the set material statistics, determining the control parameters needing to be distributed for the distributed materials in the construction material statistical data according to the distributed materials.

Description

Intelligent construction site construction material rapid distribution working method
Technical Field
The invention relates to the field of computer data analysis, in particular to a working method for quickly distributing construction materials in an intelligent construction site.
Background
Along with the needs of urban construction development, a large amount of infrastructure construction is continuously promoted, because construction sites need a large amount of construction materials, under the huge requirement of the construction materials, great challenges are provided for flexible distribution and rapid operation of the construction materials in the construction sites, if the construction materials are still manually allocated according to the prior art, low efficiency and management carelessness are certainly caused, efficient and flexible distribution under the mass data of the construction materials cannot be solved, and the technical problem of solving the corresponding technical problems by technical personnel in the field is urgently needed.
Disclosure of Invention
The invention aims to at least solve the technical problems in the prior art, and particularly provides a quick construction material distribution working method in an intelligent construction site.
In order to achieve the above object, the present invention provides a work method for fast distribution of construction materials in an intelligent construction site, comprising the steps of:
s1, acquiring a first execution task of material statistics corresponding to the to-be-distributed construction material data in the construction material data and a second execution task of material work corresponding to the to-be-distributed construction material data; comparing the difference between the quantity of construction material between the first fulfillment task material statistics and the second fulfillment task allocation material jobs; when the difference is not in the difference range of the set material statistics, determining control parameters needing to be distributed for the distributed materials in the construction material statistical data according to the distributed materials;
s2, after determining the control parameters, sending an allocation request containing construction material data identification to a rapid allocation unit, wherein the allocation request is used for requesting that the material statistics identification stored in the first execution task corresponds to a construction material data source; and receiving material distribution data fed back by the rapid distribution unit according to the difference, and determining at least a data source of construction material distribution according to the distribution data.
Preferably, the method further comprises the following steps:
s3, acquiring a construction material data calibration sequence corresponding to the material statistics from the rapid distribution unit according to the difference; calculating the material distribution space of the construction material data calibration sequence according to the construction material distribution objective function control model,
the objective function control model is
Figure BDA0002728699530000021
Wherein u isiCalculating a target function for construction material data, wherein lambda is a characteristic mean value of the construction material with the category of x, and setting a constant gamma, and k is an estimated hidden variable distributed to the construction material;
s4, constraining the first distribution range of the construction materials through the objective function control model, and acquiring a second distribution range of the construction material data sequence to make the second distribution range be an initial distribution expression area of the next construction material data sequence; and carrying out construction material distribution updating through the objective function control model to obtain an updated objective function control model, dividing initial construction material distribution content corresponding to a previous construction material data sequence according to updated objective function control to obtain an initial distribution expression area corresponding to a next construction material data sequence, and obtaining a construction material distribution result until all the construction material data in the construction material data sequence are distributed.
Preferably, the method further comprises the following steps:
s5, accumulating the times of filling the construction materials according to the times of data distribution of each construction material in the control parameters of the construction materials needing to be distributed, and calculating the corresponding construction material distribution coefficient by using the control parameters of the distribution materials needing to be distributed; the number of times of data distribution of each construction material and the distribution coefficient of the construction materials are used as the output of control parameters of the distribution materials needing to be distributed; acquiring expected values of construction material distribution according to control parameters needing to be distributed for distributing the materials, and acquiring predicted values of each construction material in different construction material attributes; and forming a construction material distribution range value according to the construction material distribution expected value and each construction material estimated value, and acquiring distribution control convergence information of each construction material estimated value, wherein the construction material distribution range value comprises the distribution times of each construction material data distributed by each construction material data, the filling times of accumulated construction materials and the filling times of accumulated construction materials.
Preferably, the method further comprises the following steps:
s6, calculating to obtain an initial value of each construction material distribution convergence interval according to the construction material distribution control type of each construction material estimated value and the construction material distribution range value; according to the construction material distribution range value, the times of distributing each kind of construction material data distributed by each kind of construction material data, the times of filling the construction materials and the times of filling the construction materials are accumulated; inquiring a construction material distribution control information table to obtain a plurality of construction material distribution convergence parameters;
determining a plurality of convergence parameter distribution convergence parameters and a hand chain parameter balance value of the initial construction material distribution type to obtain a plurality of convergence parameter balance values; calculating distribution results of a plurality of convergence parameter balance values and corresponding control parameters of distribution materials to be distributed, and processing the control parameters of the distribution materials to be distributed according to distribution process information in the construction material distribution results to obtain a plurality of construction material distribution control sets;
and sequentially extracting the construction material distribution association processes in the plurality of construction material distribution convergence parameter sets, taking the construction material distribution association units in the concentrated construction material distribution association processes as quick distribution units, and respectively and sequentially generating a construction material distribution sequence corresponding to each construction material distribution process according to the concentrated construction material distribution association processes.
Preferably, the method further comprises the following steps:
s7, respectively matching the association strength of the rapid distribution units in the centralized construction material distribution association process with each construction material distribution sequence, wherein the association strength corresponds to the sequence length of the construction material distribution sequence in an association relationship; setting corresponding construction material distribution association nodes for each construction material distribution sequence according to the association strength matched with each construction material distribution sequence, forming association relations for the construction material distribution sequences of the construction material distribution association nodes according to a concentrated construction material distribution association process, and acquiring a construction material rapid distribution model from a construction material distribution model corresponding to the formed association relations according to the classes of a plurality of construction material distribution control sets corresponding to each construction material distribution sequence completing the association relations; and combining the construction material distribution coefficients of each construction material rapid distribution model to obtain the corresponding rapid distribution coefficients.
Preferably, the method further comprises the following steps:
s8, generating a mirror image coding space for recording the construction material distribution mirror image file, mapping the construction material distribution mirror image file to the mirror image preparation space, and setting the distribution state of the construction material distribution mirror image file according to the construction material type; judging whether the construction material distribution is in a state of executing the construction material distribution control parameter according to the distribution state, and determining to judge the construction material distribution coefficient according to the analysis instruction when the distribution flow information in the construction material distribution result is not in a threshold value limited by executing the construction material distribution coefficient; analyzing a construction material distribution coefficient in the judging process, determining construction material data distribution for distributing the construction material data to be distributed according to the construction material distribution coefficient and distributing flow parameters for each construction material, performing mirror image search on each data distribution node related to the construction material data to be distributed according to the construction material distribution control flow parameters, and determining distribution type attributes corresponding to the construction material data to be distributed; and determining a construction material distribution queue according to the distribution type attribute, extracting behavior distribution data of construction material distribution business behaviors, taking a set threshold value as a business mirror region of the construction material distribution business behaviors, and extracting a construction material distribution set of which each construction material distribution data is associated with a plurality of construction material distribution queues.
Preferably, the method further comprises the following steps:
s9, generating a plurality of logic association sections according to the logic association relationship of the construction material logic blocks in the construction material allocation behaviors according to at least two associated construction material allocation behaviors in the set, calculating the construction material allocation difference between all the construction material logic blocks in the next construction material allocation behavior and all the construction material logic blocks in the previous construction material allocation behavior, and corresponding to a construction material allocation association relationship table according to each obtained difference;
according to the construction material distribution incidence relation table, construction material logic blocks are matched according to the logic incidence relation, and the construction material logic blocks of the two logic incidence sections are different from each other by less than the maximum logic difference of the construction material distribution behaviors in the logic difference, so that the construction material distribution space is established; in the establishment of each construction material distribution space, distributing a distribution interval of each construction material distribution behavior space, and mirroring the construction material distribution behavior space according to the construction material distribution behavior expression data to obtain a plurality of mirrored construction material distribution intervals; matching according to the distribution interval of the construction material distribution behavior space and the construction material distribution intervals of the plurality of mirror images to obtain a matching interval of construction material distribution; and obtaining the target data distribution of the construction material distribution to be distributed from the matching interval, and then extracting the distribution control flow parameters of each construction material distribution.
Preferably, the method further comprises the following steps:
s10, if receiving the allocation request of the construction material data identification sent by the rapid allocation unit again, checking the allocated construction material according to the allocation request, wherein the checking process detects the change of the construction material allocation identification through the rapid allocation unit, and is relative to the distribution process of the rapid allocation unit; the construction material increase or construction material decrease has an influence on control parameters of the construction materials to be distributed, the rapid distribution unit detects the increased construction material types when the construction materials are increased and reduces the distribution of the increased construction materials, the rapid distribution unit detects the reduced construction material types when the construction materials are reduced and increases the distribution of the reduced construction materials, and stores the distribution identification of the construction materials, and then the number of the corresponding construction materials to be increased and reduced is obtained; when the data source with reduced construction material distribution obtains the construction material distribution identification detected by the rapid distribution unit, and the construction material distribution identification is reduced corresponding to the data source of the rapid distribution unit, obtaining the data address of the reduced construction material distribution data source; if the data source of the construction material distribution sends a request for acquiring the data source; the received data source feeds back and obtains a data address of the construction material data source according to the construction material screening condition; marking a unique identifier according to the identifier serial number of the rapid distribution unit, forming a construction material distribution data set by using the identifiers with the same construction material distribution data, recording the time, the place and the specific material list of construction material distribution, thereby recommending data for the next construction material distribution, and distributing target data to be distributed to each construction material target data distribution control flow parameter according to the construction material distribution control parameters; executing construction material distribution operation on the construction material data to be distributed according to the determined construction material distribution data and aiming at each construction material distribution task;
preferably, the method further comprises the following steps:
s11, performing task assignment on each construction material distribution task in the rapid distribution unit according to the control parameters for distribution, determining the construction material distribution flow of each construction material distribution task, and acquiring a construction material distribution flow configuration file according to the construction material distribution flow; determining distribution process configuration information of the construction material distribution tasks according to the construction material distribution process configuration file, searching the distribution process configuration information of the construction material distribution tasks based on the last construction material distribution control configuration information, intercepting data fields at the same position according to the distribution process configuration information of two adjacent construction material distribution tasks for position comparison, and combining the data fields into one data vector according to the distribution process configuration information of the two adjacent construction material distribution tasks; extracting distribution parameters corresponding to the distribution flow configuration information of each construction material distribution task and used for representing the construction material distribution tasks from the data vectors; and controlling the calling information during construction material distribution according to the construction material distribution flow of the construction material distribution task, merging each construction material distribution flow according to the construction material distribution regulation logic relation of each calling information, traversing the calling information in the distribution regulation logic relation in sequence after merging, and performing the construction material distribution data verification process.
Preferably, the method further comprises the following steps:
s12, after calling information in the distribution adjustment logic relation is traversed in sequence, corresponding distribution information of the construction material distribution process is extracted in the verification process, the distribution information of the construction material distribution process is grouped according to different construction material types, a process distribution information identifier of each construction material type is calculated, and distribution data meeting the distribution condition in the construction material distribution is selected according to the process distribution information identifiers; and generating an extraction instruction for extracting the construction material distribution control parameters in the process distribution information identification according to the distribution data meeting the distribution conditions, and acquiring a construction material distribution mirror image file corresponding to the process distribution information identification in the construction material distribution process according to the extraction instruction.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
in the construction material distribution of the intelligent construction site, the distribution result of the construction material distribution can be accurately obtained by positioning effective construction material distribution data, the target control is carried out on the construction material distribution process according to a target function control model, the construction material distribution association processes in a plurality of construction material distribution convergence parameter sets are sequentially extracted, the construction material distribution sequence is called in real time, the distribution data are reasonably planned in the construction material distribution data set, the construction materials are quickly matched and called, and therefore the data are updated and extracted.
Additional aspects and advantages of the invention will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the invention.
Drawings
The above and/or additional aspects and advantages of the present invention will become apparent and readily appreciated from the following description of the embodiments, taken in conjunction with the accompanying drawings of which:
fig. 1 is a general schematic of the present invention.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the accompanying drawings are illustrative only for the purpose of explaining the present invention, and are not to be construed as limiting the present invention.
As shown in FIG. 1, the invention discloses a construction material rapid distribution working method in an intelligent construction site, which comprises the following steps:
s1, acquiring a first execution task of material statistics corresponding to the to-be-distributed construction material data in the construction material data and a second execution task of material work corresponding to the to-be-distributed construction material data; comparing the difference between the quantity of construction material between the first fulfillment task material statistics and the second fulfillment task allocation material jobs; when the difference is not in the difference range of the set material statistics, determining control parameters needing to be distributed for the distributed materials in the construction material statistical data according to the distributed materials;
s2, after determining the control parameters, sending an allocation request containing construction material data identification to a rapid allocation unit, wherein the allocation request is used for requesting that the material statistics identification stored in the first execution task corresponds to a construction material data source; receiving material distribution data fed back by the rapid distribution unit according to the difference, and determining at least a data source of construction material distribution according to the distribution data;
s3, acquiring a construction material data calibration sequence corresponding to the material statistics from the rapid distribution unit according to the difference; calculating the material distribution space of the construction material data calibration sequence according to the construction material distribution objective function control model,
the objective function control model is
Figure BDA0002728699530000081
Wherein u isiCalculating a target function for construction material data, wherein lambda is a characteristic mean value of the construction material with the category of x, setting a construction material constant gamma, and distributing an estimated hidden variable for the construction material;
s4, constraining the first distribution range of the construction materials through the objective function control model, and acquiring a second distribution range of the construction material data sequence to make the second distribution range be an initial distribution expression area of the next construction material data sequence; the method comprises the steps of carrying out construction material distribution updating through an objective function control model to obtain an updated objective function control model, dividing initial construction material distribution content corresponding to a previous construction material data sequence according to updated objective function control to obtain an initial distribution expression area corresponding to a next construction material data sequence, and obtaining a construction material distribution result until all construction material data in the construction material data sequence are distributed;
s5, accumulating the times of filling the construction materials according to the times of data distribution of each construction material in the control parameters of the construction materials needing to be distributed, and calculating the corresponding construction material distribution coefficient by using the control parameters of the distribution materials needing to be distributed; the number of times of data distribution of each construction material and the distribution coefficient of the construction materials are used as the output of control parameters of the distribution materials needing to be distributed; acquiring expected values of construction material distribution according to control parameters needing to be distributed for distributing the materials, and acquiring predicted values of each construction material in different construction material attributes; forming a construction material distribution range value according to the construction material distribution expected value and each construction material predicted value, and acquiring distribution control convergence information of each construction material predicted value, wherein the construction material distribution range value comprises the number of times of distribution of each construction material data distributed by each construction material data, the number of times of filling accumulated construction materials and the number of times of filling accumulated construction materials;
s6, calculating to obtain an initial value of each construction material distribution convergence interval according to the construction material distribution control type of each construction material estimated value and the construction material distribution range value; according to the construction material distribution range value, the times of distributing each kind of construction material data distributed by each kind of construction material data, the times of filling the construction materials and the times of filling the construction materials are accumulated; inquiring a construction material distribution control information table to obtain a plurality of construction material distribution convergence parameters;
determining a plurality of convergence parameter distribution convergence parameters and a hand chain parameter balance value of the initial construction material distribution type to obtain a plurality of convergence parameter balance values; calculating distribution results of a plurality of convergence parameter balance values and corresponding control parameters of distribution materials to be distributed, and processing the control parameters of the distribution materials to be distributed according to distribution process information in the construction material distribution results to obtain a plurality of construction material distribution control sets;
sequentially extracting the construction material distribution association processes in the plurality of construction material distribution convergence parameter sets, taking the construction material distribution association units in the concentrated construction material distribution association processes as quick distribution units, and respectively and sequentially generating a construction material distribution sequence corresponding to each construction material distribution process according to the concentrated construction material distribution association processes;
s7, respectively matching the association strength of the rapid distribution units in the centralized construction material distribution association process with each construction material distribution sequence, wherein the association strength corresponds to the sequence length of the construction material distribution sequence in an association relationship; setting corresponding construction material distribution association nodes for each construction material distribution sequence according to the association strength matched with each construction material distribution sequence, forming association relations for the construction material distribution sequences of the construction material distribution association nodes according to a concentrated construction material distribution association process, and acquiring a construction material rapid distribution model from a construction material distribution model corresponding to the formed association relations according to the classes of a plurality of construction material distribution control sets corresponding to each construction material distribution sequence completing the association relations; combining the construction material distribution coefficients of each construction material rapid distribution model to obtain corresponding rapid distribution coefficients, and executing S8;
s8, generating a mirror image coding space for recording the construction material distribution mirror image file, mapping the construction material distribution mirror image file to the mirror image preparation space, and setting the distribution state of the construction material distribution mirror image file according to the construction material type; judging whether the construction material distribution is in a state of executing the construction material distribution control parameter according to the distribution state, and determining to judge the construction material distribution coefficient according to the analysis instruction when the distribution flow information in the construction material distribution result is not in a threshold value limited by executing the construction material distribution coefficient; analyzing a construction material distribution coefficient in the judging process, determining construction material data distribution for distributing the construction material data to be distributed according to the construction material distribution coefficient and distributing flow parameters for each construction material, performing mirror image search on each data distribution node related to the construction material data to be distributed according to the construction material distribution control flow parameters, and determining distribution type attributes corresponding to the construction material data to be distributed; determining a construction material distribution queue according to the distribution type attribute, extracting behavior distribution data of construction material distribution business behaviors, extracting a business mirror area of the construction material distribution business behaviors by using a set threshold value, and extracting a construction material distribution set of which each construction material distribution data is associated with a plurality of construction material distribution queues;
s9, generating a plurality of logic association sections according to the logic association relationship of the construction material logic blocks in the construction material allocation behaviors according to at least two associated construction material allocation behaviors in the set, calculating the construction material allocation difference between all the construction material logic blocks in the next construction material allocation behavior and all the construction material logic blocks in the previous construction material allocation behavior, and corresponding to a construction material allocation association relationship table according to each obtained difference;
according to the construction material distribution incidence relation table, construction material logic blocks are matched according to the logic incidence relation, and the construction material logic blocks of the two logic incidence sections are different from each other by less than the maximum logic difference of the construction material distribution behaviors in the logic difference, so that the construction material distribution space is established; in the establishment of each construction material distribution space, distributing a distribution interval of each construction material distribution behavior space, and mirroring the construction material distribution behavior space according to the construction material distribution behavior expression data to obtain a plurality of mirrored construction material distribution intervals; matching according to the distribution interval of the construction material distribution behavior space and the construction material distribution intervals of the plurality of mirror images to obtain a matching interval of construction material distribution; obtaining the target data distribution of the construction material distribution to be distributed from the matching interval, and then extracting the distribution control flow parameters distributed by each construction material;
s10, if receiving the allocation request of the construction material data identification sent by the rapid allocation unit again, checking the allocated construction material according to the allocation request, wherein the checking process detects the change of the construction material allocation identification through the rapid allocation unit, and is relative to the distribution process of the rapid allocation unit; the construction material increase or construction material decrease has an influence on control parameters of the construction materials to be distributed, the rapid distribution unit detects the increased construction material types when the construction materials are increased and reduces the distribution of the increased construction materials, the rapid distribution unit detects the reduced construction material types when the construction materials are reduced and increases the distribution of the reduced construction materials, and stores the distribution identification of the construction materials, and then the number of the corresponding construction materials to be increased and reduced is obtained; when the data source with reduced construction material distribution obtains the construction material distribution identification detected by the rapid distribution unit, and the construction material distribution identification is reduced corresponding to the data source of the rapid distribution unit, obtaining the data address of the reduced construction material distribution data source; if the data source of the construction material distribution sends a request for acquiring the data source; the received data source feeds back and obtains a data address of the construction material data source according to the construction material screening condition; marking a unique identifier according to the identifier serial number of the rapid distribution unit, forming a construction material distribution data set by using the identifiers with the same construction material distribution data, recording the time, the place and the specific material list of construction material distribution, thereby recommending data for the next construction material distribution, and distributing target data to be distributed to each construction material target data distribution control flow parameter according to the construction material distribution control parameters; executing construction material distribution operation on the construction material data to be distributed according to the determined construction material distribution data and aiming at each construction material distribution task;
s11, performing task assignment on each construction material distribution task in the rapid distribution unit according to the control parameters for distribution, determining the construction material distribution flow of each construction material distribution task, and acquiring a construction material distribution flow configuration file according to the construction material distribution flow; determining distribution process configuration information of the construction material distribution tasks according to the construction material distribution process configuration file, searching the distribution process configuration information of the construction material distribution tasks based on the last construction material distribution control configuration information, intercepting data fields at the same position according to the distribution process configuration information of two adjacent construction material distribution tasks for position comparison, and combining the data fields into one data vector according to the distribution process configuration information of the two adjacent construction material distribution tasks; extracting distribution parameters corresponding to the distribution flow configuration information of each construction material distribution task and used for representing the construction material distribution tasks from the data vectors; controlling calling information during construction material distribution according to a construction material distribution flow of a construction material distribution task, merging each construction material distribution flow according to a construction material distribution regulation logic relation of each calling information, traversing the calling information in the distribution regulation logic relation in sequence after merging, and performing a construction material distribution data verification process;
s12, after calling information in the distribution adjustment logic relation is traversed in sequence, corresponding distribution information of the construction material distribution process is extracted in the verification process, the distribution information of the construction material distribution process is grouped according to different construction material types, a process distribution information identifier of each construction material type is calculated, and distribution data meeting the distribution condition in the construction material distribution is selected according to the process distribution information identifiers; and generating an extraction instruction for extracting the construction material distribution control parameters in the process distribution information identification according to the distribution data meeting the distribution conditions, and acquiring a construction material distribution mirror image file corresponding to the process distribution information identification in the construction material distribution process according to the extraction instruction.
While embodiments of the invention have been shown and described, it will be understood by those of ordinary skill in the art that: various changes, modifications, substitutions and alterations can be made to the embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the claims and their equivalents.

Claims (10)

1. A construction material rapid distribution working method in an intelligent construction site is characterized by comprising the following steps:
s1, acquiring a first execution task of material statistics corresponding to the to-be-distributed construction material data in the construction material data and a second execution task of material work corresponding to the to-be-distributed construction material data; comparing the difference between the quantity of construction material between the first fulfillment task material statistics and the second fulfillment task allocation material jobs; when the difference is not in the difference range of the set material statistics, determining control parameters needing to be distributed for the distributed materials in the construction material statistical data according to the distributed materials;
s2, after determining the control parameters, sending an allocation request containing construction material data identification to a rapid allocation unit, wherein the allocation request is used for requesting that the material statistics identification stored in the first execution task corresponds to a construction material data source; and receiving material distribution data fed back by the rapid distribution unit according to the difference, and determining at least a data source of construction material distribution according to the distribution data.
2. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s3, acquiring a construction material data calibration sequence corresponding to the material statistics from the rapid distribution unit according to the difference; calculating the material distribution space of the construction material data calibration sequence according to the construction material distribution objective function control model,
the objective function control model is
Figure FDA0002728699520000011
Wherein u isiCalculating a target function for construction material data, wherein lambda is a characteristic mean value of the construction material with the category of x, and setting a constant gamma, and k is an estimated hidden variable distributed to the construction material;
s4, constraining the first distribution range of the construction materials through the objective function control model, and acquiring a second distribution range of the construction material data sequence to make the second distribution range be an initial distribution expression area of the next construction material data sequence; and carrying out construction material distribution updating through the objective function control model to obtain an updated objective function control model, dividing initial construction material distribution content corresponding to a previous construction material data sequence according to updated objective function control to obtain an initial distribution expression area corresponding to a next construction material data sequence, and obtaining a construction material distribution result until all the construction material data in the construction material data sequence are distributed.
3. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s5, accumulating the times of filling the construction materials according to the times of data distribution of each construction material in the control parameters of the construction materials needing to be distributed, and calculating the corresponding construction material distribution coefficient by using the control parameters of the distribution materials needing to be distributed; the number of times of data distribution of each construction material and the distribution coefficient of the construction materials are used as the output of control parameters of the distribution materials needing to be distributed; acquiring expected values of construction material distribution according to control parameters needing to be distributed for distributing the materials, and acquiring predicted values of each construction material in different construction material attributes; and forming a construction material distribution range value according to the construction material distribution expected value and each construction material estimated value, and acquiring distribution control convergence information of each construction material estimated value, wherein the construction material distribution range value comprises the distribution times of each construction material data distributed by each construction material data, the filling times of accumulated construction materials and the filling times of accumulated construction materials.
4. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s6, calculating to obtain an initial value of each construction material distribution convergence interval according to the construction material distribution control type of each construction material estimated value and the construction material distribution range value; according to the construction material distribution range value, the times of distributing each kind of construction material data distributed by each kind of construction material data, the times of filling the construction materials and the times of filling the construction materials are accumulated; inquiring a construction material distribution control information table to obtain a plurality of construction material distribution convergence parameters;
determining a plurality of convergence parameter distribution convergence parameters and a hand chain parameter balance value of the initial construction material distribution type to obtain a plurality of convergence parameter balance values; calculating distribution results of a plurality of convergence parameter balance values and corresponding control parameters of distribution materials to be distributed, and processing the control parameters of the distribution materials to be distributed according to distribution process information in the construction material distribution results to obtain a plurality of construction material distribution control sets;
and sequentially extracting the construction material distribution association processes in the plurality of construction material distribution convergence parameter sets, taking the construction material distribution association units in the concentrated construction material distribution association processes as quick distribution units, and respectively and sequentially generating a construction material distribution sequence corresponding to each construction material distribution process according to the concentrated construction material distribution association processes.
5. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s7, respectively matching the association strength of the rapid distribution units in the centralized construction material distribution association process with each construction material distribution sequence, wherein the association strength corresponds to the sequence length of the construction material distribution sequence in an association relationship; setting corresponding construction material distribution association nodes for each construction material distribution sequence according to the association strength matched with each construction material distribution sequence, forming association relations for the construction material distribution sequences of the construction material distribution association nodes according to a concentrated construction material distribution association process, and acquiring a construction material rapid distribution model from a construction material distribution model corresponding to the formed association relations according to the classes of a plurality of construction material distribution control sets corresponding to each construction material distribution sequence completing the association relations; and combining the construction material distribution coefficients of each construction material rapid distribution model to obtain the corresponding rapid distribution coefficients.
6. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s8, generating a mirror image coding space for recording the construction material distribution mirror image file, mapping the construction material distribution mirror image file to the mirror image preparation space, and setting the distribution state of the construction material distribution mirror image file according to the construction material type; judging whether the construction material distribution is in a state of executing the construction material distribution control parameter according to the distribution state, and determining to judge the construction material distribution coefficient according to the analysis instruction when the distribution flow information in the construction material distribution result is not in a threshold value limited by executing the construction material distribution coefficient; analyzing a construction material distribution coefficient in the judging process, determining construction material data distribution for distributing the construction material data to be distributed according to the construction material distribution coefficient and distributing flow parameters for each construction material, performing mirror image search on each data distribution node related to the construction material data to be distributed according to the construction material distribution control flow parameters, and determining distribution type attributes corresponding to the construction material data to be distributed; and determining a construction material distribution queue according to the distribution type attribute, extracting behavior distribution data of construction material distribution business behaviors, taking a set threshold value as a business mirror region of the construction material distribution business behaviors, and extracting a construction material distribution set of which each construction material distribution data is associated with a plurality of construction material distribution queues.
7. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s9, generating a plurality of logic association sections according to the logic association relationship of the construction material logic blocks in the construction material allocation behaviors according to at least two associated construction material allocation behaviors in the set, calculating the construction material allocation difference between all the construction material logic blocks in the next construction material allocation behavior and all the construction material logic blocks in the previous construction material allocation behavior, and corresponding to a construction material allocation association relationship table according to each obtained difference;
according to the construction material distribution incidence relation table, construction material logic blocks are matched according to the logic incidence relation, and the construction material logic blocks of the two logic incidence sections are different from each other by less than the maximum logic difference of the construction material distribution behaviors in the logic difference, so that the construction material distribution space is established; in the establishment of each construction material distribution space, distributing a distribution interval of each construction material distribution behavior space, and mirroring the construction material distribution behavior space according to the construction material distribution behavior expression data to obtain a plurality of mirrored construction material distribution intervals; matching according to the distribution interval of the construction material distribution behavior space and the construction material distribution intervals of the plurality of mirror images to obtain a matching interval of construction material distribution; and obtaining the target data distribution of the construction material distribution to be distributed from the matching interval, and then extracting the distribution control flow parameters of each construction material distribution.
8. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s10, if receiving the allocation request of the construction material data identification sent by the rapid allocation unit again, checking the allocated construction material according to the allocation request, wherein the checking process detects the change of the construction material allocation identification through the rapid allocation unit, and is relative to the distribution process of the rapid allocation unit; the construction material increase or construction material decrease has an influence on control parameters of the construction materials to be distributed, the rapid distribution unit detects the increased construction material types when the construction materials are increased and reduces the distribution of the increased construction materials, the rapid distribution unit detects the reduced construction material types when the construction materials are reduced and increases the distribution of the reduced construction materials, and stores the distribution identification of the construction materials, and then the number of the corresponding construction materials to be increased and reduced is obtained; when the data source with reduced construction material distribution obtains the construction material distribution identification detected by the rapid distribution unit, and the construction material distribution identification is reduced corresponding to the data source of the rapid distribution unit, obtaining the data address of the reduced construction material distribution data source; if the data source of the construction material distribution sends a request for acquiring the data source; the received data source feeds back and obtains a data address of the construction material data source according to the construction material screening condition; marking a unique identifier according to the identifier serial number of the rapid distribution unit, forming a construction material distribution data set by using the identifiers with the same construction material distribution data, recording the time, the place and the specific material list of construction material distribution, thereby recommending data for the next construction material distribution, and distributing target data to be distributed to each construction material target data distribution control flow parameter according to the construction material distribution control parameters; and executing construction material distribution operation on the construction material data to be distributed according to the determined construction material distribution data and aiming at each construction material distribution task.
9. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s11, performing task assignment on each construction material distribution task in the rapid distribution unit according to the control parameters for distribution, determining the construction material distribution flow of each construction material distribution task, and acquiring a construction material distribution flow configuration file according to the construction material distribution flow; determining distribution process configuration information of the construction material distribution tasks according to the construction material distribution process configuration file, searching the distribution process configuration information of the construction material distribution tasks based on the last construction material distribution control configuration information, intercepting data fields at the same position according to the distribution process configuration information of two adjacent construction material distribution tasks for position comparison, and combining the data fields into one data vector according to the distribution process configuration information of the two adjacent construction material distribution tasks; extracting distribution parameters corresponding to the distribution flow configuration information of each construction material distribution task and used for representing the construction material distribution tasks from the data vectors; and controlling the calling information during construction material distribution according to the construction material distribution flow of the construction material distribution task, merging each construction material distribution flow according to the construction material distribution regulation logic relation of each calling information, traversing the calling information in the distribution regulation logic relation in sequence after merging, and performing the construction material distribution data verification process.
10. The intelligent worksite construction material rapid distribution work method according to claim 1, further comprising:
s12, after calling information in the distribution adjustment logic relation is traversed in sequence, corresponding distribution information of the construction material distribution process is extracted in the verification process, the distribution information of the construction material distribution process is grouped according to different construction material types, a process distribution information identifier of each construction material type is calculated, and distribution data meeting the distribution condition in the construction material distribution is selected according to the process distribution information identifiers; and generating an extraction instruction for extracting the construction material distribution control parameters in the process distribution information identification according to the distribution data meeting the distribution conditions, and acquiring a construction material distribution mirror image file corresponding to the process distribution information identification in the construction material distribution process according to the extraction instruction.
CN202011111332.9A 2020-10-16 2020-10-16 Intelligent construction site construction material rapid distribution working method Withdrawn CN112365124A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011111332.9A CN112365124A (en) 2020-10-16 2020-10-16 Intelligent construction site construction material rapid distribution working method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011111332.9A CN112365124A (en) 2020-10-16 2020-10-16 Intelligent construction site construction material rapid distribution working method

Publications (1)

Publication Number Publication Date
CN112365124A true CN112365124A (en) 2021-02-12

Family

ID=74506743

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011111332.9A Withdrawn CN112365124A (en) 2020-10-16 2020-10-16 Intelligent construction site construction material rapid distribution working method

Country Status (1)

Country Link
CN (1) CN112365124A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108876121A (en) * 2018-05-31 2018-11-23 康键信息技术(深圳)有限公司 Worksheet method, apparatus, computer equipment and storage medium
US20180364920A1 (en) * 2016-11-25 2018-12-20 Huawei Technologies Co.,Ltd. Data check method and storage system
CN110222918A (en) * 2019-04-18 2019-09-10 重庆恢恢信息技术有限公司 Wisdom building site management system, server and storage medium based on cloud platform
CN111209336A (en) * 2019-12-30 2020-05-29 广州博士信息技术研究院有限公司 Data distribution method and device based on block chain and server
CN111429091A (en) * 2020-03-19 2020-07-17 北京字节跳动网络技术有限公司 Resource allocation method and device, electronic equipment and storage medium
CN111639363A (en) * 2020-05-24 2020-09-08 石高峰 Data analysis method based on block chain and edge computing server
CN111695884A (en) * 2020-08-17 2020-09-22 广东新视野信息科技股份有限公司 Internet of things big data visualization method and system based on smart construction site

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180364920A1 (en) * 2016-11-25 2018-12-20 Huawei Technologies Co.,Ltd. Data check method and storage system
CN109074227A (en) * 2016-11-25 2018-12-21 华为技术有限公司 A kind of method and storage system of data check
CN108876121A (en) * 2018-05-31 2018-11-23 康键信息技术(深圳)有限公司 Worksheet method, apparatus, computer equipment and storage medium
CN110222918A (en) * 2019-04-18 2019-09-10 重庆恢恢信息技术有限公司 Wisdom building site management system, server and storage medium based on cloud platform
CN111209336A (en) * 2019-12-30 2020-05-29 广州博士信息技术研究院有限公司 Data distribution method and device based on block chain and server
CN111429091A (en) * 2020-03-19 2020-07-17 北京字节跳动网络技术有限公司 Resource allocation method and device, electronic equipment and storage medium
CN111639363A (en) * 2020-05-24 2020-09-08 石高峰 Data analysis method based on block chain and edge computing server
CN111695884A (en) * 2020-08-17 2020-09-22 广东新视野信息科技股份有限公司 Internet of things big data visualization method and system based on smart construction site

Similar Documents

Publication Publication Date Title
CN106528280A (en) Task allocation method and system
CN105912399B (en) Task processing method, device and system
CN107103009A (en) A kind of data processing method and device
CN106874112B (en) Workflow backfilling method combined with load balancing
CN113052514B (en) Method, apparatus, device, storage medium and program product for resource allocation
CN111382031B (en) Test method and device
CN109409780B (en) Change processing method, device, computer equipment and storage medium
CN109377187A (en) A kind of outsourcing human resource distribution method and device
CN111711702B (en) Distributed cooperative interaction method and system based on communication topology
CN109934368B (en) Method, device and system for predicting order quantity and order state
CN110084507A (en) The scientific workflow method for optimizing scheduling of perception is classified under cloud computing environment
US7647592B2 (en) Methods and systems for assigning objects to processing units
CN112365124A (en) Intelligent construction site construction material rapid distribution working method
CN107844496B (en) Statistical information output method and device
CN112365125A (en) Building material rapid use and distribution working method through big data analysis
CN110322143B (en) Model materialization management method, device, equipment and computer storage medium
CN116390149A (en) MR information backfilling method and system based on big data
CN109857817A (en) The whole network domain electronic mutual inductor frequent continuous data is screened and data processing method
CN112632615B (en) Scientific workflow data layout method based on hybrid cloud environment
JP6840204B1 (en) Business support system and method
CN113556380A (en) Edge distributed multi-copy processing method, device and medium of Internet of things equipment
CN110795151A (en) Operator concurrency degree adjusting method, device and equipment
KR101813165B1 (en) Adaptive control plane management method for software defined network and apparatus thereof
CN117421109B (en) Training task scheduling method and device, computer equipment and storage medium
CN112015554B (en) Task processing method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20210212