CN111680383A - A prediction method for the change of the additional confining pressure of the shield tunnel below caused by the excavation of the foundation pit - Google Patents

A prediction method for the change of the additional confining pressure of the shield tunnel below caused by the excavation of the foundation pit Download PDF

Info

Publication number
CN111680383A
CN111680383A CN202010140265.7A CN202010140265A CN111680383A CN 111680383 A CN111680383 A CN 111680383A CN 202010140265 A CN202010140265 A CN 202010140265A CN 111680383 A CN111680383 A CN 111680383A
Authority
CN
China
Prior art keywords
foundation pit
tunnel
additional
shield tunnel
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010140265.7A
Other languages
Chinese (zh)
Other versions
CN111680383B (en
Inventor
魏纲
张鑫海
林心蓓
丁玉琴
齐永洁
刘亚宇
周鑫鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou City University
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN202010140265.7A priority Critical patent/CN111680383B/en
Publication of CN111680383A publication Critical patent/CN111680383A/en
Application granted granted Critical
Publication of CN111680383B publication Critical patent/CN111680383B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种基坑开挖引起的下方盾构隧道附加围压变化的预测方法,本方法根据基坑开挖的卸载模型,计算得到隧道横断面上的附加荷载分布;提出能考虑纵向变形环间作用力的盾构隧道横向附加围压变化模型,并得到附加围压的计算方法。本发明的方法可对基坑开挖引起的下方盾构隧道衬砌围压变化进行预测,适用于不同开挖尺寸基坑上跨盾构运营隧道的工况;为相应工况下隧道结构的受力、足尺寸盾构管片加载试验和地铁隧道运营安全提供理论支持;预警围压及受力变化过大的可能,防止引发安全事故,对工程具有预防、指导作用,可节约施工成本。

Figure 202010140265

The invention discloses a method for predicting the change of the additional confining pressure of the lower shield tunnel caused by the excavation of the foundation pit. The method calculates the distribution of the additional load on the cross section of the tunnel according to the unloading model of the excavation of the foundation pit; Variation model of lateral additional confining pressure of shield tunnel based on the force between deformation rings, and the calculation method of additional confining pressure is obtained. The method of the invention can predict the change of the lining confining pressure of the shield tunnel below caused by the excavation of the foundation pit, and is suitable for the operating conditions of the shield tunnel over the foundation pit with different excavation sizes; Force, full-size shield segment loading test and subway tunnel operation safety provide theoretical support; early warning of the possibility of excessive confining pressure and force changes, preventing safety accidents, preventing and guiding the project, and saving construction costs.

Figure 202010140265

Description

一种基坑开挖引起的下方盾构隧道附加围压变化预测方法A prediction method for the change of the additional confining pressure of the shield tunnel below caused by the excavation of the foundation pit

技术领域technical field

本发明属于地下工程技术领域,具体地涉及一种基坑开挖引起的下方盾构隧道附加 围压变化预测方法。The invention belongs to the technical field of underground engineering, and in particular relates to a method for predicting the change of the additional confining pressure of a shield tunnel below caused by excavation of a foundation pit.

背景技术Background technique

随着城市轨道交通发展和地下空间开发利用,基坑工程上跨运营盾构隧道的情况会 越来越多。当基坑开挖时,开挖卸载作用会由开挖面直接通过土体传递至下方盾构隧道。 隧道随着土层发生隆起,同时在隧道结构上产生较大附加荷载。由于基坑开挖卸载量较 大,对结构产生的卸载效应会破坏管片结构的受力平衡,从而产生变形甚至损伤,对运营中盾构隧道安全产生较大影响。为保证轨道交通线路的安全运营,地铁隧道有较为严 格的变形控制要求,因此研究基坑开挖对下方盾构隧道的受力变形影响具有重要的应用 价值。因此基坑开挖引起下方盾构隧道围压变化的理论计算方法还需更深入的研究,为 地铁隧道运营安全和相关的足尺寸结构加载试验提供理论支持。With the development of urban rail transit and the development and utilization of underground space, there will be more and more cases of shield tunnels operating across foundation pit projects. When the foundation pit is excavated, the excavation unloading effect will be directly transmitted from the excavation surface to the shield tunnel below through the soil. The tunnel is uplifted with the soil layer, and at the same time, a large additional load is generated on the tunnel structure. Due to the large amount of unloading in the excavation of the foundation pit, the unloading effect on the structure will destroy the force balance of the segment structure, resulting in deformation or even damage, which has a great impact on the safety of shield tunnels in operation. In order to ensure the safe operation of rail transit lines, subway tunnels have relatively strict deformation control requirements. Therefore, it is of great application value to study the influence of foundation pit excavation on the deformation of shield tunnels below. Therefore, the theoretical calculation method of the confining pressure change of the shield tunnel below caused by the excavation of the foundation pit needs to be further studied, so as to provide theoretical support for the operation safety of the subway tunnel and related full-size structural loading tests.

此类工程问题已经得到了国内外的关注,目前主要的研究方法主要有:实测数据统 计分析、数值模拟、理论计算和离心模型试验。目前针对基坑开挖引起盾构隧道围压变化的研究结果主要由有限元模拟和离心模型得到,目前常用的有限元模拟方法得到的结果仅能作为定性判断的依据,很难得到定量的准确结果。精细化的数值模拟对计算模型 和运算设备具有较高的要求,需要较高的运算成本。离心模型试验需要大型超重力离心 机、高精度传感器和模型实验箱等实验设备,试验研究成本较高。采用基坑引起盾构隧 道围压变化的理论计算方法研究较少,尤其是基坑开挖引起的下方盾构隧道附加围压理 论计算方法成果还未见报道。This kind of engineering problem has received attention at home and abroad. At present, the main research methods are: statistical analysis of measured data, numerical simulation, theoretical calculation and centrifugal model test. At present, the research results of the confining pressure changes of shield tunnels caused by foundation pit excavation are mainly obtained by finite element simulation and centrifugal model. result. Refined numerical simulation has higher requirements for computing models and computing equipment, and requires higher computing costs. Centrifugal model tests require experimental equipment such as large-scale hypergravity centrifuges, high-precision sensors, and model experimental boxes, and the cost of experimental research is relatively high. The theoretical calculation method of shield tunnel confining pressure change caused by foundation pit is seldom studied, especially the theoretical calculation method of additional confining pressure of shield tunnel below caused by foundation pit excavation has not been reported.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于针对现有技术的不足,提供一种基坑开挖引起的下方盾构隧道附 加围压变化预测方法。该方法得到的隧道围压叠加上正常工况荷载组合,能够有效评估基坑开挖对下方盾构隧道的影响。The purpose of the present invention is to provide a method for predicting the change of the additional confining pressure of the shield tunnel below caused by the excavation of the foundation pit, aiming at the deficiencies of the prior art. The tunnel confining pressure obtained by this method is superimposed on the normal working condition load combination, which can effectively evaluate the influence of foundation pit excavation on the shield tunnel below.

本发明的目的是通过以下技术方案来实现的:一种基坑开挖引起的下方盾构隧道附 加围压变化预测方法,包括如下步骤:The purpose of this invention is to realize through the following technical scheme: a kind of bottom shield tunnel additional confining pressure change prediction method caused by foundation pit excavation, comprises the steps:

(1)在基坑的中心o处建立坐标系,x轴垂直于所述隧道的轴线,y轴平行于所述 隧道的轴线,z轴以竖直向下为正方向。(1) A coordinate system is established at the center o of the foundation pit, the x-axis is perpendicular to the axis of the tunnel, the y-axis is parallel to the axis of the tunnel, and the z-axis takes the vertical downward direction as the positive direction.

(2)根据步骤1建立的坐标系,计算上方基坑开挖引起的基坑底部开挖面卸载,并得到基坑底部开挖面卸载引起的下方盾构隧道横断面上的竖向向附加应力和水平向附 加应力分布,具体包括如下子步骤:(2) According to the coordinate system established in step 1, calculate the unloading of the excavation surface at the bottom of the foundation pit caused by the excavation of the upper foundation pit, and obtain the vertical additional on the cross section of the shield tunnel below caused by the unloading of the excavation surface at the bottom of the foundation pit. Stress and horizontal additional stress distribution, including the following sub-steps:

(2.1)基坑底部开挖面的卸载为基坑底部竖直向上的均布荷载,计算所述基坑底部 卸载p:(2.1) The unloading of the excavation surface at the bottom of the foundation pit is the uniformly distributed load vertically upward at the bottom of the foundation pit. Calculate the unloading p at the bottom of the foundation pit:

p=(1-α0)γd (1)p=(1-α 0 )γd (1)

其中:γ为土的重度,取基坑底以上开挖土层的加权平均值;d为基坑开挖深度;α0为残余应力系数。Among them: γ is the soil weight, which is the weighted average of the excavated soil layers above the foundation pit bottom; d is the excavation depth of the foundation pit; α 0 is the residual stress coefficient.

(2.2)根据Mindlin应力解,以所述基坑底开挖面作为积分区域,计算得到基坑底部开挖卸载下所述下方盾构隧道横断面上的竖向附加应力σaz(θ,l)和水平向附加应力 σax(θ,l)分别为:(2.2) According to the Mindlin stress solution, taking the excavation surface at the bottom of the foundation pit as the integral area, calculate the vertical additional stress σ az (θ, l ) and the additional horizontal stress σ ax (θ,l) are:

Figure BDA0002398854070000021
Figure BDA0002398854070000021

Figure BDA0002398854070000022
Figure BDA0002398854070000022

其中:θ为下方盾构隧道横断面上计算点的位置角度,以上顶点为0°,顺时针方向角度增加;B为基坑沿x轴方向的开挖尺寸;L为基坑沿y轴方向的开挖尺寸;d为基 坑开挖深度;h为隧道埋深;D为下方盾构隧道外径;a为基坑中心与隧道轴线的水平 距离,l为隧道轴线上任意一点在所述坐标系中对应的y坐标值;x1为第一积分变量,y1为第二积分变量,σzz为Mindlin竖向应力解,σxz为Mindlin水平应力解。Among them: θ is the position angle of the calculated point on the cross section of the shield tunnel below, the upper vertex is 0°, and the angle increases clockwise; B is the excavation size of the foundation pit along the x-axis direction; L is the foundation pit along the y-axis direction d is the excavation depth of the foundation pit; h is the buried depth of the tunnel; D is the outer diameter of the shield tunnel below; a is the horizontal distance between the center of the foundation pit and the tunnel axis, and l is any point on the tunnel axis in the The corresponding y coordinate value in the coordinate system; x 1 is the first integral variable, y 1 is the second integral variable, σ zz is the Mindlin vertical stress solution, and σ xz is the Mindlin horizontal stress solution.

(3)根据隧道纵向变形的现场监测数据,结合隧道竖向位移,得到管片竖向环间作用合力分布,具体包括以下子步骤:(3) According to the on-site monitoring data of the longitudinal deformation of the tunnel, combined with the vertical displacement of the tunnel, the distribution of the resultant force acting between the vertical rings of the segment is obtained, which specifically includes the following sub-steps:

(3.1)测量隧道沿纵向总的竖向位移w(l),测量管片环间转角引起的位移量,计算l处的管片环与前一节管片环之间的竖向环间剪切力QL(l)和后一节管片环之间的竖向环间剪切力QR(l):(3.1) Measure the total vertical displacement w(l) of the tunnel along the longitudinal direction, measure the displacement caused by the rotation angle between the segment rings, and calculate the vertical inter-ring shear between the segment ring at l and the previous segment ring Shear force Q L (l) and vertical inter-ring shear force Q R (l) between the succeeding segment rings:

QL(l)=(1-j)[w(l-Dt)-w(l)]×ksl (4)Q L (l)=(1-j)[w(lD t )-w(l)]×k sl (4)

QR(l)=(1-j)[w(l)-w(l-Dt)]×ksl (5)Q R (l)=(1-j)[w(l)-w(lD t )]×k sl (5)

其中,j为相邻管片环间转角引起的位移量与总的竖向位移之比,Dt为管片环的宽度,ksl为隧道的环间剪切刚度,QL(l)以作用方向向上为正,QR(l)以作用方向向下为正。Among them, j is the ratio of the displacement caused by the rotation angle between adjacent segment rings to the total vertical displacement, D t is the width of the segment rings, k sl is the inter-ring shear stiffness of the tunnel, and Q L (l) is given by The direction of action is upward as positive, and Q R (l) is positive when the direction of action is downward.

(3.2)再根据QL(l)和QR(l),得到l处的管片环所受管片竖向环间作用合力Fsz(l):(3.2) According to Q L (l) and Q R (l), the resultant force F sz (l) acting on the vertical ring of the segment on the segment ring at position l is obtained:

Fsz(l)=QR(l)-QL(l) (6)F sz (l) = Q R (l) - Q L (l) (6)

(4)根据步骤(2.2)得到的下方盾构隧道横断面上的竖向附加应力σaz(θ,l)和水平向附加应力σax(θ,l),计算下方盾构隧道衬砌上不同部分各个方向上的附加荷载分布:(4) According to the vertical additional stress σ az (θ,l) and the horizontal additional stress σ ax (θ,l) on the cross section of the shield tunnel below obtained in step (2.2), calculate the different linings of the shield tunnel below. Additional load distribution in all directions of the section:

Figure BDA0002398854070000031
Figure BDA0002398854070000031

Figure BDA0002398854070000032
Figure BDA0002398854070000032

其中,paz(θ,l)为下方盾构隧道上半部分衬砌的竖向附加荷载,p′ax(θ,l)为下方盾构 隧道左侧衬砌的水平向附加荷载,p″ax(θ,l)为下方盾构隧道右侧衬砌的水平向附加荷载。Among them, p az (θ,l) is the vertical additional load of the lining of the upper half of the shield tunnel below, p′ ax (θ,l) is the horizontal additional load of the left lining of the shield tunnel below, p″ ax ( θ,l) is the horizontal additional load of the lining on the right side of the shield tunnel below.

再根据下方盾构隧道衬砌上不同部分各个方向上的附加荷载分布,建立下方盾构隧 道衬砌附加围压变化模型:Then, according to the distribution of additional loads in all directions on different parts of the shield tunnel lining below, a variation model of the additional confining pressure of the shield tunnel lining below is established:

Figure BDA0002398854070000033
Figure BDA0002398854070000033

Figure BDA0002398854070000034
Figure BDA0002398854070000034

其中,Fsx为水平向的环间作用合力,Fsz为竖直向的环间作用合力,ΔqR为拱底竖向反力的卸载量。Among them, F sx is the resultant force between the rings in the horizontal direction, F sz is the resultant force between the rings in the vertical direction, and Δq R is the unloading amount of the vertical reaction force at the bottom of the arch.

(5)根据评估需求选取下方盾构隧道待分析的计算断面,将步骤(4)得到的计算断面位置处隧道衬砌上附加荷载和步骤(3)得到的计算断面位置处管片竖向环间作用 合力导入到步骤(4)建立的下方盾构隧道衬砌附加围压变化模型中,得到计算断面处 水平环间作用合力Fsx以及拱底竖向反力的卸载量ΔqR(5) Select the calculated cross section of the shield tunnel below to be analyzed according to the evaluation requirements, add the additional load on the tunnel lining at the position of the calculated cross section obtained in step (4) and the vertical ring of the segment at the position of the calculated cross section obtained in step (3). The resultant force is introduced into the additional confining pressure variation model of the lower shield tunnel lining established in step (4), and the resultant force F sx acting between the horizontal rings at the calculated section and the unloading amount Δq R of the vertical reaction force at the bottom of the arch are obtained.

Figure RE-GDA0002607251010000035
Figure RE-GDA0002607251010000035

Figure BDA0002398854070000036
Figure BDA0002398854070000036

(6)根据下方盾构隧道衬砌上不同部分各个方向上的附加荷载的分布及拱底竖向反力的卸载量ΔqR,得到变形稳定后的下方盾构隧道衬砌附加围压par(θ,l):(6) According to the distribution of additional loads in all directions on different parts of the shield tunnel lining below and the unloading amount Δq R of the vertical reaction force at the bottom of the arch, the additional confining pressure par (θ) of the shield tunnel lining below after the deformation is stabilized is obtained. ,l):

Figure BDA0002398854070000037
Figure BDA0002398854070000037

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

(1)本发明可适用于不同基坑开挖尺寸和不同位置关系的基坑跨越运营盾构隧道工况;(1) The present invention can be applied to the operating conditions of shield tunnels spanning the operation of foundation pits with different excavation sizes of foundation pits and different positional relationships;

(2)本发明在基坑施工开挖前预测下方盾构隧道的围压变化情况过程中采用的都是相应工程所必需的工程地质水文信息和设计参数,无需增加额外的勘察设计成本投入。(2) The present invention adopts the engineering geological and hydrological information and design parameters necessary for the corresponding project in the process of predicting the change of the confining pressure of the shield tunnel below before the excavation of the foundation pit construction, and does not need to increase the investment of additional survey and design costs.

(3)本发明可对基坑开挖引起的下方盾构隧道的围压变化进行预测,为相应工况下隧道结构的受力、足尺寸盾构管片加载试验和地铁隧道运营安全提供理论支持;预警 围压及受力变化过大的可能,防止引发安全事故,对工程具有预防、指导作用,可节约 施工成本。(3) The invention can predict the confining pressure change of the shield tunnel below caused by the excavation of the foundation pit, and provide the theory for the stress of the tunnel structure, the loading test of the full-size shield segment and the operation safety of the subway tunnel under the corresponding working conditions Support; early warning of the possibility of excessive changes in confining pressure and force, preventing safety accidents, preventing and guiding the project, and saving construction costs.

附图说明Description of drawings

图1是基坑开挖对下方盾构隧道影响的示意图;Figure 1 is a schematic diagram of the impact of foundation pit excavation on the shield tunnel below;

图2是基坑与盾构隧道位置关系图;Figure 2 is a diagram showing the positional relationship between the foundation pit and the shield tunnel;

图3是基坑开挖附加荷载作用下隧道围压重分布示意图,其中,(a)是第一阶段示意图,(b)是第二阶段示意图,(c)是第三阶段示意图;Figure 3 is a schematic diagram of the redistribution of the confining pressure of the tunnel under the additional load of the excavation of the foundation pit, wherein (a) is a schematic diagram of the first stage, (b) is a schematic diagram of the second stage, and (c) is a schematic diagram of the third stage;

图4是初始荷载组合与附加荷载组合示意图,其中,(a)是隧道初始工况下的荷载组合示意图,(b)是隧道变形稳定后的隧道衬砌附加围压示意图;Figure 4 is a schematic diagram of the initial load combination and the additional load combination, in which (a) is a schematic diagram of the load combination under the initial working condition of the tunnel, and (b) is a schematic diagram of the additional confining pressure of the tunnel lining after the tunnel is deformed and stabilized;

图5是基坑开挖前后的围压对比图;Figure 5 is a comparison diagram of the confining pressure before and after excavation of the foundation pit;

图6是上方基坑开挖引起的盾构隧道附加围压对比图;Figure 6 is a comparison diagram of the additional confining pressure of the shield tunnel caused by the excavation of the upper foundation pit;

图7是基坑开挖引起下方隧道水平向附加收敛变形的实测值与计算值对比图。Figure 7 is a comparison diagram of the measured and calculated values of the additional horizontal convergence deformation of the tunnel below caused by the excavation of the foundation pit.

具体实施方式Detailed ways

下面通过实施例和附图对本发明作进一步的说明。The present invention will be further described below through embodiments and accompanying drawings.

图1为基坑开挖对下方盾构隧道影响的示意图,如图1所示,基坑工程上跨下方盾构隧道不仅会使下方盾构隧道轴线产生纵向的隆起变形,影响范围内的隧道衬砌截面也会产生整体位移和椭圆化变形。图2为本发明适用工况的基坑与盾构隧道位置关系图, 如2图所示,上方基坑跨越下方盾构隧道,d为基坑开挖深度,h为隧道埋深,D为下 方盾构隧道外径,a为基坑中心与隧道轴线的水平距离。Figure 1 is a schematic diagram of the influence of foundation pit excavation on the shield tunnel below. As shown in Figure 1, the shield tunnel below the foundation pit project will not only cause longitudinal uplift and deformation of the axis of the shield tunnel below, but also affect the tunnel within the scope of influence. The lining section also produces global displacement and elliptical deformation. Fig. 2 is the positional relationship diagram of the foundation pit and the shield tunnel in the applicable working conditions of the present invention. As shown in Fig. 2, the upper foundation pit spans the lower shield tunnel, d is the excavation depth of the foundation pit, h is the buried depth of the tunnel, and D is the The outer diameter of the shield tunnel below, a is the horizontal distance between the center of the foundation pit and the tunnel axis.

本发明的一种基坑开挖引起的下方盾构隧道附加围压变化预测方法,包括如下步骤:A method for predicting the change of the additional confining pressure of the lower shield tunnel caused by the excavation of the foundation pit of the present invention comprises the following steps:

(1)根据设计资料,如图1~2所示,在基坑的中心o处建立坐标系,x轴垂直于 所述隧道的轴线,y轴平行于所述隧道的轴线,z轴以竖直向下为正方向。(1) According to the design data, as shown in Figures 1-2, a coordinate system is established at the center o of the foundation pit, the x-axis is perpendicular to the axis of the tunnel, the y-axis is parallel to the axis of the tunnel, and the z-axis is vertical Straight down is the positive direction.

(2)根据步骤1建立的坐标系,计算上方基坑开挖引起的基坑底部开挖面卸载, 并得到基坑底部开挖面卸载引起的下方盾构隧道横断面上的竖向向附加应力和水平向 附加应力分布,具体包括如下子步骤:(2) According to the coordinate system established in step 1, calculate the unloading of the excavation surface at the bottom of the foundation pit caused by the excavation of the foundation pit above, and obtain the vertical additional on the cross section of the shield tunnel below caused by the unloading of the excavation surface at the bottom of the foundation pit. Stress and horizontal additional stress distribution, including the following sub-steps:

(2.1)基坑底部开挖面的卸载为基坑底部竖直向上的均布荷载,计算所述基坑底部 卸载p:(2.1) The unloading of the excavation surface at the bottom of the foundation pit is the uniformly distributed load vertically upward at the bottom of the foundation pit. Calculate the unloading p at the bottom of the foundation pit:

p=(1-α0)γd (1)p=(1-α 0 )γd (1)

其中:γ为土的重度,取基坑底以上开挖土层的加权平均值;d为基坑开挖深度;α0为残余应力系数,该系数可以用来考虑基坑底部应力不完全释放的情况。Among them: γ is the soil weight, which is the weighted average value of the excavated soil layer above the foundation pit bottom; d is the foundation pit excavation depth; α 0 is the residual stress coefficient, which can be used to consider the incomplete stress release at the foundation pit bottom Case.

(2.2)根据Mindlin应力解,以所述基坑底开挖面作为积分区域,计算得到基坑底部开挖卸载下所述下方盾构隧道横断面上的竖向附加应力σaz(θ,l)和水平向附加应力 σax(θ,l)分别为:(2.2) According to the Mindlin stress solution, taking the excavation surface at the bottom of the foundation pit as the integral area, calculate the vertical additional stress σ az (θ, l ) and the additional horizontal stress σ ax (θ,l) are:

Figure BDA0002398854070000053
Figure BDA0002398854070000053

Figure BDA0002398854070000051
Figure BDA0002398854070000051

其中:θ为下方盾构隧道横断面上计算点的位置角度,以上顶点为0°,顺时针方向角度增加;B为基坑沿x轴方向的开挖尺寸;L为基坑沿y轴方向的开挖尺寸;如图2 所示,d为基坑开挖深度,h为隧道埋深,D为下方盾构隧道外径,a为基坑中心与隧道 轴线的水平距离;l为隧道轴线上任意一点在所述坐标系中对应的y坐标值;x1为第一 积分变量,y1为第二积分变量,σzz为Mindlin竖向应力解,σxz为Mindlin水平应力解。Among them: θ is the position angle of the calculated point on the cross section of the shield tunnel below, the upper vertex is 0°, and the angle increases clockwise; B is the excavation size of the foundation pit along the x-axis direction; L is the foundation pit along the y-axis direction As shown in Figure 2, d is the excavation depth of the foundation pit, h is the buried depth of the tunnel, D is the outer diameter of the shield tunnel below, a is the horizontal distance between the center of the foundation pit and the tunnel axis; l is the tunnel axis The y-coordinate value corresponding to any point above in the coordinate system; x 1 is the first integral variable, y 1 is the second integral variable, σ zz is the Mindlin vertical stress solution, and σ xz is the Mindlin horizontal stress solution.

(3)根据隧道纵向变形的现场监测数据,结合隧道竖向位移,得到管片竖向环间作用合力分布,具体包括以下子步骤:(3) According to the on-site monitoring data of the longitudinal deformation of the tunnel, combined with the vertical displacement of the tunnel, the distribution of the resultant force acting between the vertical rings of the segment is obtained, which specifically includes the following sub-steps:

(3.1)测量隧道沿纵向总的竖向位移w(l),测量管片环间转角引起的位移量,计算l处的管片环与前一节管片环之间的竖向环间剪切力QL(l)和后一节管片环之间的竖向环间剪切力QR(l):(3.1) Measure the total vertical displacement w(l) of the tunnel along the longitudinal direction, measure the displacement caused by the rotation angle between the segment rings, and calculate the vertical inter-ring shear between the segment ring at l and the previous segment ring Shear force Q L (l) and vertical inter-ring shear force Q R (l) between the succeeding segment rings:

QL(l)=(1-j)[w(l-Dt)-w(l)]×ksl (4)Q L (l)=(1-j)[w(lD t )-w(l)]×k sl (4)

QR(l)=(1-j)[w(l)-w(l-Dt)]×ksl (5)Q R (l)=(1-j)[w(l)-w(lD t )]×k sl (5)

其中,j为相邻管片环间转角引起的位移量与总的竖向位移之比,Dt为管片环的宽度,ksl为隧道的环间剪切刚度,QL(l)以作用方向向上为正,QR(l)以作用方向向下为正。Among them, j is the ratio of the displacement caused by the rotation angle between adjacent segment rings to the total vertical displacement, D t is the width of the segment rings, k sl is the inter-ring shear stiffness of the tunnel, and Q L (l) is given by The direction of action is upward as positive, and Q R (l) is positive when the direction of action is downward.

(3.2)再根据QL(l)和QR(l),得到l处的管片环所受管片竖向环间作用合力Fsz(l):(3.2) According to Q L (l) and Q R (l), the resultant force F sz (l) acting on the vertical ring of the segment on the segment ring at position l is obtained:

Fsz(l)=QR(l)-QL(l) (6)F sz (l) = Q R (l) - Q L (l) (6)

(4)如图3为基坑开挖附加荷载作用下隧道围压重分布示意图,该隧道围压重分成3个阶段,第一阶段如图3(a),基坑开挖会引起下方隧道上半部分衬砌的竖向附加 荷载paz和左右两侧衬砌的水平向附加荷载p′ax和p″ax,根据步骤(2.2)得到的下方盾构 隧道横断面上的竖向附加应力σaz(θ,l)和水平向附加应力σax(θ,l),计算下方盾构隧道衬 砌上不同部分各个方向上的附加荷载分布:(4) Figure 3 is a schematic diagram of the tunnel confining pressure redistribution under the additional load of foundation pit excavation. The tunnel confining pressure redistribution is divided into three stages. The first stage is shown in Figure 3(a). The foundation pit excavation will cause the tunnel below. The vertical additional load p az of the upper half of the lining and the horizontal additional loads p′ ax and p″ ax of the lining on the left and right sides, the vertical additional stress σ az on the cross section of the shield tunnel below is obtained according to step (2.2). (θ,l) and the horizontal additional stress σ ax (θ,l), calculate the additional load distribution in all directions on different parts of the shield tunnel lining below:

Figure BDA0002398854070000052
Figure BDA0002398854070000052

Figure BDA0002398854070000061
Figure BDA0002398854070000061

其中,paz(θ,l)为下方盾构隧道上半部分衬砌的竖向附加荷载,p′ax(θ,l)为下方盾构 隧道左侧衬砌的水平向附加荷载,p″ax(θ,l)为下方盾构隧道右侧衬砌的水平向附加荷载。Among them, p az (θ,l) is the vertical additional load of the lining of the upper half of the shield tunnel below, p′ ax (θ,l) is the horizontal additional load of the left lining of the shield tunnel below, p″ ax ( θ,l) is the horizontal additional load of the lining on the right side of the shield tunnel below.

第二阶段如图3(b),附加荷载使隧道围压平衡破坏,隧道横断面整体发生位移,纵向轴线产生变形。由于隧道纵向的不均匀变形,相邻管片环之间出现相对位移。由纵 向螺栓连接的相邻管片环相互约束,并产生了环间作用力。In the second stage, as shown in Figure 3(b), the additional load destroys the confining pressure balance of the tunnel, the overall cross-section of the tunnel is displaced, and the longitudinal axis is deformed. Relative displacement occurs between adjacent segment rings due to uneven deformation in the longitudinal direction of the tunnel. Adjacent segment rings connected by longitudinal bolts restrain each other and generate inter-ring forces.

第三阶段如图3(c),隧道上部的卸载最终会通过结构传递至底部,隧道底部的拱底竖向反力将部分卸载,实际结构设计中常将拱底反力视作矩形荷载,竖直向上作用在 衬砌上,根据下方盾构隧道衬砌上不同部分各个方向上的附加荷载分布,建立下方盾构 隧道衬砌附加围压变化模型:In the third stage, as shown in Figure 3(c), the unloading of the upper part of the tunnel will eventually be transmitted to the bottom through the structure, and the vertical reaction force of the arch bottom at the bottom of the tunnel will be partially unloaded. Acting on the lining in the straight direction, according to the additional load distribution in all directions of different parts of the shield tunnel lining below, establish the additional confining pressure variation model of the shield tunnel lining below:

Figure BDA0002398854070000062
Figure BDA0002398854070000062

Figure BDA0002398854070000063
Figure BDA0002398854070000063

其中,Fsx为水平向的环间作用合力,Fsz为竖直向的环间作用合力,ΔqR为拱底竖向反力的卸载量。Among them, F sx is the resultant force between the rings in the horizontal direction, F sz is the resultant force between the rings in the vertical direction, and Δq R is the unloading amount of the vertical reaction force at the bottom of the arch.

(5)基坑下方隧道的水平位移及其引起的环间水平作用力主要是由于隧道整环衬砌围压水平方向上不对称卸载引起的,并考虑纵横向受力相互影响的情况下,研究下方 隧道围压变化的关键就是在隧道横向受力的基础上结合纵向环间作用力,因此根据评估 需求选取下方盾构隧道待分析的计算断面,将步骤(4)得到的计算断面位置处隧道衬 砌上附加荷载和步骤(3)得到的计算断面位置处管片竖向环间作用合力导入到步骤(4) 建立的下方盾构隧道衬砌附加围压变化模型中,得到计算断面处水平环间作用合力Fsx以及拱底竖向反力的卸载量ΔqR(5) The horizontal displacement of the tunnel under the foundation pit and the horizontal force between the rings are mainly caused by the asymmetric unloading of the confining pressure of the entire ring of the tunnel in the horizontal direction, and considering the mutual influence of the longitudinal and lateral forces, the research The key to the change of the confining pressure of the tunnel below is to combine the longitudinal inter-ring force on the basis of the lateral force of the tunnel. Therefore, according to the evaluation requirements, select the calculated cross-section of the shield tunnel below to be analyzed, and use the calculated cross-section obtained in step (4) at the position of the tunnel. The additional load on the lining and the resultant force acting between the vertical rings of the segment at the calculated cross-section position obtained in step (3) are imported into the additional confining pressure variation model of the shield tunnel lining below established in step (4) to obtain the horizontal ring at the calculated cross-section. The resultant force F sx and the unloading amount Δq R of the vertical reaction force of the arch bottom.

Figure RE-GDA0002607251010000064
Figure RE-GDA0002607251010000064

Figure BDA0002398854070000065
Figure BDA0002398854070000065

(6)根据下方盾构隧道衬砌上不同部分各个方向上的附加荷载的分布及拱底竖向反力的卸载量ΔqR,得到变形稳定后的下方盾构隧道衬砌附加围压par(θ,l):(6) According to the distribution of additional loads in all directions on different parts of the shield tunnel lining below and the unloading amount Δq R of the vertical reaction force at the bottom of the arch, the additional confining pressure par (θ) of the shield tunnel lining below after the deformation is stabilized is obtained. ,l):

Figure BDA0002398854070000071
Figure BDA0002398854070000071

需要说明的是,本发明求得的是隧道衬砌附加围压,初始围压可以由隧道初始工况 下的荷载组合求得。本发明考虑的隧道初始工况下的荷载组合如图4(a)所示。图中初始工况荷载组合包括:(1)衬砌自重g;(2)上覆土竖向土压力q;(3)侧向主动土压力pe;(4) 静水压力pw;(5)拱底反力qR;(6)各项荷载作用下管片环发生变形后侧向的土体抗力pk。 当基坑开挖完成后,根据本发明方法计算得到的隧道变形稳定后的隧道衬砌附加围压如 图4(b)所示。将初始围压和附加围压叠加得到最终隧道衬砌围压值,运用于常用的修正 惯用法或者有限元分析模型即可研究隧道衬砌的内力和变形响应。It should be noted that the invention obtains the additional confining pressure of the tunnel lining, and the initial confining pressure can be obtained from the load combination under the initial working condition of the tunnel. The load combination under the initial working condition of the tunnel considered in the present invention is shown in Fig. 4(a). The initial load combination in the figure includes: (1) the dead weight g of the lining; (2) the vertical earth pressure q of the overlying soil; (3) the lateral active earth pressure p e ; (4) the hydrostatic pressure p w ; (5) the arch bottom reaction force q R ; (6) lateral soil resistance p k after the segment ring is deformed under various loads. After the excavation of the foundation pit is completed, the additional confining pressure of the tunnel lining after the tunnel deformation is stabilized calculated according to the method of the present invention is shown in Figure 4(b). The initial confining pressure and the additional confining pressure are superimposed to obtain the final confining pressure value of the tunnel lining, which can be used to study the internal force and deformation response of the tunnel lining by applying the commonly used correction method or finite element analysis model.

实施例Example

以杭州市延安路~仁和路过街通道一期工程上跨地铁1号线左线隧道为例:基坑平 面开挖尺寸L=11.4m,B=14.83m,开挖深度d=8.2m。下方盾构隧道轴线埋深h=15.3m,盾构隧道衬砌外径D=6.2m,环宽Dt=1.2m;管片环之间由16根M30纵向螺栓连接。地 下水位埋深约为1m,施工过程中水位波动较小,计算中不考虑地下水位的变化。土层 分布及相应参数如表1所示。计算基坑开挖卸载时,残余应力系数取α0=0.3。Taking the tunnel on the left line of Metro Line 1 on the first phase of the Yan'an Road-Renhe Road crossing in Hangzhou as an example: the excavation size of the foundation pit is L=11.4m, B=14.83m, and the excavation depth d=8.2m. The axial buried depth of the shield tunnel below is h=15.3m, the outer diameter of the shield tunnel lining is D=6.2m, and the ring width Dt =1.2m; the segment rings are connected by 16 M30 longitudinal bolts. The buried depth of the groundwater level is about 1m, and the fluctuation of the water level during the construction process is small, and the change of the groundwater level is not considered in the calculation. The soil layer distribution and corresponding parameters are shown in Table 1. When calculating the excavation and unloading of the foundation pit, the residual stress coefficient is taken as α 0 =0.3.

表1:土层分布及物理力学参数Table 1: Soil layer distribution and physical and mechanical parameters

Figure BDA0002398854070000072
Figure BDA0002398854070000072

采用取加权平均值的方法得到土体相关的计算参数取值:土的重度γ(kN/m3);内聚 力C(kPa);内摩擦角Φ(°);土的泊松比μ。所需计算的隧道断面沿y轴方向与基坑开挖中心的水平距离l。The weighted average method is used to obtain the calculation parameters related to the soil: soil gravity γ(kN/m 3 ); cohesion C(kPa); internal friction angle Φ(°); soil Poisson's ratio μ. The horizontal distance l between the tunnel section and the excavation center of the foundation pit along the y-axis direction to be calculated.

根据本发明的方法,得到变形稳定后的隧道衬砌附加围压par(θ,l)。According to the method of the present invention, the additional confining pressure par (θ,l) of the tunnel lining after the deformation is stabilized is obtained.

图5为基坑开挖前后的围压对比图。根据该实施例工况采用本发明方法可计算得到 基坑开挖前和基坑开挖后的隧道围压,以开挖中心下方l=0m处的断面为例,如图5所示。基坑开挖前,由于水土压力随深度的增加而增加,计算得到的盾构隧道围压上小下 大,左右对称分布。以上顶点为0°,顺时针方向角度增加。0°~90°范围内围压变化较小, 在218.46kPa~234.56kPa之间。90°~150°之间围压逐渐增大,在150°附近围压最大,约 为272.45kPa。由于本实施中基坑位于隧道的正上方,根据本发明理论方法计算得到的 隧道衬砌围压依然呈对称分布。如图5所示,基坑开挖后,开挖中心下方(l=0m处) 的隧道围压明显减小。基坑开挖引起的围压卸载效应主要作用在下方隧道衬砌的拱顶和 拱底附近。其中隧道拱顶(0°处)的卸载效应最为明显,围压从开挖前的218.46kPa减 小至161.92kPa,减小了25.88%。Figure 5 is a comparison chart of the confining pressure before and after excavation of the foundation pit. According to the working conditions of this embodiment, the method of the present invention can be used to calculate the confining pressure of the tunnel before and after the excavation of the foundation pit, taking the section at l=0m below the excavation center as an example, as shown in Figure 5. Before the excavation of the foundation pit, since the water and soil pressure increases with the depth, the calculated confining pressure of the shield tunnel is small in the upper part and larger in the lower part, and is symmetrically distributed on the left and right. The vertex above is 0° and the angle increases clockwise. The change of confining pressure in the range of 0°~90° is small, between 218.46kPa~234.56kPa. The confining pressure increases gradually between 90° and 150°, and the confining pressure is the largest near 150°, about 272.45kPa. Since the foundation pit is located directly above the tunnel in this implementation, the confining pressure of the tunnel lining calculated according to the theoretical method of the present invention is still distributed symmetrically. As shown in Figure 5, after the excavation of the foundation pit, the confining pressure of the tunnel below the excavation center (at l=0m) is significantly reduced. The confining pressure unloading effect caused by the excavation of the foundation pit mainly acts near the vault and vault bottom of the tunnel lining below. Among them, the unloading effect of the tunnel vault (at 0°) is the most obvious, and the confining pressure is reduced from 218.46kPa before excavation to 161.92kPa, a decrease of 25.88%.

图6为沿着盾构隧道方向距离开挖中心不同距离处作用于管片衬砌环的附加围压。 如图所示,附加围压皆为负值,即基坑开挖主要引起下方隧道衬砌围压减小。附加围压影响区域主要为拱顶和拱底附近,拱腰处附加围压绝对值较小。基坑开挖中心下方(l=0m)隧道衬砌拱顶处的附加围压绝对值最大,为56.54kPa。随着与开挖中心的水平距离增大,作用于下方盾构隧道衬砌上的附加围压绝对值减小。在开挖区域下方附近,作用于盾构 隧道衬砌上半部分的附加围压绝对值大于下半部分。随着与开挖区域距离增大,衬砌上 部和下部的附加围压差异逐渐减小,直到位于距开挖中心7.2m处(l=7.2m),拱顶和拱 底处的附加围压基本相当,分别为-22.42kPa和-21.12kPa。随着与开挖中心的距离进一 步增大,隧道衬砌上的附加荷载绝对值将转变为下大上小的分布。Figure 6 shows the additional confining pressure acting on the segment lining ring at different distances from the excavation center along the shield tunnel direction. As shown in the figure, the additional confining pressures are all negative values, that is, the excavation of the foundation pit mainly causes the confining pressure of the tunnel lining below to decrease. The area affected by the additional confining pressure is mainly near the top and bottom of the vault, and the absolute value of the additional confining pressure at the arch waist is small. The absolute value of the additional confining pressure at the tunnel lining vault below the excavation center of the foundation pit (l=0m) is the largest, which is 56.54kPa. As the horizontal distance from the excavation center increases, the absolute value of the additional confining pressure acting on the shield tunnel lining below decreases. Near the bottom of the excavation area, the absolute value of the additional confining pressure acting on the upper half of the shield tunnel lining is greater than that on the lower half. As the distance from the excavation area increases, the difference in the additional confining pressure between the upper and lower parts of the lining gradually decreases until it is located 7.2m away from the excavation center (l=7.2m), and the additional confining pressure at the top and bottom of the vault is basically Equivalent, -22.42kPa and -21.12kPa respectively. With the further increase of the distance from the excavation center, the absolute value of the additional load on the tunnel lining will change to the distribution of the lower large and the upper small.

实际工程中盾构隧道衬砌上的围压变化数据难以获取,为验证本发明方法的可靠性, 将本发明理论方法计算得到的初始围压和上方基坑开挖引起的附加围压及环间作用力 作为荷载组合用于有限元模型中的结构受力分析。通过计算可以获得不同位置处管片环 的变形,并于各环管片水平向附加收敛变形实测值进行对比。图7为该案例中基坑开挖引起的下方隧道水平向附加收敛变形实测值与计算结果的对比。正值表示盾构隧道管片环水平向压缩,拱腰径向收敛变形,单位为mm。如图7所示,本发明的方法计算得到 的下方隧道各个位置处水平收敛变形值以及其沿隧道纵向的变化规律与实测值基本吻 合,验证了本发明方法计算结果的可靠性。It is difficult to obtain the confining pressure change data on the shield tunnel lining in the actual project. In order to verify the reliability of the method of the present invention, the initial confining pressure calculated by the theoretical method of the present invention and the additional confining pressure caused by the excavation of the foundation pit above and the inter-ring Forces are used as load combinations for structural force analysis in finite element models. The deformation of the segment ring at different positions can be obtained by calculation, and the measured values of the additional convergent deformation in the horizontal direction of each ring segment are compared. Figure 7 shows the comparison between the measured value and the calculated result of the additional horizontal convergence deformation of the lower tunnel caused by the excavation of the foundation pit in this case. A positive value indicates that the shield tunnel segment ring is compressed horizontally, and the arch waist radially converges and deforms, and the unit is mm. As shown in Fig. 7 , the horizontal convergence deformation values at various positions of the tunnel below calculated by the method of the present invention and its variation law along the longitudinal direction of the tunnel are basically consistent with the measured values, which verifies the reliability of the calculation results of the method of the present invention.

Claims (1)

1.一种基坑开挖引起的下方盾构隧道附加围压变化预测方法,其特征在于,包括如下步骤:1. a method for predicting the additional confining pressure variation of the shield tunnel below caused by excavation of foundation pit, is characterized in that, comprises the steps: (1)在基坑的中心o处建立坐标系,x轴垂直于所述隧道的轴线,y轴平行于所述隧道的轴线,z轴以竖直向下为正方向。(1) A coordinate system is established at the center o of the foundation pit, the x-axis is perpendicular to the axis of the tunnel, the y-axis is parallel to the axis of the tunnel, and the z-axis is vertically downward as the positive direction. (2)根据步骤1建立的坐标系,计算上方基坑开挖引起的基坑底部开挖面卸载,并得到基坑底部开挖面卸载引起的下方盾构隧道横断面上的竖向向附加应力和水平向附加应力分布,具体包括如下子步骤:(2) According to the coordinate system established in step 1, calculate the unloading of the excavation surface at the bottom of the foundation pit caused by the excavation of the upper foundation pit, and obtain the vertical additional on the cross section of the shield tunnel below caused by the unloading of the excavation surface at the bottom of the foundation pit. Stress and horizontal additional stress distribution, including the following sub-steps: (2.1)基坑底部开挖面的卸载为基坑底部竖直向上的均布荷载,计算所述基坑底部卸载p:(2.1) The unloading of the excavation surface at the bottom of the foundation pit is the uniformly distributed load vertically upward at the bottom of the foundation pit. Calculate the unloading p at the bottom of the foundation pit: p=(1-α0)γd (1)p=(1-α 0 )γd (1) 其中:γ为土的重度,取基坑底以上开挖土层的加权平均值;d为基坑开挖深度;α0为残余应力系数。Among them: γ is the soil weight, which is the weighted average of the excavated soil layers above the foundation pit bottom; d is the excavation depth of the foundation pit; α 0 is the residual stress coefficient. (2.2)根据Mindlin应力解,以所述基坑底开挖面作为积分区域,计算得到基坑底部开挖卸载下所述下方盾构隧道横断面上的竖向附加应力σaz(θ,l)和水平向附加应力σax(θ,l)分别为:(2.2) According to the Mindlin stress solution, taking the excavation surface at the bottom of the foundation pit as the integral area, calculate the vertical additional stress σ az (θ, l ) and the additional horizontal stress σ ax (θ,l) are:
Figure RE-FDA0002509050000000011
Figure RE-FDA0002509050000000011
Figure RE-FDA0002509050000000012
Figure RE-FDA0002509050000000012
其中:θ为下方盾构隧道横断面上计算点的位置角度,以上顶点为0°,顺时针方向角度增加;B为基坑沿x轴方向的开挖尺寸;L为基坑沿y轴方向的开挖尺寸;d为基坑开挖深度;h为隧道埋深;D为下方盾构隧道外径;a为基坑中心与隧道轴线的水平距离,l为隧道轴线上任意一点在所述坐标系中对应的y坐标值;x1为第一积分变量,y1为第二积分变量,σzz为Mindlin竖向应力解,σxz为Mindlin水平应力解。Among them: θ is the position angle of the calculated point on the cross section of the shield tunnel below, the upper vertex is 0°, and the angle increases clockwise; B is the excavation size of the foundation pit along the x-axis direction; L is the foundation pit along the y-axis direction d is the excavation depth of the foundation pit; h is the buried depth of the tunnel; D is the outer diameter of the shield tunnel below; a is the horizontal distance between the center of the foundation pit and the tunnel axis, and l is any point on the tunnel axis in the The corresponding y coordinate value in the coordinate system; x 1 is the first integral variable, y 1 is the second integral variable, σ zz is the Mindlin vertical stress solution, and σ xz is the Mindlin horizontal stress solution. (3)根据隧道纵向变形的现场监测数据,结合隧道竖向位移,得到管片竖向环间作用合力分布,具体包括以下子步骤:(3) According to the on-site monitoring data of the longitudinal deformation of the tunnel, combined with the vertical displacement of the tunnel, the distribution of the resultant force acting between the vertical rings of the segment is obtained, which specifically includes the following sub-steps: (3.1)测量隧道沿纵向总的竖向位移w(l),测量管片环间转角引起的位移量,计算l处的管片环与前一节管片环之间的竖向环间剪切力QL(l)和后一节管片环之间的竖向环间剪切力QR(l):(3.1) Measure the total vertical displacement w(l) of the tunnel along the longitudinal direction, measure the displacement caused by the rotation angle between the segment rings, and calculate the vertical inter-ring shear between the segment ring at l and the previous segment ring Shear force Q L (l) and vertical inter-ring shear force Q R (l) between the succeeding segment rings: QL(l)=(1-j)[w(l-Dt)-w(l)]×ksl (4)Q L (l)=(1-j)[w(lD t )-w(l)]×k sl (4) QR(l)=(1-j)[w(l)-w(l-Dt)]×ksl (5)Q R (l)=(1-j)[w(l)-w(lD t )]×k sl (5) 其中,j为相邻管片环间转角引起的位移量与总的竖向位移之比,Dt为管片环的宽度,ksl为隧道的环间剪切刚度,QL(l)以作用方向向上为正,QR(l)以作用方向向下为正。Among them, j is the ratio of the displacement caused by the rotation angle between adjacent segment rings to the total vertical displacement, D t is the width of the segment rings, k sl is the inter-ring shear stiffness of the tunnel, and Q L (l) is given by The upward direction of action is positive, and Q R (l) is positive when the action direction is downward. (3.2)再根据QL(l)和QR(l),得到l处的管片环所受管片竖向环间作用合力Fsz(l):(3.2) According to Q L (l) and Q R (l), the resultant force F sz (l) acting on the vertical ring of the segment on the segment ring at position l is obtained: Fsz(l)=QR(l)-QL(l) (6)F sz (l) = Q R (l) - Q L (l) (6) (4)根据步骤(2.2)得到的下方盾构隧道横断面上的竖向附加应力σaz(θ,l)和水平向附加应力σax(θ,l),计算下方盾构隧道衬砌上不同部分各个方向上的附加荷载分布:(4) According to the vertical additional stress σ az (θ,l) and the horizontal additional stress σ ax (θ,l) on the cross section of the shield tunnel below obtained in step (2.2), calculate the different linings of the shield tunnel below. Additional load distribution in all directions of the section:
Figure RE-FDA0002509050000000021
Figure RE-FDA0002509050000000021
Figure RE-FDA0002509050000000022
Figure RE-FDA0002509050000000022
其中,paz(θ,l)为下方盾构隧道上半部分衬砌的竖向附加荷载,p′ax(θ,l)为下方盾构隧道左侧衬砌的水平向附加荷载,p″ax(θ,l)为下方盾构隧道右侧衬砌的水平向附加荷载。Among them, p az (θ,l) is the vertical additional load of the lining of the upper half of the shield tunnel below, p′ ax (θ,l) is the horizontal additional load of the left lining of the shield tunnel below, p″ ax ( θ,l) is the horizontal additional load of the lining on the right side of the shield tunnel below. 再根据下方盾构隧道衬砌上不同部分各个方向上的附加荷载分布,建立下方盾构隧道衬砌附加围压变化模型:Then, according to the additional load distribution in all directions on different parts of the shield tunnel lining below, the additional confining pressure variation model of the shield tunnel lining below is established:
Figure RE-FDA0002509050000000023
Figure RE-FDA0002509050000000023
Figure RE-FDA0002509050000000024
Figure RE-FDA0002509050000000024
其中,Fsx为水平向的环间作用合力,Fsz为竖直向的环间作用合力,ΔqR为拱底竖向反力的卸载量。Among them, F sx is the resultant force between the rings in the horizontal direction, F sz is the resultant force between the rings in the vertical direction, and Δq R is the unloading amount of the vertical reaction force at the bottom of the arch. (5)根据评估需求选取下方盾构隧道待分析的计算断面,将步骤(4)得到的计算断面位置处隧道衬砌上附加荷载和步骤(3)得到的计算断面位置处管片竖向环间作用合力导入到步骤(4)建立的下方盾构隧道衬砌附加围压变化模型中,得到计算断面处水平环间作用合力Fsx以及拱底竖向反力的卸载量ΔqR(5) Select the calculated cross section of the shield tunnel below to be analyzed according to the evaluation requirements, add the additional load on the tunnel lining at the position of the calculated cross section obtained in step (4) and the vertical ring of the segment at the position of the calculated cross section obtained in step (3). The resultant force is introduced into the additional confining pressure variation model of the lower shield tunnel lining established in step (4), and the resultant force F sx acting between the horizontal rings at the calculated section and the unloading amount Δq R of the vertical reaction force at the bottom of the arch are obtained.
Figure RE-FDA0002509050000000025
Figure RE-FDA0002509050000000025
Figure RE-FDA0002509050000000026
Figure RE-FDA0002509050000000026
(6)根据下方盾构隧道衬砌上不同部分各个方向上的附加荷载的分布及拱底竖向反力的卸载量ΔqR,得到变形稳定后的下方盾构隧道衬砌附加围压par(θ,l):(6) According to the distribution of additional loads in all directions on different parts of the shield tunnel lining below and the unloading amount Δq R of the vertical reaction force at the bottom of the arch, the additional confining pressure par (θ) of the shield tunnel lining below after the deformation is stabilized is obtained. ,l):
Figure RE-FDA0002509050000000031
Figure RE-FDA0002509050000000031
CN202010140265.7A 2020-03-03 2020-03-03 A method for predicting the change of additional confining pressure of the lower shield tunnel caused by foundation pit excavation Active CN111680383B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010140265.7A CN111680383B (en) 2020-03-03 2020-03-03 A method for predicting the change of additional confining pressure of the lower shield tunnel caused by foundation pit excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010140265.7A CN111680383B (en) 2020-03-03 2020-03-03 A method for predicting the change of additional confining pressure of the lower shield tunnel caused by foundation pit excavation

Publications (2)

Publication Number Publication Date
CN111680383A true CN111680383A (en) 2020-09-18
CN111680383B CN111680383B (en) 2023-07-07

Family

ID=72451386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010140265.7A Active CN111680383B (en) 2020-03-03 2020-03-03 A method for predicting the change of additional confining pressure of the lower shield tunnel caused by foundation pit excavation

Country Status (1)

Country Link
CN (1) CN111680383B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112597674A (en) * 2020-12-05 2021-04-02 福建工程学院 Method for determining lateral pipeline transverse additional internal force caused by foundation pit excavation
CN113111417A (en) * 2021-04-15 2021-07-13 交通运输部公路科学研究所 Additional load calculation method for local removal of tunnel lining
CN113987662A (en) * 2021-11-09 2022-01-28 北京城建设计发展集团股份有限公司 A method for determining the floating deformation of the tunnel caused by the excavation of the upper foundation pit of an existing shield tunnel
CN114964122A (en) * 2022-04-25 2022-08-30 广州大学 A Convergence Monitoring Method for Lining Rings of Shield Tunnels

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2209978C1 (en) * 2002-11-15 2003-08-10 Общество с ограниченной ответственностью "Трансстройтоннель-99" Method of tunnel construction and device for method embodiment
CN101550698A (en) * 2009-05-05 2009-10-07 上海隧道工程股份有限公司 Constructing method for basic pit at the upper part of shield tunnel
CN102839674A (en) * 2012-09-19 2012-12-26 中国水电顾问集团华东勘测设计研究院 Foundation pit excavation supporting structure on near end well shield tunnel and construction method of foundation pit excavation supporting structure
CN202865850U (en) * 2012-09-19 2013-04-10 中国水电顾问集团华东勘测设计研究院 Near-end shield tunnel foundation pit excavation supporting structure
CN106339554A (en) * 2016-08-29 2017-01-18 浙江大学城市学院 Method for caculating displacement of nearby existing subway tunnel due to foundation pit excavation
CN109299578A (en) * 2018-11-20 2019-02-01 中南大学 Calculation Method of Uplift Deformation of Underlying Existing Shield Tunnel Caused by Excavation of Foundation Pit
CN110046470A (en) * 2019-05-13 2019-07-23 湖南大学 A kind of shield driving causes ground settlement method for determination of amount after work
CN110188413A (en) * 2019-05-13 2019-08-30 浙江大学城市学院 A Prediction Method for Confining Pressure Change of Side Shield Tunnel Caused by Foundation Pit Excavation
CN110245401A (en) * 2019-05-31 2019-09-17 浙江大学城市学院 An evaluation method for the impact of shield tunnel underpass on existing shield tunnels

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2209978C1 (en) * 2002-11-15 2003-08-10 Общество с ограниченной ответственностью "Трансстройтоннель-99" Method of tunnel construction and device for method embodiment
CN101550698A (en) * 2009-05-05 2009-10-07 上海隧道工程股份有限公司 Constructing method for basic pit at the upper part of shield tunnel
CN102839674A (en) * 2012-09-19 2012-12-26 中国水电顾问集团华东勘测设计研究院 Foundation pit excavation supporting structure on near end well shield tunnel and construction method of foundation pit excavation supporting structure
CN202865850U (en) * 2012-09-19 2013-04-10 中国水电顾问集团华东勘测设计研究院 Near-end shield tunnel foundation pit excavation supporting structure
CN106339554A (en) * 2016-08-29 2017-01-18 浙江大学城市学院 Method for caculating displacement of nearby existing subway tunnel due to foundation pit excavation
CN109299578A (en) * 2018-11-20 2019-02-01 中南大学 Calculation Method of Uplift Deformation of Underlying Existing Shield Tunnel Caused by Excavation of Foundation Pit
CN110046470A (en) * 2019-05-13 2019-07-23 湖南大学 A kind of shield driving causes ground settlement method for determination of amount after work
CN110188413A (en) * 2019-05-13 2019-08-30 浙江大学城市学院 A Prediction Method for Confining Pressure Change of Side Shield Tunnel Caused by Foundation Pit Excavation
CN110245401A (en) * 2019-05-31 2019-09-17 浙江大学城市学院 An evaluation method for the impact of shield tunnel underpass on existing shield tunnels

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
魏纲 等: "基坑开挖引起的旁侧盾构隧道横向受力变化研究", 《岩土力学》, vol. 41, no. 2, pages 635 - 644 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112597674A (en) * 2020-12-05 2021-04-02 福建工程学院 Method for determining lateral pipeline transverse additional internal force caused by foundation pit excavation
CN112597674B (en) * 2020-12-05 2022-07-08 福建工程学院 A method for determining the lateral additional internal force of side pipelines caused by foundation pit excavation
CN113111417A (en) * 2021-04-15 2021-07-13 交通运输部公路科学研究所 Additional load calculation method for local removal of tunnel lining
CN113987662A (en) * 2021-11-09 2022-01-28 北京城建设计发展集团股份有限公司 A method for determining the floating deformation of the tunnel caused by the excavation of the upper foundation pit of an existing shield tunnel
CN114964122A (en) * 2022-04-25 2022-08-30 广州大学 A Convergence Monitoring Method for Lining Rings of Shield Tunnels

Also Published As

Publication number Publication date
CN111680383B (en) 2023-07-07

Similar Documents

Publication Publication Date Title
CN111680383A (en) A prediction method for the change of the additional confining pressure of the shield tunnel below caused by the excavation of the foundation pit
Lin et al. Deformation behaviors of existing tunnels caused by shield tunneling undercrossing with oblique angle
Chen et al. An improved method to calculate the vertical earth pressure for deep shield tunnel in Shanghai soil layers
CN111753363A (en) A calculation method of confining pressure change of shield tunnel beside the foundation pit considering the deformation and space effect of the foundation pit envelope
Huang et al. Exploring the three-dimensional response of a water storage and sewage tunnel based on full-scale loading tests
CN110188413B (en) Method for predicting lateral shield tunnel confining pressure change caused by foundation pit excavation
Chen et al. Numerical simulation of the uplift behavior of shield tunnel during construction stage
CN117172032B (en) Method and related equipment for calculating soil covering pressure distribution based on tunnel floating
Wang et al. Analysis of deep foundation pit construction monitoring in a metro station in Jinan city
CN102368277A (en) Building method of load-structure model in view of arch effect of tunnel stress
CN115809498A (en) A Calculation Method for Longitudinal Deformation of Deep-buried Shield Tunnel Passing Through Existing Lines
Huang et al. Effects of different construction sequences on ground surface settlement and displacement of single long pile due to twin paralleled shield tunneling
Song et al. Effect of seepage on soil arching effect in deep shield tunnel
Wu et al. Finite element analysis on mechanical behavior of semi-exposed pipeline subjected to debris flows
CN106815445A (en) A kind of shallow buried coal seam section coal pillar LOAD FOR model and its computational methods
Gu et al. A finite element-based dynamic simulation method for modeling shield-ground interactions: 3D numerical simulations with comparison to physical experiments
Wang et al. Field monitoring of a subsea shield tunnel during standpipe lifting
CN111985021B (en) Safety analysis method for fluid-solid coupling of all-over joints of shield excavation surface
Xie et al. Analytical Solution for the Steady‐State Karst Water Inflow into a Tunnel
WO2024139683A1 (en) Active support force calculation method and system for tunnel passing under existing structure
CN117473603A (en) Simulation method for stress characteristics of large-diameter shield tunnel opening expansion segments
Qin et al. Effect of deficiencies in the tunnel crown thickness on pressure tunnels with posttensioned concrete linings
Qin et al. Mechanical mechanism and theoretical analysis of anchor net support based on model test and numerical simulation
Hu et al. Analysis of structural characteristics of underground cavern group by simulating all cavern excavation
CN111898283A (en) Tunnel deformation quantity determining method and device, computer equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant