CN111626755A - Engineering prototype management method and device and related equipment thereof - Google Patents

Engineering prototype management method and device and related equipment thereof Download PDF

Info

Publication number
CN111626755A
CN111626755A CN202010479000.XA CN202010479000A CN111626755A CN 111626755 A CN111626755 A CN 111626755A CN 202010479000 A CN202010479000 A CN 202010479000A CN 111626755 A CN111626755 A CN 111626755A
Authority
CN
China
Prior art keywords
prototype
information
target
engineering
change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010479000.XA
Other languages
Chinese (zh)
Inventor
王晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Goertek Techology Co Ltd
Original Assignee
Goertek Techology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Goertek Techology Co Ltd filed Critical Goertek Techology Co Ltd
Priority to CN202010479000.XA priority Critical patent/CN111626755A/en
Publication of CN111626755A publication Critical patent/CN111626755A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/018Certifying business or products
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • G06K17/0025Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device the arrangement consisting of a wireless interrogation device in combination with a device for optically marking the record carrier

Abstract

The application discloses a project prototype management method, which comprises the steps of obtaining prototype screening information; determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code; acquiring change information generated when the target engineering prototype is subjected to change action; storing the change information to a target tracing code corresponding to the target engineering prototype; according to the engineering prototype management method, all the change information of the engineering prototype is stored through the unique tracing code, the dependence on human brain memory is completely eliminated, the change information of the engineering prototype can be traced reliably more conveniently, the accuracy and the integrity of the tracing information are further guaranteed, and the use experience of technicians is improved. The application also discloses an engineering prototype management device, equipment and a computer readable storage medium, which have the beneficial effects.

Description

Engineering prototype management method and device and related equipment thereof
Technical Field
The application relates to the technical field of computers, in particular to a project prototype management method, and further relates to a project prototype management device, equipment and a computer readable storage medium.
Background
An engineering prototype refers to a prototype used by engineers to test hardware performance and related technical parameters of a product, namely, a product assembled in an early stage of a project, and the prototype can undergo multiple verifications and initiate changes to solve various problems until a mature design is completed. However, as the number of engineering prototypes increases, more and more changes and verifications are needed, and a plurality of verifications are overlapped on the engineering prototypes, and when the verification is performed, the current state of the engineering prototypes needs to be known first, and then which engineering prototype needs to be selected for verification is determined, so that if only depending on the mind memory of an engineer, the change information tracing of the engineering prototypes cannot be effectively realized, the accuracy and the integrity of the tracing information cannot be ensured, and much inconvenience is brought to technical personnel.
Therefore, how to implement the change information tracing of the engineering prototype so as to effectively ensure the accuracy and integrity of the tracing information is a problem to be solved urgently by those skilled in the art.
Disclosure of Invention
The engineering prototype management method can effectively trace the change information of an engineering prototype, and further ensure the accuracy and integrity of the trace information; another object of the present application is to provide an engineering prototype management apparatus, device and computer-readable storage medium, which also have the above-mentioned advantages.
In a first aspect, the application provides a method for managing an engineering prototype, which includes:
acquiring model machine screening information;
determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
acquiring change information generated when the target engineering prototype is subjected to change action;
and storing the change information to a target tracing code corresponding to the target engineering prototype.
Preferably, the determining a target engineering prototype according to the prototype screening information includes:
performing model machine screening according to the model machine screening information to obtain at least one piece of model machine information corresponding to the model machine screening information;
screening and acquiring target prototype information according to the prototype information;
acquiring the target tracing code according to the target prototype information;
and outputting the target tracing code, and scanning the target tracing code to obtain the target engineering prototype.
Preferably, after the target engineering prototype is determined according to the prototype screening information, the method further comprises the following steps:
sending a confirmation request to the management terminal;
judging whether the confirmation information fed back by the management terminal is received or not;
if yes, outputting a change permission instruction;
if not, a reselection instruction is output.
Preferably, after the step of storing the change information into the target tracing code corresponding to the target engineering prototype, the method further includes:
and sending change completion information to the management terminal so that the management terminal confirms the change information.
Preferably, the change information includes a change time, a change executor, a change content, and a change result.
Preferably, the engineering prototype management method further comprises:
receiving a scanning instruction aiming at the target tracing code;
and outputting prototype information and historical change information of the engineering prototype corresponding to the target tracing code according to the scanning instruction.
Preferably, the tracing code is a two-dimensional code.
In a second aspect, the present application further discloses an engineering prototype management device, including:
the model machine screening information acquisition module is used for acquiring model machine screening information;
the target engineering prototype determining module is used for determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
the change information acquisition module is used for acquiring change information generated when the target engineering prototype is subjected to change action;
and the change information storage module is used for storing the change information to the target tracing code corresponding to the target engineering prototype.
In a third aspect, the present application further discloses an engineering prototype management apparatus, including:
a memory for storing a computer program;
a processor for executing said computer program to implement the steps of any of the engineering prototyping management methods described above.
In a fourth aspect, the present application also discloses a computer-readable storage medium having a computer program stored therein, which, when executed by a processor, is configured to implement the steps of any of the engineering prototyping management methods described above.
The engineering prototype management method comprises the steps of obtaining prototype screening information; determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code; acquiring change information generated when the target engineering prototype is subjected to change action; and storing the change information to a target tracing code corresponding to the target engineering prototype.
Therefore, according to the engineering prototype management method provided by the application, the unique tracing code is set for each engineering prototype in advance, the prototype information and the change information corresponding to the engineering prototype are stored, namely the prototype information and all the change information of the engineering prototype are stored through the unique tracing code, the dependence on the human brain memory is completely separated, the change information of the engineering prototype can be traced more conveniently, the accuracy and the integrity of the tracing information are further ensured, and the use experience of technical personnel is improved.
The engineering prototype management device, the engineering prototype management equipment and the computer-readable storage medium have the beneficial effects, and are not described again.
Drawings
In order to more clearly illustrate the technical solutions in the prior art and the embodiments of the present application, the drawings that are needed to be used in the description of the prior art and the embodiments of the present application will be briefly described below. Of course, the following description of the drawings related to the embodiments of the present application is only a part of the embodiments of the present application, and it will be obvious to those skilled in the art that other drawings can be obtained from the provided drawings without any creative effort, and the obtained other drawings also belong to the protection scope of the present application.
Fig. 1 is a schematic flow chart of a management method of an engineering prototype provided by the present application;
FIG. 2 is a schematic flow chart of another engineering prototype management method provided by the application;
fig. 3 is a schematic structural diagram of an engineering prototype management system provided by the present application;
fig. 4 is a schematic structural diagram of an engineering prototype management device provided by the present application;
fig. 5 is a schematic structural diagram of an engineering prototype management device provided by the application.
Detailed Description
The core of the application is to provide a project prototype management method, which can effectively trace the change information of a project prototype, thereby ensuring the accuracy and integrity of the trace information; another core of the present application is to provide an engineering prototype management apparatus, an engineering prototype management device, and a computer-readable storage medium, which also have the above-mentioned advantages.
In order to more clearly and completely describe the technical solutions in the embodiments of the present application, the technical solutions in the embodiments of the present application will be described below with reference to the drawings in the embodiments of the present application. It is to be understood that the embodiments described are only a few embodiments of the present application and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
An engineering prototype refers to a prototype used by engineers to test hardware performance and related technical parameters of a product, namely, a product assembled in an early stage of a project, and the prototype can undergo multiple verifications and initiate changes to solve various problems until a mature design is completed. However, as the number of engineering prototypes increases, more and more changes and verifications are needed, and a plurality of verifications are overlapped on the engineering prototypes, and when the verification is performed, the current state of the engineering prototypes needs to be known first, and then which engineering prototype needs to be selected for verification is determined, so that if only depending on the mind memory of an engineer, the change information tracing of the engineering prototypes cannot be effectively realized, the accuracy and the integrity of the tracing information cannot be ensured, and much inconvenience is brought to technical personnel. Therefore, in order to solve the technical problems, the engineering prototype management method realizes the storage of all the change information of the engineering prototype through the unique tracing code, completely breaks away from the dependence on the human brain memory, is more convenient to carry out the reliability tracing on the change information of the engineering prototype, further ensures the accuracy and the integrity of the tracing information and improves the use experience of technicians.
Referring to fig. 1, fig. 1 is a schematic flow chart of a engineering prototype management method provided in the present application, where the engineering prototype management method may include:
s101: acquiring model machine screening information;
the step aims to realize the acquisition of prototype screening information, the prototype screening information is the relevant information of the engineering prototype needing to be changed and verified, the specific content is not unique, and the information can be hardware version number, prototype upgrading time, prototype verification time and the like. The prototype information corresponding to the engineering prototype and the corresponding tracing code can be stored in the server or the memory, when prototype screening information is input for screening, automatic screening can be carried out from the server or the memory, the prototype information meeting the conditions is obtained, the screened prototype information comprises various information corresponding to the specific engineering prototype, and then the target engineering prototype is further determined according to the prototype information. Specifically, when an engineer needs to perform change verification on a certain engineering prototype, a change request can be initiated based on the system terminal, corresponding prototype screening information is input in the change request, and the system processor can screen the engineering prototypes meeting the conditions according to the prototype screening information and determine a target engineering prototype from the engineering prototypes meeting the screening conditions.
S102: determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
the step aims to realize the determination of the target engineering prototype, which is the engineering prototype needing to be changed and verified, the prototype screening information can be the relevant information of the engineering prototype, such as the hardware version number, the prototype upgrading time, the prototype verification time and the like, the prototype screening information can be set according to the user requirements and can be the relevant information of one or more engineering prototypes, therefore, the prototype information is obtained by analyzing the prototype screening information, the determination of the target engineering prototype can be realized by further screening from the prototype information, and for example, the corresponding target engineering prototype can be obtained by inquiring in a prototype library based on the prototype information.
Each engineering prototype in the prototype library is provided with a unique tracing code, namely the engineering prototype corresponds to the tracing code one by one, and various information corresponding to the engineering prototype is stored in the tracing code, including but not limited to change information, prototype parameter information, upgrade information, version information and the like, so that all information of the engineering prototype can be obtained by scanning the tracing code. It can be understood that the specific type of the tracing code does not affect the implementation of the technical scheme, and the information tracing may be implemented, which is not limited in the present application, and may be, for example, a two-dimensional code, a barcode, a label, and the like.
As a preferred embodiment, the tracing code is specifically a two-dimensional code.
The preferred embodiment provides a specific type of tracing code, namely a two-dimensional code, compared with a bar code, the two-dimensional code can store more information and display more data types, and has the characteristics of large amount of stored information, easiness in identification, low cost and the like.
As a preferred embodiment, the determining the target engineering prototype according to the prototype screening information may include: performing model machine screening according to the model machine screening information to obtain at least one piece of model machine information corresponding to the model machine screening information; screening and acquiring target prototype information according to the prototype information; acquiring a target tracing code according to the target prototype information; and outputting the target tracing code, and scanning the target tracing code to obtain the target engineering prototype.
The preferred embodiment provides a more specific method for determining a target engineering prototype. Specifically, when prototype screening is performed based on prototype screening information, there may be a case where a plurality of pieces of prototype information satisfying conditions are obtained by screening, for example, when the prototype screening information is a hardware version of an engineering prototype, a plurality of engineering prototypes may all adopt hardware of the version, so that a plurality of pieces of prototype information can be obtained by screening, when screening is performed based on the prototype screening information, if prototype information corresponding to a plurality of engineering prototypes satisfying conditions is screened, further screening is performed according to specific contents in the prototype information to obtain target prototype information, and a target tracing code is obtained according to the target prototype information, so that an engineer can scan the target tracing code to determine a required target engineering prototype.
S103: acquiring change information generated when the target engineering prototype is subjected to change action;
the step aims to realize the acquisition of the change information, and the change information is the related information of the change generated in the process that the target engineering prototype is subjected to the change action again. Specifically, after a target engineering prototype is determined, an engineer can change and verify the target engineering prototype, namely, corresponding change actions are executed, after the change actions are executed, various change information in the change process can be submitted to the system, during specific implementation, the engineer can scan a target tracing code corresponding to the target engineering prototype, then various change information is filled in a visual interface, and then the submission is completed, so that the system can obtain all change information generated when the change actions are executed on the target engineering prototype. It can be understood that the specific content of the change information is not unique, and may include change time, change content such as software and hardware update version number, prototype verification content and verification result thereof, change result, and the like, which is not limited in this application.
As a preferred embodiment, the change information may include a change time, a change executor, a change content, and a change result.
S104: and storing the change information into a target tracing code corresponding to the target engineering prototype.
The method comprises the steps of storing change information, namely storing the change information of a target engineering prototype to a corresponding target tracing code, so that a technician can scan all information of the corresponding engineering prototype through the tracing code to further realize information tracing, and the accuracy and the integrity of the tracing information are effectively guaranteed.
As a preferred embodiment, the engineering prototype management method may further include: receiving a scanning instruction aiming at a target tracing code; and outputting prototype information and historical change information of the target engineering prototype corresponding to the target tracing code according to the scanning instruction.
The preferred implementation provides a specific information tracing implementation method, technicians can scan the tracing code by using terminal equipment such as a mobile phone, a scanning gun and the like, at the moment, the system receives a scanning instruction aiming at the target tracing code, and then outputs corresponding prototype information and historical change information of the target engineering prototype according to the scanning instruction, so that the information tracing of the target engineering prototype is realized. The model machine information can comprise model machine model, assembly time, structure version number, software and hardware version number, upgrading version number, verification information and the like; the history change information may include a change time, a change executor, a change content, a change result, and the like in the course of the past change.
Therefore, according to the engineering prototype management method provided by the application, the unique tracing code is set for each engineering prototype in advance, the prototype information and the change information corresponding to the engineering prototype are stored, namely the prototype information and all the change information of the engineering prototype are stored through the unique tracing code, the dependence on the human brain memory is completely separated, the change information of the engineering prototype can be traced more conveniently, the accuracy and the integrity of the tracing information are further ensured, and the use experience of technical personnel is improved.
On the basis of the foregoing embodiments, please refer to fig. 2, fig. 2 is a schematic flow chart of another engineering prototype management method provided in the present application, where the engineering prototype management method may include:
s201: acquiring model machine screening information;
s202: determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
s203: sending a confirmation request to the management terminal;
s204: judging whether confirmation information fed back by the management terminal is received; if not, executing S205, if yes, executing S206;
s205: outputting a reselection instruction, and returning to S202;
s206: outputting a change permission instruction;
s207: acquiring change information generated when the target engineering prototype is subjected to change action;
s208: storing the change information into a target tracing code;
s209: and sending the change completion information to the management terminal so that the management terminal confirms the change information.
In order to facilitate the management of the engineering prototype and realize unified scheduling, a management terminal can be additionally arranged. Specifically, when an engineer selects a target engineering prototype to change and verify, a confirmation request can be sent to the management terminal to ask for permission of an administrator, if confirmation information fed back by the management terminal is received, the permission of the administrator is obtained, and at the moment, a change permission instruction can be output to inform the engineer that the target engineering prototype can be changed, operated and verified; if the confirmation information fed back by the management terminal is not received, the permission of the administrator is not obtained, and at the moment, a reselection instruction can be output to inform the engineer to reselect the target engineering prototype until a new target engineering prototype is determined.
Furthermore, after the change and verification of the target engineering prototype and the storage of the change information are completed, the change completion information can be sent to the management terminal, so that the administrator can confirm and archive the current change information. In addition, if the management terminal does not confirm the change information, other users are not allowed to execute any change operation on the target engineering prototype.
Therefore, the engineering prototypes are managed by adding the administrator role, so that unified scheduling of the engineering prototypes is realized more conveniently, and the system reliability is further improved.
For the specific implementation of the above steps S201 and S202, and S207 and S208, reference may be made to the content of the foregoing embodiments, and details are not repeated herein.
On the basis of the foregoing embodiments, the preferred embodiment provides a more specific engineering prototype management method, which is implemented in the following specific steps:
firstly, attaching a two-dimensional code on each engineering prototype, wherein the two-dimensional code corresponds to the engineering prototypes one to one, when scanning the two-dimensional code, the relevant information of the corresponding engineering prototypes can be obtained, such as hardware version, software version, structure version, assembly time, upgrade version, verification time, verification result and the like, and the prototype information can be stored in a system, and can be specifically stored in a memory or a server.
Further, when an engineer has a change demand, the engineer firstly searches for an engineering prototype meeting the demand, specifically, screening conditions are input in the system, such as one or more prototype information, at the moment, the system outputs prototype information of at least one engineering prototype meeting the conditions, the engineer can further determine a target engineering prototype from a screening result conveniently, a corresponding target two-dimensional code is obtained according to the target engineering prototype, and then the change action is executed and the verification is carried out on the target two-dimensional code. After the verification is finished, the engineer scans the two-dimensional code again, inputs relevant information of the verification change, such as change time, change person, change content, change result and the like, and stores the change information into the system.
When the engineer determines the target engineering prototype, a confirmation request needs to be sent to the administrator to inquire whether the engineering prototype can be used or not, and after permission of the administrator is obtained, the engineer can perform change action on the engineering prototype. After the change is completed, the administrator needs to be informed again that the verification is completed, so that the administrator can confirm the change information and complete the model machine management.
On this basis, please refer to fig. 3, fig. 3 is a schematic structural diagram of an engineering prototype management system provided in the present application, the engineering prototype management system includes a tracing code, a tracing code identification module, a prototype screening module, a prototype use request processing module, a tracing content editing module, a prototype after-change confirmation module, and a storage module, and the specific description is as follows:
(1) tracing code: the identifier distributed to the engineering prototype has uniqueness which can be realized by using a two-dimensional code, and the prototype information of the engineering prototype can be obtained by scanning the two-dimensional code and can be edited;
(2) tracing code identification module: identifying the tracing code, wherein if the tracing code is a two-dimensional code, the specific implementation equipment of the module can be a mobile phone or a gun scanner;
(3) a prototype screening module: the change initiator inputs the related model machine information, so that the system can conveniently screen the model machines based on the model machine information and output the tracing codes of the engineering model machines meeting the screening conditions;
(4) the model machine use request processing module: after receiving the model machine use request, the administrator makes a processing suggestion which can be used or can not be used and transmits the processing suggestion to the change initiator;
(5) a tracing content editing module: the tracing content can be changed by a change initiator and a change executor, and past changes of the engineering prototype can be checked;
(6) confirming module after prototype change: after the engineering prototype is used, sending information to an administrator so that the administrator can confirm the change information; before the administrator confirms the change information, other users cannot initiate a change request to the engineering prototype;
(7) a storage module: the method is used for supporting the operation of the process and storing the tracing content.
Therefore, the engineering prototype management method provided by the embodiment of the application sets the unique tracing code for each engineering prototype in advance, stores the prototype information and the change information corresponding to the engineering prototype, namely, the prototype information and all the change information of the engineering prototype are stored through the unique tracing code, dependence on human brain memory is completely eliminated, the change information of the engineering prototype can be traced reliably more conveniently, the accuracy and the integrity of the tracing information are further ensured, and the use experience of technical personnel is improved.
To solve the above technical problem, the present application further provides an engineering prototype management device, please refer to fig. 4, where fig. 4 is a schematic structural diagram of the engineering prototype management device provided in the present application, and the engineering prototype management device may include:
the model machine screening information acquisition module 1 is used for acquiring model machine screening information;
the target engineering prototype determining module 2 is used for determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
the change information acquisition module 3 is used for acquiring change information generated when the target engineering prototype is subjected to change action;
and the change information storage module 4 is used for storing the change information into the target tracing code corresponding to the target engineering prototype.
Therefore, the engineering prototype management device provided by the embodiment of the application sets the unique tracing code for each engineering prototype in advance, stores the prototype information and the change information corresponding to the engineering prototype, namely, the prototype information and all the change information of the engineering prototype are stored through the unique tracing code, the dependence on the human brain memory is completely separated, the change information of the engineering prototype can be traced more conveniently, the accuracy and the integrity of the tracing information are further ensured, and the use experience of technical personnel is improved.
As a preferred embodiment, the target prototype determining module 2 may include:
the first screening unit is used for screening the prototype according to the prototype screening information to obtain at least one prototype information corresponding to the prototype screening information;
the second screening unit is used for screening and acquiring target prototype information according to the prototype information;
the first acquisition unit is used for acquiring the target tracing code according to the information of the target prototype;
and the second acquisition unit is used for outputting the target tracing code and acquiring the target engineering prototype by scanning the target tracing code.
As a preferred embodiment, the engineering prototype management device may further include a prototype management module, configured to send a confirmation request to the management terminal after determining the target engineering prototype according to the prototype screening information; judging whether confirmation information fed back by the management terminal is received; if yes, outputting a change permission instruction; if not, a reselection instruction is output.
As a preferred embodiment, the engineering prototype management apparatus may further include a change confirmation module, configured to send change completion information to the management terminal after the change information is stored in the target tracing code corresponding to the target engineering prototype, so that the management terminal confirms the change information.
As a preferred embodiment, the engineering prototype management device may further include a code scanning feedback module, configured to receive a scanning instruction for the target tracing code; and outputting prototype information and historical change information of the engineering prototype corresponding to the target tracing code according to the scanning instruction.
For the introduction of the apparatus provided in the present application, please refer to the above method embodiments, which are not described herein again.
In order to solve the above technical problem, the present application further provides an engineering prototype management device, please refer to fig. 5, where fig. 5 is a schematic structural diagram of the engineering prototype management device provided in the present application, and the engineering prototype management device may include:
a memory 10 for storing a computer program;
the processor 20, when executing the computer program, may implement the steps of any of the above-described engineering prototype management methods.
For the introduction of the device provided in the present application, please refer to the above method embodiment, which is not described herein again.
In order to solve the above problem, the present application further provides a computer-readable storage medium, on which a computer program is stored, and the computer program, when executed by a processor, can implement the steps of any one of the engineering prototype management methods described above.
The computer-readable storage medium may include: various media capable of storing program codes, such as a usb disk, a removable hard disk, a Read-only Memory (ROM), a Random Access Memory (RAM), a magnetic disk, or an optical disk.
For the introduction of the computer-readable storage medium provided in the present application, please refer to the above method embodiments, which are not described herein again.
The embodiments are described in a progressive manner in the specification, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. The device disclosed by the embodiment corresponds to the method disclosed by the embodiment, so that the description is simple, and the relevant points can be referred to the method part for description.
Those of skill would further appreciate that the various illustrative elements and algorithm steps described in connection with the embodiments disclosed herein may be implemented as electronic hardware, computer software, or combinations of both, and that the various illustrative components and steps have been described above generally in terms of their functionality in order to clearly illustrate this interchangeability of hardware and software. Whether such functionality is implemented as hardware or software depends upon the particular application and design constraints imposed on the implementation. Skilled artisans may implement the described functionality in varying ways for each particular application, but such implementation decisions should not be interpreted as causing a departure from the scope of the present application.
The steps of a method or algorithm described in connection with the embodiments disclosed herein may be embodied directly in hardware, in a software module executed by a processor, or in a combination of the two. A software module may reside in Random Access Memory (RAM), memory, Read Only Memory (ROM), electrically programmable ROM, electrically erasable programmable ROM, registers, hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.
The technical solutions provided by the present application are described in detail above. The principles and embodiments of the present application are explained herein using specific examples, which are provided only to help understand the method and the core idea of the present application. It should be noted that, for those skilled in the art, without departing from the principle of the present application, several improvements and modifications can be made to the present application, and these improvements and modifications also fall into the protection scope of the present application.

Claims (10)

1. A project prototype management method is characterized by comprising the following steps:
acquiring model machine screening information;
determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
acquiring change information generated when the target engineering prototype is subjected to change action;
and storing the change information to a target tracing code corresponding to the target engineering prototype.
2. The engineering prototype management method according to claim 1, wherein the determining a target engineering prototype according to the prototype screening information comprises:
performing model machine screening according to the model machine screening information to obtain at least one piece of model machine information corresponding to the model machine screening information;
screening and acquiring target prototype information according to the prototype information;
acquiring the target tracing code according to the target prototype information;
and outputting the target tracing code, and scanning the target tracing code to obtain the target engineering prototype.
3. The engineering prototype management method according to claim 1 or 2, wherein after determining the target engineering prototype according to the prototype screening information, further comprising:
sending a confirmation request to the management terminal;
judging whether the confirmation information fed back by the management terminal is received or not;
if yes, outputting a change permission instruction;
if not, a reselection instruction is output.
4. The engineering prototype management method according to claim 3, wherein the step of storing the change information after the target tracing code corresponding to the target engineering prototype further comprises the steps of:
and sending change completion information to the management terminal so that the management terminal confirms the change information.
5. The engineering prototype management method according to claim 4, wherein the change information includes a change time, a change executor, a change content, and a change result.
6. The engineering prototyping management method of claim 1 further comprising:
receiving a scanning instruction aiming at the target tracing code;
and outputting prototype information and historical change information of the target engineering prototype corresponding to the target tracing code according to the scanning instruction.
7. The engineering prototype management method according to claim 1, wherein the tracing code is a two-dimensional code.
8. An engineering prototype management device is characterized by comprising:
the model machine screening information acquisition module is used for acquiring model machine screening information;
the target engineering prototype determining module is used for determining a target engineering prototype according to the prototype screening information; wherein, each engineering prototype is provided with a tracing code;
the change information acquisition module is used for acquiring change information generated when the target engineering prototype is subjected to change action;
and the change information storage module is used for storing the change information to the target tracing code corresponding to the target engineering prototype.
9. An engineering prototype management device, comprising:
a memory for storing a computer program;
a processor for executing said computer program to carry out the steps of the engineering prototype management method according to any of claims 1 to 7.
10. A computer-readable storage medium, in which a computer program is stored which, when being executed by a processor, is adapted to carry out the steps of the engineering prototyping management method of any one of claims 1-7.
CN202010479000.XA 2020-05-29 2020-05-29 Engineering prototype management method and device and related equipment thereof Pending CN111626755A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010479000.XA CN111626755A (en) 2020-05-29 2020-05-29 Engineering prototype management method and device and related equipment thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010479000.XA CN111626755A (en) 2020-05-29 2020-05-29 Engineering prototype management method and device and related equipment thereof

Publications (1)

Publication Number Publication Date
CN111626755A true CN111626755A (en) 2020-09-04

Family

ID=72260705

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010479000.XA Pending CN111626755A (en) 2020-05-29 2020-05-29 Engineering prototype management method and device and related equipment thereof

Country Status (1)

Country Link
CN (1) CN111626755A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022100139A1 (en) * 2020-11-10 2022-05-19 长鑫存储技术有限公司 Detection method and detection apparatus for wafer testing machines

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202758387U (en) * 2012-06-13 2013-02-27 北京智领世纪物联科技有限公司 Engineering prototype tracking management system
CN105550725A (en) * 2016-02-18 2016-05-04 国网冀北电力有限公司电力科学研究院 Testing management method based on RFID
JP2018032134A (en) * 2016-08-23 2018-03-01 川田テクノシステム株式会社 Construction machine management system
WO2018133068A1 (en) * 2017-01-22 2018-07-26 深圳市梓菡科技有限公司 Mobile phone test machine and mobile phone test method
CN209624692U (en) * 2018-11-23 2019-11-12 无锡恩梯量仪科技有限公司 A kind of BMS automatic aging test macro
CN110738335A (en) * 2019-10-22 2020-01-31 苏州智加科技有限公司 Test equipment management system and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202758387U (en) * 2012-06-13 2013-02-27 北京智领世纪物联科技有限公司 Engineering prototype tracking management system
CN105550725A (en) * 2016-02-18 2016-05-04 国网冀北电力有限公司电力科学研究院 Testing management method based on RFID
JP2018032134A (en) * 2016-08-23 2018-03-01 川田テクノシステム株式会社 Construction machine management system
WO2018133068A1 (en) * 2017-01-22 2018-07-26 深圳市梓菡科技有限公司 Mobile phone test machine and mobile phone test method
CN209624692U (en) * 2018-11-23 2019-11-12 无锡恩梯量仪科技有限公司 A kind of BMS automatic aging test macro
CN110738335A (en) * 2019-10-22 2020-01-31 苏州智加科技有限公司 Test equipment management system and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022100139A1 (en) * 2020-11-10 2022-05-19 长鑫存储技术有限公司 Detection method and detection apparatus for wafer testing machines

Similar Documents

Publication Publication Date Title
CN109165170B (en) Method and system for automatic request test
CN105573755A (en) Method and device for acquiring application Activity rendering time
CN104317618A (en) Firmware partitioning method and device
CN112416327A (en) Project construction method and device, computer equipment and storage medium
CN110825705A (en) Data set caching method and related device
CN111625294A (en) Server project execution method, device and related equipment
CN115617780A (en) Data import method, device, equipment and storage medium
CN111626755A (en) Engineering prototype management method and device and related equipment thereof
CN110888804A (en) Interface test method and interface test platform
CN106557419B (en) Program testing method and device
CN114201346A (en) HIL (hardware-in-the-loop) testing method and device of CAN (controller area network) communication interface and electronic equipment
CN117493188A (en) Interface testing method and device, electronic equipment and storage medium
CN116578497A (en) Automatic interface testing method, system, computer equipment and storage medium
KR101252358B1 (en) Apparatus and method for testing plc command
CN115220707B (en) Software development management method and system based on block chain
CN113206849B (en) Vulnerability scanning method and device based on ghidra and related equipment
CN112350879B (en) Data communication equipment test management method, device, system and storage medium
CN114785847B (en) Network control software development configuration method, terminal and storage medium
CN111488283B (en) Task generation method and device, electronic equipment and storage medium
CN116225441B (en) Code hosting method and system for online coding system
CN112035358B (en) Method, device and equipment for determining detection information
CN109871231B (en) Code sharing method and system
CN111399903B (en) Server connection method, device and related equipment
CN110750684B (en) Message prompting method for multi-dimensional verification, storage medium, electronic device and system
CN110874316B (en) Method, device and system for scanning codes

Legal Events