CN112095482A - Steel box girder bridge-spanning existing bridge hoisting construction method - Google Patents

Steel box girder bridge-spanning existing bridge hoisting construction method Download PDF

Info

Publication number
CN112095482A
CN112095482A CN202011013753.8A CN202011013753A CN112095482A CN 112095482 A CN112095482 A CN 112095482A CN 202011013753 A CN202011013753 A CN 202011013753A CN 112095482 A CN112095482 A CN 112095482A
Authority
CN
China
Prior art keywords
steel box
box girder
crane
existing bridge
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011013753.8A
Other languages
Chinese (zh)
Inventor
王效
姜友荣
刘力铭
黄闯
陈罗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202011013753.8A priority Critical patent/CN112095482A/en
Publication of CN112095482A publication Critical patent/CN112095482A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention discloses a hoisting construction method for a steel box girder across an existing bridge, and solves the technical problem that the hoisting construction efficiency is low and the overall construction progress is influenced in the prior art. The temporary conversion support is hung on one end of the steel box girder, and the other end of the steel box girder is supported by the other crane. The steel box girder erection device is simple in structure, scientific and reasonable in design and convenient to use, can effectively improve the erection construction efficiency of the steel box girder across the existing bridge, thereby ensuring the overall construction progress, and meanwhile, the erection construction can be safe and stable without affecting the safety of the existing bridge.

Description

Steel box girder bridge-spanning existing bridge hoisting construction method
Technical Field
The invention belongs to the technical field of steel structure construction, and particularly relates to a hoisting construction method for a steel box girder across an existing bridge.
Background
Along with city development, the steel box girder hoist and mount construction of striding existing bridge is the technique commonly used in the construction of municipal steel structure bridge engineering project, and traditional mode hoist and mount efficiency of construction is low, influences whole construction progress. Especially under the limited operating mode of site environment, not only seriously influence whole construction progress, still can produce the influence to existing bridge safety.
Therefore, the steel box girder striding existing bridge hoisting construction method is designed to improve the steel box girder striding existing bridge hoisting construction efficiency, so that the whole construction progress is ensured, and meanwhile, the hoisting construction can also be safe and stable without influencing the safety of the existing bridge, so that the technical problem to be solved urgently by technical personnel in the technical field is solved.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the hoisting construction method for the steel box girder across the existing bridge is provided, and the technical problem that the hoisting construction efficiency is low and the overall construction progress is influenced in the prior art is solved.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
a steel box girder striding existing bridge hoisting construction method comprises the following steps:
step 1, setting up a temporary conversion support on one side of an existing bridge, and simultaneously setting a crane No. 1 and a crane No. 2 on two sides of the existing bridge respectively, wherein the steel box girder, the temporary conversion support and the crane No. 1 are positioned on the same side of the existing bridge;
step 2, hoisting the steel box girder by using a No. 1 crane and enabling the steel box girder to be positioned above the existing bridge;
step 3, adjusting the height of the steel box girder to enable one end of the steel box girder to be supported on the temporary conversion support, and hooking the other end of the steel box girder by a No. 2 crane;
step 4, fixing the temporary conversion support and the steel box girder;
step 5, loosening the hook of the crane No. 1, and completely supporting the steel box girder by the temporary conversion bracket and the crane No. 2;
step 6, hooking one end of the steel box girder, which is fixed with the temporary conversion support, by the crane No. 1, and removing the connection between the steel box girder and the temporary conversion support;
and 7, cooperatively hoisting the steel box girder to the installation position across the existing bridge by the No. 1 crane and the No. 2 crane.
Further, in the step 1, when the temporary conversion support is erected, a steel box girder on-site assembling platform for assembling the steel box girder is erected synchronously.
Further, the steel box girder on-site assembling platform and the temporary conversion support are positioned on the same side of the existing bridge.
Further, in the step 2, before the steel box girder is hoisted by the crane No. 1, the beam sections on the two sides of the existing bridge for installing the steel box girder are installed first.
Further, in the step 2, when the steel box girder is hoisted to the upper part of the existing bridge by using a crane No. 1, the position of the steel box girder is adjusted to be vertically distributed with the existing bridge.
Further, in the step 4, when the temporary conversion support and the steel box girder are fixed, welding is adopted for fixing.
Further, in the step 6, the connection between the steel box girder and the temporary conversion bracket is released by cutting.
Further, in the step 5, in the hooking releasing process of the crane 1, the stress state of the crane 2 is monitored in real time until the stress system of the steel box girder is completely converted to the temporary conversion support and the crane 2, so that the crane 1 can be completely released.
Compared with the prior art, the invention has the following beneficial effects:
the steel box girder erection device is simple in structure, scientific and reasonable in design and convenient to use, can effectively improve the erection construction efficiency of the steel box girder across the existing bridge, thereby ensuring the overall construction progress, and meanwhile, the erection construction can be safe and stable without affecting the safety of the existing bridge.
The method comprises the steps of firstly arranging a crane on each of two sides of an existing bridge, building a temporary conversion support and a steel box girder field assembly platform on one side of the existing bridge, assembling the steel box girder on the site by the steel box girder field assembly platform before hoisting, and simultaneously completing the installation of girder sections for installing the steel box girders on two sides of the existing bridge to ensure the readiness of the installation working condition of the steel box girders. When hoisting, firstly, hoisting the steel box girder by adopting a crane positioned at the same side of the steel box girder, and adjusting the position of the steel box girder to ensure that the steel box girder is vertical to the existing bridge; and then, the steel box girder descends to enable one end of the steel box girder to be placed on the temporary conversion support, the other end of the steel box girder is hung by using the other crane hook, after the steel box girder and the temporary conversion support are welded and fixed, the previous crane is unhooked, the unhooked crane hook is hung at one end of the steel box girder welded with the temporary conversion support, the steel box girder and the temporary conversion support are cut to remove connection of the steel box girder and the temporary conversion support, at the moment, the two cranes are respectively hung at the two ends of the steel box girder, and then the steel box girder is hung to a bridge installation position by means of cooperation of the two cranes. The whole process is smooth and efficient, safe and stable, and meanwhile, the safety of the existing bridge cannot be affected.
Drawings
FIG. 1 is a schematic view of the No. 1 crane of the invention for lifting a steel box girder.
Fig. 2 is an enlarged view of the crane No. 1 in fig. 1.
Fig. 3 is a vertical view of the steel box girder and the existing bridge by adjusting the crane No. 1 according to the invention.
Fig. 4 is an enlarged view of the crane of fig. 31.
Fig. 5 shows that two ends of the steel box girder are respectively supported on the temporary conversion support and the crane No. 2.
Fig. 6 is an enlarged view of the steel box girder of fig. 5 supported by the temporary transfer support and the crane No. 2, respectively.
FIG. 7 is a schematic diagram of the hoisting of a steel box girder by the matching of the No. 1 crane and the No. 2 crane.
Fig. 8 is a partially enlarged view of the crane No. 1, the crane No. 2 and the steel box girder in fig. 7.
Fig. 9 is a view of the steel box girder of the present invention being hoisted to the installation station by the hoist No. 1 and the hoist No. 2.
Fig. 10 is a partial enlarged view of the crane No. 1, the crane No. 2 and the steel box girder of fig. 9 according to the present invention.
Wherein, the names corresponding to the reference numbers are:
1-existing bridge, 2-1 crane, 3-2 crane, 4-steel box girder, 5-temporary conversion support, 6-girder segment and 7-steel box girder on-site assembly platform.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail below with reference to the accompanying drawings. It is to be understood that the described embodiments are merely exemplary of the invention, and not restrictive of the full scope of the invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation or be constructed and operated in a particular orientation, and thus, it should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; of course, mechanical connection and electrical connection are also possible; alternatively, they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
As shown in fig. 1-10, the construction method for hoisting the existing bridge spanned by the steel box girder provided by the invention has the advantages of simple structure, scientific and reasonable design and convenient use, can effectively improve the construction efficiency for hoisting the existing bridge spanned by the steel box girder, thereby ensuring the whole construction progress, and simultaneously, the hoisting construction can be safe and stable without affecting the safety of the existing bridge. The invention comprises the following steps:
step 1, setting up a temporary conversion support on one side of an existing bridge, and simultaneously setting a crane No. 1 and a crane No. 2 on two sides of the existing bridge respectively, wherein the steel box girder, the temporary conversion support and the crane No. 1 are positioned on the same side of the existing bridge;
step 2, hoisting the steel box girder by using a No. 1 crane and enabling the steel box girder to be positioned above the existing bridge;
step 3, adjusting the height of the steel box girder to enable one end of the steel box girder to be supported on the temporary conversion support, and hooking the other end of the steel box girder by a No. 2 crane;
step 4, fixing the temporary conversion support and the steel box girder;
step 5, loosening the hook of the crane No. 1, and completely supporting the steel box girder by the temporary conversion bracket and the crane No. 2;
step 6, hooking one end of the steel box girder, which is fixed with the temporary conversion support, by the crane No. 1, and removing the connection between the steel box girder and the temporary conversion support;
and 7, cooperatively hoisting the steel box girder to the installation position across the existing bridge by the No. 1 crane and the No. 2 crane.
Preferably, in the step 1, when the temporary conversion support is erected, a steel box girder on-site assembling table for assembling the steel box girder is erected synchronously. The steel box girder on-site assembling platform and the temporary conversion support are positioned on the same side of the existing bridge.
Preferably, in the step 2, before the steel box girder is hoisted by the crane No. 1, the beam sections on the two sides of the existing bridge for installing the steel box girder are installed first.
Preferably, in the step 2, when the steel box girder is hoisted to the upper part of the existing bridge by using a crane No. 1, the position of the steel box girder is adjusted to be vertically distributed with the existing bridge.
Preferably, in the step 4, when the temporary conversion support and the steel box girder are fixed, welding is adopted for fixing.
Preferably, in the step 6, the connection between the steel box girder and the temporary conversion bracket is released by cutting.
Preferably, in the step 5, in the hooking releasing process of the crane 1, the stress state of the crane 2 is monitored in real time until the stress system of the steel box girder is completely converted into the temporary conversion support and the crane 2, so that the crane 1 can be completely released.
The method comprises the steps of firstly arranging a crane on each of two sides of an existing bridge, building a temporary conversion support 5 and a steel box girder field assembly platform 7 on one side of the existing bridge 1, wherein the steel box girder field assembly platform and the temporary conversion support are positioned on the same side of the existing bridge, assembling the steel box girder 4 on the site in the steel box girder field assembly platform before hoisting, and simultaneously finishing the installation of beam sections 6 for installing the steel box girders on two sides of the existing bridge to ensure the readiness of the installation working condition of the steel box girders. When hoisting, firstly, hoisting the steel box girder by using a crane 2 No. 1 positioned at the same side of the steel box girder, and adjusting the position of the steel box girder to ensure that the steel box girder is vertical to the existing bridge in the process; and then, the steel box girder descends to enable one end of the steel box girder to be placed on the temporary conversion support, the other end of the steel box girder is hung and hung by a crane No. 2 and a crane No. 3, after the steel box girder and the temporary conversion support are stabilized, the steel box girder and the temporary conversion support are welded and fixed, the crane No. 1 and the crane No. 2 are loosened, the crane No. 1 is hung and hung on one end of the steel box girder welded with the temporary conversion support, the steel box girder and the temporary conversion support are cut to remove the connection of the steel box girder and the temporary conversion support, at the moment, the two cranes are respectively hung at the two ends of the steel box girder, and then the steel box girder is hung to a bridge-crossing installation position. The whole process is smooth and efficient, safe and stable, and meanwhile, the safety of the existing bridge cannot be affected.
In the construction process, an assembling field is arranged on the side of the crane No. 1, a span beam section (the span beam section is a steel box beam, the same applies below) is assembled, the beam sections on two sides of the existing bridge are completely installed before hoisting, and a temporary conversion support is erected. Then, the No. 1 crane lifts the assembled span beam section. And then, rotating the crane No. 1 to enable the span line beam section to be perpendicular to the existing bridge, and reducing the height of the span line beam section to enable one end of the span line beam section to fall on the temporary conversion support. And then the other end of the span line beam section is connected by a No. 2 crane on the other side of the existing bridge. And (4) temporarily fixing the span beam section and the temporary conversion support, preferably welding and fixing. And then slowly releasing the hook of the crane No. 1, and monitoring the stress state of the crane No. 2 until the conversion of a stress system is completed. Then the No. 1 crane changes the hook to the cross-line beam section conversion bracket end, slowly lifts the hook, cuts off the conversion bracket, completes the conversion of the stress system, and forms the double-crane lifting state. And finally, synchronously rotating the No. 1 crane and the No. 2 crane to the in-place position of the span beam section in a coordinated manner to finish hoisting.
The method is different from a common method for hoisting the steel box girder across the existing bridge, has strong pertinence, and solves the problems of limited field, large crane selection and poor economy in the process of hoisting the steel box girder across the existing bridge. Meanwhile, the method has the advantages of low operation difficulty, low cost, low requirement on environment during use, high hoisting speed, small influence on the traffic of the existing bridge and good use effect. The invention has good applicability and strong practicability, and is suitable for popularization and application in hoisting construction of a plurality of existing bridge-spanning steel box girders.
Finally, it should be noted that: the above embodiments are only preferred embodiments of the present invention to illustrate the technical solutions of the present invention, but not to limit the technical solutions, and certainly not to limit the patent scope of the present invention; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention; that is, the technical problems to be solved by the present invention, which are not substantially changed or supplemented by the spirit and the concept of the main body of the present invention, are still consistent with the present invention and shall be included in the scope of the present invention; in addition, the technical scheme of the invention is directly or indirectly applied to other related technical fields, and the technical scheme is included in the patent protection scope of the invention.

Claims (8)

1. A steel box girder striding existing bridge hoisting construction method is characterized by comprising the following steps:
step 1, setting up a temporary conversion support on one side of an existing bridge, and simultaneously setting a crane No. 1 and a crane No. 2 on two sides of the existing bridge respectively, wherein the steel box girder, the temporary conversion support and the crane No. 1 are positioned on the same side of the existing bridge;
step 2, hoisting the steel box girder by using a No. 1 crane and enabling the steel box girder to be positioned above the existing bridge;
step 3, adjusting the height of the steel box girder to enable one end of the steel box girder to be supported on the temporary conversion support, and hooking the other end of the steel box girder by a No. 2 crane;
step 4, fixing the temporary conversion support and the steel box girder;
step 5, loosening the hook of the crane No. 1, and completely supporting the steel box girder by the temporary conversion bracket and the crane No. 2;
step 6, hooking one end of the steel box girder, which is fixed with the temporary conversion support, by the crane No. 1, and removing the connection between the steel box girder and the temporary conversion support;
and 7, cooperatively hoisting the steel box girder to the installation position across the existing bridge by the No. 1 crane and the No. 2 crane.
2. The construction method for hoisting the steel box girder across the existing bridge according to claim 1, wherein in the step 1, a steel box girder on-site assembling table for assembling the steel box girder is synchronously erected when the temporary conversion support is erected.
3. The construction method for hoisting the steel box girder across the existing bridge according to claim 2, wherein the steel box girder field assembling platform and the temporary conversion support are positioned on the same side of the existing bridge.
4. The construction method for hoisting the steel box girder across the existing bridge according to claim 1, wherein in the step 2, beam sections used for installing the steel box girder on two sides of the existing bridge are installed before the steel box girder is hoisted by a crane No. 1.
5. The construction method for hoisting the steel box girder across the existing bridge according to claim 1, wherein in the step 2, when the steel box girder is hoisted to the position above the existing bridge by using a crane No. 1, the position of the steel box girder is adjusted to be vertically distributed with the existing bridge.
6. The construction method for hoisting the steel box girder across the existing bridge according to claim 1, wherein in the step 4, the temporary conversion support and the steel box girder are fixed by welding.
7. The construction method for hoisting the steel box girder across the existing bridge according to claim 6, wherein in the step 6, the connection between the steel box girder and the temporary conversion bracket is released by cutting.
8. The construction method for hoisting the steel box girder across the existing bridge according to claim 1, wherein in the step 5, the stress state of the crane 2 is monitored in real time in the process of releasing the hook of the crane No. 1 until the stress system of the steel box girder is completely converted into the temporary conversion bracket and the crane No. 2, so that the crane No. 1 can be completely released.
CN202011013753.8A 2020-09-24 2020-09-24 Steel box girder bridge-spanning existing bridge hoisting construction method Pending CN112095482A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011013753.8A CN112095482A (en) 2020-09-24 2020-09-24 Steel box girder bridge-spanning existing bridge hoisting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011013753.8A CN112095482A (en) 2020-09-24 2020-09-24 Steel box girder bridge-spanning existing bridge hoisting construction method

Publications (1)

Publication Number Publication Date
CN112095482A true CN112095482A (en) 2020-12-18

Family

ID=73755271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011013753.8A Pending CN112095482A (en) 2020-09-24 2020-09-24 Steel box girder bridge-spanning existing bridge hoisting construction method

Country Status (1)

Country Link
CN (1) CN112095482A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113322823A (en) * 2021-06-03 2021-08-31 陕西重型机械制造有限公司 Rapid hoisting method for large-span steel bridge
CN114687293A (en) * 2022-04-13 2022-07-01 上海市机械施工集团有限公司 Steel box girder hoisting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101324146A (en) * 2008-08-11 2008-12-17 河北建工集团有限责任公司 Construction method for hanging wide span arcuated open-web beam
CN101864730A (en) * 2009-04-14 2010-10-20 上海市第一建筑有限公司 Construction method for hoisting steel-structure box girder to cross original high racks
CN203767902U (en) * 2014-03-14 2014-08-13 武汉通联路桥机械技术有限公司 Hoisting crane structure of folding block of steel box girder of cable-stayed bridge
CN105332515A (en) * 2015-10-29 2016-02-17 中冶建工集团有限公司 Erection method of large-span truss structure in limited space
JP6344879B1 (en) * 2018-01-24 2018-06-20 株式会社フジみらい Suspension scaffold construction method and suspension scaffold in bridge structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101324146A (en) * 2008-08-11 2008-12-17 河北建工集团有限责任公司 Construction method for hanging wide span arcuated open-web beam
CN101864730A (en) * 2009-04-14 2010-10-20 上海市第一建筑有限公司 Construction method for hoisting steel-structure box girder to cross original high racks
CN203767902U (en) * 2014-03-14 2014-08-13 武汉通联路桥机械技术有限公司 Hoisting crane structure of folding block of steel box girder of cable-stayed bridge
CN105332515A (en) * 2015-10-29 2016-02-17 中冶建工集团有限公司 Erection method of large-span truss structure in limited space
JP6344879B1 (en) * 2018-01-24 2018-06-20 株式会社フジみらい Suspension scaffold construction method and suspension scaffold in bridge structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113322823A (en) * 2021-06-03 2021-08-31 陕西重型机械制造有限公司 Rapid hoisting method for large-span steel bridge
CN114687293A (en) * 2022-04-13 2022-07-01 上海市机械施工集团有限公司 Steel box girder hoisting method

Similar Documents

Publication Publication Date Title
CN112095482A (en) Steel box girder bridge-spanning existing bridge hoisting construction method
CN114134990B (en) Installation and uninstallation method of large-span overhanging corridor
LU501962B1 (en) Long Platform Guy-Wire Hanging Basket and Construction Method For Main Girder Section
CN112049235B (en) High-altitude large-span cantilever structure construction platform and method
CN201746781U (en) Diagonal draw type bracket for cast-in-place of continuous beam
CN111535190A (en) Bridge mounting and dismounting construction method with high safety
CN112942661A (en) Construction method of stay cable with flexible cable net boundary
CN116837967A (en) Construction method of large-span cable-stayed truss structure
CN216891987U (en) Special-shaped steel ladle concrete upper tower column
CN215670948U (en) Steel cable truss device for dome structure construction
CN216196728U (en) Overhanging type prefabricated stand board sliding installation device
CN212247877U (en) Main tower inner formword and maintenance platform integrated device
CN212315371U (en) Cable installation lifting device for cable-stayed bridge
CN112761367A (en) Overhanging type prefabricated stand plate sliding installation device and construction method thereof
CN113882280A (en) Construction method of steel-concrete mixed combined continuous rigid frame bridge
CN220638385U (en) Movable tensioning device suitable for precast T beam edge and midspan hogging moment
CN107700363B (en) Bridge tower rack with lifting system and construction method
JPH11269825A (en) Installation method of bridge girder and lifting equipment
CN110219416A (en) A kind of precast concrete Y type beam assembly and its construction method
CN220564178U (en) Truss lifting device
CN216239717U (en) Y-shaped inclined strut supporting system for cantilever plate
CN113463758B (en) Large square steel structure framework based on self-balancing and manufacturing method thereof
CN218931529U (en) Lifting device for column top steel beam
CN214527669U (en) Bridge steel case roof beam hoisting structure
CN212505806U (en) Cable-stayed bridge construction system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201218

RJ01 Rejection of invention patent application after publication