CN112031807A - Variable-section supporting structure of station tunnel and construction method of station tunnel - Google Patents

Variable-section supporting structure of station tunnel and construction method of station tunnel Download PDF

Info

Publication number
CN112031807A
CN112031807A CN202010718762.0A CN202010718762A CN112031807A CN 112031807 A CN112031807 A CN 112031807A CN 202010718762 A CN202010718762 A CN 202010718762A CN 112031807 A CN112031807 A CN 112031807A
Authority
CN
China
Prior art keywords
tunnel
station tunnel
station
construction
pilot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010718762.0A
Other languages
Chinese (zh)
Inventor
李小刚
黄朝根
邹盛全
方涛
唐顺治
郭俊强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ranken Railway Construction Group Co Ltd
Original Assignee
Ranken Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ranken Railway Construction Group Co Ltd filed Critical Ranken Railway Construction Group Co Ltd
Priority to CN202010718762.0A priority Critical patent/CN112031807A/en
Publication of CN112031807A publication Critical patent/CN112031807A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a variable-section supporting structure of a station tunnel and a construction method of the station tunnel, wherein the supporting structure comprises a construction channel and the station tunnel, the station tunnel is vertical and communicated with the end part of the construction channel, primary supports and secondary linings are arranged in the construction channel and the station tunnel, a plurality of transverse supports and vertical supports are arranged in the station tunnel, and the transverse supports and the vertical supports divide the station tunnel into a plurality of pilot tunnels; according to the method, certain reinforcement measures are taken at the primary combination position of the construction tunnel and the station tunnel, the construction tunnel directly expands and excavates the station tunnel to the section form after entering the station tunnel, then transversely excavates the station tunnel to the other end, and then excavates the station tunnel in sequence, so that the construction period is short, the construction efficiency is high, and the risk is low; in addition, the plurality of small pilot tunnels are arranged in the station tunnel, and each small pilot tunnel is independently constructed in the axial direction of the station tunnel to complete the tunneling of the station tunnel, so that the construction period is shortened, and the construction efficiency is improved.

Description

Variable-section supporting structure of station tunnel and construction method of station tunnel
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a variable section supporting structure of a station tunnel and a construction method of the station tunnel.
Background
With the acceleration of the urbanization process in China, the utilization of underground space resources becomes one of the most important means for solving the problems of traffic congestion and land resource shortage. For subway stations, because the stations are deep in buried depth and large in size, underground excavation methods are mainly adopted for construction at present. The method specifically comprises the following steps: firstly, digging a construction channel, then digging a station tunnel from the construction channel, and finally tunneling the station tunnel along the axial direction of the station tunnel; when the construction channel is excavated, the construction channel firstly reaches the excavation end along the advancing direction of the construction channel, then the construction channel section is reversely excavated and expanded, and the length range of the channel is completely expanded and excavated in place according to the construction channel section. The disadvantages of the excavation mode are as follows: firstly, when the reverse expanding excavation is carried out, the method belongs to the excavation of 'immortal soil', the safety risk is high, the top stones of the heads of workers are easy to fall off to hurt people, and meanwhile, the collapse risk also exists; firstly, excavating once according to the section of the construction channel, and then reversely expanding and excavating once, wherein the two-time excavation period is long, and the progress of the construction period is influenced; and thirdly, the station tunnel is large in size and deep in burial depth, so that primary supporting and secondary lining of the station tunnel are difficult, excavation is difficult, the risk of excavation is large, and the efficiency is low.
Disclosure of Invention
The invention provides a variable-section supporting structure of a station tunnel and a construction method of the station tunnel, which aim to solve the technical problems of low efficiency and large risk of variable-section excavation when the station tunnel and an underground construction channel enter the station tunnel.
The technical scheme adopted by the invention is as follows: the variable-section supporting structure of the station tunnel comprises a construction channel and the station tunnel, wherein the station tunnel is vertical and is communicated with the end part of the construction channel, an initial support and a secondary lining are arranged in the construction channel and the station tunnel, a plurality of transverse supports and vertical supports are arranged in the station tunnel, and the station tunnel is separated into a plurality of guide holes by the transverse supports and the vertical supports. Because the station tunnel is deep in buried depth and large in size, a plurality of small pilot tunnels are arranged in the station tunnel, and each small pilot tunnel is independently constructed in the axial direction of the station tunnel to complete the tunneling of the station tunnel; and meanwhile, the risk of station tunnel collapse is also reduced.
Further, the number of the transverse supports is six, the number of the vertical supports is two, and the transverse supports and the vertical supports divide the station tunnel into nine pilot tunnels; the transverse supports are respectively arranged at the middle upper part and the middle lower part of the station tunnel, and the vertical supports are symmetrically arranged relative to the central line of the station tunnel. Too many pilot tunnels are arranged, so that the construction cost of primary support and secondary lining is increased, and the construction efficiency is reduced; the pilot tunnel is arranged too few, the stability of surrounding rocks of the station tunnel is poor, and the risk of construction collapse is also improved; therefore, the invention preferably selects nine pilot tunnels in a plurality of modes, thereby not only ensuring the construction efficiency and the construction cost, but also reducing the construction risk to the minimum; and the transverse supports are arranged at the middle upper part and the middle lower part of the station tunnel, so that the area difference of each pilot tunnel is small, and the stability of the pilot tunnel is further ensured.
Further, the vertical supports are arc-shaped, and the vertical supports are bent towards the center of the tunnel. Because the vault and the arch bottom in tunnel are the arc, if set up vertical braces for the structure of the direction on perpendicular to ground, can make the country rock side atress of tunnel inner wall, cause the tunnel atress inhomogeneous, vertical braces can't be with the perpendicular atress of tunnel inner wall, vertical braces's support poor stability. Therefore, the vertical supports are arranged in the arc shape, the arc-shaped vertical supports are stressed perpendicularly to the inner wall of the tunnel, stress is more uniform, and stability is higher.
Furthermore, one end of the construction tunnel, which is close to the station tunnel, is provided with a door frame extending into the station tunnel. The invention adopts certain reinforcement measures at the primary combination position of the construction tunnel and the station tunnel, directly expands and excavates the construction tunnel and the station tunnel to the section form of the station tunnel after entering the station tunnel, then transversely excavates the construction tunnel to the other end in the station tunnel, and excavates the station tunnel in sequence.
Further, an arc-shaped arch center is arranged below the door frame. Further improve the stability of construction tunnel and the first combination department of station tunnel.
Further, a first grouting anchor rod penetrating into the primary support and the secondary lining is arranged on the inner wall of the station tunnel; the first grouting anchor rod is of a hollow structure. The first grouting anchor rod plays a role in supporting and reinforcing the surrounding rock of the tunnel, and the interlayer friction resistance is improved. In addition, mortar can be injected into the concrete in the primary support and the secondary lining through the grouting anchor rod to fill the concrete gap, so that the effects of reinforcing the concrete and preventing water seepage are achieved.
Further, two opposite sides of the vertical supports are provided with second grouting anchor rods; the second slip casting stock is hollow structure. All there is the concrete layer on vertical braces and the horizontal support, can pour into the mortar into to the concrete on the vertical braces through the slip casting stock, play the effect of reinforced concrete and prevention of seepage water.
The construction method of the station tunnel comprises the following steps:
s1, firstly digging a construction channel, and carrying out primary support and secondary lining in the construction channel;
s2, arranging a door frame at one end of the construction channel connected with the station tunnel, and arranging an arch frame below the door frame;
s3, according to the trend of the construction channel, excavating a station tunnel in the direction perpendicular to the construction channel at the end part of the construction channel; the method specifically comprises the following steps: excavating from one end of the station tunnel to the other end of the station tunnel in the transverse direction of the station tunnel; firstly digging the upper half part of the station tunnel along a base line in the station tunnel, performing primary support, secondary lining and a first grouting anchor rod, then digging the lower half part of the station tunnel, and performing primary support and secondary lining;
s4, erecting a vertical support and a transverse support in the station tunnel, and erecting a second grouting anchor rod; the station tunnel is divided into nine pilot tunnels by the transverse supports and the vertical supports, primary support and secondary lining are carried out on each pilot tunnel, and each pilot tunnel is independently constructed in the axial direction of the station tunnel to carry out tunneling of the station tunnel; and after the construction of the station tunnel is finished, the transverse support and the vertical support are removed.
According to the method, certain reinforcement measures are taken at the primary combination position of the construction tunnel and the station tunnel, the construction tunnel directly expands and excavates the station tunnel to the section of the station tunnel after entering the station tunnel, then the construction tunnel transversely excavates the station tunnel to the other end, and then each pilot tunnel of the station tunnel is excavated separately in sequence. Compared with the traditional one-time tunneling mode of the station tunnel, the method can more conveniently carry out primary support and secondary lining on the station tunnel, reduce the construction period and improve the construction efficiency; and meanwhile, the risk of station tunnel collapse is also reduced. The method is safe, reliable, economical and feasible, and short in construction period.
Further, in step S3, the base line is inclined toward the top of the tunnel, and the included angle between the base line and the horizontal direction is 5 ° to 10 °. In the process of tunnel excavation, a scaffold is required to be erected in a tunnel, and the tunnel is excavated transversely in an inclined mode, so that the working height during station excavation can be reduced, the erecting height of the scaffold can be reduced, the labor intensity of workers can be reduced, and the erecting efficiency can be improved; on the other hand is convenient for collect and carry the dregs in the tunnel work progress, and the operation of the base line of slope on being convenient for the dregs roll off and haulage vehicle on the benchmark line, labour saving and time saving improves the efficiency of construction.
Further, in step S4, the construction sequence of the nine pilot holes sequentially includes: and constructing an upper right pilot tunnel, an upper left pilot tunnel, a middle right pilot tunnel, a middle left pilot tunnel, a lower right pilot tunnel, a lower left pilot tunnel, an upper core pilot tunnel, a middle core pilot tunnel and a lower core pilot tunnel. From the construction sequence, the pilot tunnel is constructed from top to bottom, and the lower part of the pilot tunnel which is not constructed plays a role in supporting the pilot tunnel in the upper part construction, so that the stability of the constructed pilot tunnel is improved, the collapse risk is reduced, and the safety of constructors is ensured; meanwhile, the dregs in the upper guide tunnel can naturally fall to the lower guide tunnel, so that the collection and transportation of the dregs are facilitated. In terms of construction sequence, the invention firstly constructs the pilot tunnels at two sides, then constructs the core pilot tunnel in the middle, and the un-constructed core pilot tunnel is connected between the arch crown and the arch bottom, thereby supporting the whole tunnel, enhancing the stability of the whole tunnel, ensuring the effective and stable construction of the rest pilot tunnels, and reducing the risk to the minimum.
The invention has the beneficial effects that:
1. according to the method, certain reinforcement measures are taken at the primary combination position of the construction tunnel and the station tunnel, the construction tunnel directly expands and excavates the cross section of the station tunnel after entering the station tunnel, then the station tunnel is transversely excavated to the other end in the station tunnel, and then the station tunnel is excavated in sequence, so that the construction period is short, the construction efficiency is high, and the risk is low.
2. According to the invention, the plurality of small pilot tunnels are arranged in the station tunnel, and each small pilot tunnel is independently constructed in the axial direction of the station tunnel to complete the tunneling of the station tunnel; and meanwhile, the risk of station tunnel collapse is also reduced.
3. According to the tunnel vertical support, the vertical supports are arranged to be arc-shaped, the arc-shaped vertical supports are stressed perpendicularly to the inner wall of the tunnel, stress is more uniform, and stability is higher.
4. The invention excavates transversely on the tunnel in an inclined mode, so that the working height during station excavation can be reduced, the building height of a scaffold can be reduced, the labor intensity of workers can be reduced, and the building efficiency can be improved; on the other hand is convenient for collect and carry the dregs in the tunnel work progress, and the operation of the base line of slope on being convenient for the dregs roll off and haulage vehicle on the benchmark line, labour saving and time saving improves the efficiency of construction.
5. The pilot tunnel construction sequence of the invention is from top to bottom construction, the lower part of the non-constructed pilot tunnel supports the upper part of the pilot tunnel, thus improving the stability of the constructed pilot tunnel, reducing the collapse risk and ensuring the safety of constructors; meanwhile, the dregs in the upper guide tunnel can naturally fall to the lower guide tunnel, so that the collection and transportation of the dregs are facilitated.
6. The pilot tunnel construction sequence of the invention is that pilot tunnels on two sides are constructed firstly, then a core pilot tunnel in the middle is constructed, and the un-constructed core pilot tunnel is connected between the arch crown and the arch crown, thereby supporting the whole tunnel, enhancing the stability of the whole tunnel, ensuring the effective and stable construction of the rest pilot tunnels and reducing the risk to the minimum.
Drawings
Fig. 1 is a diagram of a pilot tunnel layout of the present invention.
Fig. 2 is a plan view of a construction tunnel and a station tunnel.
Fig. 3 is a schematic view of a construction tunnel entering a station tunnel.
Fig. 4 is a top view of fig. 3.
FIG. 5 is a schematic diagram of a station tunnel lateral expanding excavation
Fig. 6 is a top view of fig. 5.
Fig. 7 is a schematic diagram of excavation of an upper right pilot tunnel in a station tunnel.
Fig. 8 is a top view of fig. 7.
Fig. 9 is a schematic structural view of the door frame.
Labeled as:
1. constructing a tunnel; 2. a station tunnel; 3. transversely supporting; 4. vertical support; 5. the central line of the station tunnel; 6. a door frame; 7. an arch frame; 8. a first slip casting anchor rod; 9. a second slip casting anchor rod; 10. a ground locking anchor rod; 11. a baseline; i, guiding a hole at the upper right; II, guiding holes at the upper left; III, guiding a hole in the right middle; IV, guiding holes in the left middle; v, guiding holes at the right lower part; VI, guiding the hole at the left lower part; VII, a guide hole is formed in the core; VIII, guiding a hole in the core; IX, a core lower pilot tunnel.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
Example one
Referring to fig. 1 to 9, the variable cross-section supporting structure of the station tunnel comprises a construction channel 1 and the station tunnel 2, wherein the station tunnel 2 is perpendicular to and communicated with the end of the construction channel 1, primary supports (not shown in the figure) and secondary linings (not shown in the figure) are arranged in the construction channel 1 and the station tunnel 2, a plurality of transverse supports 3 and vertical supports 4 are arranged in the station tunnel 2, and the transverse supports 3 and the vertical supports 4 divide the station tunnel 2 into a plurality of guide holes. Because the station tunnel is deep in buried depth and large in size, a plurality of small pilot tunnels are arranged in the station tunnel, and each small pilot tunnel is independently constructed in the axial direction of the station tunnel to complete the tunneling of the station tunnel; and meanwhile, the risk of station tunnel collapse is also reduced.
Referring to fig. 1, the number of the transverse supports 3 is six, the number of the vertical supports 4 is two, and the transverse supports 3 and the vertical supports 4 divide the station tunnel 2 into nine pilot tunnels; the transverse supports 3 are respectively arranged at the middle upper part and the middle lower part of the station tunnel 2, and the vertical supports 4 are symmetrically arranged about the central line 5 of the station tunnel. Too many pilot tunnels are arranged, so that the construction cost of primary support and secondary lining is increased, and the construction efficiency is reduced; the pilot tunnel is arranged too few, the stability of surrounding rocks of the station tunnel is poor, and the risk of construction collapse is also improved; therefore, the invention preferably selects nine pilot tunnels in a plurality of modes, thereby not only ensuring the construction efficiency and the construction cost, but also reducing the construction risk to the minimum; and the transverse supports are arranged at the middle upper part and the middle lower part of the station tunnel, so that the area difference of each pilot tunnel is small, and the stability of the pilot tunnel is further ensured.
Referring to fig. 1, the vertical supports 4 of the present embodiment are arc-shaped, and the vertical supports 4 are bent in the direction of the center of the tunnel. Because the vault and the arch bottom in tunnel are the arc, if set up vertical braces for the structure of the direction on perpendicular to ground, can make the country rock side atress of tunnel inner wall, cause the tunnel atress inhomogeneous, vertical braces can't be with the perpendicular atress of tunnel inner wall, vertical braces's support poor stability. Therefore, the vertical supports are arranged in the arc shape, the arc-shaped vertical supports are stressed perpendicularly to the inner wall of the tunnel, stress is more uniform, and stability is higher.
Referring to fig. 1, one end of the construction tunnel 1 of the present embodiment, which is close to the station tunnel 2, is provided with a door frame 6 extending into the station tunnel 2. The invention adopts certain reinforcement measures at the primary combination position of the construction tunnel and the station tunnel, directly expands and excavates the construction tunnel and the station tunnel to the section form of the station tunnel after entering the station tunnel, then transversely excavates the construction tunnel to the other end in the station tunnel, and excavates the station tunnel in sequence.
Referring to fig. 1, the present embodiment is provided with an arc-shaped arch 7 below a door frame 6. Further improve the stability of construction tunnel and the first combination department of station tunnel.
Referring to fig. 1, in the present embodiment, a first grouting anchor rod 8 is provided on the inner wall of a station tunnel 2 to penetrate into a primary support and a secondary lining; the first grouting anchor rod 8 is of a hollow structure. The first grouting anchor rod plays a role in supporting and reinforcing the surrounding rock of the tunnel, and the interlayer friction resistance is improved. In addition, mortar can be injected into the concrete in the primary support and the secondary lining through the grouting anchor rod to fill the concrete gap, so that the effects of reinforcing the concrete and preventing water seepage are achieved.
Referring to fig. 1, the present embodiment is provided with second grouting bolts 9 at opposite sides of the vertical supports 4; the second grouting anchor rod 9 is of a hollow structure. All there is the concrete layer on vertical braces and the horizontal support, can pour into the mortar into to the concrete on the vertical braces through the slip casting stock, play the effect of reinforced concrete and prevention of seepage water.
Referring to fig. 7, this embodiment is provided with ground locking anchors in connection with the tunnel on the lateral supports. The stability of the lateral support is enhanced.
Example two
The construction method of the station tunnel comprises the variable cross-section supporting structure of the station tunnel in the first embodiment, and comprises the following steps:
s1, firstly digging a construction channel 1, and carrying out primary support and secondary lining in the construction channel;
s2, arranging a door frame 6 at one end of the construction channel connected with the station tunnel, and arranging an arch center 7 below the door frame 6; the door frame is a steel door frame, the steel door frame is formed by welding three densely-arranged I22 b-shaped steels, the door frame is longitudinally welded and connected into a whole by adopting phi 22 steel bars at an annular interval of 1m, and the sprayed concrete is tight.
S3, according to the trend of the construction channel 1, excavating a station tunnel 2 in the direction that the end part of the construction channel 1 is vertical to the construction channel; the method specifically comprises the following steps: excavating from one end of the station tunnel to the other end of the station tunnel in the transverse direction of the station tunnel; firstly digging the upper half part of the station tunnel along a base line 11 in the station tunnel, carrying out primary support, secondary lining and a first grouting anchor rod 8, then digging the lower half part of the station tunnel, and carrying out primary support and secondary lining;
the excavation section of the station tunnel is 30cm larger than the outline range of the station tunnel, the excavation depth is 1m each time, first grouting anchor rods are arranged next to the excavation section, steel door frames are erected and sprayed with C25 early strength concrete with the thickness of 30cm for sealing, the distance between every two frames is 0.5m, the door frames are welded into a whole at the circumferential distance of 1m by phi 22 steel bars, the door frames are different in size and are gradually increased;
after a station tunnel is dug to the head transversely, installing arch frames on the lower parts of steel door frames, wherein the arch frames are arc-shaped, the distance between every two frames is 0.5m, each door-shaped frame is welded and connected into a whole by using phi 22 steel bars at the circumferential distance of 1m, and C25 early strength concrete with the thickness of 30cm is sprayed to seal the door-shaped frame;
s4, erecting a vertical support 3 and a transverse support 4 in the station tunnel 2; the station tunnel is divided into nine pilot tunnels by the transverse supports 3 and the vertical supports 4, a second grouting anchor rod 9 is erected, primary support and secondary lining are carried out on each pilot tunnel, and each pilot tunnel is independently constructed in the axial direction of the station tunnel to carry out tunneling of the station tunnel; and after the construction of the station tunnel is finished, the transverse support and the vertical support are removed.
According to the method, certain reinforcement measures are taken at the primary combination position of the construction tunnel and the station tunnel, the construction tunnel directly expands and excavates the station tunnel to the section of the station tunnel after entering the station tunnel, then the construction tunnel transversely excavates the station tunnel to the other end, and then each pilot tunnel of the station tunnel is excavated separately in sequence. Compared with the traditional one-time tunneling mode of the station tunnel, the method can more conveniently carry out primary support and secondary lining on the station tunnel, reduce the construction period and improve the construction efficiency; and meanwhile, the risk of station tunnel collapse is also reduced. The method is safe, reliable, economical and feasible, and short in construction period.
Referring to fig. 5, in step S3, the baseline 11 is inclined toward the top of the tunnel, and the angle between the baseline 11 and the horizontal direction is 8 °. In the process of tunnel excavation, a scaffold is required to be erected in a tunnel, and the tunnel is excavated transversely in an inclined mode, so that the working height during station excavation can be reduced, the erecting height of the scaffold can be reduced, the labor intensity of workers can be reduced, and the erecting efficiency can be improved; on the other hand is convenient for collect and carry the dregs in the tunnel work progress, and the operation of the base line of slope on being convenient for the dregs roll off and haulage vehicle on the benchmark line, labour saving and time saving improves the efficiency of construction.
Referring to fig. 1, in step S4, the construction sequence of nine pilot holes is as follows: and constructing an upper right pilot tunnel I, an upper left pilot tunnel II, a middle right pilot tunnel III, a middle left pilot tunnel IV, a lower right pilot tunnel V, a lower left pilot tunnel VI, an upper core pilot tunnel VII, a middle core pilot tunnel VIII and a lower core pilot tunnel IX. From the construction sequence, the pilot tunnel is constructed from top to bottom, and the lower part of the pilot tunnel which is not constructed plays a role in supporting the pilot tunnel in the upper part construction, so that the stability of the constructed pilot tunnel is improved, the collapse risk is reduced, and the safety of constructors is ensured; meanwhile, the dregs in the upper guide tunnel can naturally fall to the lower guide tunnel, so that the collection and transportation of the dregs are facilitated. In terms of construction sequence, the invention firstly constructs the pilot tunnels at two sides, then constructs the core pilot tunnel in the middle, and the un-constructed core pilot tunnel is connected between the arch crown and the arch bottom, thereby supporting the whole tunnel, enhancing the stability of the whole tunnel, ensuring the effective and stable construction of the rest pilot tunnels, and reducing the risk to the minimum.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. Variable section supporting construction in station tunnel, including construction passageway (1) and station tunnel (2), its characterized in that, the tip of station tunnel (2) perpendicular and intercommunication construction passageway (1), all be provided with preliminary bracing and secondary lining in construction passageway (1) and station tunnel (2), arranged a plurality of horizontal support (3) and vertical braces (4) in station tunnel (2), horizontal support (3) and vertical braces (4) separate station tunnel (2) for a plurality of pilot tunnel.
2. A variable-section supporting structure of a station tunnel as claimed in claim 1, wherein the number of the lateral supports (3) is six, the number of the vertical supports (4) is two, and the lateral supports (3) and the vertical supports (4) divide the station tunnel (2) into nine pilot tunnels; the transverse supports (3) are respectively arranged at the middle upper part and the middle lower part of the station tunnel (2), and the vertical supports (4) are symmetrically arranged relative to the central line (5) of the station tunnel.
3. A support structure for a varying section of a station tunnel according to claim 1, characterized in that said vertical supports (4) are arc-shaped, the vertical supports (4) being bent in the direction of the center of the tunnel.
4. A station tunnel variable-section supporting structure as claimed in claim 1, wherein one end of the construction tunnel (1) near the station tunnel (2) is provided with a door frame (6) extending into the station tunnel (2).
5. A supporting construction for a station tunnel in a varying section as claimed in claim 4, characterized in that an arc-shaped arch (7) is provided under said door frame (6).
6. A variable-section supporting structure of a station tunnel as claimed in claim 1, wherein the inner wall of the station tunnel (2) is provided with a first grouting bolt (8) penetrating into the primary support and the secondary lining; the first grouting anchor rod (8) is of a hollow structure.
7. A variable-section supporting structure of a station tunnel as claimed in any one of claims 1 to 6, wherein second grouting anchor rods (9) are arranged on two opposite sides of the vertical supports (4); the second grouting anchor rod (9) is of a hollow structure.
8. A construction method of a station tunnel, including the variable-section supporting structure of a station tunnel as claimed in claim 7, characterized by comprising the steps of:
s1, digging a construction channel (1) first, and performing primary support and secondary lining in the construction channel;
s2, arranging a door frame (6) at one end of the construction channel connected with the station tunnel, and arranging an arch center (7) below the door frame (6);
s3, according to the trend of the construction channel (1), excavating a station tunnel (2) on the end part of the construction channel (1) in the direction vertical to the construction channel; the method specifically comprises the following steps: excavating from one end of the station tunnel to the other end of the station tunnel in the transverse direction of the station tunnel; firstly digging the upper half part of the station tunnel along a base line (11) in the station tunnel, performing primary support, secondary lining and a first grouting anchor rod (8), then digging the lower half part of the station tunnel, and performing primary support and secondary lining;
s4, erecting a vertical support (3) and a transverse support (4) in the station tunnel (2); the station tunnel is divided into nine pilot tunnels by the transverse supports (3) and the vertical supports (4), second grouting anchor rods (9) are erected, primary support and secondary lining are carried out on each pilot tunnel, and each pilot tunnel is independently constructed in the axial direction of the station tunnel to carry out tunneling of the station tunnel; and after the construction of the station tunnel is finished, the transverse support and the vertical support are removed.
9. A construction method of a station tunnel according to claim 8, characterized in that in the step S3, the base line (11) is inclined toward the top of the tunnel, and an angle between the base line (11) and the horizontal direction is 5 ° to 10 °.
10. A construction method of a station tunnel as claimed in claim 8, wherein in the step S4, the construction sequence of the nine pilot tunnels is as follows: constructing an upper right pilot tunnel (I), an upper left pilot tunnel (II), a middle right pilot tunnel (III), a middle left pilot tunnel (IV), a lower right pilot tunnel (V), a lower left pilot tunnel (VI), an upper core pilot tunnel (VII), a middle core pilot tunnel (VIII) and a lower core pilot tunnel (IX).
CN202010718762.0A 2020-07-23 2020-07-23 Variable-section supporting structure of station tunnel and construction method of station tunnel Pending CN112031807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010718762.0A CN112031807A (en) 2020-07-23 2020-07-23 Variable-section supporting structure of station tunnel and construction method of station tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010718762.0A CN112031807A (en) 2020-07-23 2020-07-23 Variable-section supporting structure of station tunnel and construction method of station tunnel

Publications (1)

Publication Number Publication Date
CN112031807A true CN112031807A (en) 2020-12-04

Family

ID=73582997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010718762.0A Pending CN112031807A (en) 2020-07-23 2020-07-23 Variable-section supporting structure of station tunnel and construction method of station tunnel

Country Status (1)

Country Link
CN (1) CN112031807A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105822310A (en) * 2016-05-23 2016-08-03 重庆大学 Rapid low-risk station tunnel digging method
CN107762535A (en) * 2017-10-30 2018-03-06 重庆城建控股(集团)有限责任公司 Cut-and-cover tunnel secretly does construction technology under complicated geological environment
CN207453979U (en) * 2017-09-26 2018-06-05 中铁隧道集团二处有限公司 A kind of extra-large cross-section subway station combed construction passage
CN108590662A (en) * 2018-05-09 2018-09-28 中国建筑第八工程局有限公司 Construction method of ventilation shaft of subway station tunnel with high and steep slope
CN110645024A (en) * 2019-09-02 2020-01-03 重庆市轨道交通设计研究院有限责任公司 Method for enlarging arch foot and primarily supporting arch cover
CN110905524A (en) * 2019-11-08 2020-03-24 中建隧道建设有限公司 Method for excavating and supporting subway station tunnel by adopting underground excavation construction channel
CN111271093A (en) * 2020-03-24 2020-06-12 中铁二院昆明勘察设计研究院有限责任公司 Underground excavation subway station auxiliary cross passage interface primary support system and construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105822310A (en) * 2016-05-23 2016-08-03 重庆大学 Rapid low-risk station tunnel digging method
CN207453979U (en) * 2017-09-26 2018-06-05 中铁隧道集团二处有限公司 A kind of extra-large cross-section subway station combed construction passage
CN107762535A (en) * 2017-10-30 2018-03-06 重庆城建控股(集团)有限责任公司 Cut-and-cover tunnel secretly does construction technology under complicated geological environment
CN108590662A (en) * 2018-05-09 2018-09-28 中国建筑第八工程局有限公司 Construction method of ventilation shaft of subway station tunnel with high and steep slope
CN110645024A (en) * 2019-09-02 2020-01-03 重庆市轨道交通设计研究院有限责任公司 Method for enlarging arch foot and primarily supporting arch cover
CN110905524A (en) * 2019-11-08 2020-03-24 中建隧道建设有限公司 Method for excavating and supporting subway station tunnel by adopting underground excavation construction channel
CN111271093A (en) * 2020-03-24 2020-06-12 中铁二院昆明勘察设计研究院有限责任公司 Underground excavation subway station auxiliary cross passage interface primary support system and construction method

Similar Documents

Publication Publication Date Title
CN101864963B (en) Large-section loess tunnel construction method
CN102758632B (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN103174434B (en) Construction method of asymmetric double-arch tunnel structure
CN109707399B (en) Tunnel exit supporting structure and construction method thereof
CN108487911A (en) The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition
CN201991017U (en) Subway large-span station body structure based on arch cover method construction forming
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN211006756U (en) Interface structure of open cut station and large-span duplex arch buried tunnel
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN104989425A (en) Underground excavation hole entering supporting structure and method
CN109707388B (en) Method for preventing ground collapse when shield tunneling machine starts to pass through existing shield tunnel
CN110318772A (en) Canal in Loess Area is greatly across the asymmetric bore tunnel supporting construction of small interval and construction method
CN105370289A (en) Ultra-long shallow-buried excavation construction method for existing pipeline in complex environment
CN109403985A (en) The gate-type of pole weak broken wall rock layer is caunched engineering method
CN205152983U (en) Stratum pre -reinforcing of underground space construction handles structure
CN109339800A (en) A kind of Rapid Construction of Tunnels method in the connected section of bridge tunnel
CN114412475A (en) Reverse tunnel exit construction method for shallow-buried broken surrounding rock
CN108951647A (en) Construction method for supporting is excavated in hole in the hole of open trench tunnel
CN210919066U (en) Fully mechanized caving face coal top down integrated tunneling device
CN218439399U (en) Auxiliary supporting device for tunnel inverted arch construction
CN207554062U (en) A kind of asymmetric supporting construction of Unevenly-pressured shallow tunnel
CN113294178B (en) Combined support system for extremely-broken surrounding rock tunnel and construction method thereof
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN113958322B (en) Tunnel excavation method under existing subway line
CN115977103A (en) Supporting structure for span of track section to be built on open-cut tunnel and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201204