CN112144866A - A kind of support structure of steel truss floor deck - Google Patents

A kind of support structure of steel truss floor deck Download PDF

Info

Publication number
CN112144866A
CN112144866A CN202011059640.1A CN202011059640A CN112144866A CN 112144866 A CN112144866 A CN 112144866A CN 202011059640 A CN202011059640 A CN 202011059640A CN 112144866 A CN112144866 A CN 112144866A
Authority
CN
China
Prior art keywords
plate
auxiliary
support structure
beams
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011059640.1A
Other languages
Chinese (zh)
Inventor
刘健
吕锴涛
李双拓
刘洋涛
龚梓翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Huachang Technology Co ltd
Original Assignee
Fujian Huachang Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Huachang Technology Co ltd filed Critical Fujian Huachang Technology Co ltd
Priority to CN202011059640.1A priority Critical patent/CN112144866A/en
Publication of CN112144866A publication Critical patent/CN112144866A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开一种钢筋桁架楼承板的支撑结构,包括两主钢梁,及通过连接组件固定在两主钢梁之间的的辅梁。本发明通过在主钢梁之间设置辅梁,用于辅助支撑楼承板,可以实现长跨度楼承板浇筑的支撑,防止产生楼承板的不平、凹陷变形等问题,由于辅梁通过连接组件与主钢梁形成一个稳定的框架,有利于后续混凝土浇筑受力的分散和分摊,具有极高的施工稳定性和安全性;此外,本发明的结构可以与楼承板同步安装在主钢梁上,施工简单方便,安全可靠,有助于缩短施工周期,实现立体施工。

Figure 202011059640

The invention discloses a support structure for a steel truss floor deck, which comprises two main steel beams and an auxiliary beam fixed between the two main steel beams through connecting components. In the present invention, auxiliary beams are arranged between the main steel beams to assist the floor deck, so that the long-span floor deck can be supported for pouring, and problems such as unevenness, depression and deformation of the floor deck can be prevented. The component and the main steel beam form a stable frame, which is beneficial to the dispersion and apportionment of the subsequent concrete pouring force, and has extremely high construction stability and safety; in addition, the structure of the present invention can be installed on the main steel synchronously with the floor deck On the beam, the construction is simple, convenient, safe and reliable, which helps to shorten the construction period and realize three-dimensional construction.

Figure 202011059640

Description

一种钢筋桁架楼承板的支撑结构A kind of support structure of steel truss floor deck

技术领域technical field

本发明涉及建筑技术领域,特别是指一种钢筋桁架楼承板的支撑结构。The invention relates to the technical field of construction, in particular to a support structure for a steel truss floor deck.

背景技术Background technique

以钢筋为上弦、下弦及腹杆,通过电阻点焊连接而成的桁架叫做钢筋桁架。钢筋桁架与底板连接固定形成整体的组合承重板叫做钢筋桁架楼承板。目前,以钢结构为主体的钢筋桁架楼承板在大跨度建筑及超高层建筑中运用较多,而此类建筑物施工过程中危险性较大且工期要求较高。便捷安全的施工措施不仅可以保证作业人员的人身安全,也可以提高作业效率。根据设计及规范要求,当进行长跨度楼承板浇筑时,需要在楼承板下方设置支撑结构,以避免底板的长边中部向下凹陷甚至造成坍塌。A truss connected by resistance spot welding with steel bars as the upper chord, lower chord and web member is called a steel bar truss. The combined bearing plate in which the steel truss and the bottom plate are connected and fixed to form a whole is called a steel truss floor bearing plate. At present, reinforced truss floor slabs with steel structure as the main body are used more in long-span buildings and super high-rise buildings, and the construction process of such buildings is more dangerous and requires higher construction period. Convenient and safe construction measures can not only ensure the personal safety of operators, but also improve work efficiency. According to the design and specification requirements, when the long-span floor deck is poured, it is necessary to set up a support structure under the floor deck to prevent the middle of the long side of the bottom plate from sinking downward or even causing collapse.

如附图1所示,现有一种支撑结构是采用钢管支撑架+托梁体系,楼承板1’两端架设在钢梁3’上,在楼承板1’下部设置钢管支撑架2’,并通过上部加设托梁4’作为临时支撑体系。该结构的缺点在于:①钢管支撑架底部需要平坦的板面,因此必须等到下方的楼承板浇筑完成并达到一定强度后方可使用,施工周期将大大加长,无法实现立体施工,楼层越高的建筑施工越慢;②临时支撑体系拆卸繁琐,耗用时间长;③钢管支撑架投入使用后周转周期较长,投入量较大。As shown in Figure 1, an existing support structure adopts a steel pipe support frame + joist system. , and add joists 4' to the upper part as a temporary support system. The disadvantages of this structure are: 1. The bottom of the steel pipe support frame needs a flat surface, so it must wait until the floor deck below is poured and reaches a certain strength before it can be used. The construction period will be greatly lengthened, and three-dimensional construction cannot be achieved. The slower the construction; ② the dismantling of the temporary support system is cumbersome and time-consuming; ③ the steel pipe support frame is put into use with a longer turnover period and a larger investment.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种钢筋桁架楼承板的支撑结构,可以实现长跨度楼承板浇筑的支撑,强度高、可防止变形,且可以与楼承板同步组装,缩短施工周期,实现立体施工。The purpose of the present invention is to provide a support structure for a reinforced truss floor deck, which can realize the support of long-span floor deck casting, has high strength, can prevent deformation, and can be assembled synchronously with the floor deck, shortens the construction period, and realizes three-dimensional construction.

为了达成上述目的,本发明的解决方案是:In order to achieve the above-mentioned purpose, the solution of the present invention is:

一种钢筋桁架楼承板的支撑结构,包括两主钢梁,及通过连接组件固定在两主钢梁之间的的辅梁。A support structure for a steel truss floor deck comprises two main steel beams and an auxiliary beam fixed between the two main steel beams through connecting components.

所述主钢梁为工字钢,所述工字钢包括上下依次连接设置的上板、竖板和下板。The main steel beam is an I-beam, and the I-beam comprises an upper plate, a vertical plate and a lower plate which are connected and arranged up and down in sequence.

所述连接组件架设在所述上板的上下表面、所述下板的上下表面或所述竖板的侧面。The connecting assembly is erected on the upper and lower surfaces of the upper plate, the upper and lower surfaces of the lower plate or the side surface of the vertical plate.

所述连接组件连接在所述辅梁上同时所述辅梁的两端分别架设在两主钢梁上,所述辅梁的上表面用于支撑所述楼承板的底板。The connecting components are connected to the auxiliary beams, and two ends of the auxiliary beams are respectively erected on the two main steel beams, and the upper surfaces of the auxiliary beams are used to support the bottom plate of the floor deck.

所述连接组件为钢筋桁架。The connecting component is a steel bar truss.

所述连接组件的数量至少有两个,两个所述连接组件分别连接在所述辅梁上表面的两端并架设在对应的主钢梁上。The number of the connecting assemblies is at least two, and the two connecting assemblies are respectively connected to both ends of the upper surface of the auxiliary beams and are erected on the corresponding main steel beams.

所述连接组件包括上板件和下板件,所述上板件、下板件和辅梁上下层叠并连接,所述上板件架设在所述主钢梁上。The connecting assembly includes an upper plate and a lower plate, the upper plate, the lower plate and the auxiliary beam are stacked and connected up and down, and the upper plate is erected on the main steel beam.

所述辅梁至少设置有1个。At least one auxiliary beam is provided.

所述辅梁之间设置有至少一加强结构,加强结构的两端分别连接相邻的辅梁。At least one reinforcement structure is arranged between the auxiliary beams, and two ends of the reinforcement structure are respectively connected to the adjacent auxiliary beams.

采用上述技术方案后,本发明通过在主钢梁之间设置辅梁,用于辅助支撑楼承板,可以实现长跨度楼承板浇筑的支撑,防止产生楼承板的不平、凹陷变形等问题,由于辅梁通过连接组件与主钢梁形成一个稳定的框架,有利于后续混凝土浇筑受力的分散和分摊,具有极高的施工稳定性和安全性;此外,本发明的结构可以与楼承板同步安装在主钢梁上,施工简单方便,安全可靠,有助于缩短施工周期,实现立体施工。After adopting the above technical solution, in the present invention, auxiliary beams are arranged between the main steel beams to support the floor deck, so that the long-span floor deck can be supported for pouring, and problems such as unevenness, depression and deformation of the floor deck can be prevented. , because the auxiliary beam forms a stable frame with the main steel beam through the connecting component, which is conducive to the dispersion and apportionment of the subsequent concrete pouring force, and has extremely high construction stability and safety; The plate is installed on the main steel beam synchronously, the construction is simple and convenient, safe and reliable, which helps to shorten the construction period and realize three-dimensional construction.

附图说明Description of drawings

图1为现有的楼承板支撑架构的示意图;Fig. 1 is the schematic diagram of the existing floor deck support structure;

图2为本发明第一实施例的俯视角立体图;2 is a top-view perspective view of the first embodiment of the present invention;

图3为本发明第一实施例的仰视角立体图;Fig. 3 is the perspective view of the bottom view of the first embodiment of the present invention;

图4为本发明第一实施例的安装示意图;Fig. 4 is the installation schematic diagram of the first embodiment of the present invention;

图5为本发明第二实施例的俯视角立体图;5 is a top-view perspective view of a second embodiment of the present invention;

图6为本发明第二实施例的仰视角立体图;Fig. 6 is the perspective view of the bottom view of the second embodiment of the present invention;

图7为本发明第二实施例的安装示意图;7 is a schematic diagram of the installation of the second embodiment of the present invention;

图8为本发明第三实施例的俯视角立体图;8 is a top-view perspective view of a third embodiment of the present invention;

图9为本发明第三实施例的仰视角立体图;9 is a perspective view of a third embodiment of the present invention;

图10为本发明第三实施例的安装示意图;10 is a schematic diagram of the installation of the third embodiment of the present invention;

图11为本发明第四实施例的俯视角立体图;FIG. 11 is a top-view perspective view of the fourth embodiment of the present invention;

图12为本发明第四实施例的仰视角立体图;FIG. 12 is a perspective view of the fourth embodiment of the present invention;

图13为本发明第四实施例的安装示意图;FIG. 13 is a schematic diagram of the installation of the fourth embodiment of the present invention;

附图标号说明:主钢梁1;辅梁2;台阶21;连接组件3;上板件31;下板件32;楼承板4;底板41;缺口411;加强结构5。Description of reference numerals: main steel beam 1; auxiliary beam 2; step 21; connecting assembly 3; upper plate part 31; lower plate part 32; floor deck 4;

具体实施方式Detailed ways

为了进一步解释本发明的技术方案,下面通过具体实施例来对本发明进行详细阐述。In order to further explain the technical solutions of the present invention, the present invention will be described in detail below through specific embodiments.

本发明为一种钢筋桁架楼承板的支撑结构,包括相平行的两主钢梁1,及通过连接组件3固定在两主钢梁1之间并与主钢梁1相垂直的辅梁2。The present invention is a support structure for a steel truss floor deck, comprising two parallel main steel beams 1, and an auxiliary beam 2 fixed between the two main steel beams 1 through a connecting component 3 and perpendicular to the main steel beam 1 .

上述主钢梁1为工字钢,工字钢包括上下依次连接设置的上板11、竖板12和下板13,连接组件3架设在上板11的上下表面、下板13的上下表面或竖板12的侧面。其中架设在上板11的上表面可以保证辅梁2、连接组件3对主钢梁1的压力集中在主钢梁1的上方,支撑能力更强。The above-mentioned main steel beam 1 is an I-beam, and the I-beam includes an upper plate 11, a vertical plate 12 and a lower plate 13 that are connected and arranged up and down in sequence, and the connecting assembly 3 is erected on the upper and lower surfaces of the upper plate 11, the upper and lower surfaces of the lower plate 13 or The side of the riser 12 . The installation on the upper surface of the upper plate 11 can ensure that the pressure of the auxiliary beam 2 and the connecting component 3 on the main steel beam 1 is concentrated above the main steel beam 1, and the supporting capacity is stronger.

上述连接组件3对主钢梁1的施力点到辅梁2端部的距离不小于主钢梁1上表面宽度的一半。则浇筑混凝土使辅梁2承重后,辅梁2受到的压力通过连接组件3传递到主钢梁1上,其应力集中在主钢梁1中部的竖板上,支撑能力更强。The distance from the point where the connection component 3 applies force to the main steel beam 1 to the end of the auxiliary beam 2 is not less than half of the width of the upper surface of the main steel beam 1 . After the concrete is poured to make the auxiliary beam 2 bear the load, the pressure on the auxiliary beam 2 is transmitted to the main steel beam 1 through the connecting component 3, and its stress is concentrated on the vertical plate in the middle of the main steel beam 1, and the supporting capacity is stronger.

参考图2至图4所示,示出了本发明的第一实施例。Referring to Figures 2 to 4, a first embodiment of the present invention is shown.

上述主钢梁1的设置方向与楼承板4的长度方向相垂直,连接组件3连接在辅梁2上同时辅梁2的两端分别架设在两主钢梁1上,辅梁2的上表面两侧均设置有台阶21,用于支撑楼承板4的底板41。The setting direction of the above-mentioned main steel beam 1 is perpendicular to the length direction of the floor deck 4, and the connecting component 3 is connected to the auxiliary beam 2 while the two ends of the auxiliary beam 2 are respectively erected on the two main steel beams 1, and the upper part of the auxiliary beam 2. Both sides of the surface are provided with steps 21 for supporting the bottom plate 41 of the floor deck 4 .

上述连接组件3为钢筋桁架,即底板41与辅梁2都使用钢筋桁架作为固定结构,满足强度需求。The above-mentioned connecting component 3 is a steel truss, that is, both the bottom plate 41 and the auxiliary beam 2 use a steel truss as a fixed structure to meet the strength requirements.

参考图4所示,本发明的安装结构为:用钢筋桁架作为连接组件3固定在辅梁2的上表面,连接组件3的两端固定在两主钢梁1的上表面,使得辅梁2固定在两主钢梁1之间,然后再铺设楼承板4,且底板41的长边搭在台阶21上,浇筑混凝土时台阶21支撑底板41的长边以避免凹陷。Referring to Fig. 4, the installation structure of the present invention is as follows: a steel truss is used as the connecting component 3 to be fixed on the upper surface of the auxiliary beam 2, and both ends of the connecting component 3 are fixed to the upper surface of the two main steel beams 1, so that the auxiliary beam 2 It is fixed between the two main steel beams 1, and then the floor slab 4 is laid, and the long side of the bottom plate 41 is placed on the step 21. When pouring concrete, the step 21 supports the long side of the bottom plate 41 to avoid depression.

参考图5至图7所示,示出了本发明的第二实施例。Referring to Figures 5 to 7, a second embodiment of the present invention is shown.

上述主钢梁1的设置方向与楼承板4的长度方向相平行,连接组件3的数量至少有两个,两个连接组件3分别连接在辅梁2上表面的两端并架设在对应的主钢梁1上。The setting direction of the above-mentioned main steel beam 1 is parallel to the length direction of the floor deck 4, and the number of connecting components 3 is at least two. on the main steel beam 1.

上述连接组件3包括上板件31和下板件32,上板件31、下板件32和辅梁2上下层叠并连接,上板件31架设在主钢梁1上。本实施例中,下板件32的厚度与底板41的厚度相同,则辅梁2与主钢梁1上表面的高度差刚好等于底板41的厚度,以保证结构组装完成后底板41的表面与主钢梁1的上表面平齐。The above connecting assembly 3 includes an upper plate 31 and a lower plate 32 . The upper plate 31 , the lower plate 32 and the auxiliary beam 2 are stacked and connected up and down. The upper plate 31 is erected on the main steel beam 1 . In this embodiment, the thickness of the lower plate member 32 is the same as the thickness of the bottom plate 41, so the height difference between the upper surface of the auxiliary beam 2 and the main steel beam 1 is just equal to the thickness of the bottom plate 41, so as to ensure that the surface of the bottom plate 41 and the bottom plate 41 after the structural assembly is completed. The upper surface of the main steel beam 1 is flush.

参考图7所示,本发明的安装结构为:先通过螺栓锁固、焊接等方式将连接组件3固定在辅梁2的端部,再将辅梁2固定在两主钢梁1之间,然后再铺设楼承板4,辅梁2向上支撑所有底板41的中部以避免凹陷。此外,临近主钢梁1的底板41需要预先开设让位上板件31的缺口411。Referring to Fig. 7, the installation structure of the present invention is as follows: firstly, the connecting component 3 is fixed to the end of the auxiliary beam 2 by means of bolt locking, welding, etc., and then the auxiliary beam 2 is fixed between the two main steel beams 1, Then the floor deck 4 is laid, and the auxiliary beams 2 support the middle of all the bottom plates 41 upward to avoid depression. In addition, the bottom plate 41 adjacent to the main steel girder 1 needs to have a gap 411 to allow the upper plate member 31 to be opened in advance.

参考图8至图10所示,示出了本发明的第三实施例,是在第二实施例的基础上增加辅梁2的数量,在第三实施例中辅梁2的数量有两个,相比于第二实施例,其能够用于支撑更长跨度的楼承板4。Referring to FIGS. 8 to 10 , a third embodiment of the present invention is shown, which is to increase the number of auxiliary beams 2 on the basis of the second embodiment. In the third embodiment, there are two auxiliary beams 2 . , compared to the second embodiment, it can be used to support the floor deck 4 with a longer span.

参考图11至图13所示,示出了本发明的第四实施例,是在第三实施例的基础上增加加强结构5,相邻辅梁2之间设置有至少一加强结构5,加强结构5的两端分别连接相邻的辅梁2侧面,加强结构5在辅梁2的长度较大时可以实现交叉补强。如果辅梁2要求强度大,则需要通过加强结构5连接多个辅梁2来补强。Referring to FIGS. 11 to 13 , the fourth embodiment of the present invention is shown, and a reinforcing structure 5 is added on the basis of the third embodiment. At least one reinforcing structure 5 is arranged between adjacent auxiliary beams 2 to strengthen the The two ends of the structure 5 are respectively connected to the side surfaces of the adjacent auxiliary beams 2 , and the reinforcement structure 5 can realize cross reinforcement when the length of the auxiliary beams 2 is relatively large. If the auxiliary beam 2 requires high strength, it needs to be reinforced by connecting a plurality of auxiliary beams 2 through the reinforcement structure 5 .

上述连接组件3的架设方式可以是通过螺栓锁固、焊接等方式固定在主钢梁1上,也可以是直接搭在主钢梁1的上表面。The erection method of the above-mentioned connecting assembly 3 may be fixed on the main steel beam 1 by means of bolt locking, welding, etc., or may be directly mounted on the upper surface of the main steel beam 1 .

通过上述方案,本发明通过在主钢梁1之间设置辅梁2,用于辅助支撑楼承板4,可以实现长跨度楼承板4浇筑的支撑,防止产生楼承板4的不平、凹陷变形等问题,由于辅梁2通过连接组件3与主钢梁1形成一个稳定的框架,有利于后续混凝土浇筑受力的分散和分摊,具有极高的施工稳定性和安全性;此外,本发明的结构可以与楼承板4同步安装在主钢梁1上,施工简单方便,安全可靠,有助于缩短施工周期,实现立体施工。Through the above solution, in the present invention, the auxiliary beams 2 are arranged between the main steel beams 1 for supporting the floor deck 4, so that the long-span floor deck 4 can be supported for pouring, and the unevenness and depression of the floor deck 4 can be prevented from being generated. Problems such as deformation, because the auxiliary beam 2 forms a stable frame with the main steel beam 1 through the connecting component 3, which is conducive to the dispersion and apportionment of the subsequent concrete pouring force, and has extremely high construction stability and safety; In addition, the present invention The structure can be installed on the main steel beam 1 synchronously with the floor deck 4, the construction is simple, convenient, safe and reliable, which helps to shorten the construction period and realize three-dimensional construction.

上述实施例和图式并非限定本发明的产品形态和式样,任何所属技术领域的普通技术人员对其所做的适当变化或修饰,皆应视为不脱离本发明的专利范畴。The above-mentioned embodiments and drawings do not limit the product form and style of the present invention, and any appropriate changes or modifications made by those of ordinary skill in the art should be regarded as not departing from the scope of the present invention.

Claims (9)

1. The utility model provides a bearing structure of steel bar truss floor bearing plate which characterized in that: the auxiliary beam comprises two main steel beams and an auxiliary beam fixed between the two main steel beams through a connecting component.
2. The support structure for a slab of a steel bar truss building as claimed in claim 1, wherein:
the main steel beam is an I-steel, and the I-steel comprises an upper plate, a vertical plate and a lower plate which are sequentially connected from top to bottom.
3. The support structure for a slab of a steel bar truss building as claimed in claim 2, wherein:
the connecting assembly is erected on the upper surface and the lower surface of the upper plate, the upper surface and the lower surface of the lower plate or the side surfaces of the vertical plates.
4. The support structure for a slab of a steel bar truss building as claimed in claim 1, wherein:
coupling assembling is connected simultaneously on the auxiliary beam the both ends of auxiliary beam are erect respectively on two main girder steels, the upper surface of auxiliary beam is used for supporting the bottom plate of building carrier plate.
5. The support structure for a slab of a steel bar truss building as claimed in claim 4, wherein:
the connecting assembly is a steel bar truss.
6. The support structure for a slab of a steel bar truss building as claimed in claim 1, wherein:
the number of the connecting components is at least two, and the two connecting components are respectively connected to the two ends of the upper surface of the auxiliary beam and erected on the corresponding main steel beams.
7. The support structure for a slab of a steel bar truss building as claimed in claim 6, wherein:
coupling assembling includes plate and lower plate, it stacks up from top to bottom and connects to go up plate, lower plate and auxiliary girder, it erects to go up the plate on the main girder steel.
8. A support structure for a slab of a steel bar truss as claimed in any one of claims 1 to 7, wherein:
the auxiliary beam is at least provided with 1.
9. The support structure for a slab of a steel bar truss building as claimed in claim 8, wherein:
at least one reinforcing structure is arranged between the auxiliary beams, and two ends of each reinforcing structure are respectively connected with the adjacent auxiliary beams.
CN202011059640.1A 2020-09-30 2020-09-30 A kind of support structure of steel truss floor deck Pending CN112144866A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011059640.1A CN112144866A (en) 2020-09-30 2020-09-30 A kind of support structure of steel truss floor deck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011059640.1A CN112144866A (en) 2020-09-30 2020-09-30 A kind of support structure of steel truss floor deck

Publications (1)

Publication Number Publication Date
CN112144866A true CN112144866A (en) 2020-12-29

Family

ID=73894318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011059640.1A Pending CN112144866A (en) 2020-09-30 2020-09-30 A kind of support structure of steel truss floor deck

Country Status (1)

Country Link
CN (1) CN112144866A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115126223A (en) * 2022-06-30 2022-09-30 歌山建设集团有限公司 Simplified formwork supporting system for auxiliary beam type floor support plate and construction method of simplified formwork supporting system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204212418U (en) * 2014-10-16 2015-03-18 中国建筑股份有限公司 A kind of primary-secondary beam connector
CN208518204U (en) * 2018-05-28 2019-02-19 山东大源建设集团有限公司 A kind of welding for steel structure truss
CN209620403U (en) * 2019-01-17 2019-11-12 惠州雅泰钢结构工程有限公司 a steel structure beam
CN110630015A (en) * 2019-09-25 2019-12-31 中国一冶集团有限公司 Large-span steel bar truss floor support plate assembled support and construction method
CN210316542U (en) * 2019-07-09 2020-04-14 中建二局广东建设基地有限公司 Steel bar truss floor bearing plate strutting arrangement that can reuse
CN216007793U (en) * 2020-09-30 2022-03-11 福建华桁科技有限公司 Supporting structure of steel bar truss floor bearing plate

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204212418U (en) * 2014-10-16 2015-03-18 中国建筑股份有限公司 A kind of primary-secondary beam connector
CN208518204U (en) * 2018-05-28 2019-02-19 山东大源建设集团有限公司 A kind of welding for steel structure truss
CN209620403U (en) * 2019-01-17 2019-11-12 惠州雅泰钢结构工程有限公司 a steel structure beam
CN210316542U (en) * 2019-07-09 2020-04-14 中建二局广东建设基地有限公司 Steel bar truss floor bearing plate strutting arrangement that can reuse
CN110630015A (en) * 2019-09-25 2019-12-31 中国一冶集团有限公司 Large-span steel bar truss floor support plate assembled support and construction method
CN216007793U (en) * 2020-09-30 2022-03-11 福建华桁科技有限公司 Supporting structure of steel bar truss floor bearing plate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈富生: "高层建筑钢结构设计", 31 July 2004, 中国建筑工业出版社, pages: 380 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115126223A (en) * 2022-06-30 2022-09-30 歌山建设集团有限公司 Simplified formwork supporting system for auxiliary beam type floor support plate and construction method of simplified formwork supporting system
CN115126223B (en) * 2022-06-30 2024-07-30 歌山建设集团有限公司 Auxiliary beam type floor carrier plate simplified formwork system and construction method thereof

Similar Documents

Publication Publication Date Title
WO2021078309A1 (en) Temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and method of constructing same
CN105839846A (en) Prefabricated reinforced concrete composite beam
CN108978856B (en) A prefabricated honeycomb beam-slab structure system
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN212224234U (en) A precast concrete beam-column connection structure
CN111206680B (en) Combined floor system frame structure building system
CN216042835U (en) A layering device for a high-rise frame structure with lightweight wall panels
CN111411721A (en) A prefabricated prefabricated sub-beam composite member
CN108222480B (en) High-altitude cantilever main truss type steel formwork construction platform
CN116104206A (en) A steel node connecting PEC columns and steel composite beams
CN216007260U (en) Rigid connection joint of steel beam and concrete column
CN207633734U (en) A kind of high-altitude overhanging main truss posture steel mould base operation platform
CN2818421Y (en) Upper bearing frame for laminated floorslab construction
CN111910914B (en) Multi-high-rise assembled steel structure non-composite floor slab supporting system and construction method thereof
CN214737317U (en) Steel-concrete combined rigid frame bridge connected through slots
CN112144866A (en) A kind of support structure of steel truss floor deck
CN113944309A (en) Cold-formed steel support beam framework and construction method thereof
CN216007793U (en) Supporting structure of steel bar truss floor bearing plate
CN207987777U (en) A kind of high pier girder steel pushing tow support device
CN214573279U (en) composite bridge structure
CN210066467U (en) Assembled corrugated steel web plate combined box girder
CN208950125U (en) A kind of large-span steel truss floor system
CN113202208B (en) Assembled steel-concrete combined shear wall and construction method thereof
CN112502023A (en) Slot-connected steel-concrete combined rigid frame bridge and construction method thereof
CN110872809A (en) Precast concrete beam with built-in steel plate and concrete slab combination beam and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination