CN111535362A - PE water meter well construction method - Google Patents
PE water meter well construction method Download PDFInfo
- Publication number
- CN111535362A CN111535362A CN202010395438.XA CN202010395438A CN111535362A CN 111535362 A CN111535362 A CN 111535362A CN 202010395438 A CN202010395438 A CN 202010395438A CN 111535362 A CN111535362 A CN 111535362A
- Authority
- CN
- China
- Prior art keywords
- well
- water meter
- cover
- water
- surface bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/124—Shaft entirely made of synthetic material
Abstract
A PE water meter well construction method comprises the following construction steps: (1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs; (2) drilling a hole on the well wall: the height of the hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes; (3) backfilling: tamping one layer by one layer and backfilling the tamping one layer to the well neck; (4) installing a water meter: putting the water meter into the inner cavity of the water meter well and connecting the water meter with a water pipe; (5) covering the well cover: and (3) mounting a ground surface bearing well cover support on backfill lime soil at the height of the well neck in the pit body, and pouring the ground surface bearing well cover on the ground surface bearing well cover support by using concrete. The water meter well in the pit body is integrally injection-molded, so that the bottom leakage of the well body is effectively prevented, the later maintenance and meter reading work is facilitated, the top of the well body is designed by the double cover bodies of the plastic well cover and the earth surface bearing well cover, the leakage of the top of the well body is prevented, and the water meter well cover is prevented from being repeatedly rolled and damaged by a vehicle passing by the water meter well cover by the additionally arranged bearing well cover.
Description
Technical Field
The invention relates to the field of water meter wells, in particular to a PE water meter well construction method.
Background
A brick structure well is always used in the application of a water meter well, but the well has a plurality of problems in the using process, including that the construction period is long, the main structure is not tight, serious water accumulation in the well is easily caused, and the like. In order to overcome the defects of the water meter well with the brick structure, the water meter well with a prefabricated member of a steel structure and a concrete structure is designed. The prefabricated water meter well comprises a well body and a well cover, wherein the well body and the well cover are both formed by a reinforced concrete structure and a steel surface beam upright post, and the water meter is placed in the well body. The existing prefabricated water meter well has the following defects: heavy weight, which is inconvenient to carry; when bearing the weight on the well cover, the well cover is easy to collapse, namely the bearing capacity is poor; the water pipe and the water meter well are not hermetically connected or are sealed by coating glue, water can permeate into the water meter well along the surface of the water pipe if the water pipe and the water meter well are not hermetically connected, the water pipe is troublesome to replace if the water pipe and the water meter well are sealed by coating the glue, and the water pipe can be buried after the glue is solidified, so that the construction period is prolonged; the vibration generated on the ground can cause the vibration of the water meter in the well body, and the vibration of the water meter is easy to generate part damage and joint cracking and water seepage. When the existing plastic water meter well is generally installed, concrete is still needed to be paved on the bottom surface of a foundation pit at the bottom, and then the periphery is backfilled after the water meter well is installed. Therefore, underground water can also infiltrate into the well, and the maintenance and meter reading are not convenient later. And the well lid of present plastics water gauge well all adopts plastics to make, often is rolled by the vehicle of passing by on the road and destroys for plastics water gauge well can not the wide use.
Disclosure of Invention
The invention aims to solve the problems and provides a plastic water meter well construction method which can effectively prevent the water meter well from leaking and can protect a plastic well cover.
The technical scheme adopted by the invention is as follows:
a PE water meter well construction method comprises the following construction steps:
(1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs, wherein the diameter of the well body is larger than that of the plastic water meter well, the depth of the well body is larger than the water meter well by a certain height, and the height which is higher than that of the water meter well is used for installing a ground surface bearing well cover;
(2) drilling a hole on the well wall: the height of the hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes, after the water outlet pipes are opened, the sealing ring is firstly installed at the hole opening position of the well wall, and in order to reduce the penetration resistance, a little washing agent or soapy water is coated on the head part of the pipeline to penetrate from outside to inside;
(3) backfilling: covering a plastic cover of the well mouth to prevent foreign matters from entering the well, and tamping and backfilling 2:8 lime soil or two lime soils layer by layer to the neck of the well;
(4) installing a water meter: uncovering the plastic cover of the well mouth, placing the water meter in the inner cavity of the water meter well and connecting the water meter with the water pipe;
(5) covering the well cover: and (3) mounting a ground surface bearing well cover support on backfill lime soil at the height of a well neck in the pit body, tightly covering and sealing a water meter well plastic cover, measuring the height of the center and the periphery, and pouring the ground surface bearing well cover on the ground surface bearing well cover support by using concrete.
And (2) the diameter of the pit body in the step (1) is 50-60 cm larger than that of the plastic water meter well.
And (2) in the step (1), the depth of the pit body is 8-10 cm greater than the height of the water meter well.
And (4) when the ash soil or the two-ash soil is backfilled into the pit body in the step (3), well body and pipeline protection work is well done, and irregular garbage objects such as sharp hard objects and the like are prevented from being touched with the well body and the pipeline.
And (5) the outer edge of the earth surface bearing well cover is larger than the outer edge of the top of the water meter well, so that direct bearing of the water meter well in the pit body is avoided.
The invention has the beneficial effects that: the water meter well in the pit body is integrally injection-molded, leakage at the bottom of the well body is effectively prevented, later maintenance and meter reading work are facilitated, the water pipe is installed in the hole formed in the side wall of the well body in a strictly sealed mode, the top of the well body is designed through the plastic well cover and the earth surface bearing well cover, leakage at the top of the well body is prevented, meanwhile, due to the fact that the bearing well cover is additionally arranged, the water meter well cover is prevented from being repeatedly rolled and damaged by vehicles passing by the water meter well cover, and maintenance.
Detailed Description
A PE water meter well construction method comprises the following construction steps:
(1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs, wherein the diameter of a well body is 50-60 cm larger than that of the plastic water meter well, the depth of the well body is 8-10 cm larger than that of the water meter well, and the height of the well body is used for installing a ground surface bearing well cover;
(2) drilling a hole on the well wall: the height of the hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes, after the water outlet pipes are opened, the sealing ring is firstly installed at the hole opening position of the well wall, and in order to reduce the penetration resistance, a little washing agent or soapy water is coated on the head part of the pipeline to penetrate from outside to inside;
(3) backfilling: covering a plastic cover of a well mouth to prevent foreign matters from entering the well, tamping and backfilling 2:8 lime soil or two layers of lime soil to the neck of the well, and protecting the well body and the pipeline when backfilling the lime soil in the well body to prevent irregular garbage objects such as sharp hard objects and the like from contacting the well body and the pipeline;
(4) installing a water meter: uncovering the plastic cover of the well mouth, placing the water meter in the inner cavity of the water meter well and connecting the water meter with the water pipe;
(5) covering the well cover: installing a ground surface bearing well cover support on backfill lime soil at the height of a well neck in the pit body, covering and sealing a water meter well plastic cover tightly, measuring the height of the center and the height of the periphery, pouring the ground surface bearing well cover on the ground surface bearing well cover support by using concrete, wherein the outer edge of the ground surface bearing well cover is larger than the outer edge of the top of the water meter well so as to avoid direct bearing of the water meter well in the pit body.
Example 1
A PE water meter well construction method comprises the following construction steps:
(1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs, wherein the diameter of a pit digging body is larger than 50cm of the plastic water meter well, the depth of the pit digging body is larger than 8cm of the height of the water meter well, the height of the pit digging body is used for installing a ground surface bearing well cover, the diameter of the dug well body is 120cm, and the height of the dug well body is 120 cm;
(2) drilling a hole on the well wall: the height of a hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes, the aperture of a water inlet formed in the side wall of a well body is 10-15 cm, the aperture of a water outlet formed in the side wall of the well body is 2.5-8 cm, after a water pipe hole is formed, a sealing ring is firstly installed at the hole opening position of the well wall, and in order to reduce penetration resistance, a small amount of detergent or soapy water is coated on the head of a pipeline to penetrate from outside;
(3) backfilling: covering a plastic cover of a well mouth to prevent foreign matters from entering the well, tamping and backfilling 2:8 lime soil layer by layer to the neck of the well, and when the lime soil is backfilled into the well body, protecting the well body and the pipeline to prevent irregular garbage such as sharp and hard objects from contacting the well body and the pipeline;
(4) installing a water meter: uncovering the plastic cover of the well mouth, placing the water meter in the inner cavity of the water meter well and connecting the water meter with the water pipe;
(5) covering the well cover: installing a ground surface bearing well cover support on backfill lime soil at the height of a well neck in a pit body, tightly covering and sealing a water meter well plastic cover, measuring the height of the center and the periphery of the top of the water meter well, and pouring ground surface bearing well covers with concrete on the ground surface bearing well cover support when the center of the top of the water meter well is consistent with the height of the ground surface bearing well cover support, wherein the outer edge of the ground surface bearing well cover is larger than the outer edge of the top of the water meter well so as to avoid direct bearing of the water meter well in the pit body, and the thickness of the ground surface bearing well cover is 8cm at the moment, so that the water meter well is prevented.
Example 2
A PE water meter well construction method comprises the following construction steps:
(1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs, wherein the diameter of a pit digging body is larger than 55cm of the plastic water meter well, the depth of the pit digging body is larger than 9cm of the water meter well, the height of the pit digging body is used for installing a ground surface bearing well cover, the diameter of the dug well body is 200cm, and the height of the dug well body is 180 cm;
(2) drilling a hole on the well wall: the height of a hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes, the aperture of a water inlet formed in the side wall of the well body is 10-15 cm, the aperture of a water outlet formed in the side wall of the well body is 5-10 cm, after a water pipe hole is formed, a sealing ring is firstly installed at the hole opening position of the well wall, and in order to reduce penetration resistance, a little washing agent or soapy water is coated on the head of a pipeline to penetrate from outside to;
(3) backfilling: covering a well mouth plastic cover to prevent foreign matters from entering the well, tamping and backfilling the well neck part by two layers of lime soil one by one, and performing protection work on a well body and a pipeline when the two layers of lime soil are backfilled in the well body to prevent irregular garbage objects such as sharp and hard objects and the like from being contacted with the well body and the pipeline;
(4) installing a water meter: uncovering the plastic cover of the well mouth, placing the water meter in the inner cavity of the water meter well and connecting the water meter with the water pipe;
(5) covering the well cover: installing a ground surface bearing well cover support on backfill lime soil at the height of a well neck in a pit body, tightly covering and sealing a water meter well plastic cover, measuring the height of the center and the periphery of the top of the water meter well, and pouring ground surface bearing well covers with concrete on the ground surface bearing well cover support when the center of the top of the water meter well is consistent with the height of the ground surface bearing well cover support, wherein the outer edge of the ground surface bearing well cover is larger than the outer edge of the top of the water meter well so as to avoid direct bearing of the water meter well in the pit body, and the thickness of the ground surface bearing well cover is 8cm at the moment, so that the water meter well is prevented.
Example 3
A PE water meter well construction method comprises the following construction steps:
(1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs, wherein the diameter of a pit digging body is larger than 60cm of the plastic water meter well, the depth of the pit digging body is larger than 10cm of the water meter well, the height of the pit digging body is used for installing a ground surface bearing well cover, the diameter of the dug well body is 250cm, and the height of the dug well body is 200 cm;
(2) drilling a hole on the well wall: the height of a hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes, the aperture of a water inlet formed in the side wall of the well body is 15-18 cm, the aperture of a water outlet formed in the side wall of the well body is 8-15 cm, after a water pipe hole is opened, a sealing ring is firstly installed at the hole opening position of the well wall, and in order to reduce penetration resistance, a little washing agent or soapy water is coated on the head of a pipeline to penetrate from outside to;
(3) backfilling: covering a well mouth plastic cover to prevent foreign matters from entering the well, tamping and backfilling the well neck part by two layers of lime soil one by one, and performing protection work on a well body and a pipeline when the two layers of lime soil are backfilled in the well body to prevent irregular garbage objects such as sharp and hard objects and the like from being contacted with the well body and the pipeline;
(4) installing a water meter: uncovering the plastic cover of the well mouth, placing the water meter in the inner cavity of the water meter well and connecting the water meter with the water pipe;
(5) covering the well cover: the method comprises the steps of installing a ground surface bearing well cover support on backfill lime soil at the height of a well neck in a pit body, tightly covering and sealing a water meter well plastic cover, measuring the height of the center and the periphery of the top of the water meter well, pouring ground surface bearing well covers on the ground surface bearing well cover support by concrete when the center of the top of the water meter well is consistent with the height of the ground surface bearing well cover support, wherein the outer edge of the ground surface bearing well cover is larger than the outer edge of the top of the water meter well so as to prevent the water meter well in the pit body from directly bearing, and the thickness of the ground surface bearing well cover is 10cm at the moment, so that the.
The embodiments of the present invention have been described in detail, but the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.
Claims (5)
1. A PE water meter well construction method is characterized by comprising the following construction steps:
(1) excavating a pit body: selecting plastic water meter wells of different specifications and models according to actual needs, wherein the diameter of the well body is larger than that of the plastic water meter well, the depth of the well body is larger than the water meter well by a certain height, and the height which is higher than that of the water meter well is used for installing a ground surface bearing well cover;
(2) drilling a hole on the well wall: the height of the hole opening point and the number of the holes are determined according to the outer diameter and the number of the water outlet pipes, after the water outlet pipes are opened, the sealing ring is firstly installed at the hole opening position of the well wall, and in order to reduce the penetration resistance, a little washing agent or soapy water is coated on the head part of the pipeline to penetrate from outside to inside;
(3) backfilling: covering a plastic cover of the well mouth to prevent foreign matters from entering the well, and tamping and backfilling 2:8 lime soil or two lime soils layer by layer to the neck of the well;
(4) installing a water meter: uncovering the plastic cover of the well mouth, placing the water meter in the inner cavity of the water meter well and connecting the water meter with the water pipe;
(5) covering the well cover: and (3) mounting a ground surface bearing well cover support on backfill lime soil at the height of a well neck in the pit body, tightly covering and sealing a water meter well plastic cover, measuring the height of the center and the periphery, and pouring the ground surface bearing well cover on the ground surface bearing well cover support by using concrete.
2. The PE water meter well construction method as claimed in claim 1, wherein the diameter of the pit body in the step (1) is 50-60 cm larger than that of the plastic water meter well.
3. The PE water meter well construction method as claimed in claim 1, wherein the depth of the pit body in the step (1) is 8-10 cm greater than the height of the water meter well.
4. The PE water meter well construction method as claimed in claim 1, wherein protection of the well body and the pipeline is performed when the pit body is backfilled with lime soil or lime-clay soil in the step (3) to prevent sharp hard objects and irregular garbage objects from touching the well body and the pipeline.
5. The PE water meter well construction method according to claim 1, wherein in the step (5), the outer edge of the earth surface bearing well cover is larger than the outer edge of the top of the water meter well, so that direct bearing of the water meter well in the pit body is avoided.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010395438.XA CN111535362A (en) | 2020-05-12 | 2020-05-12 | PE water meter well construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010395438.XA CN111535362A (en) | 2020-05-12 | 2020-05-12 | PE water meter well construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111535362A true CN111535362A (en) | 2020-08-14 |
Family
ID=71971929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010395438.XA Pending CN111535362A (en) | 2020-05-12 | 2020-05-12 | PE water meter well construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111535362A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2939158A1 (en) * | 2008-12-01 | 2010-06-04 | Persohn Sa | Modular buried manhole for receiving water meter, has tubular segments whose peripheral wall is equipped with annular flange forming internal annular braced stiffener and external annular braced stiffeners |
CN202831065U (en) * | 2012-04-26 | 2013-03-27 | 北京仁创科技集团有限公司 | Filter well |
CN107964984A (en) * | 2018-01-19 | 2018-04-27 | 齐建军 | A kind of new closed composite plastic inspection shaft and its manufacture craft |
CN208088346U (en) * | 2018-03-02 | 2018-11-13 | 天津泰达津联自来水有限公司 | Closing type composite plastic water meter well |
CN208472781U (en) * | 2018-07-12 | 2019-02-05 | 山东省水利科学研究院 | It is assembled can load-bearing concentrate water meter chamber |
-
2020
- 2020-05-12 CN CN202010395438.XA patent/CN111535362A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2939158A1 (en) * | 2008-12-01 | 2010-06-04 | Persohn Sa | Modular buried manhole for receiving water meter, has tubular segments whose peripheral wall is equipped with annular flange forming internal annular braced stiffener and external annular braced stiffeners |
CN202831065U (en) * | 2012-04-26 | 2013-03-27 | 北京仁创科技集团有限公司 | Filter well |
CN107964984A (en) * | 2018-01-19 | 2018-04-27 | 齐建军 | A kind of new closed composite plastic inspection shaft and its manufacture craft |
CN208088346U (en) * | 2018-03-02 | 2018-11-13 | 天津泰达津联自来水有限公司 | Closing type composite plastic water meter well |
CN208472781U (en) * | 2018-07-12 | 2019-02-05 | 山东省水利科学研究院 | It is assembled can load-bearing concentrate water meter chamber |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106759449B (en) | Rock-based seabed offshore wind turbine rock-socketed single-pile foundation and construction method thereof | |
CN103266638B (en) | A kind of detection method of underground concrete diaphragm wall breakthrough position | |
CN109881694A (en) | A kind of constructing structure blocked for foundation pit substrate Sand and method | |
CN105203080B (en) | Roadbed settlement observation device and observation method thereof | |
CN206090653U (en) | Anchor rod static pressure pile slip casting structure | |
CN108086358B (en) | Large-caliber long-distance multi-pipe same-ditch immersed pipe construction method | |
CN103161173B (en) | Shut-in construction method of pumping shaft in basement base plate | |
CN102465525B (en) | The Deep Embedded Piles of freezing and defrosting area plane vertical control point and method for embedding thereof | |
CN113373962B (en) | Combined leakage stoppage construction method for deep foundation pit | |
CN111365020A (en) | Back-pressure backfill construction method suitable for biased hole entry under poor geological conditions | |
CN203684204U (en) | Plastic flow soft foundation reinforced structure | |
CN111535362A (en) | PE water meter well construction method | |
CN104099946A (en) | Novel jacking pipe intersegment overhaul well | |
CN109736355B (en) | Reverse construction method basement construction method in factory building transformation | |
CN216965781U (en) | Landfill area groundwater is restoreed and is monitored access structure | |
CN111139854A (en) | Construction method for treating piping of exploration hole of foundation pit by drainage grouting method | |
CN112816660B (en) | Centrifugal model test device and method for researching underground continuous wall construction environmental effect | |
CN206625238U (en) | A kind of assembled waveform steel liner plate supporting construction of Circular Pit | |
CN205066754U (en) | Subgrade settlement observation device | |
JPS63181819A (en) | Fitting of measuring bar for settlement of object buried under ground | |
CN107975376A (en) | Tunneling shield push pipe and vertical duct connection structure and construction method | |
CN208331799U (en) | High-precision positioner for water pipe leak detection | |
CN208455573U (en) | A kind of full library basin Anti-seeping technology structure of karst area | |
CN211951889U (en) | Protective measure for buried flexible gas pipeline | |
CN212801527U (en) | Structure is buried underground to a fender of bored concrete pile is dug soon to major diameter |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200814 |