Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010352691.7A
Other languages
Chinese (zh)
Other versions
CN111612415A (en
Inventor
刘坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Yindun Tai'an Network Technology Co ltd
Original Assignee
Beijing Yindun Tai'an Network Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Yindun Tai'an Network Technology Co ltd filed Critical Beijing Yindun Tai'an Network Technology Co ltd
Priority to CN202010352691.7A priority Critical patent/CN111612415B/en
Publication of CN111612415A publication Critical patent/CN111612415A/en
Application granted granted Critical
Publication of CN111612415B publication Critical patent/CN111612415B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F18/00Pattern recognition
    • G06F18/20Analysing
    • G06F18/22Matching criteria, e.g. proximity measures
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/60Protecting data
    • G06F21/604Tools and structures for managing or administering access control systems

Abstract

The invention discloses a project management method and a device, wherein the method comprises the following steps: receiving a project creation request of a user; creating a first number of items according to item contents corresponding to the item creating request; receiving a sub-account creation request of a user; creating a second number of sub-accounts according to the sub-account creation request; matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result; and performing authority operation function division on the sub-accounts of the second number based on a second preset rule according to the first matching result. Has the beneficial effects that: through setting and dividing the items, the item members and the authority of the item members respectively, the work efficiency of the item members can be effectively improved, meanwhile, the information of the items and the users can be effectively protected, and the risk of information safety leakage is greatly reduced.

Description

Project management method and device
Technical Field
The present invention relates to the field of project management technologies, and in particular, to a project management method and apparatus.
Background
In the existing background management software platform, a plurality of projects may exist, and each project involves different degrees of development or operation and maintenance services. When the employees of the company use the platform server, due to the authority problem, the employees must establish their own accounts, and it is troublesome to manage the accounts and the authority distribution. Such an operation cannot improve the work efficiency. Meanwhile, management authority division cannot be well performed on a plurality of development and operation and maintenance personnel serving one project, and certain information security risks can exist on the project. In a background management platform, when multiple roles and multiple projects need to be developed and operated and maintained simultaneously, the problems of low development and operation and maintenance working efficiency and hidden danger of information safety exist.
Disclosure of Invention
The present invention is directed to solving, at least to some extent, one of the technical problems in the art described above. Therefore, a first objective of the present invention is to provide a project management method, which can effectively improve the work efficiency of project members, effectively protect information of projects and users, and greatly reduce the risk of information security leakage by setting and dividing the projects, the project members, and the authority of the project members.
A second object of the present invention is to provide a project management apparatus.
In order to achieve the above object, an embodiment of a first aspect of the present invention provides a project management method, which is applicable to a background management software platform, and includes:
receiving a project creation request of a user;
creating a first number of items according to item contents corresponding to the item creating request;
receiving a sub-account creation request of a user;
creating a second number of sub-accounts according to the sub-account creation request;
matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result;
and performing authority operation function division on the sub-accounts of the second number based on a second preset rule according to the first matching result.
According to the project management method provided by the embodiment of the first aspect of the invention, each sub-account can be logged in and managed by a project member, and the project member can be a developer or an operation and maintenance person; through setting and dividing the items, the item members and the authority of the item members respectively, the work efficiency of the item members can be effectively improved, meanwhile, the information of the items and the users can be effectively protected, and the risk of information safety leakage is greatly reduced.
According to some embodiments of the invention, the first preset rule includes that each sub-account can exist in a plurality of projects simultaneously for resource operation without interfering with other resources;
the second preset rule comprises the division of different authority operation functions among different sub-accounts in the same project.
According to some embodiments of the invention, the project content includes project demand information, project feasibility analysis information, project cost, and cycle information;
the creating a first number of items according to the item content corresponding to the item creating request includes:
respectively evaluating and scoring project demand information, project feasibility analysis information, project cost and period information according to the project content to obtain a first score, a second score and a third score;
calculating a total project score according to the first score, the second score and the third score, and judging whether the total project score is greater than or equal to a preset project score;
and when the total item score is judged to be larger than or equal to the preset item score, creating a first number of items according to the item content corresponding to the item creating request.
According to some embodiments of the present invention, the total score of the project is calculated according to the first score, the second score and the third score, and the total score of the project is determined according to the following algorithm:
the total item score:
M=M1×P1+M2×P2+M3×P3
wherein, M1A first score, M, for the project requirement information review score2A second score, M, of scoring the project feasibility analysis information review3A third score, P, for the project cost and period information review score1Is the weight, P, of the project requirement information2For the weight, P, of the project feasibility analysis information3Is a weight value, P, of project cost and period information1+P2+P3=1。
According to some embodiments of the invention, the sub-account creation request includes security authentication information; the security authentication information includes: identity card information, face information and iris information of the user;
creating a second number of sub-accounts according to the sub-account creation request, comprising:
acquiring personal information of a user for creating a main account;
judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold value or not;
and if the similarity between the safety authentication information in the sub-account creation request and the personal information is determined to be larger than or equal to a preset similarity threshold, creating a second number of sub-accounts according to the sub-account creation request.
According to some embodiments of the present invention, whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold is determined, which includes the following specific steps:
step A, preprocessing the security authentication information in the sub-account creation request;
Figure BDA0002470730840000031
wherein, x'iFor the ith information x in the security authentication informationiIn the preprocessed data, alpha is the mean value of the safety certification information, and tau is an accurate coefficient;
wherein h is xiMinimum value of possible values, H being xiThe maximum value of the possible values;
b, calculating the similarity between the safety authentication information and the personal information;
Figure BDA0002470730840000032
wherein epsilon is the similarity, x ', of the safety certification information and the personal information'iFor the ith information x in the security authentication informationiPreprocessed data, yiThe data is the data of the ith information in the personal information, and n is the number of information contained in the personal information and also the number of information contained in the safety certification information;
step C, judging the relation between the similarity and a preset similarity threshold according to the following formula;
k=sgn(ε-a)
in the above formula, k is a relationship value between the similarity and a preset similarity threshold, where when k is 0, the similarity is equal to the preset similarity threshold, and when k is 1, the similarity is greater than the preset similarity threshold; when k is equal to-1, the similarity is smaller than a preset similarity threshold.
According to some embodiments of the invention, the matching the second number of sub-accounts with the first number of items based on a first preset rule to obtain a first matching result includes:
acquiring a project plan corresponding to each project in a first number of projects;
and obtaining a first matching result according to the sub-account number required by the project plan distribution.
According to some embodiments of the invention, the project management method further comprises: correcting the first matching result to obtain a second matching result; the method comprises the following steps:
acquiring participation data and active data of sub accounts distributed by each project in the first matching result;
determining the participation degree score of the sub-account according to the participation data;
determining an activity score of a sub-account according to the activity data;
obtaining the distribution score of the sub-account in a first matching result according to the engagement score and the activity score;
and respectively judging whether the distribution scores of all the sub-accounts are within a preset score range, screening the sub-accounts which are not within the preset score range, and redistributing to obtain a second distribution result.
According to some embodiments of the invention, the project management method further comprises:
receiving a monitoring request of a user;
and monitoring the items with the first quantity and the sub-accounts with the second quantity according to the monitoring request.
In order to achieve the above object, a second embodiment of the present invention provides an item management apparatus, including:
the first receiving module is used for receiving a project creation request of a user;
a first creating module, configured to create a first number of items according to item content corresponding to the item creating request;
the second receiving module is used for receiving a sub-account creating request of a user;
the second creating module is used for creating a second number of sub-accounts according to the sub-account creating request;
the matching module is used for matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result;
and the function division module is used for dividing the authority operation functions of the sub-accounts of the second number based on a second preset rule according to the first matching result.
Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by the practice of the invention. The objectives and other advantages of the invention will be realized and attained by the structure particularly pointed out in the written description and drawings.
The technical solution of the present invention is further described in detail by the accompanying drawings and embodiments.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention. In the drawings:
FIG. 1 is a flow diagram of a project management method according to one embodiment of the invention;
FIG. 2 is a schematic illustration of project management according to one embodiment of the present invention;
FIG. 3 is a flow diagram of creating a project, according to one embodiment of the invention;
FIG. 4 is a flow diagram of creating a sub-account according to one embodiment of the invention;
FIG. 5 is a flow diagram of obtaining a first match result according to one embodiment of the invention;
FIG. 6 is a flow diagram of obtaining a second match result according to one embodiment of the invention;
fig. 7 is a block diagram of an item management apparatus according to an embodiment of the present invention.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it should be understood that they are presented herein only to illustrate and explain the present invention and not to limit the present invention.
A project management method and apparatus according to an embodiment of the present invention will be described with reference to fig. 1 to 7.
FIG. 1 is a flow diagram of a project management method according to one embodiment of the invention; as shown in fig. 1, an embodiment of the first aspect of the present invention provides a project management method, which is applicable to a background management software platform, and includes steps S1-S6:
s1, receiving a project creation request of a user;
s2, creating a first number of items according to the item content corresponding to the item creating request;
s3, receiving a sub-account creation request of a user;
s4, creating a second number of sub-accounts according to the sub-account creation request;
s5, matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result;
and S6, performing authority operation function division on the sub-accounts of the second number based on a second preset rule according to the first matching result.
The working principle of the technical scheme is as follows: as shown in FIG. 2, a project creation request is received from a user, wherein the user has permission to create a project, and a first number of projects are created based on project content corresponding to the project creation request, wherein the project content is input by the user, and the project content can be a project name, a project plan, a project profile, a project principal, and the like. By way of example, project A and project B are created; receiving a sub-account creating request of a user, wherein the user has the permission of creating the sub-accounts, creating a second number of sub-accounts according to the sub-account creating request, and the sub-accounts can be logged in and used by developers and operation and maintenance personnel; by way of example, sub-account A and sub-account B are created; matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result; the first preset rule includes that each sub-account can exist in a plurality of projects simultaneously for resource operation without interfering other resources. For example, the sub account a and the sub account B are responsible for managing the project a, and the sub account a can manage the project B at the same time; dividing the authority operation functions of the sub-accounts with the second number based on a second preset rule according to the first matching result; the second preset rule comprises the division of different authority operation functions between different sub-accounts in the same project. For example, in item a, a sub-account a has an authority operation function a and an authority operation function B, and the sub-account B has an authority operation function B; in item B, the sub-account a has only the authority operation function a. The authority operation function can be financial statistics, financial scheduling and the like.
The beneficial effects of the above technical scheme are that: each sub-account can be logged in and managed by a project member, and the project member can be a developer or an operation and maintenance person; through setting and dividing the items, the item members and the authority of the item members respectively, the work efficiency of the item members can be effectively improved, meanwhile, the information of the items and the users can be effectively protected, and the risk of information safety leakage is greatly reduced.
In an embodiment, when a first number of projects are created according to the project content corresponding to the project creation request and a second number of sub-accounts are created according to the sub-account creation request, the project content and the sub-accounts can be queried, and the progress of creating the projects can be accurately mastered through querying the entry condition of the projects, such as which information of the projects has been entered and which information has not been entered; by inquiring the sub-accounts, the progress of creating the sub-accounts, for example, how many sub-accounts are created, can be accurately mastered.
FIG. 3 is a flow diagram of creating a project, according to one embodiment of the invention; as shown in fig. 3, according to some embodiments of the invention, the project content includes project requirement information, project feasibility analysis information, project cost and period information;
the creating of the first number of items according to the item content corresponding to the item creation request includes steps S21-S23:
s21, respectively carrying out evaluation and scoring on project demand information, project feasibility analysis information, project cost and cycle information according to the project content to obtain a first score, a second score and a third score;
s22, calculating a total project score according to the first score, the second score and the third score, and judging whether the total project score is greater than or equal to a preset project score;
and S23, when the total item score is judged to be larger than or equal to the preset item score, creating a first number of items according to the item content corresponding to the item creating request.
The working principle of the technical scheme is as follows: the project content comprises project demand information, project feasibility analysis information, project cost and cycle information, the project demand information, the project feasibility analysis information, the project cost and the cycle information are respectively evaluated and graded according to the project content to obtain a first score, a second score and a third score, the total score of the project is calculated according to the first score, the second score and the third score, whether the total score of the project is larger than or equal to a preset project score or not is judged, the preset project score can be 85, and when the total score of the project is judged to be larger than or equal to the preset project score, the project is created according to the project content corresponding to the project creation request. Specifically, the total score of the project is 90 points and is greater than the score of a preset project score of 85 points, and the project can be created; if the total score of the project is 80 points and is less than the preset project score of 85 points, the project is not created.
The beneficial effects of the above technical scheme are as follows: when the project is created, the project is scored according to the content of the project, the project is analyzed, and the project with the total score of the project larger than or equal to the preset score of the project is created. And the projects with the total project score smaller than the preset project score are not created, so that excellent projects can be screened out, the quality of the created projects is ensured, and the income is improved.
According to some embodiments of the present invention, the total project score is calculated according to the first score, the second score and the third score, and the total project score is determined according to the following algorithm:
the total item score:
M=M1×P1+M2×P2+M3×P3
wherein, M1A first score, M, for the project requirement information review score2A second score, M, for project feasibility analysis information review scoring3A third score, P, for the project cost and period information review score1Is the weight, P, of the project requirement information2For the weight, P, of the project feasibility analysis information3Is the weight, P, of the project cost and period information1+P2+P3=1。
The beneficial effects of the above technical scheme are as follows: and calculating according to the first score, the second score, the third score and a preset corresponding weight to obtain the total score of the project, which is more accurate.
FIG. 4 is a flow diagram of creating a sub-account according to one embodiment of the invention; as shown in fig. 4, the sub-account creation request includes security authentication information; the security authentication information includes: identity card information, face information and iris information of the user;
creating a second number of sub-accounts according to the sub-account creation request, including:
s41, acquiring personal information of a user for creating a main account;
s42, judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is larger than or equal to a preset similarity threshold value or not;
and S43, if the similarity between the safety certification information in the sub-account creation request and the personal information is determined to be larger than or equal to a preset similarity threshold, creating a second number of sub-accounts according to the sub-account creation request.
The working principle of the technical scheme is as follows: the sub-account creation request includes security authentication information; the security authentication information includes: identity card information, face information and iris information of the user; when creating the sub-account, creating personal information of the main account according to the user, wherein the personal information comprises identity card information, face information and iris information; and judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold, and creating a second number of sub-accounts according to the sub-account creation request when the similarity between the security authentication information in the sub-account creation request and the personal information is determined to be greater than or equal to the preset similarity threshold. For example, the preset similarity threshold may be 95%, the similarity between the security authentication information in the sub-account creation request and the personal information may be 96%, and the sub-account may be created.
The beneficial effects of the above technical scheme are that: and safety authentication is carried out when the sub-account is created, so that the user creating the sub-account and the user creating the main account are the same user, the information of the project and the user can be effectively protected, and the risk of information safety leakage is greatly reduced.
According to an embodiment of the present invention, whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold is determined, which specifically includes the following steps:
step A, preprocessing the security authentication information in the sub-account creation request;
Figure BDA0002470730840000091
wherein, x'iFor the ith information x in the security authentication informationiIn the preprocessed data, alpha is the mean value of the safety certification information, and tau is an accurate coefficient;
wherein h is xiThe minimum value of possible values, H being xiThe maximum value of possible values;
b, calculating the similarity between the safety authentication information and the personal information;
Figure BDA0002470730840000101
wherein epsilon is the similarity x 'of the safety certification information and the personal information'iFor the ith information x in the security authentication informationiPreprocessed data, yiFor the ith one of the personal informationData, n is the number of information contained in the personal information and is also the number of information contained in the security authentication information;
step C, judging the relation between the similarity and a preset similarity threshold according to the following formula;
k=sgn(ε-a)
in the above formula, k is a relationship value between the similarity and a preset similarity threshold, where when k is 0, the similarity is equal to the preset similarity threshold, and when k is 1, the similarity is greater than the preset similarity threshold; when k is-1, the similarity is smaller than a preset similarity threshold.
Has the beneficial effects that: in the above technical solution, when it is determined whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold, the security authentication information in the sub-account creation request is preprocessed first, then the similarity between the security authentication information and the personal information is calculated, and finally the relationship between the similarity and the preset similarity threshold is determined. According to the technical scheme, the safety certification information in the sub-account creation request is preprocessed, so that information data in the safety certification information are neatly normalized, calculation and comparison are facilitated, the technical scheme can be executed in a computer, a relation value between the similarity and a preset similarity threshold value can be conveniently and visually obtained according to the safety certification information in the sub-account creation request and the personal information, and further the relation between the similarity and the preset similarity threshold value can be known.
FIG. 5 is a flow diagram of obtaining a first match result according to one embodiment of the invention; as shown in fig. 5, the matching the second number of sub-accounts with the first number of items based on a first preset rule to obtain a first matching result includes:
s51, acquiring a project plan corresponding to each project in the first number of projects;
and S52, distributing the required sub-account number according to the project plan to obtain a first matching result.
The working principle of the technical scheme is as follows: acquiring a project plan corresponding to each project in a first quantity of projects, and distributing the required sub-account quantity according to the project plan to obtain a first matching result; the method comprises the steps of dividing a first priority project, a second priority project and a third priority project according to the emergency degree of a project plan, and dividing the first priority project into A number of sub-accounts, the second priority project into B number of sub-accounts and the third priority project into C number of sub-accounts, wherein A is more than B and more than C.
The beneficial effects of the above technical scheme are as follows: and completing in time according to the progress of the project plan.
FIG. 6 is a flow diagram of obtaining a second match result according to one embodiment of the invention; as shown in fig. 6, the project management method further includes: correcting the first matching result to obtain a second matching result; the method comprises the following steps:
s53, acquiring participation data and active data of the sub-accounts distributed by each project in the first matching result;
s54, determining the participation degree score of the sub-account according to the participation data;
s55, determining the activity score of the sub-account according to the activity data;
s56, obtaining the distribution score of the sub-account in the first matching result according to the engagement degree score and the activity degree score;
and S57, respectively judging whether the distribution scores of all the sub-accounts are within the preset score range, screening the sub-accounts which are not within the preset score range, and redistributing to obtain a second distribution result.
The working principle of the technical scheme is as follows: acquiring participation data and active data of sub-accounts distributed to each project in the project in a first matching result, determining participation scores of the sub-accounts according to the participation data, determining activity scores of the sub-accounts according to the active data, and obtaining distribution scores of the sub-accounts in the first matching result according to the participation scores and the activity scores; and respectively judging whether the distribution scores of all the sub-accounts are within a preset score range, screening the sub-accounts which are not within the preset score range, and redistributing to obtain a second distribution result. Specifically, the preset score range is 80-90 minutes, and when the distribution score of the sub-account M is judged to be 70 minutes, the sub-account M has a large promotion space, and needs to be redistributed to improve the utilization efficiency of the sub-account M; and when the distribution score of the sub-account N is judged to be 95 minutes, the load intensity of the sub-account N is high, and in order to ensure the balance among the sub-accounts, the first matching result is corrected to obtain a second matching result, wherein the redistribution is also needed.
The beneficial effects of the above technical scheme are that: the balance among all the sub-accounts can be ensured, and the work efficiency of project members is improved.
According to some embodiments of the invention, the project management method further comprises:
receiving a monitoring request of a user;
and monitoring the items with the first quantity and the sub-accounts with the second quantity according to the monitoring request.
The beneficial effects of the above technical scheme are as follows: the project management system has the advantages that projects of the first quantity and sub-accounts of the second quantity can be monitored, information such as execution progress of the projects and states of the sub-accounts can be known in time, unified and effective management can be conducted on the projects of the first quantity and the sub-accounts of the second quantity, and management efficiency is improved.
FIG. 7 is a block diagram of an item management device according to one embodiment of the present invention; as shown in fig. 7, a second embodiment of the present invention provides an item management apparatus, including:
a first receiving module 1, configured to receive a project creation request of a user;
a first creating module 2, configured to create a first number of items according to item content corresponding to the item creating request;
the second receiving module 3 is used for receiving a sub-account creation request of a user;
a second creating module 4, configured to create a second number of sub-accounts according to the sub-account creation request;
the matching module 5 is configured to match the second number of sub-accounts with the first number of items based on a first preset rule, and obtain a first matching result;
and the function division module 6 is used for dividing the authority operation functions of the sub-accounts of the second number according to the first matching result and based on a second preset rule.
The beneficial effects of the above technical scheme are as follows: each sub-account can be logged in and managed by a project member, and the project member can be a developer or an operation and maintenance person; through setting and dividing the items, the item members and the authority of the item members respectively, the work efficiency of the item members can be effectively improved, meanwhile, the information of the items and the users can be effectively protected, and the risk of information safety leakage is greatly reduced.
As will be appreciated by one skilled in the art, embodiments of the present invention may be provided as a method, system, or computer program product. Accordingly, the present invention may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present invention may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, optical storage, and the like) having computer-usable program code embodied therein.
The present invention has been described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It will be understood that each flow and/or block of the flowchart illustrations and/or block diagrams, and combinations of flows and/or blocks in the flowchart illustrations and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory produce an article of manufacture including instruction means which implement the function specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus to cause a series of operational steps to be performed on the computer or other programmable apparatus to produce a computer implemented process such that the instructions which execute on the computer or other programmable apparatus provide steps for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (6)

1. A project management method is suitable for a background management software platform and is characterized by comprising the following steps:
receiving a project creation request of a user;
creating a first number of items according to item contents corresponding to the item creating request;
receiving a sub-account creation request of a user;
creating a second number of sub-accounts according to the sub-account creation request;
matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result;
performing authority operation function division on the sub-accounts of the second number based on a second preset rule according to the first matching result;
the project content comprises project demand information, project feasibility analysis information, project cost and period information;
the creating a first number of items according to the item content corresponding to the item creating request includes:
respectively evaluating and scoring the project demand information, the project feasibility analysis information, the project cost and the period information according to the project content to obtain a first score, a second score and a third score;
calculating a total project score according to the first score, the second score and the third score, and judging whether the total project score is greater than or equal to a preset project score;
when the total item score is judged to be larger than or equal to a preset item score, a first number of items are created according to item contents corresponding to the item creation request;
calculating the total item score according to the first score, the second score and the third score, and judging the total item score, wherein the algorithm is as follows:
the total item score is:
Figure 684588DEST_PATH_IMAGE001
wherein the content of the first and second substances,
Figure 840763DEST_PATH_IMAGE002
a first score is scored for project requirement information review,
Figure 903397DEST_PATH_IMAGE003
a second score obtained by scoring for project feasibility analysis information review,
Figure 791194DEST_PATH_IMAGE004
a third score obtained by scoring the project expense and period information review,
Figure 230266DEST_PATH_IMAGE005
is the weight value of the project requirement information,
Figure 506526DEST_PATH_IMAGE006
for the weight of the project feasibility analysis information,
Figure 740061DEST_PATH_IMAGE007
the weight of the project cost and the period information,
Figure 367352DEST_PATH_IMAGE008
the sub-account creation request includes security authentication information; the security authentication information includes: identity card information, face information and iris information of the user;
creating a second number of sub-accounts according to the sub-account creation request, comprising:
acquiring personal information of a user for creating a main account;
judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold value or not;
if the similarity between the security authentication information in the sub-account creation request and the personal information is determined to be greater than or equal to a preset similarity threshold, creating a second number of sub-accounts according to the sub-account creation request;
judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold, specifically comprising the following steps:
step A, preprocessing the security authentication information in the sub-account creation request;
Figure 344535DEST_PATH_IMAGE009
wherein the content of the first and second substances,
Figure 226035DEST_PATH_IMAGE010
as the first in the security authentication information
Figure 896050DEST_PATH_IMAGE011
Information of a person
Figure 745058DEST_PATH_IMAGE012
The data after the pre-processing is carried out,
Figure 260353DEST_PATH_IMAGE013
is the average value of the security authentication information,
Figure 776785DEST_PATH_IMAGE014
is an accuracy factor;
b, calculating the similarity between the safety authentication information and the personal information;
Figure 352122DEST_PATH_IMAGE015
wherein, the first and the second end of the pipe are connected with each other,
Figure 704737DEST_PATH_IMAGE016
for the similarity of the security authentication information and the personal information,
Figure 23723DEST_PATH_IMAGE010
as the first in the security authentication information
Figure 129083DEST_PATH_IMAGE011
Personal information
Figure 875322DEST_PATH_IMAGE012
The data after the pre-processing is carried out,
Figure 698921DEST_PATH_IMAGE017
is the first in the personal information
Figure 821598DEST_PATH_IMAGE011
The data of the individual pieces of information,
Figure 532196DEST_PATH_IMAGE018
the number of information contained in the personal information is the number of information contained in the security authentication information;
step C, judging the relation between the similarity and a preset similarity threshold according to the following formula;
Figure 449337DEST_PATH_IMAGE019
in the above-mentioned formula,
Figure 25811DEST_PATH_IMAGE020
is the relation value between the similarity and a preset similarity threshold value
Figure 686600DEST_PATH_IMAGE021
When the similarity is equal to the preset similarity threshold value, when the similarity is equal to the preset similarity threshold value
Figure 500972DEST_PATH_IMAGE022
If so, the similarity is greater than a preset similarity threshold; when in use
Figure 854593DEST_PATH_IMAGE023
When the similarity is smaller than a preset similarity threshold value,
Figure 394728DEST_PATH_IMAGE024
is a preset similarity threshold.
2. The project management method of claim 1,
the first preset rule comprises that each sub-account can exist in a plurality of projects simultaneously for resource operation without interfering other resources;
the second preset rule comprises the division of different authority operation functions between different sub-accounts in the same project.
3. The project management method of claim 1, wherein the matching the second number of sub-accounts with the first number of projects based on a first preset rule to obtain a first matching result comprises:
acquiring a project plan corresponding to each project in a first number of projects;
and acquiring a first matching result according to the sub-account number required by the project plan distribution.
4. The project management method of claim 3, further comprising: correcting the first matching result to obtain a second matching result; the method comprises the following steps:
acquiring participation data and active data of sub accounts distributed by each project in the first matching result;
determining the participation degree score of the sub-account according to the participation data;
determining an activity score of a sub-account according to the activity data;
obtaining the distribution score of the sub-account in a first matching result according to the engagement score and the activity score;
and respectively judging whether the distribution scores of all the sub-accounts are within a preset score range, screening the sub-accounts which are not within the preset score range, and redistributing to obtain a second distribution result.
5. The project management method according to claim 1, further comprising:
receiving a monitoring request of a user;
and monitoring the items with the first quantity and the sub-accounts with the second quantity according to the monitoring request.
6. An item management apparatus, comprising:
the first receiving module is used for receiving a project creation request of a user;
a first creating module, configured to create a first number of items according to item content corresponding to the item creating request;
the second receiving module is used for receiving a sub-account creating request of a user;
the second creating module is used for creating a second number of sub-accounts according to the sub-account creating request;
the matching module is used for matching the sub-accounts with the second quantity with the items with the first quantity based on a first preset rule to obtain a first matching result;
the function division module is used for dividing the authority operation functions of the sub-accounts with the second number based on a second preset rule according to the first matching result;
the project content comprises project demand information, project feasibility analysis information, project cost and period information;
the first creation module includes:
respectively evaluating and scoring project demand information, project feasibility analysis information, project cost and period information according to the project content to obtain a first score, a second score and a third score;
calculating a total project score according to the first score, the second score and the third score, and judging whether the total project score is greater than or equal to a preset project score;
when the total score of the project is judged to be larger than or equal to the preset project score, a first number of projects are created according to the project content corresponding to the project creation request;
calculating the total item score according to the first score, the second score and the third score, and judging the total item score, wherein the algorithm is as follows:
the total item score is:
Figure 859208DEST_PATH_IMAGE025
wherein the content of the first and second substances,
Figure 528086DEST_PATH_IMAGE002
a first score is scored for project requirement information review,
Figure 318188DEST_PATH_IMAGE003
a second score obtained by scoring for project feasibility analysis information review,
Figure 338096DEST_PATH_IMAGE004
a third score obtained by scoring the project expense and period information review,
Figure 340688DEST_PATH_IMAGE005
is the weight value of the project requirement information,
Figure 129652DEST_PATH_IMAGE006
in order to analyze the weight value of the information for the feasibility of the project,
Figure 841387DEST_PATH_IMAGE007
as the weight of the project cost and the period information,
Figure 83013DEST_PATH_IMAGE008
the sub-account creation request includes security authentication information; the security authentication information includes: identity card information, face information and iris information of the user;
creating a second number of sub-accounts according to the sub-account creation request, comprising:
acquiring personal information of a user for creating a main account;
judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold value or not;
if the similarity between the safety authentication information in the sub-account creation request and the personal information is determined to be larger than or equal to a preset similarity threshold, creating a second number of sub-accounts according to the sub-account creation request;
judging whether the similarity between the security authentication information in the sub-account creation request and the personal information is greater than or equal to a preset similarity threshold, specifically comprising the following steps:
step A, preprocessing the security authentication information in the sub-account creation request;
Figure 154874DEST_PATH_IMAGE009
wherein the content of the first and second substances,
Figure 63924DEST_PATH_IMAGE010
as the first in the security authentication information
Figure 664670DEST_PATH_IMAGE011
Information of a person
Figure 659170DEST_PATH_IMAGE012
The data after the pre-processing is carried out,
Figure 19876DEST_PATH_IMAGE013
is the average value of the security authentication information,
Figure 783432DEST_PATH_IMAGE014
is an accuracy factor;
b, calculating the similarity between the safety authentication information and the personal information;
Figure 555079DEST_PATH_IMAGE026
wherein the content of the first and second substances,
Figure 36876DEST_PATH_IMAGE016
for the similarity of the security authentication information and the personal information,
Figure 450540DEST_PATH_IMAGE010
as the first in the security authentication information
Figure 68603DEST_PATH_IMAGE011
Information of a person
Figure 27463DEST_PATH_IMAGE012
The data after the pre-processing is carried out,
Figure 730977DEST_PATH_IMAGE017
is the first in the personal information
Figure 682752DEST_PATH_IMAGE011
The data of the individual pieces of information,
Figure 420901DEST_PATH_IMAGE018
the number of information contained in the personal information is the number of information contained in the security authentication information;
step C, judging the relation between the similarity and a preset similarity threshold according to the following formula;
Figure 534351DEST_PATH_IMAGE019
in the above-mentioned formula,
Figure 725161DEST_PATH_IMAGE020
is the relation value between the similarity and a preset similarity threshold value when
Figure 228430DEST_PATH_IMAGE021
When the similarity is equal to the preset similarity threshold value, when the similarity is equal to the preset similarity threshold value
Figure 821085DEST_PATH_IMAGE022
If so, the similarity is greater than a preset similarity threshold; when in use
Figure 371015DEST_PATH_IMAGE023
When the similarity is smaller than a preset similarity threshold value,
Figure 314700DEST_PATH_IMAGE024
is a preset similarity threshold.
CN202010352691.7A 2020-04-28 2020-04-28 Project management method and device Active CN111612415B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010352691.7A CN111612415B (en) 2020-04-28 2020-04-28 Project management method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010352691.7A CN111612415B (en) 2020-04-28 2020-04-28 Project management method and device

Publications (2)

Publication Number Publication Date
CN111612415A CN111612415A (en) 2020-09-01
CN111612415B true CN111612415B (en) 2022-07-22

Family

ID=72199711

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010352691.7A Active CN111612415B (en) 2020-04-28 2020-04-28 Project management method and device

Country Status (1)

Country Link
CN (1) CN111612415B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114115003B (en) * 2021-11-12 2023-08-22 浙江银盾云科技有限公司 Remote start-stop control platform
CN114253518B (en) * 2022-03-01 2022-05-31 上海金仕达软件科技有限公司 Intelligent project management method and system

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130097092A1 (en) * 2011-01-28 2013-04-18 Brian Tully Unclaimed property method and system
CN110223040B (en) * 2019-05-31 2024-02-09 深圳市元征科技股份有限公司 Project management method and device, electronic equipment and storage medium
CN110309635A (en) * 2019-06-25 2019-10-08 深圳前海微众银行股份有限公司 Management method, device, equipment and the computer storage medium of data quality model
CN110417820A (en) * 2019-09-05 2019-11-05 曙光信息产业(北京)有限公司 Processing method, device and the readable storage medium storing program for executing of single-node login system

Also Published As

Publication number Publication date
CN111612415A (en) 2020-09-01

Similar Documents

Publication Publication Date Title
US20190130407A1 (en) Real-time cross-channel fraud protection
CN103970851B (en) The method that magnanimity Credential data directly provides general headquarters of large-size enterprise group financial statement
US20110055852A1 (en) Event processing for detection of suspicious financial activity
CN108256810B (en) Insurance business approval process processing method and device
CN111612415B (en) Project management method and device
US20220030025A1 (en) Information technology security assessment model for process flows and associated automated remediation
CN110084606B (en) Risk control method, apparatus, computer device and storage medium
KR101368103B1 (en) Risk-management device
CN112581000A (en) Enterprise risk index calculation method and device
CN110807643A (en) User trust evaluation method, device and equipment
CN115688110A (en) Financial Internet of things platform equipment early warning method and device
CN111353901A (en) Risk identification monitoring method and device and electronic equipment
CN113111095B (en) Intelligent information management method and system
KR20220115357A (en) A method and apparatus for generating future demand forecast data based on attention mechanism
CN116662387A (en) Service data processing method, device, equipment and storage medium
CN115208893B (en) Resource scheduling method and device
CN114637674A (en) Application evaluation method and device, electronic equipment and computer storage medium
CN112613978B (en) Bank capital sufficiency prediction method and device, electronic equipment and medium
Krahulec et al. Business impact analysis in the process of Business continuity management
CN110852602A (en) Data monitoring method and device based on machine learning
KR20140029994A (en) Method for verifying sutability of loss given default/exposure at default
CN112101816B (en) Intelligent recommendation method and device for audit plan
Khlevna et al. Development of the Automated Fraud Detection System Concept in Payment Systems
Kamos et al. Credit rating using a hybrid voting ensemble
Ergashevich et al. Risk Management System And Factors Affecting The Level Of Risk In The Customs Authorities Of Uzbekistan

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant