CN111523166A - 一种基于bim技术的大体量钢结构安装深化施工方法 - Google Patents
一种基于bim技术的大体量钢结构安装深化施工方法 Download PDFInfo
- Publication number
- CN111523166A CN111523166A CN202010302907.9A CN202010302907A CN111523166A CN 111523166 A CN111523166 A CN 111523166A CN 202010302907 A CN202010302907 A CN 202010302907A CN 111523166 A CN111523166 A CN 111523166A
- Authority
- CN
- China
- Prior art keywords
- steel structure
- construction
- installation
- bim
- bim technology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T2210/00—Indexing scheme for image generation or computer graphics
- G06T2210/04—Architectural design, interior design
Abstract
本发明公开了一种基于BIM技术的大体量钢结构安装深化施工方法,涉及建筑安装技术领域。该基于BIM技术的大体量钢结构安装深化施工方法,包含以下步骤:步骤1.熟悉设计文件以及施工图纸,对于其中存在的问题及时与设计进行沟通交流,及时解决问题;步骤2.根据项目特点选用BIM技术软件。该基于BIM技术的大体量钢结构安装深化施工方法,利用并发挥BIM技术的优势,使得大体量钢结构安装施工更加高效,更加可靠,提高钢结构钢构件材料加工生产以及使用率,避免浪费,在进行施工前期便将施工过程、安装信息以及大体量钢结构安装成型以后的安装效果以360度无死角的展现在眼前,能够很好的控制和指导现场施工,提高了工程建设的效益。
Description
技术领域
本发明涉及建筑安装技术领域,具体为一种基于BIM技术的大体量钢结构安装深化施工方法。
背景技术
BIM技术目前已经在全球范围内得到业界的广泛认可,它可以帮助实现建筑信息的集成,从建筑的设计、施工、运行直至建筑全寿命周期的终结,各种信息始终整合于一个三维模型信息数据库中,设计团队、施工单位、设施运营部门和业主等各方人员可以基于BIM进行协同工作,有效提高工作效率、节省资源、降低成本、以实现可持续发展。
目前,建筑安装工程中大体量钢结构安装施工仍依据CAD二维平面设计施工,仅靠二维设计数据以及人脑的空间想象,很难判定出设计图纸中存在的大量问题,从而造成材料加工尺寸错误甚至导致施工返工,从而使得工程建设成本增加,效益降低。
发明内容
(一)解决的技术问题
针对现有技术的不足,本发明提供了一种基于BIM技术的大体量钢结构安装深化施工方法,解决了建筑安装工程中大体量钢结构安装施工仍依据CAD二维平面设计施工,仅靠二维设计数据以及人脑的空间想象,很难判定出设计图纸中存在的大量问题,从而造成材料加工尺寸错误甚至导致施工返工的问题。
(二)技术方案
为实现以上目的,本发明通过以下技术方案予以实现:一种基于BIM技术的大体量钢结构安装深化施工方法,包含以下步骤:
步骤1.熟悉设计文件以及施工图纸,对于其中存在的问题及时与设计进行沟通交流,及时解决问题;
步骤2.根据项目特点选用BIM技术软件,掌握相关建模标准以及建模规范,避免模型出现问题而带来一系列不必要的麻烦;
步骤3.创建精度高的精细化三维模型,包括土建主体结构模型、预埋件模型、大体量钢结构模型,并将模型整合为一体;
步骤4.对整合后的模型进行全面检查复核,对于存在的问题以高亮形式进行标注,及时与设计进行沟通交流,及时解决问题;
步骤5.依据模型信息对大体量钢结构材料进行生产加工,避免出现差错;
步骤6.进行施工模拟以及可视化交底;
步骤7.指导现场土建、预埋件、钢结构现场焊接拼装以及吊装安装施工。
优选的,在步骤2中所述的根据项目特点选用BIM技术软件,BIM技术软件包括好多款,不同的软件所具有的功能以及实现的效果存在很大的差别,具体实施时难易程度也存在着差异,具体实施前要根据项目特点认真选择使用最佳利于项目的BIM软件。
优选的,在步骤5中所述模型信息包括待加工钢结构钢构件材料的空间几何信息、尺寸信息、角度弧度信息和位置信息。
优选的,在步骤6中所述施工模拟,利用所选择的BIM软件进行施工模拟,然后通过专家论证,确保方案的顺利实施。
(三)有益效果
本发明提供了一种基于BIM技术的大体量钢结构安装深化施工方法。具备以下有益效果:该基于BIM技术的大体量钢结构安装深化施工方法,利用并发挥BIM技术的优势,使得大体量钢结构安装施工更加高效,更加可靠,提高钢结构钢构件材料加工生产以及使用率,避免浪费,在进行施工前期便将施工过程、安装信息以及大体量钢结构安装成型以后的安装效果以360度无死角的展现在眼前,能够很好的控制和指导现场施工,提高了工程建设的效益。
附图说明
图1为基于BIM技术的大体量钢结构安装深化施工方法的流程图。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
请参阅图1,本发明提供一种技术方案:一种基于BIM技术的大体量钢结构安装深化施工方法,包含以下步骤:
步骤1.熟悉设计文件以及施工图纸,对于其中存在的问题及时与设计进行沟通交流,及时解决问题;
步骤2.根据项目特点选用BIM技术软件,掌握相关建模标准以及建模规范,避免模型出现问题而带来一系列不必要的麻烦,其中根据项目特点选用BIM技术软件,BIM技术软件包括好多款,不同的软件所具有的功能以及实现的效果存在很大的差别,具体实施时难易程度也存在着差异,具体实施前要根据项目特点认真选择使用最佳利于项目的BIM软件;
步骤3.创建精度高的精细化三维模型,包括土建主体结构模型、预埋件模型、大体量钢结构模型,并将模型整合为一体;
步骤4.对整合后的模型进行全面检查复核,对于存在的问题以高亮形式进行标注,及时与设计进行沟通交流,及时解决问题;
步骤5.依据模型信息对大体量钢结构材料进行生产加工,避免出现差错,其中模型信息包括待加工钢结构钢构件材料的空间几何信息、尺寸信息、角度弧度信息和位置信息;
步骤6.进行施工模拟以及可视化交底,其中利用所选择的BIM软件进行施工模拟,然后通过专家论证,确保方案的顺利实施;
步骤7.指导现场土建、预埋件、钢结构现场焊接拼装以及吊装安装施工。
综上所述,该基于BIM技术的大体量钢结构安装深化施工方法,利用并发挥BIM技术的优势,使得大体量钢结构安装施工更加高效,更加可靠,提高钢结构钢构件材料加工生产以及使用率,避免浪费,在进行施工前期便将施工过程、安装信息以及大体量钢结构安装成型以后的安装效果以360度无死角的展现在眼前,能够很好的控制和指导现场施工,提高了工程建设的效益。
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。
Claims (4)
1.一种基于BIM技术的大体量钢结构安装深化施工方法,其特征在于,包含以下步骤:
步骤1.熟悉设计文件以及施工图纸,对于其中存在的问题及时与设计进行沟通交流,及时解决问题;
步骤2.根据项目特点选用BIM技术软件,掌握相关建模标准以及建模规范,避免模型出现问题而带来一系列不必要的麻烦;
步骤3.创建精度高的精细化三维模型,包括土建主体结构模型、预埋件模型、大体量钢结构模型,并将模型整合为一体;
步骤4.对整合后的模型进行全面检查复核,对于存在的问题以高亮形式进行标注,及时与设计进行沟通交流,及时解决问题;
步骤5.依据模型信息对大体量钢结构材料进行生产加工,避免出现差错;
步骤6.进行施工模拟以及可视化交底;
步骤7.指导现场土建、预埋件、钢结构现场焊接拼装以及吊装安装施工。
2.根据权利要求1所述的一种基于BIM技术的大体量钢结构安装深化施工方法,其特征在于:在步骤2中所述的根据项目特点选用BIM技术软件,BIM技术软件包括好多款,不同的软件所具有的功能以及实现的效果存在很大的差别,具体实施时难易程度也存在着差异,具体实施前要根据项目特点认真选择使用最佳利于项目的BIM软件。
3.根据权利要求1所述的一种基于BIM技术的大体量钢结构安装深化施工方法,其特征在于:在步骤5中所述模型信息包括待加工钢结构钢构件材料的空间几何信息、尺寸信息、角度弧度信息和位置信息。
4.根据权利要求1所述的一种基于BIM技术的大体量钢结构安装深化施工方法,其特征在于:在步骤6中所述施工模拟,利用所选择的BIM软件进行施工模拟,然后通过专家论证,确保方案的顺利实施。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010302907.9A CN111523166A (zh) | 2020-04-17 | 2020-04-17 | 一种基于bim技术的大体量钢结构安装深化施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010302907.9A CN111523166A (zh) | 2020-04-17 | 2020-04-17 | 一种基于bim技术的大体量钢结构安装深化施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111523166A true CN111523166A (zh) | 2020-08-11 |
Family
ID=71912023
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010302907.9A Pending CN111523166A (zh) | 2020-04-17 | 2020-04-17 | 一种基于bim技术的大体量钢结构安装深化施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111523166A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112163264A (zh) * | 2020-10-10 | 2021-01-01 | 中国建筑第二工程局有限公司 | 基于bim的假山模块化施工方法、装置及存储介质 |
CN113638607A (zh) * | 2021-09-22 | 2021-11-12 | 中铁二十二局集团第五工程有限公司 | 基于bim的钢结构停车楼施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120005103A1 (en) * | 2010-06-30 | 2012-01-05 | Hitachi, Ltd. | Method and apparatus for construction simulation |
CN108629141A (zh) * | 2018-05-15 | 2018-10-09 | 中国十七冶集团有限公司 | 一种基于bim技术的钢结构施工深化方法 |
CN108647450A (zh) * | 2018-05-15 | 2018-10-12 | 中国十七冶集团有限公司 | 一种基于bim技术的预埋大地脚螺栓施工方法 |
CN109920036A (zh) * | 2019-04-02 | 2019-06-21 | 中国十七冶集团有限公司 | 一种基于bim技术的弧形钢结构施工方法 |
CN110929328A (zh) * | 2019-12-04 | 2020-03-27 | 中国电建集团江西省水电工程局有限公司 | 基于bim的混凝土装配式建筑施工方法 |
CN110968907A (zh) * | 2019-12-04 | 2020-04-07 | 北京建都设计研究院有限责任公司 | 基于bim的集团房地产建设工程的实施方法 |
-
2020
- 2020-04-17 CN CN202010302907.9A patent/CN111523166A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120005103A1 (en) * | 2010-06-30 | 2012-01-05 | Hitachi, Ltd. | Method and apparatus for construction simulation |
CN108629141A (zh) * | 2018-05-15 | 2018-10-09 | 中国十七冶集团有限公司 | 一种基于bim技术的钢结构施工深化方法 |
CN108647450A (zh) * | 2018-05-15 | 2018-10-12 | 中国十七冶集团有限公司 | 一种基于bim技术的预埋大地脚螺栓施工方法 |
CN109920036A (zh) * | 2019-04-02 | 2019-06-21 | 中国十七冶集团有限公司 | 一种基于bim技术的弧形钢结构施工方法 |
CN110929328A (zh) * | 2019-12-04 | 2020-03-27 | 中国电建集团江西省水电工程局有限公司 | 基于bim的混凝土装配式建筑施工方法 |
CN110968907A (zh) * | 2019-12-04 | 2020-04-07 | 北京建都设计研究院有限责任公司 | 基于bim的集团房地产建设工程的实施方法 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112163264A (zh) * | 2020-10-10 | 2021-01-01 | 中国建筑第二工程局有限公司 | 基于bim的假山模块化施工方法、装置及存储介质 |
CN112163264B (zh) * | 2020-10-10 | 2021-09-07 | 中国建筑第二工程局有限公司 | 基于bim的假山模块化施工方法、装置及存储介质 |
CN113638607A (zh) * | 2021-09-22 | 2021-11-12 | 中铁二十二局集团第五工程有限公司 | 基于bim的钢结构停车楼施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021128675A1 (zh) | 一种基于bim技术的地下连续墙施工方法 | |
CN111143915A (zh) | 基于Tekla软件平台的钢结构模块化安装方法 | |
CN109784004B (zh) | 一种基于bim技术的异形金属屋面安装施工方法 | |
CN109543233A (zh) | 一种基于bim技术的机电管线装配式施工方法 | |
CN110210097B (zh) | 一种基于bim技术的金属屋面优化施工方法 | |
CN112163256B (zh) | 基于有限元分析与bim的模板支架模型的建立与分析方法 | |
CN112257160B (zh) | 一种基于bim的垃圾焚烧发电厂标准化正向设计方法 | |
CN109785436A (zh) | 一种基于bim技术的钢筋信息全生命周期的管理方法 | |
CN108733863B (zh) | 基于bim的大型城市综合体机电系统安装方法 | |
CN111523166A (zh) | 一种基于bim技术的大体量钢结构安装深化施工方法 | |
CN111177832A (zh) | 一种基于bim的机电管线综合规范自动化检查系统 | |
CN109583149A (zh) | 基于bim管理的超大盖体车辆段深化改造系统及其施工方法 | |
KR20190099779A (ko) | 건축물 구조 설계 방법 | |
CN102855362B (zh) | 一种基于计算机辅助设计的检验管路装配的方法 | |
CN110990914A (zh) | 基于bim技术的大型锅炉安装方法 | |
CN113269527A (zh) | 一种基于bim钢筋形状和参数精确加工钢筋方法 | |
CN110990933A (zh) | 用于盾构隧道的建模方法 | |
CN112465390A (zh) | 一种基于bim的地铁车站施工进度管理方法 | |
CN110489895B (zh) | 一种基于bim技术的桥梁花瓶墩盖梁钢模板设计方法 | |
CN111597625A (zh) | 一种基于bim的基坑支护开挖质量控制方法 | |
CN108984876A (zh) | 一种基于bim的预埋套管自动化建模方法和系统 | |
CN116541929A (zh) | 室外堆场土建标准化单元参数化bim模型的构建方法 | |
CN110634186A (zh) | 一种基于bim的拱盖法暗挖施工方法 | |
CN115526988A (zh) | 一种基于bim模型的异形管道模板制造及安装方法 | |
CN111625889A (zh) | 一种基于bim技术的曲面异形钢结构施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |