CN112072714B - Online-calculation-based power system minimum startup mode optimization method - Google Patents

Online-calculation-based power system minimum startup mode optimization method Download PDF

Info

Publication number
CN112072714B
CN112072714B CN202010947044.0A CN202010947044A CN112072714B CN 112072714 B CN112072714 B CN 112072714B CN 202010947044 A CN202010947044 A CN 202010947044A CN 112072714 B CN112072714 B CN 112072714B
Authority
CN
China
Prior art keywords
safety
simulation
generator sets
power grid
stability
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010947044.0A
Other languages
Chinese (zh)
Other versions
CN112072714A (en
Inventor
呙虎
陈道君
王玎
柳永妍
崔挺
左剑
杨丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd, State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202010947044.0A priority Critical patent/CN112072714B/en
Publication of CN112072714A publication Critical patent/CN112072714A/en
Application granted granted Critical
Publication of CN112072714B publication Critical patent/CN112072714B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • H02J3/466Scheduling the operation of the generators, e.g. connecting or disconnecting generators to meet a given demand
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Control Of Eletrric Generators (AREA)

Abstract

The invention discloses an online calculation-based power system minimum startup mode optimization method, which comprises the following steps: acquiring real-time operation state data and model parameters of a power grid to form online calculation data of the power grid; setting the number of initial simulation shutdown generator sets and an initial value of a simulation reduction rotation reserve capacity coefficient; by sequentially stopping a specific number of generator sets and performing safety and stability assessment: if the requirement of safety and stability is met, updating the number of the shutdown generator sets and repeating the steps to determine the starting number of the minimum starting mode calculated on line; the rotating reserve capacity of the generator set is reduced through proportional simulation, and safety and stability evaluation is carried out: and if the safety and stability requirements are met, updating, simulating and reducing the rotating reserve capacity and repeating the steps to determine the rotating reserve capacity of each started generator set. The invention can reduce the constraint of the minimum starting mode determined by off-line calculation on the generator set, and improve the flexibility and the power supply capacity of the power grid operation mode.

Description

Online-calculation-based power system minimum startup mode optimization method
Technical Field
The invention belongs to the technical field of power grid dispatching operation control, and particularly relates to a power system minimum startup mode optimization method based on online calculation.
Background
When the load in a certain area increases to a certain extent, in order to maintain the voltage of a load point within a specified range, a certain number of starting units and a certain rotation standby capacity are generally required to be maintained, which is the reason of the minimum starting mode of a regional power grid. With the application and development of the ultra-high voltage direct current transmission technology, the power transmitted by direct current is continuously increased, and the influence on the accessed alternating current power grid is more obvious. The method mainly solves the problems of high frequency, high voltage and even power angle stability of a generator set caused by surplus power of a transmitting-end alternating current power grid when an extra-high voltage direct current lock is locked or large disturbance occurs to an alternating current power grid, and low frequency, low voltage and even voltage stability caused by power loss of a receiving-end alternating current power grid. In order to ensure the safety of the ac power grid at the transmitting end and the receiving end, on the basis of maintaining the minimum startup mode in each region, a certain number of startup units and a certain rotation reserve capacity need to be maintained in a larger range, such as a provincial power grid region.
At present, in the prior art, the minimum starting mode of the provincial power grid is determined by adopting off-line simulation calculation software and carrying out calculation analysis on a limited typical operation mode. The cycle of rechecking is long, usually once every half year. In order to be able to cover as much as possible the various operating conditions, typical operating modes often choose the most severe combinations of operating conditions that have ever occurred. The minimum starting mode obtained by the method is always conservative in actual operation, and has an optimized space in most of time.
Disclosure of Invention
The invention solves the technical problem that aiming at the defects of the prior art, the invention provides the power system minimum starting mode optimization method based on the online calculation, which can reduce the constraint of the minimum starting mode determined by the offline calculation on the generator set and improve the flexibility and the power supply capacity of the power grid operation mode.
In order to achieve the technical purpose, the invention adopts the following technical scheme:
a minimum startup mode optimization method of an electric power system based on online calculation comprises the following steps:
step 1, acquiring real-time operation state data and model parameters of a power grid to form online calculation data of the power grid;
step 2, setting the number of the generator sets constrained by the minimum starting-up mode obtained by off-line calculation as N, the total rotating reserve capacity as P megawatts, the number of the initial simulation shutdown generator sets as i equal to 1, and the simulation reduction rotating reserve capacity coefficient as j equal to 1;
step 3, selecting i generator sets from the N generator sets to simulate shutdown, and carrying out operation comparison on the generator sets
Figure BDA0002675678810000011
The simulation shutdown mode is characterized in that safety and stability evaluation is carried out according to the online calculation data of the power grid: if it is not
Figure BDA0002675678810000012
If the simulation shutdown modes meet the safety and stability requirement, updating the number of the simulation shutdown generator sets to be i +1, then repeating the step 3 until the simulation shutdown modes do not meet the safety and stability requirement, if the i is 1, executing the step 4, and if the i is more than 1, executing the step 5
Step 4, calculating data on line according to the power grid, simulating and reducing the rotation reserve capacity of the current N generator sets by j x delta in proportion, and checking whether the generator sets subjected to the simulation reduction of the rotation reserve capacity meet the requirements of safety and stability: if the safety and stability requirements are met, updating the simulation rotation reduction spare capacity coefficient to j ═ j +1, and repeating the step 4 until the safety and stability requirements are not met, and executing the step 5;
and 5, determining the minimum starting-up mode optimization result of the power system calculated on line as follows: the number of the generator sets is N- (i-1), and the rotating reserve capacity of the generator sets is P (1- (j-1) delta) megawatts.
The minimum starting mode optimization only considers reducing the number of starting machines or reducing the rotating standby capacity of the generator set so as to reserve a certain safety margin.
Further, the real-time operation state data of the power grid comprises: the system comprises a power grid load, the output of each generator set, a main transformer, a line state and a switching state of reactive compensation equipment.
Further, the model parameters include: the system comprises load model parameters, generator set synchronous motor, excitation system and PSS, speed regulation system model parameters, transformer nameplate parameters and line actual measurement or typical parameters.
Further, δ is 10%.
Further, whether the generator set meets the safety and stability requirements is judged according to whether the power system after the fault can be recovered stably or not by traversing all the bus and the main transformer three-phase faults.
Further, the minimum power-on mode optimization is performed every five to fifteen minutes.
Advantageous effects
The invention forms the online calculation data of the power grid by regularly acquiring the real-time running state of the power grid, thereby regularly checking the minimum startup mode of the concerned power system, and when the power system has an optimization space, adjusting the power system from multiple aspects: the number of the starting units is reduced, or the rotating reserve capacity of the generator set is reduced, and the flexibility of the operation mode of the power grid and the power supply capacity can be improved while a certain safety margin is kept.
Drawings
Fig. 1 is a flowchart of a minimum startup mode optimization method of an electric power system based on online computing according to the present invention.
Detailed Description
The following describes embodiments of the present invention in detail, which are developed based on the technical solutions of the present invention, and give detailed implementation manners and specific operation procedures to further explain the technical solutions of the present invention.
The invention provides an optimization method of a minimum startup mode of an electric power system based on online calculation, which comprises the following steps as shown in figure 1:
step 1, regularly (the optimized frequency range is every five minutes or every fifteen minutes, and can be selected according to actual needs) acquiring real-time operation state data and model parameters of a power grid to form online calculation data of the power grid;
wherein, the real-time running state data of electric wire netting includes: the system comprises a power grid load, the output of each generator set, main transformers, line states and the switching state of reactive compensation equipment; the model parameters include: the system comprises load model parameters, generator set synchronous motor, excitation system and PSS, speed regulation system model parameters, transformer nameplate parameters and line actual measurement or typical parameters.
Step 2, setting the number of the generator sets constrained by the minimum starting-up mode obtained by off-line calculation as N, the total rotating reserve capacity as P megawatts, the number of the initial simulation shutdown generator sets as i equal to 1, and the simulation reduction rotating reserve capacity coefficient as j equal to 1; the number of the generator sets constrained by the minimum starting-up mode obtained by off-line calculation is obtained by calculating by adopting the existing off-line simulation calculation software;
step 3, selecting i generator sets from the N generator sets to simulate shutdown, and carrying out operation comparison on the generator sets
Figure BDA0002675678810000032
The simulation shutdown mode is characterized in that safety and stability evaluation is carried out according to the online calculation data of the power grid: if it is not
Figure BDA0002675678810000033
If the simulation shutdown modes meet the safety and stability requirement, updating the number of the simulation shutdown generator sets to be i +1, then repeating the step 3 until the simulation shutdown modes do not meet the safety and stability requirement, if the i is 1, executing the step 4, and if the i is more than 1, executing the step 5;
step 4, calculating data on line according to the power grid, simulating and reducing the rotation reserve capacity of the current N generator sets by j x delta in proportion, and checking whether the generator sets with the reduced rotation reserve capacity meet the requirements of safety and stability or not: if the safety and stability requirements are met, updating the simulation rotation reduction spare capacity coefficient to j ═ j +1, and repeating the step 4 until the safety and stability requirements are not met, and executing the step 5; wherein, the value of δ may be δ 10%;
and 5, determining the minimum starting-up mode optimization result of the power system calculated on line as follows: the number of the generator sets is N- (i-1), and the rotating reserve capacity of the generator sets is P (1- (j-1) delta) megawatts.
And 3, performing safety and stability assessment related to the step 3 and the step 5 by adopting a transient stability checking method of online computing software in the prior art, traversing all bus and main transformer three-phase faults, and judging whether the generator set meets the safety and stability requirement according to whether the power system after the faults can recover to be stable.
The following parts take a certain provincial power grid as an example, the provincial power grid has extra-high voltage direct current transmission, and certain minimum starting number and rotation reserve capacity of the thermal power generating units in the load center are kept at different load levels according to the extra-high voltage direct current transmission power due to the voltage stability problem. The minimum boot-up requirement calculated off-line is shown in table 1.
TABLE 1 minimum startup mode requirement from some provincial level power grid offline calculation
Figure BDA0002675678810000031
Figure BDA0002675678810000041
Example 1:
if the maximum load of a certain day is 2100 ten thousand kilowatts, 1 more thermal power generating units are normally started on the basis of the minimum starting number required by the maximum direct current power in order to guarantee the consumption of clean energy, so that the direct current transmission power is not influenced after any thermal power generating unit is tripped due to faults. According to the requirements of table 1, 19 thermal power generating units are started on the day, and the maximum direct current transmission power can reach 400 ten thousand kilowatts.
If the actual load exceeds the predicted load to 2150 ten thousand kilowatts due to the fact that the temperature is higher, according to the requirements of the table 1, under the load level of the current gear, when the minimum starting time of the thermal power generating unit in the load center is 19 machines, the maximum power of direct current transmission is only 300 ten thousand kilowatts. Therefore, it is necessary to reduce the dc transmission power from 400 to 300 kw.
If the minimum starting-up mode optimization method is applied, when the actual load exceeds 2100 ten thousand kilowatts, the real-time running state data and the model parameters of the power grid are obtained, the online calculation data of the power grid is formed, the minimum starting-up mode of the power grid is checked at the moment, and whether the minimum starting-up mode obtained by offline calculation has the optimization space or not is evaluated. If the minimum starting mode of the thermal power generating unit with the direct current transmission of 400 ten thousand kilowatt hours can be reduced from 20 to 19, the direct current transmission power does not need to be reduced from 400 ten thousand kilowatts to 300 ten thousand kilowatts. Therefore, the external power receiving capacity of the provincial power grid is not reduced, and the stable operation of the power grid is guaranteed.
Example 2:
if the load level of the provincial power grid reaches 3100 thousands of kilowatts in a certain load peak period, the direct current transmission power is 400 thousands of kilowatts, and the power supply pressure is higher. According to the requirements of table 1, the minimum number of the power generating units in the load center is 24, and the minimum rotation reserve capacity is 300 ten thousand kilowatts.
By applying the minimum starting-up mode optimization method, the real-time running state data and the model parameters of the power grid are obtained, the online calculation data of the power grid are formed, the minimum starting-up mode of the power grid is checked at the moment, and whether the minimum starting-up mode obtained by offline calculation has the optimization space is evaluated. If the minimum rotating reserve capacity can be reduced from 300 to 270 million kilowatts, the output of the limited unit can be increased by 30 million kilowatts, so that the power supply capacity of a power grid is increased by 30 million kilowatts, and the power supply pressure is relieved.
The above embodiments are preferred embodiments of the present application, and those skilled in the art can make various changes or modifications without departing from the general concept of the present application, and such changes or modifications should fall within the scope of the claims of the present application.

Claims (6)

1. A minimum startup mode optimization method of an electric power system based on online calculation is characterized by comprising the following steps:
step 1, acquiring real-time operation state data and model parameters of a power grid to form online calculation data of the power grid;
step 2, setting the number of the generator sets constrained by the minimum starting-up mode obtained by off-line calculation as N, the total rotating reserve capacity as P megawatts, the number of the initial simulation shutdown generator sets as i equal to 1, and the simulation reduction rotating reserve capacity coefficient as j equal to 1;
step 3, selecting i generator sets from the N generator sets to simulate shutdown, and carrying out operation Ci NThe simulation shutdown mode is characterized in that safety and stability evaluation is carried out according to the online calculation data of the power grid: if C is presenti NIf the simulation shutdown modes meet the safety and stability requirement, updating the number of the simulation shutdown generator sets to be i +1, then repeating the step 3 until the simulation shutdown modes do not meet the safety and stability requirement, if the i is 1, executing the step 4, and if the i is more than 1, executing the step 5;
step 4, calculating data on line according to the power grid, simulating and reducing the rotation reserve capacity of the current N generator sets by j x delta in proportion, and checking whether the generator sets subjected to the simulation reduction of the rotation reserve capacity meet the requirements of safety and stability: if the safety and stability requirements are met, updating the simulation rotation reduction spare capacity coefficient to j ═ j +1, and repeating the step 4 until the safety and stability requirements are not met, and executing the step 5;
and 5, determining the minimum starting-up mode optimization result of the power system calculated on line as follows: the number of the generator sets is N- (i-1), and the rotating reserve capacity of the generator sets is P (1- (j-1) delta) megawatts.
2. The method of claim 1, wherein the grid real-time operating state data comprises: the system comprises a power grid load, the output of each generator set, a main transformer, a line state and a switching state of reactive compensation equipment.
3. The method of claim 1, wherein the model parameters comprise: the system comprises load model parameters, generator set synchronous motor, excitation system and PSS, speed regulation system model parameters, transformer nameplate parameters and line actual measurement or typical parameters.
4. The method of claim 1, wherein δ is 10%.
5. The method according to claim 1, wherein whether the generator set meets the safety and stability requirement is judged according to whether the power system after the fault can be recovered to be stable or not by traversing all the bus and main transformer three-phase faults.
6. The method of claim 1, wherein the minimal power-on optimization is performed every five to fifteen minutes.
CN202010947044.0A 2020-09-10 2020-09-10 Online-calculation-based power system minimum startup mode optimization method Active CN112072714B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010947044.0A CN112072714B (en) 2020-09-10 2020-09-10 Online-calculation-based power system minimum startup mode optimization method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010947044.0A CN112072714B (en) 2020-09-10 2020-09-10 Online-calculation-based power system minimum startup mode optimization method

Publications (2)

Publication Number Publication Date
CN112072714A CN112072714A (en) 2020-12-11
CN112072714B true CN112072714B (en) 2022-03-15

Family

ID=73663472

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010947044.0A Active CN112072714B (en) 2020-09-10 2020-09-10 Online-calculation-based power system minimum startup mode optimization method

Country Status (1)

Country Link
CN (1) CN112072714B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102545208A (en) * 2011-12-26 2012-07-04 东北电网有限公司 Power grid running mode getting method based on frequency response
CN104242355A (en) * 2014-09-19 2014-12-24 清华大学 Wind-power-plant-having-access-to-power-grid position and capacity control method with minimum wind curtailment considered
CN104318323A (en) * 2014-10-13 2015-01-28 华南理工大学 Quick dispatching method for unit commitment considering reliability constraint
CN109088427A (en) * 2018-07-23 2018-12-25 国网青海省电力公司经济技术研究院 Conventional power unit minimum booting scheme determines method and system in a kind of AC-DC hybrid power grid

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103259285B (en) * 2013-05-03 2015-04-29 国家电网公司 Method for optimizing short running of electric power system comprising large-scale wind power

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102545208A (en) * 2011-12-26 2012-07-04 东北电网有限公司 Power grid running mode getting method based on frequency response
CN104242355A (en) * 2014-09-19 2014-12-24 清华大学 Wind-power-plant-having-access-to-power-grid position and capacity control method with minimum wind curtailment considered
CN104318323A (en) * 2014-10-13 2015-01-28 华南理工大学 Quick dispatching method for unit commitment considering reliability constraint
CN109088427A (en) * 2018-07-23 2018-12-25 国网青海省电力公司经济技术研究院 Conventional power unit minimum booting scheme determines method and system in a kind of AC-DC hybrid power grid

Also Published As

Publication number Publication date
CN112072714A (en) 2020-12-11

Similar Documents

Publication Publication Date Title
Ayodele et al. Challenges of grid integration of wind power on power system grid integrity: A review
RU2605083C2 (en) Method of electric generator controlling
Paál et al. Grid connected inverters influence on power quality of smart grid
Sakipour et al. Voltage stability improvement of wind farms by self-correcting static volt-ampere reactive compensator and energy storage
CN112529373A (en) Power grid frequency stability evaluation method under simultaneous fault of multiple loops of direct current
Wasiak et al. Application of DSTATCOM compensators for mitigation of power quality disturbances in low voltage grid with distributed generation
CN112072714B (en) Online-calculation-based power system minimum startup mode optimization method
Zare et al. Intelligent topology-oriented load shedding scheme in power systems
Dinic et al. Increasing wind farm capacity
Beus et al. Microgrid dispatch with protection constraints
Joshı et al. Analysis of stability of wind based distributed energy generation system
Jayaweera et al. Customer security assessment in distribution networks with high penetration of wind power
CN113300397A (en) Alternating current-direct current reactive power exchange reference value optimization method and system
Xiaohui et al. Power system risk assessment method based on dynamic power flow
Shrestha et al. Minimum-cost generation-shedding for dynamic remedial action scheme
Gazizova et al. Research of the Effectiveness of Existing Laws of Automatic Regulation of Excitation of Synchronous Generators of Industrial Power Plants under Various Conditions of Connection to the Electric Power System
Tantawy et al. Techno-Economic Assessment of Voltage Sags Mitigation in Distribution System Connected to DGs
CN112003320A (en) Voltage stabilizing method under urban power grid hollowing trend
Lin et al. The calculation method of critical permeability of new energy constrained by static voltage stability
Liu et al. Temporary overvoltage assessment and suppression in heterogeneous renewable energy power systems
Atallah et al. Supervisory control of reactive power in wind farms with doubly fed induction generator-based wind turbines for voltage regulation and power losses reduction
Hossain et al. Dynamic interactions among multiple DER controllers in distribution systems
JP7434093B2 (en) Power system stabilization device, power system stabilization method, and program
Choube Research on fuzzy logic-based wind grid system to improve power quality
Sabo et al. A Review of Power System Oscillations for a Grid-Connected Photovoltaic (PV) System

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant