CN111827465A - A kind of reinforced rockfill concrete structure and construction method thereof - Google Patents

A kind of reinforced rockfill concrete structure and construction method thereof Download PDF

Info

Publication number
CN111827465A
CN111827465A CN202010608113.5A CN202010608113A CN111827465A CN 111827465 A CN111827465 A CN 111827465A CN 202010608113 A CN202010608113 A CN 202010608113A CN 111827465 A CN111827465 A CN 111827465A
Authority
CN
China
Prior art keywords
concrete
rockfill
self
substitute
compacting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010608113.5A
Other languages
Chinese (zh)
Other versions
CN111827465B (en
Inventor
金峰
聂建国
周虎
黄杜若
梁婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
Original Assignee
Tsinghua University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University filed Critical Tsinghua University
Priority to CN202010608113.5A priority Critical patent/CN111827465B/en
Publication of CN111827465A publication Critical patent/CN111827465A/en
Application granted granted Critical
Publication of CN111827465B publication Critical patent/CN111827465B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/167Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with permanent forms made of particular materials, e.g. layered products
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种钢筋堆石混凝土结构及其施工方法,钢筋堆石混凝土结构包括堆石混凝土和位于堆石混凝土仓面底部、四周、顶部及内部含有按设计要求布设的钢筋。施工方法包括:按设计要求布设底部钢筋及竖向钢筋后,浇筑能够完全覆盖底部钢筋且超过钢筋的厚度不小于150mm~300mm的自密实混凝土;采用抛石型堆石混凝土工艺,将满足设定粒径要求的块石抛入含有粗骨料的自密实混凝土;继续按照抛石型堆石混凝土工艺或采用普通型堆石混凝土施工工艺,继续施工至结构顶面,完成浇筑过程。本发明将堆石混凝土与钢筋混凝土相结合,适用于底部、四周、顶部及内部有配筋要求的大体积混凝土结构,具有水泥用量少,水化温升低,易于连续施工等优点。

Figure 202010608113

The invention discloses a reinforced rockfill concrete structure and a construction method thereof. The reinforced rockfill concrete structure comprises rockfill concrete and steel bars arranged at the bottom, surrounding, top and interior of the rockfill concrete silo surface according to design requirements. The construction method includes: after laying the bottom steel bars and vertical steel bars according to the design requirements, pouring self-compacting concrete that can completely cover the bottom steel bars and the thickness of the excess steel bars is not less than 150mm to 300mm; The blocks with the required particle size are thrown into the self-compacting concrete containing coarse aggregate; continue to follow the riprap type rockfill concrete process or use the ordinary rockfill concrete construction process, continue to construct to the top surface of the structure, and complete the pouring process. The invention combines rockfill concrete and reinforced concrete, and is suitable for large-volume concrete structures requiring reinforcement at the bottom, surrounding, top and interior, and has the advantages of less cement consumption, low hydration temperature rise, easy continuous construction and the like.

Figure 202010608113

Description

一种钢筋堆石混凝土结构及其施工方法A kind of reinforced rockfill concrete structure and construction method thereof

技术领域technical field

本发明涉及一种混凝土结构及施工方法,特别是涉及具有外围配筋和少量内部配筋设计要求的大体积混凝土结构,及其配套的施工方法。The invention relates to a concrete structure and a construction method, in particular to a large-volume concrete structure with design requirements for peripheral reinforcement and a small amount of internal reinforcement, and a matching construction method.

背景技术Background technique

大体积混凝土是混凝土工程中非常重要的组成部分,在实际工程中往往对大体积混凝土有配筋要求以形成大体积钢筋混凝土结构,该结构普遍应用于桥梁、水闸、地铁、高层建筑等工程,而传统的大体积混凝土施工方法,水泥用量高,温控困难,造成大体积钢筋混凝土结构容易开裂,且成本较高。Mass concrete is a very important part of concrete engineering. In actual engineering, there are often reinforcement requirements for mass concrete to form a mass reinforced concrete structure. This structure is widely used in bridges, sluices, subways, high-rise buildings and other projects. However, the traditional mass concrete construction method has high cement consumption and difficult temperature control, which makes the mass reinforced concrete structure easy to crack and the cost is high.

堆石混凝土(金峰,安雪晖,堆石混凝土大坝施工方法,ZL03102674.5)使用大量大粒径块石或卵石,不仅节省水泥用量,降低成本,而且大幅度降低水化热,简化温控,已广泛应用于大坝工程。堆石混凝土施工工艺,可以分为普通堆石混凝土施工方法(金峰,安雪晖,小原孝之等.普通型堆石混凝土施工方法,ZL200710100315.3)和抛石型堆石混凝土施工方法(安雪晖,金峰,小原孝之等.抛石型堆石混凝土施工方法,ZL200710121791.3)。普通型堆石混凝土先将满足要求的堆石运输至仓面自然堆积,然后使用满足要求的自密实混凝土从堆石体表面浇注,仅依靠自密实混凝土自重填充堆石空隙,形成致密且具有较高强度的堆石混凝土。而抛石型堆石混凝土是先将抗离析性能优越且保塑性能良好的自密实混凝土浇注入仓,然后将块石或卵石使用机械或者人工的方式抛入已浇注的自密实混凝土中,最终形成完整密实的堆石混凝土。堆石混凝土简化了施工工艺和所需设备,施工速度得到大幅度提高;使用大量块石和卵石,每方堆石混凝土只需要40~50%的混凝土,有效降低30%以上的混凝土成本,有效解决了大体积混凝土的水化热问题。但是,堆石混凝土目前仅使用于大坝等大体积混凝土结构,当采用大体积钢筋混凝土,需要在仓面底部或内部配置钢筋时,堆石入仓会砸坏钢筋,因此,传统堆石混凝土技术不能直接应用于大体积钢筋混凝土结构。Rockfill concrete (Jin Feng, An Xuehui, Construction method of rockfill concrete dam, ZL03102674.5) uses a large number of large-diameter blocks or pebbles, which not only saves cement consumption and costs, but also greatly reduces hydration heat and simplifies temperature. It has been widely used in dam projects. Rockfill concrete construction technology can be divided into ordinary rockfill concrete construction method (Jin Feng, An Xuehui, Xiaoyuan Xiaozhi, etc. Ordinary rockfill concrete construction method, ZL200710100315.3) and riprap rockfill concrete construction method (An Xue Hui, Jin Feng, Xiaoyuan Xiaozhi, etc. Construction method of riprap type rockfill concrete, ZL200710121791.3). Ordinary rockfill concrete first transports the rockfill that meets the requirements to the warehouse surface for natural accumulation, and then uses the self-compacting concrete that meets the requirements to pour from the surface of the rockfill body. High strength rockfill concrete. The riprap type rockfill concrete is to pour the self-compacting concrete with excellent segregation resistance and good plasticity into the silo, and then throw the boulders or pebbles into the poured self-compacting concrete by mechanical or manual methods. Form a complete and dense rockfill concrete. Rockfill concrete simplifies the construction process and required equipment, and the construction speed is greatly improved; using a large number of blocks and pebbles, only 40-50% of the concrete is needed for each square of rockfill concrete, which effectively reduces the cost of concrete by more than 30% and effectively solves the problem. The heat of hydration problem of mass concrete. However, rockfill concrete is currently only used in large-volume concrete structures such as dams. When large-volume reinforced concrete is used, it is necessary to arrange steel bars at the bottom or inside of the silo surface. The technology cannot be directly applied to large-volume reinforced concrete structures.

发明内容SUMMARY OF THE INVENTION

本发明的目的是为了克服现有技术的不足之处,提出一种钢筋堆石混凝土结构及其施工方法,将堆石混凝土技术的优势应用于含有配筋要求,特别具有外围配筋和少量内部配筋设计要求的大体积混凝土工程中,拓宽堆石混凝土应用范围,解决桥梁、水闸、地铁、高层建筑等工程中的大体积钢筋混凝土温控困难,成本较高的难题。The purpose of the present invention is to overcome the deficiencies of the prior art, propose a reinforced rockfill concrete structure and a construction method thereof, and apply the advantages of the rockfill concrete technology to contain reinforcement requirements, especially with peripheral reinforcement and a small amount of internal reinforcement. In the mass concrete projects required by the reinforcement design, the application scope of rockfill concrete is widened to solve the difficult temperature control and high cost of mass reinforced concrete in bridges, sluices, subways, high-rise buildings and other projects.

为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:

本发明提出的一种钢筋堆石混凝土结构,其特征在于,包括钢筋或其替代物与堆石混凝土;所述钢筋或其替代物为按设计要求布设的钢筋或其替代物,布设于仓面底部、四周、顶部及内部;所述堆石混凝土包括堆石与自密实混凝土,其中,所述堆石采用块石或卵石,其饱和抗压强度应超过大体积钢筋混凝土抗压强度要求,所述堆石的最小粒径为50mm;当采用抛石型堆石混凝土时使用堆石的最大粒径不超过500mm;当采用普通型堆石混凝土时使用堆石的最大粒径不超过施工机械的运输能力,且小于结构尺寸的1/8~1/4或浇筑层厚度;所述自密实混凝土含有粗骨料,粗骨料的最大粒径为10mm~20mm,所述自密实混凝土性能满足大体积钢筋混凝土设计要求;在仓面底部和内部铺设钢筋或其替代物处通过浇筑够完全覆盖相应钢筋或其替代物且超过相应钢筋或其替代物的厚度不小于150mm~300mm的所述自密实混凝土形成保护层;在仓面顶部铺设钢筋或其替代物处浇筑能够完全覆盖该钢筋或其替代物且达到仓面顶部设计高度的所述自密实混凝土。A reinforced rockfill concrete structure proposed by the present invention is characterized in that it includes steel bars or their substitutes and rockfill concrete; the steel bars or their substitutes are steel bars or their substitutes arranged according to design requirements, and are arranged on the warehouse surface. Bottom, surrounding, top and interior; the rockfill concrete includes rockfill and self-compacting concrete, wherein, the rockfill is made of boulders or pebbles, and its saturated compressive strength should exceed the compressive strength requirements of large-volume reinforced concrete. The minimum particle size of the rockfill mentioned above is 50mm; when using riprap type rockfill concrete, the maximum particle size of the rockfill used shall not exceed 500mm; when using ordinary rockfill concrete, the maximum particle size of the rockfill used shall not exceed that of the construction machinery. The transportation capacity is less than 1/8~1/4 of the structure size or the thickness of the pouring layer; the self-compacting concrete contains coarse aggregate, and the maximum particle size of the coarse aggregate is 10mm~20mm, and the performance of the self-compacting concrete meets the requirements of large Design requirements for volumetric reinforced concrete; the self-compacting material with a thickness of not less than 150mm to 300mm in excess of the thickness of the corresponding steel bar or its substitute by pouring steel bars or their substitutes at the bottom and inside of the silo surface The concrete forms a protective layer; the self-compacting concrete that can completely cover the steel bar or its substitute and reach the design height of the top of the silo surface is poured at the place where the steel bar or its substitute is laid on the top of the silo surface.

本发明还提出上述钢筋堆石混凝土结构的施工方法,其特征在于,包含以下步骤:The present invention also proposes a construction method for the above-mentioned reinforced rockfill concrete structure, which is characterized by comprising the following steps:

1)为所需浇注堆石混凝土的仓面布设底部钢筋或其替代物和四周钢筋或其替代物,并设置模板或模板替代物;1) Arrange bottom steel bars or their substitutes and surrounding steel bars or their substitutes for the silo surface where the rockfill concrete needs to be poured, and set up formwork or formwork substitutes;

2)仓面的底部采用抛石型堆石混凝土施工方法施工,先浇筑能够完全覆盖底部钢筋或其替代物且超过该钢筋或其替代物的厚度不小于150mm~300mm的所述自密实混凝土,然后将粒径为50mm~500mm的堆石均匀抛入所述自密实混凝土中;2) The bottom of the warehouse surface shall be constructed by using the riprap type rockfill concrete construction method. First pour the self-compacting concrete that can completely cover the bottom steel bar or its substitute and whose thickness exceeds the steel bar or its substitute by not less than 150mm to 300mm. Then the rockfill with a particle size of 50mm to 500mm is evenly thrown into the self-compacting concrete;

3)继续向仓面内抛石并同时浇注自密实混凝土,连续进行抛石型堆石混凝土施工直至仓面浇筑完成;或者仅在底部采用抛石型堆石混凝土施工,而在完成抛石型堆石混凝土施工后,继续抛填粒径为50mm~500mm的堆石至设定高度,采用普通型堆石混凝土工艺,浇筑自密实混凝土将模板或其替代物内的堆石空隙填充密实,直至浇筑到仓面顶部的设计高度。3) Continue to rip rock into the silo surface and pour self-compacting concrete at the same time, and continue to carry out riprap type rockfill concrete construction until the silo surface is poured; After the rockfill concrete is constructed, continue to dump and fill the rockfill with a particle size of 50mm to 500mm to the set height, adopt the ordinary rockfill concrete process, and pour the self-compacting concrete to fill the rockfill voids in the formwork or its substitute until it reaches the set height. Design height for pouring to the top of the silo face.

进一步地,当按照设计要求需要在仓面内部铺设钢筋或其替代物时,步骤3)由以下步骤替换:先将堆石混凝土施工至内部的钢筋或其替代物高度之下,然后布设该钢筋或其替代物;再浇筑所述自密实混凝土完全覆盖该钢筋或其替代物且超过该钢筋或其替代物的厚度不小于150mm~300mm的自密实混凝土,随后采用抛石型堆石混凝土的施工工艺,将堆石均匀抛入已浇筑的自密实混凝土中;继续向仓面内抛石并同时浇注自密实混凝土,连续进行抛石型堆石混凝土施工直至仓面浇筑完成。Further, when it is necessary to lay steel bars or their substitutes inside the warehouse surface according to the design requirements, step 3) is replaced by the following steps: first, the rockfill concrete is constructed to below the height of the internal steel bars or their substitutes, and then the steel bars are laid out. or its substitute; then pour the self-compacting concrete that completely covers the steel bar or its substitute and the thickness of the steel bar or its substitute is not less than 150mm to 300mm, and then adopts the construction of riprap type rockfill concrete The process is to throw the rockfill into the poured self-compacting concrete evenly; continue to rip rock into the silo surface and pour the self-compacting concrete at the same time, and continue to carry out the riprap type rockfill concrete construction until the silo surface is poured.

进一步地,当按照设计要求需要在仓面顶部铺设钢筋或其替代物时,步骤3)还包括以下步骤:当堆石混凝土施工至仓面顶部的钢筋或其替代物的设计高度时,布设顶部的钢筋或其替代物;浇筑能够完全覆盖顶部的钢筋或其替代物且达到仓面顶部设计高度的所述自密实混凝土。Further, when the steel bar or its substitute needs to be laid on the top of the warehouse surface according to the design requirements, step 3) also includes the following steps: when the rockfill concrete is constructed to the design height of the steel bar or its substitute on the top of the warehouse surface, the top is laid. The rebar or its substitute; pour the self-compacting concrete that can completely cover the top rebar or its substitute and reach the design height of the top of the silo surface.

本发明是在对已有的堆石混凝土结构及施工方法的基础上,将堆石混凝土与钢筋混凝土结合,提出的一种钢筋堆石混凝土结构及其施工方法。其与现有的大体积混凝土结构与施工方法相比,本发明具有以下优点:①与现有堆石混凝土结构相比,本发明结构所浇注仓面的底部、四周、顶部及内部均可布设钢筋,以达到设计要求;②与普通大体积混凝土相比,本发明在仓面中部浇注为堆石混凝土,经实际现场试验验证,施工中堆石率可达50%,大幅度减少水泥用量,降低混凝土水化热,从而取消埋设冷却水管等温控措施;③本发明采用抛石型堆石混凝土施工时先浇注的自密实混凝土可以保护钢筋,避免堆石砸坏钢筋;④本发明采用抛石型堆石混凝土及普通型堆石混凝土施工方法搭配进行施工,可以进一步降低对施工设备的要求,加快施工进程,降低施工成本。The invention proposes a reinforced rockfill concrete structure and a construction method by combining the rockfill concrete and the reinforced concrete on the basis of the existing rockfill concrete structure and construction method. Compared with the existing large-volume concrete structure and construction method, the present invention has the following advantages: 1. Compared with the existing rockfill concrete structure, the bottom, surrounding, top and interior of the poured silo surface of the structure of the present invention can be arranged 2. Compared with ordinary mass concrete, the present invention pours rockfill concrete in the middle of the silo surface, and the actual field test verification shows that the rockfill rate can reach 50% during construction, and the cement consumption is greatly reduced. Reduce the heat of concrete hydration, thereby canceling the temperature control measures such as burying cooling water pipes; 3. The present invention adopts the self-compacting concrete poured first during construction of the riprap type rockfill concrete, which can protect the steel bars and prevent the rockfill from smashing the steel bars; ④ The present invention adopts the throwing The combination of rock-type rockfill concrete and ordinary rockfill concrete construction methods can further reduce the requirements for construction equipment, speed up the construction process, and reduce construction costs.

附图说明Description of drawings

图1为本发明实施例的一种钢筋堆石混凝土结构的示意图。FIG. 1 is a schematic diagram of a reinforced rockfill concrete structure according to an embodiment of the present invention.

图2、3、4是设有底部水平钢筋、四周竖向钢筋和顶部水平钢筋的钢筋堆石混凝土结构的施工过程示意图;Figures 2, 3, and 4 are schematic diagrams of the construction process of a reinforced rockfill concrete structure with bottom horizontal steel bars, surrounding vertical steel bars and top horizontal steel bars;

图5、6是设置钢筋堆石混凝土结构中内部水平钢筋的施工过程示意图。Figures 5 and 6 are schematic diagrams of the construction process of setting internal horizontal steel bars in a reinforced rockfill concrete structure.

图7、8是内部和顶部有配筋要求的钢筋堆石混凝结构施工过程示意图;Figures 7 and 8 are schematic diagrams of the construction process of the reinforced rockfill concrete structure with reinforcement requirements in the interior and the top;

图9是内部配筋的钢筋堆石混凝土浇筑完成的结构示意图。FIG. 9 is a structural schematic diagram of the completion of pouring of reinforced rockfill concrete with internal reinforcement.

附图标记:Reference number:

1:底部水平钢筋;2:四周竖向钢筋;3:模板或模板替代物;4:自密实混凝土;5:堆石;6:顶部水平钢筋;7:内部水平钢筋;8:保护层。1: Bottom horizontal rebar; 2: All around vertical rebar; 3: Formwork or formwork substitute; 4: Self-compacting concrete; 5: Rockfill; 6: Top horizontal rebar; 7: Internal horizontal rebar; 8: Protective layer.

具体实施方式Detailed ways

为使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步的详细说明。应当理解,此处所描述的具体实施方式仅仅用以解释本发明,并不限定本发明的保护范围。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, and do not limit the protection scope of the present invention.

为了更好地理解本发明,以下详细阐述本发明提出的一种钢筋堆石混凝土结构及其施工方法的应用实例。In order to better understand the present invention, an application example of a reinforced rockfill concrete structure and a construction method thereof proposed by the present invention will be described in detail below.

本发明是在现有的堆石混凝土技术基础上引入钢筋配置,通过抛石型堆石混凝和普通型堆石混凝土施工方法的结合进行施工,最终形成完整密实的能满足结构配筋要求的钢筋堆石混凝结构。下面结合附图进一步说明本发明的具体实施方式:In the present invention, steel bar configuration is introduced on the basis of the existing rockfill concrete technology, and construction is carried out through the combination of riprap type rockfill concrete and ordinary rockfill concrete construction methods, and finally a complete and dense structure that can meet the requirements of structural reinforcement is formed. Reinforced rockfill concrete structure. The specific embodiments of the present invention are further described below in conjunction with the accompanying drawings:

本发明的一种钢筋堆石混凝土结构,参见图1,包括位于模板或其替代物3内的钢筋(1、2、6、7)或其替代物(如钢板、钢筋桁架、预应力钢绞线等)与堆石混凝土。所述钢筋或其替代物按设计要求布设,可布设于仓面底部、四周、顶部及内部(如图1中所示底部水平钢筋1、四周竖向钢筋2、顶部水平钢筋6和内部水平钢筋7)。所述堆石混凝土包括:堆石5与自密实混凝土4,其中,堆石5采用块石或卵石,其饱和抗压强度应超过大体积钢筋混凝土抗压强度要求,最小粒径50mm;当采用抛石型堆石混凝土时使用堆石的最大粒径不超过500mm;当采用普通型堆石混凝土时使用堆石的最大粒径不超过施工机械的运输能力,且小于钢筋堆石混凝土结构尺寸的1/8~1/4或浇筑层厚。所述自密实混凝土4含有一定量的粗骨料,粗骨料的最大粒径为10mm~20mm,其性能(主要包括坍落度、扩展度、V型漏斗通过时间、抗压强度等)应满足大体积钢筋混凝土设计要求。在仓面底部和内部铺设钢筋或其替代物处通过浇筑够完全覆盖相应钢筋或其替代物处且超过相应钢筋或其替代物的厚度不小于150mm~300mm的自密实混凝土4(该自密实混凝土要求抗离析性能优越且保塑性能良好)以形成保护层8,之后再进行余下钢筋和堆石混凝土的构筑。A reinforced rockfill concrete structure of the present invention, referring to FIG. 1, includes steel bars (1, 2, 6, 7) or their substitutes (such as steel plates, steel trusses, prestressed steel strands) located in the formwork or its substitutes 3 line, etc.) and rockfill concrete. The reinforcing bars or their substitutes are laid out according to the design requirements, and can be laid on the bottom, surrounding, top and interior of the warehouse surface (as shown in Figure 1, bottom horizontal reinforcing bars 1, surrounding vertical reinforcing bars 2, top horizontal reinforcing bars 6 and internal horizontal reinforcing bars are shown in Figure 1). 7). The rockfill concrete includes: rockfill 5 and self-compacting concrete 4, wherein the rockfill 5 is made of boulders or pebbles, and its saturated compressive strength should exceed the compressive strength requirements of large-volume reinforced concrete, with a minimum particle size of 50 mm; The maximum particle size of rockfill used in riprap type rockfill concrete shall not exceed 500mm; when ordinary rockfill concrete is used, the maximum particle size of rockfill shall not exceed the transportation capacity of construction machinery, and be smaller than the size of the reinforced rockfill concrete structure. 1/8~1/4 or pouring layer thickness. The self-compacting concrete 4 contains a certain amount of coarse aggregate, and the maximum particle size of the coarse aggregate is 10 mm to 20 mm. Meet the design requirements of large-volume reinforced concrete. The self-compacting concrete 4 (the self-compacting concrete) that can completely cover the corresponding steel bar or its substitute and the thickness exceeding the corresponding steel bar or its substitute is not less than 150mm to 300mm by pouring the steel bar or its substitute at the bottom and inside of the silo. It is required to have excellent anti-segregation performance and good plastic retention performance) to form the protective layer 8, and then proceed with the construction of the remaining steel bars and rockfill concrete.

本发明还提出一种上述钢筋堆石混凝土结构的施工方法,可以按照设计要求对大体积混凝土结构进行配筋,并按照以下步骤进行施工:The present invention also proposes a construction method for the above-mentioned reinforced rockfill concrete structure, which can reinforced the mass concrete structure according to the design requirements, and carry out construction according to the following steps:

1)参见图2,在大体积钢筋混凝土中按照设计要求,为所需浇注堆石混凝土的仓面布设底部水平钢筋1和四周竖向钢筋2,并设置模板或模板替代物3;1) Referring to Figure 2, according to the design requirements in the large-volume reinforced concrete, the bottom horizontal steel bar 1 and the surrounding vertical steel bars 2 are arranged for the silo surface where the rockfill concrete needs to be poured, and the formwork or formwork substitute 3 is set;

2)仓面的底部采用抛石型堆石混凝土施工方法施工,先浇筑能够完全覆盖底部水平钢筋1且超过底部水平钢筋的厚度不小于150mm~300mm的自密实混凝土4形成底部钢筋的保护层8,参见图2,然后将粒径为50mm~500mm的堆石5均匀抛入已浇筑的自密实混凝土4中,参见图3;该自密实混凝土的性能要求应满足:坍落度250mm~290mm、扩展度500mm~700mm和V型漏斗通过时间5s~30s;2) The bottom of the silo surface is constructed by the riprap type rockfill concrete construction method. First pour the self-compacting concrete 4 that can completely cover the bottom horizontal steel bar 1 and exceed the bottom horizontal steel bar with a thickness of not less than 150mm to 300mm to form a protective layer 8 for the bottom steel bar , see Figure 2, and then throw the rockfill 5 with a particle size of 50mm to 500mm into the self-compacting concrete 4 that has been poured evenly, see Figure 3; the performance requirements of the self-compacting concrete should meet: slump 250mm ~ 290mm, Expansion 500mm~700mm and V-shaped funnel passing time 5s~30s;

3)继续向仓面内抛石并同时浇注自密实混凝土4,连续进行抛石型堆石混凝土施工(根据抛石速度决定一次浇筑自密实混凝土的厚度,需在所浇筑的自密实混凝土性能损失超过下限标准前完成抛石工作)直至仓面浇筑完成,参见图4;或者仅在仓面底部采用抛石型堆石混凝土施工,而在完成抛石型堆石混凝土施工后,继续抛填150mm~1200mm的堆石至设定高度(该高度与施工能力相关,抛石型堆石混凝土可以连续施工几十米只要施工能力满足要求;当仓面较大时,浇筑的速度要保证混凝土不能初凝),然后采用普通堆石混凝土施工工艺,浇筑自密实混凝土4将模板或模板替代物3内的堆石空隙填充密实,直至浇筑到仓面顶部的设计高度。普通型堆石混凝土施工所用的自密实混凝土性能要求应满足:坍落度250mm~290mm、扩展度600mm~800mm、V型漏斗通过时间5s~30s。3) Continue to rip rock into the silo surface and pour self-compacting concrete 4 at the same time, and continuously carry out the construction of riprap type rockfill concrete (the thickness of the self-compacting concrete poured at one time is determined according to the riprap speed, and the performance loss of the self-compacting concrete to be poured is required. Complete the riprap work before exceeding the lower limit standard) until the silo surface pouring is completed, see Figure 4; or only use riprap rockfill concrete at the bottom of the silo surface, and continue to fill 150mm after the riprap rockfill concrete construction is completed. ~1200mm of rockfill to the set height (this height is related to the construction capacity, the riprap type rockfill concrete can be continuously constructed for several tens of meters as long as the construction capacity meets the requirements; when the warehouse surface is large, the pouring speed must ensure that the concrete cannot be initially constructed. Then, using the ordinary rockfill concrete construction technology, pour the self-compacting concrete 4 to fill and compact the rockfill voids in the formwork or formwork substitute 3 until it is poured to the design height of the top of the silo surface. The performance requirements of self-compacting concrete used in ordinary rockfill concrete construction should meet: slump 250mm-290mm, expansion 600mm-800mm, V-shaped funnel passing time 5s-30s.

进一步地,参见图5、图6,当按照设计要求需要铺设内部水平钢筋7时,先将堆石混凝土施工至内部水平钢筋7设计高度之下,然后布设内部水平钢筋7,再浇筑能够完全覆盖内部水平钢筋7且超过该钢筋的厚度不小于150mm~300mm的自密实混凝土,起到垫层作用,保护钢筋不被抛石损坏,随后采用抛石型堆石混凝土的施工工艺,将堆石均匀抛入已浇筑的自密实混凝土中,再按照步骤3)的操作浇筑达到仓面顶部的设计高度。Further, referring to Fig. 5 and Fig. 6, when the inner horizontal steel bar 7 needs to be laid according to the design requirements, first the rockfill concrete is constructed to below the design height of the inner horizontal steel bar 7, and then the inner horizontal steel bar 7 is laid out, and then the pouring can completely cover. Self-compacting concrete with internal horizontal steel bar 7 and the thickness exceeding the steel bar is not less than 150mm~300mm, which plays the role of cushion and protects the steel bar from being damaged by riprap. Throw it into the poured self-compacting concrete, and then pour it to the design height of the top of the silo surface according to the operation of step 3).

进一步地,参见图7~图9,当按照设计要求需要铺设顶部水平钢筋6时,先将堆石混凝土施工至顶部水平钢筋6的设计高度之下,然后布设顶部水平钢筋6;再浇筑能够完全覆盖顶部水平钢筋6且达到仓面顶部设计高度的自密实混凝土4。Further, referring to Figures 7 to 9, when the top horizontal steel bar 6 needs to be laid according to the design requirements, the rockfill concrete is first constructed to below the design height of the top horizontal steel bar 6, and then the top horizontal steel bar 6 is laid; Self-compacting concrete 4 covering the top horizontal steel bar 6 and reaching the design height of the top of the silo face.

进一步地,当仓面较大或其他原因需要到达仓面内部某高度(如内部水平钢筋高度以下)以后,浇筑停歇时间超过自密实混凝土初凝时间,且浇筑停歇的自密实混凝土顶面应低于堆石,以保证有部分堆石露出自密实混凝土顶部,确保上下两层混凝土的粘结强度。Further, when the silo surface is large or needs to reach a certain height inside the silo surface (such as below the height of the internal horizontal steel bars), the pouring stop time exceeds the initial setting time of the self-compacting concrete, and the top surface of the self-compacting concrete where the pouring stops should be low. To ensure that part of the rockfill is exposed to the top of the self-compacting concrete and to ensure the bonding strength of the upper and lower layers of concrete.

进一步地,浇筑停歇的自密实混凝土顶面应进行养护,并在混凝土强度到达2.5MPa以后,方进行上层自密实混凝土的施工;可对浇筑停歇的自密实混凝土顶面进行凿毛或冲毛,以满足钢筋堆石混凝土结构的抗渗要求或强度要求。Further, the top surface of the self-compacting concrete that has been stopped for pouring should be maintained, and after the concrete strength reaches 2.5MPa, the construction of the upper layer of self-compacting concrete can be carried out; In order to meet the impermeability requirements or strength requirements of reinforced rockfill concrete structures.

最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的精神和范围。Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand: it can still be Modifications are made to the technical solutions described in the foregoing embodiments, or some technical features thereof are equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions depart from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims (6)

1.一种钢筋堆石混凝土结构,其特征在于,包括钢筋或其替代物与堆石混凝土;所述钢筋或其替代物为按设计要求布设的钢筋或其替代物,布设于仓面底部、四周、顶部及内部;所述堆石混凝土包括堆石与自密实混凝土,其中,所述堆石采用块石或卵石,其饱和抗压强度应超过大体积钢筋混凝土抗压强度要求,所述堆石的最小粒径为50mm;当采用抛石型堆石混凝土时使用堆石的最大粒径不超过500mm;当采用普通型堆石混凝土时使用堆石的最大粒径不超过施工机械的运输能力,且小于结构尺寸的1/8~1/4或浇筑层厚度;所述自密实混凝土含有粗骨料,粗骨料的最大粒径为10mm~20mm,所述自密实混凝土性能满足大体积钢筋混凝土设计要求;在仓面底部和内部铺设钢筋或其替代物处通过浇筑够完全覆盖相应钢筋或其替代物且超过相应钢筋或其替代物的厚度不小于150mm~300mm的所述自密实混凝土形成保护层;在仓面顶部铺设钢筋或其替代物处浇筑能够完全覆盖该钢筋或其替代物且达到仓面顶部设计高度的所述自密实混凝土。1. a reinforced rockfill concrete structure, is characterized in that, comprises reinforcing bar or its substitute and rockfill concrete; Described reinforcing bar or its substitute is the reinforcing bar or its substitute that is laid out according to design requirements, and is arranged at the bottom of warehouse surface, Surroundings, tops and interiors; the rockfill concrete includes rockfill and self-compacting concrete, wherein the rockfill is made of boulders or pebbles, and its saturated compressive strength should exceed the compressive strength requirements of large-volume reinforced concrete. The minimum particle size of the rock is 50mm; when using riprap type rockfill concrete, the maximum particle size of the rockfill used shall not exceed 500mm; when using ordinary rockfill concrete, the maximum particle size of the rockfill used shall not exceed the transportation capacity of the construction machinery , and less than 1/8-1/4 of the structure size or the thickness of the pouring layer; the self-compacting concrete contains coarse aggregate, and the maximum particle size of the coarse aggregate is 10mm-20mm, and the performance of the self-compacting concrete meets the requirements of large-volume steel bars Concrete design requirements; the self-compacting concrete is formed by pouring the self-compacting concrete that can completely cover the corresponding steel bar or its substitute and the thickness exceeding the corresponding steel bar or its substitute is not less than 150mm to 300mm at the bottom and inside of the warehouse surface where steel bars or their substitutes are laid. Protective layer; pour the self-compacting concrete that can completely cover the steel bar or its substitute and reach the design height of the top of the silo surface at the place where the steel bar or its substitute is laid on the top of the silo surface. 2.一种根据权利要求1所述钢筋堆石混凝土结构的施工方法,其特征在于,包含以下步骤:2. a construction method of reinforced rockfill concrete structure according to claim 1, is characterized in that, comprises the following steps: 1)为所需浇筑堆石混凝土的仓面布设底部钢筋或其替代物和四周钢筋或其替代物,并设置模板或模板替代物;1) Arrange bottom steel bars or their substitutes and surrounding steel bars or their substitutes for the silo surface where the rockfill concrete needs to be poured, and set up formwork or formwork substitutes; 2)仓面的底部采用抛石型堆石混凝土施工方法施工,先浇筑能够完全覆盖底部钢筋或其替代物且超过该钢筋或其替代物的厚度不小于150mm~300mm的所述自密实混凝土,然后将粒径为50mm~500mm的堆石均匀抛入所述自密实混凝土中;2) The bottom of the warehouse surface shall be constructed by using the riprap type rockfill concrete construction method. First pour the self-compacting concrete that can completely cover the bottom steel bar or its substitute and whose thickness exceeds the steel bar or its substitute by not less than 150mm to 300mm. Then the rockfill with a particle size of 50mm to 500mm is evenly thrown into the self-compacting concrete; 3)继续向仓面内抛石并同时浇注自密实混凝土,连续进行抛石型堆石混凝土施工直至仓面浇筑完成;或者仅在底部采用抛石型堆石混凝土施工,而在完成抛石型堆石混凝土施工后,继续抛填粒径为50mm~500mm的堆石至设定高度,采用普通型堆石混凝土工艺,浇筑自密实混凝土将模板或其替代物内的堆石空隙填充密实,直至浇筑到仓面顶部的设计高度。3) Continue to rip rock into the silo surface and pour self-compacting concrete at the same time, and continue to carry out riprap type rockfill concrete construction until the silo surface is poured; After the rockfill concrete is constructed, continue to dump and fill the rockfill with a particle size of 50mm to 500mm to the set height, adopt the ordinary rockfill concrete process, and pour the self-compacting concrete to fill the rockfill voids in the formwork or its substitute until it reaches the set height. Design height for pouring to the top of the silo face. 3.根据权利要求2所述钢筋堆石混凝土结构的施工方法,其特征在于,当按照设计要求需要在仓面内部铺设钢筋或其替代物时,步骤3)由以下步骤替换:先将堆石混凝土施工至内部的钢筋或其替代物高度之下,然后布设该钢筋或其替代物;再浇筑所述自密实混凝土完全覆盖该钢筋或其替代物且超过该钢筋或其替代物的厚度不小于150mm~300mm的自密实混凝土,随后采用抛石型堆石混凝土的施工工艺,将堆石均匀抛入已浇筑的自密实混凝土中;继续向仓面内抛石并同时浇注自密实混凝土,连续进行抛石型堆石混凝土施工直至仓面浇筑完成。3. according to the construction method of the described reinforced rockfill concrete structure of claim 2, it is characterized in that, when needing to lay reinforcement or its substitute in the interior of the warehouse surface according to the design requirement, step 3) is replaced by the following steps: Concrete is constructed to below the height of the internal steel bar or its substitute, and then the steel bar or its substitute is laid out; then the self-compacting concrete is poured to completely cover the steel bar or its substitute and the thickness beyond the steel bar or its substitute is not less than 150mm~300mm of self-compacting concrete, and then adopt the construction technology of rockfill type rockfill concrete to evenly throw the rockfill into the poured self-compacting concrete; continue to rip rock into the silo surface and pour the self-compacting concrete at the same time. The riprap type rockfill concrete is constructed until the silo surface is poured. 4.根据权利要求2或3所述钢筋堆石混凝土结构的施工方法,其特征在于,当按照设计要求需要在仓面顶部铺设钢筋或其替代物时,步骤3)还包括以下步骤:当堆石混凝土施工至仓面顶部的钢筋或其替代物的设计高度时,布设顶部的钢筋或其替代物;浇筑能够完全覆盖顶部的钢筋或其替代物且达到仓面顶部设计高度的所述自密实混凝土。4. according to the construction method of the described reinforced rockfill concrete structure of claim 2 or 3, it is characterized in that, when needing to lay reinforcement or its substitute on the top of the warehouse surface according to the design requirement, step 3) also comprises the following steps: When the stone concrete is constructed to the design height of the rebar or its substitute at the top of the silo surface, the rebar on the top or its substitute shall be laid; concrete. 5.根据权利要求4所述钢筋堆石混凝土结构的施工方法,其特征在于,当仓面较大或其他原因到达仓内设定高度以后,浇筑停歇时间超过所述自密实混凝土的初凝时间,且浇筑停歇的所述自密实混凝土顶面应低于堆石,以保证有部分堆石露出自密实混凝土顶部,确保上下两层混凝土的粘结强度。5. according to the construction method of the described reinforced rockfill concrete structure of claim 4, it is characterized in that, when the warehouse surface is larger or other reasons reach the set height in the warehouse, the pouring stop time exceeds the initial setting time of the self-compacting concrete , and the top surface of the self-compacting concrete when the pouring stops should be lower than the rockfill, so as to ensure that some of the rockfill is exposed on the top of the self-compacting concrete and ensure the bonding strength of the upper and lower layers of concrete. 6.根据权利要求5所述钢筋堆石混凝土结构的施工方法,其特征在于,浇筑停歇的自密实混凝土顶面应进行养护,并在混凝土强度到达2.5MPa以后,方进行上层混凝土施工;对浇筑停歇的自密实混凝土顶面进行凿毛或冲毛,以满足钢筋堆石混凝土结构的抗渗要求或强度要求。6. the construction method of the reinforced rockfill concrete structure according to claim 5, is characterized in that, the self-compacting concrete top surface of the pouring stop should be maintained, and after the concrete strength reaches 2.5MPa, the upper concrete construction is carried out; The top surface of the suspended self-compacting concrete is chiseled or punched to meet the impermeability or strength requirements of the reinforced rockfill concrete structure.
CN202010608113.5A 2020-06-30 2020-06-30 Reinforced rockfill concrete structure and construction method thereof Active CN111827465B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010608113.5A CN111827465B (en) 2020-06-30 2020-06-30 Reinforced rockfill concrete structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010608113.5A CN111827465B (en) 2020-06-30 2020-06-30 Reinforced rockfill concrete structure and construction method thereof

Publications (2)

Publication Number Publication Date
CN111827465A true CN111827465A (en) 2020-10-27
CN111827465B CN111827465B (en) 2021-12-31

Family

ID=72899632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010608113.5A Active CN111827465B (en) 2020-06-30 2020-06-30 Reinforced rockfill concrete structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN111827465B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113211649A (en) * 2021-05-20 2021-08-06 李友彬 Method for cutting, processing and forming rock-fill concrete large test piece
CN113279479A (en) * 2021-05-13 2021-08-20 中建八局第三建设有限公司 High-strength concrete structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170343A (en) * 1994-12-16 1996-07-02 Fujita Corp Finishing construction method of underwater rubble mound
CN101074560A (en) * 2007-06-08 2007-11-21 清华大学 Method for constructing normal piled concrete
CN101144279A (en) * 2007-09-14 2008-03-19 清华大学 Construction method of riprap type rockfill concrete
CN201367593Y (en) * 2009-03-18 2009-12-23 中国水电顾问集团中南勘测设计研究院 Cofferdam with flexible structure
CN203284973U (en) * 2012-08-16 2013-11-13 万旋枝 Construction technological structure of reinforced concrete cast-in-place hollow floor

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170343A (en) * 1994-12-16 1996-07-02 Fujita Corp Finishing construction method of underwater rubble mound
CN101074560A (en) * 2007-06-08 2007-11-21 清华大学 Method for constructing normal piled concrete
CN101144279A (en) * 2007-09-14 2008-03-19 清华大学 Construction method of riprap type rockfill concrete
CN201367593Y (en) * 2009-03-18 2009-12-23 中国水电顾问集团中南勘测设计研究院 Cofferdam with flexible structure
CN203284973U (en) * 2012-08-16 2013-11-13 万旋枝 Construction technological structure of reinforced concrete cast-in-place hollow floor

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113279479A (en) * 2021-05-13 2021-08-20 中建八局第三建设有限公司 High-strength concrete structure and construction method thereof
CN113279479B (en) * 2021-05-13 2022-05-24 中建八局第三建设有限公司 High-strength concrete structure and construction method thereof
CN113211649A (en) * 2021-05-20 2021-08-06 李友彬 Method for cutting, processing and forming rock-fill concrete large test piece

Also Published As

Publication number Publication date
CN111827465B (en) 2021-12-31

Similar Documents

Publication Publication Date Title
CN100451245C (en) Method for constructing normal piled concrete
CN113718777A (en) Mass concrete crack prevention construction method
CN102425307A (en) Pouring method for avoiding formation of large-volume concrete cracks
CN109235891A (en) A kind of Large Span Prestressed Beam concrete pitched roof jump storehouse method construction method
CN104452591B (en) A kind of construction of cast-in-situ box-beam technique that is applied to science of bridge building
CN104652371B (en) The glue of crossing set up based on old dam coagulates rock-fill dams and construction method thereof
CN107269295A (en) A kind of PVA ECC set lining structures and construction method
CN111827465A (en) A kind of reinforced rockfill concrete structure and construction method thereof
CN113668928B (en) Method for controlling construction cracks of ultra-large-volume concrete water pool
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN103306439A (en) Pouring technology for implanting high anti-leakage and anti-crack protective layer into roof structure layer
CN108914734A (en) High tensile pervious concrete sandwich structure and preparation method
CN104652280B (en) Overlength, after water fish ridge wall one-time continuous moulding irrigation method and overlength fish ridge wall thereof
CN108193689A (en) The Anti-cracking Technology of volume of concrete foundation
CN113774957B (en) Open-cut cast-in-place tunnel main structure concrete anti-cracking construction method
CN214659212U (en) Large anti-cracking thin-wall water pool
CN205348103U (en) Gabion and river course revetment structure
CN108035453A (en) A kind of sliding and shock isolation device and its construction method for having collar tie beam masonry structure
CN107151988A (en) Trough girder bridge deck structure and its reinforcement means that a kind of ultra-high performance concrete is reinforced
CN113969794A (en) A pressureless water diversion tunnel vertical form shotcrete lining and construction method
CN207919794U (en) A kind of sliding and shock isolation device having collar tie beam masonry structure
CN112554628A (en) Large anti-cracking thin-wall water pool and construction method thereof
CN108468281B (en) Combined type cover plate culvert, combined type bridge structure and construction method thereof
CN106564122B (en) A kind of pre-tensioning system U beam method for controlling crack
CN104929314B (en) Bracket column concrete construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant