Prior art keywords
rainwater
water storage
road construction
urban road
sponge urban
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910054496.3A
Other languages
Chinese (zh)
Inventor
覃大伟
张隽
孙鉴清
张烽
赵巍
李骋
武申申
宋世龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Pudong Architectural Design & Research Institute Co ltd
Original Assignee
Shanghai Pudong Architectural Design & Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Pudong Architectural Design & Research Institute Co ltd filed Critical Shanghai Pudong Architectural Design & Research Institute Co ltd
Priority to CN201910054496.3A priority Critical patent/CN111456188A/en
Publication of CN111456188A publication Critical patent/CN111456188A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/101Dedicated additional structures, interposed or parallel to the sewer system
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/105Accessories, e.g. flow regulators or cleaning devices
    • E03F5/106Passive flow control devices, i.e. not moving during flow regulation

Abstract

The invention relates to a regulation and storage structure for sponge urban road construction, which is arranged on two sides of a road and comprises a rainwater well and a multifunctional overflow water storage unit arranged on one side of the rainwater well, wherein the bottom of the multifunctional overflow water storage unit is provided with a slow release device and a sewage discharge assembly, the bottom of the slow release device is connected to the rainwater well through a slow release water outlet pipe, the bottom of the sewage discharge assembly is connected with a sewage discharge pipe, and an overflow port is arranged between the upper part of the multifunctional overflow water storage unit and the rainwater well. Compared with the prior art, the invention can effectively reduce the urban rainwater discharge peak value, reduce the drainage pressure of the existing drainage pipe network, reduce the investment cost of the drainage pipe network, particularly effectively reduce the pollution caused by the runoff of the initial rain, improve the water quality of the river channel and have good ecological benefit and social benefit.

Description

A regulation structure for sponge urban road construction
Technical Field
The invention belongs to the field of urban construction, and particularly relates to a regulation and storage structure for sponge urban road construction.
Background
Sponge city construction is an important concept transformation of city development mode, is an important part of ecological civilization construction, belongs to the embodiment of the mainstream value of ecological civilization, and is the most important factor in source emission reduction. In actual engineering practice, "two rates" of "source emission reduction" are: the two indexes of the total annual runoff control rate and the annual runoff pollution removal rate are the most important.
With the continuous promotion of the construction projects of sponge cities of various test points, the relation between two rates in the construction of the sponge cities is more clear in the industry: the index of the total annual runoff control rate is really important, but finally the pollution control effect of the rainwater runoff is also taken as a target. In a series of measures for sponge city construction, the control of rainwater volume is a way, method or carrier, and the pollution of rainwater runoff is controlled by controlling the rainwater volume. Namely: the total control rate of the annual runoff is a process and a means, the pollution removal rate of the annual runoff is a final effect target to be achieved, and the volume control is one of an effective method and an important way for realizing the pollutant reduction target.
Wanghenliang, li junqi, car wu et al in "a discussion of several problems in the determination of total runoff control target and landing" point out "control" in the term "total runoff total control rate" in the technical guidance of construction of sponge cities "refers to" total runoff control ", i.e. including the total runoff pollutant amount and the runoff volume. For biological retention facilities with bottom outflow, a delayed regulation pond and the like, rainwater is mainly subjected to percolation and emptying time control (delayed discharge is used for increasing SS retention time) to realize total pollutant amount control, rainwater is not directly discharged outside but discharged outside after being treated to achieve a certain effect, and runoff pollution control is an important content of total amount control, so that the situation also belongs to the category of total amount control, namely 'discharge after treatment'.
The general road sponge city construction is a regulation and storage facility designed by preferentially adopting an ecological drainage mode for rainwater on the road surface and draining the rainwater into the underground space of the road and the surrounding public land if necessary. Before road runoff rainwater enters low-influence development facilities in green lands inside and outside a red line of a road, the runoff rainwater entering the green lands is pretreated by using a sedimentation tank, a preposed pond and the like, so that the damage of the runoff rainwater to the green land environment is prevented; when the green space in the red line is not enough, the road rainwater is introduced into the low-influence development facilities in the green space outside the red line of the road in the city to be consumed, and the low-influence development facilities are connected with the urban rainwater pipe system through the overflow drainage system, so that the smoothness of the upstream and downstream drainage systems is ensured.
When the road is narrow and no green land is available outside the red line, the sponge urban facilities of the road can be built only on only a small green land on the sidewalk, and the green land cannot have a large height difference with the sidewalk in order to ensure the walking safety of people, so that the traditional low-influence development and storage facilities such as rainwater gardens and the like are difficult to implement.
Patent CN207582239U discloses a be applied to road structure of sponge city construction, including pavement, aqueduct and rainwater garden, the pavement is including permeating water concrete layer and guarantor's water layer, the concrete layer that permeates water of pavement is located the top, guarantor's water layer is located permeate water concrete layer's below, the upper end of aqueduct with guarantor's water layer intercommunication, the lower extreme and the pipeline intercommunication in the municipal pipe network of aqueduct, the rainwater garden sets up one side of pavement, the upper surface slope on the concrete layer that permeates water on the pavement sets up, and to rainwater garden side slope, the ground surface in rainwater garden is less than the upper surface of pavement. On the one hand, rainwater on the sidewalk is collected, on the other hand, the rainwater on the sidewalk is drained to the rainwater garden to be utilized, the rainwater utilization rate is improved, and the drainage speed of the sidewalk during raining is improved. However, the structure cannot have the functions of regulating and storing rainwater and purifying rainwater, cannot effectively reduce the urban rainwater discharge peak value, reduces the drainage pressure of the existing drainage pipe network, and is limited for improving the water quality of the river channel.
Disclosure of Invention
The invention aims to solve the problems and provide a regulating and storing structure for sponge urban road construction.
The purpose of the invention is realized by the following technical scheme:
the utility model provides a regulation structure for construction of sponge urban road sets up in the both sides of road, includes rainwater well and the multi-functional overflow retaining unit of locating rainwater well one side, the bottom of multi-functional overflow retaining unit is equipped with slowly-releasing ware and blowdown subassembly, slowly-releasing ware bottom is through slowly-releasing water piping connection to rainwater well, the blow off pipe is connected to blowdown subassembly bottom, be equipped with the overflow mouth between the upper portion of multi-functional overflow retaining unit and the rainwater well.
Furthermore, a municipal rainwater pipe communicated with the rainwater well is arranged at the bottom of the rainwater well.
Furthermore, water storage pipes are arranged on two sides of the multifunctional overflow water storage unit.
Furthermore, the water storage pipe is an HDPE pipeline of DN 400-DN 600.
Further, the water storage pipe is obliquely arranged, the lower part of the water storage pipe faces to the multifunctional overflow water storage unit, and the longitudinal slope is 0.5%.
Further, multi-functional overflow retaining unit includes the concrete well body, the lower part of the concrete well body sets up the concrete cushion, the upper portion lid of the concrete well body establishes the trompil granite slab.
Furthermore, fine aggregate concrete and a cement mortar waterproof layer are arranged on the upper surface of the bottom of the concrete well body, and a granite baffle plate is arranged between the perforated granite plate and the well body.
Furthermore, the upper part of the multifunctional overflow water storage unit is provided with a rainwater inlet communicated with a curb opening, the curb opening is provided with a vertical rain grate, and the lower part of the rainwater inlet is provided with a sewage interception hanging basket.
Furthermore, the slow releaser is the unpowered slow releaser of Water Bike, sets up the multiunit as required side by side, and unpowered slow releaser bottom links to each other with the slow release outlet pipe through the PVC elbow, and the unpowered slow releaser of Water Bike is novel flow control device, and it is full automatic operation, need not power consumption, can be more accurate with Water ration output. The purposes of no power, full automation, uniformity and slow release water delivery are achieved.
The blowdown subassembly is unpowered automatic waste fitting discharging, sets up the multiunit as required side by side, unpowered waste fitting discharging is through reducing tee junction blowdown pipe, unpowered waste fitting discharging is a novel pollutant eduction gear, it uses with water storage facility or treatment facility cooperation, through the trigger liquid level and the blowdown liquid level of settlement, utilize the combined action of gravity, buoyancy and combination drive mechanism etc. have the automatic pollutant of discharging the facility bottom enrichment of planning ground, thereby avoid the pollutant of enrichment in earlier stage to cause the secondary pollution of storage water quality of water, the quality of water in the guarantee water storage facility is often new often, the water yield utilization who utilizes for the normal operating and the storage of facility provides the condition. Meanwhile, the water storage device does not need manual operation for pollution discharge, so that the labor cost is saved, and the long-term stable operation of facilities is ensured. The design quantity of the unpowered sewage discharge devices is determined according to the volume of the water storage facility, and the volume of the water storage facility suitable for a single unpowered sewage discharge device is not more than 3.5m3For example, the volume of the water storage facility is 0 to 3.5m3Selecting an unpowered sewage discharge device, wherein the volume of the water storage facility is 3.5-7.0m3Two unpowered sewage discharge devices are selected, and the rest is done in the same way.
Furthermore, the diameter of the slow-release water outlet pipe is 50mm, and the cross section of the overflow port is a rectangle of 150mm × 450 mm.
The specific working principle of the structure is that the multifunctional overflow water storage units are built on two sides of a road motor lane, the unpowered slow-release devices are arranged in the multifunctional overflow water storage units, the drainage ditch is divided into a plurality of drainage sections according to the distance between trees in green lands of sidewalks, and water storage pipes are laid in the drainage sections. When the rainfall is small, rainwater on the road surface enters pipelines at two sides for storage through the multifunctional overflow water storage unit after pollutants such as garbage, leaves and the like are removed through the sewage intercepting hanging basket in the rainwater port, and then the rainwater is uniformly and slowly released by the slow release device and is discharged into a municipal rainwater pipeline through the slow release water outlet pipe; when the rainfall is large, the rainwater can directly overflow through the overflow port and is discharged into a municipal rainwater pipeline so as to achieve the purposes of water storage, peak clipping and purification. The dirty water at the lower part of the storage facility is discharged into a road sewage pipeline through the unpowered sewage discharge device. After rainwater enters the regulation facility, the water is dispersed from the source and stored, the retention time of the rainwater in the regulation and purification facility is prolonged, the pollutant removal effect is enhanced, the drainage pressure of a municipal pipeline is reduced, and the pollution of initial rainwater runoff on a discharged water body is reduced.
The invention has the advantages that the invention constructs a source low-influence development system by controlling the peak value of the runoff of the rainwater, reduces the rainwater collection speed, delays the peak value occurrence time, reduces the drainage intensity, relieves the drainage pressure during rainfall, and achieves the purposes of reducing the runoff of the earth surface and controlling the urban waterlogging. Meanwhile, the pollution load of initial rainwater runoff can be effectively reduced, and the surrounding river water environment is improved. Have the function of regulation rainwater concurrently and purify the rainwater, be convenient for set up on narrower road. By the design of the invention, the urban rainwater emission peak can be effectively reduced, the drainage pressure of the existing drainage pipe network is reduced, the investment cost of the drainage pipe network is reduced, especially the pollution caused by the runoff of the initial rainwater can be effectively reduced, the water quality of the river channel is improved, and good ecological benefit and social benefit are achieved.
Drawings
FIG. 1 is a plan view of a storage regulating structure of the present invention;
FIG. 2 is a cross-sectional view taken along line 1-1 of FIG. 1;
FIG. 3 is a cross-sectional view taken along line 2-2 of FIG. 1;
FIG. 4 is a cross-sectional view taken along line 3-3 of FIG. 1;
fig. 5 is a cross-sectional view of 4-4 of fig. 1.
In the figure: municipal administration downspout 1, catch basin 2, slowly-releasing outlet pipe 3, slowly-releasing ware 4, vertical rain grate 5, blowdown subassembly 6, blow off pipe 7, water storage pipe 8, granite baffle 9, trompil granite board 10, cement mortar waterproof layer 11, fine aggregate concrete 12, concrete well body 13, concrete cushion 14, cut dirty basket 15, overflow mouth 16, PVC elbow 17, reducing tee 18.
Detailed Description
The invention is described in detail below with reference to the figures and specific embodiments.
Examples
The novel storage and purification facility is already used in the Baiwei road of the Lingang New City in Shanghai city.
Referring to fig. 1-5, a regulation structure for sponge urban road construction sets up in the both sides of road, including rainwater well 2 and locate the multi-functional overflow retaining unit of rainwater well 2 one side, the bottom of multi-functional overflow retaining unit is equipped with slowly-releasing ware 4 and blowdown subassembly 6, slowly-releasing ware 4 bottom is connected to rainwater well 2 through slowly-releasing outlet pipe 3, blowdown subassembly 6 bottom is connected drain pipe 7, be equipped with overflow mouth 16 between the upper portion of multi-functional overflow retaining unit and rainwater well 2, rainwater well 2 bottom is equipped with rather than communicating municipal rainwater pipe 1.
The multifunctional overflow water storage unit is internally provided with an unpowered slow release device and a DN50 water outlet pipe 3 for uniformly and slowly releasing rainwater to a road rainwater pipeline, the multifunctional overflow water storage unit is internally provided with an unpowered sewage discharge device, a sewage discharge component adopts a DN110 sewage discharge pipe and is connected from the bottom of a rainwater port to a sewage pipeline, the multifunctional overflow water storage unit is also provided with a 150mm × mm rainwater overflow port, when the rainfall exceeds the storage capacity of the rainwater storage pipe, the rainwater is discharged into the road rainwater pipeline in an overflowing manner, the normal operation of the regulation and storage facility is ensured, and the diameter of the slow release water outlet pipe 3 is 50 mm.
The multifunctional overflow water storage unit comprises a concrete well body 13, a concrete cushion layer 14 is arranged on the lower portion of the concrete well body 13, and a perforated granite plate 10 is covered on the upper portion of the concrete well body. The upper surface of the bottom of the concrete well body 13 is provided with fine aggregate concrete 12 and a cement mortar waterproof layer 11, and a granite baffle plate 9 is arranged between the perforated granite plate 10 and the well body. The upper part of the multifunctional overflow water storage unit is provided with a rainwater inlet communicated with a curb opening, the curb opening is provided with a vertical rain grate 5, and the lower part of the rainwater inlet is provided with a sewage interception hanging basket 15.
The slow releasers are Water Bike unpowered slow releasers, a plurality of groups of the slow releasers are arranged in parallel according to needs, and the bottoms of the unpowered slow releasers are connected with a slow release Water outlet pipe 3 through PVC elbows 17. The Water Bike unpowered slow release device is a novel flow control device, runs fully automatically, does not need power consumption, and can output Water quantitatively and accurately. The purposes of unpowered, full-automatic, uniform and slow-release water delivery are achieved; the sewage discharge assembly is an unpowered automatic sewage discharge device, a plurality of groups of the unpowered automatic sewage discharge devices are arranged in parallel according to needs, and the unpowered sewage discharge devices are connected with a sewage discharge pipe through a reducing tee 18. The unpowered sewage discharge device is a novel pollutant discharge device, is matched with a water storage facility or a treatment facility for use, and can automatically discharge pollutants enriched at the bottom of the facility in a planning way by using the combined action of gravity, buoyancy, a transmission mechanism and the like through the set trigger liquid level and the set sewage discharge liquid level, so that the secondary pollution of the water quality of the stored water caused by the pollutants enriched in the early stage is avoided, the water quality in the water storage facility is ensured to be frequently new, and conditions are provided for the normal operation of the facility and the utilization of the stored water amount. Meanwhile, the water storage device does not need manual operation for pollution discharge, so that the labor cost is saved, and the long-term stable operation of facilities is ensured. The design quantity of the unpowered sewage discharge devices is determined according to the volume of the water storage facility, and the volume of the water storage facility suitable for a single unpowered sewage discharge device is not more than 3.5m3For example, the volume of the water storage facility is 0 to 3.5m3Selecting an unpowered sewage discharge device, wherein the volume of the water storage facility is 3.5-7.0m3Two unpowered sewage discharge devices are selected, and the rest is done in the same way. The unpowered slow release device and the buried water storage pipe are used as main components and are mainly used for roads with narrow width, the regulation and purification facility runs fully automatically, power consumption is not needed, the rainwater discharge peak value can be effectively reduced, and the initial rainwater runoff pollution is greatly reduced.
The embodiments described above are described to facilitate an understanding and use of the invention by those skilled in the art. It will be readily apparent to those skilled in the art that various modifications to these embodiments may be made, and the generic principles described herein may be applied to other embodiments without the use of the inventive faculty. Therefore, the present invention is not limited to the above embodiments, and those skilled in the art should make improvements and modifications within the scope of the present invention based on the disclosure of the present invention.

Claims (10)

1. The utility model provides a regulation structure for sponge urban road construction sets up in the both sides of road, its characterized in that, includes rainwater well (2) and locates the multi-functional overflow retaining unit of rainwater well (2) one side, the bottom of multi-functional overflow retaining unit is equipped with slowly-releasing ware (4) and blowdown subassembly (6), slowly-releasing ware (4) bottom is connected to rainwater well (2) through slowly-releasing outlet pipe (3), blowdown pipe (7) are connected to blowdown subassembly (6) bottom, be equipped with overflow mouth (16) between the upper portion of multi-functional overflow retaining unit and rainwater well (2).
2. A storage structure for sponge urban road construction according to claim 1, characterized in that the rainwater well (2) is provided at its bottom with a municipal rainwater pipe (1) communicating with it.
3. The regulation and storage structure for sponge urban road construction according to claim 1, characterized in that the multifunctional overflow water storage unit is provided with water storage pipes (8) on both sides.
4. A storage structure for sponge urban road construction according to claim 3, characterized in that the water storage pipe (8) is a HDPE pipe of DN 400-DN 600.
5. The regulation structure for sponge urban road construction according to claim 3, characterized by that, the water storage pipe (8) is set up in an inclined way, the lower part is towards the multifunctional overflow water storage unit, the longitudinal slope is 0.5%.
6. A storage structure for sponge urban road construction according to claim 1, characterized in that the multifunctional overflow water storage unit comprises a concrete shaft (13), a concrete cushion (14) is arranged at the lower part of the concrete shaft (13), and an open-pore granite slab (10) is covered at the upper part of the concrete shaft (13).
7. A storage structure for sponge urban road construction according to claim 6, characterized in that the concrete shaft (13) is provided with fine stone concrete (12) and cement mortar waterproof layer (11) on the upper surface of the bottom, and granite baffle plate (9) is provided between the perforated granite plate (10) and the shaft.
8. The regulation and storage structure for sponge urban road construction according to claim 1, wherein the upper part of the multifunctional overflow water storage unit is provided with a rainwater inlet communicated with a curb opening, the curb opening is provided with a vertical rain grate (5), and the lower part of the rainwater inlet is provided with a sewage interception hanging basket (15).
9. The regulation and storage structure for sponge urban road construction according to claim 1, characterized in that the slow-release devices (4) are Water Bike unpowered slow-release devices, a plurality of groups are arranged in parallel as required, and the bottoms of the unpowered slow-release devices are connected with the slow-release Water outlet pipe (3) through PVC elbows (17); the sewage discharging assembly (6) is an unpowered automatic sewage discharging device, a plurality of groups of the unpowered automatic sewage discharging devices are arranged in parallel according to needs, and the unpowered sewage discharging devices are connected with the sewage discharging pipe (7) through a reducing tee (18).
10. A storage structure for sponge urban road construction according to claim 1, characterized in that the diameter of slow-release outlet pipe (3) is 50mm, and the cross section of overflow outlet (16) is rectangle 150mm × 450 mm.
CN201910054496.3A 2019-01-21 2019-01-21 A regulation structure for sponge urban road construction Pending CN111456188A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910054496.3A CN111456188A (en) 2019-01-21 2019-01-21 A regulation structure for sponge urban road construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910054496.3A CN111456188A (en) 2019-01-21 2019-01-21 A regulation structure for sponge urban road construction

Publications (1)

Publication Number Publication Date
CN111456188A true CN111456188A (en) 2020-07-28

Family

ID=71677351

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910054496.3A Pending CN111456188A (en) 2019-01-21 2019-01-21 A regulation structure for sponge urban road construction

Country Status (1)

Country Link
CN (1) CN111456188A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006243A (en) * 2021-01-27 2021-06-22 上海立高贸易有限公司 Catch basin that municipal drainage was used

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006243A (en) * 2021-01-27 2021-06-22 上海立高贸易有限公司 Catch basin that municipal drainage was used

Similar Documents

Publication Publication Date Title
CN102182242B (en) Rainwater treatment system and rainwater treatment method
CN108104247B (en) Mixed flow non-concave biological detention pool with initial rainwater discarding function
CN103088897A (en) Green community impact resistance rainwater ecological utilization system
CN203080677U (en) Ecological road anti-shocking rainwater utilizing system
CN103548601A (en) Tree pool and method for filtering runoff rainwater through tree pool
CN103088896A (en) Ecological road shock resistance rainwater utilization system
CN211057960U (en) Stepped rainwater storage and purification ecological retention system
CN109179890B (en) Urban pipe network overflow sewage storage and quality-grading purification system and method
CN102531282A (en) Device and method for quality-based rainwater collection, treatment and utilization
CN105714914B (en) Built-up areas dispersion rainfall runoff stores row's integral system and its application process only
CN102400494A (en) Method for collection, flow bypass, peak clipping and biological purification of initial rainwater
CN201850630U (en) Hydraulic control bend siphon overflow type intercepting well
CN111646574A (en) Urban river water environment treatment method
CN106545069A (en) A kind of series connection of improvement city black and odorous water cuts dirt and receives pipe method
CN103967105A (en) Housing cluster rainwater ecological drain-off system
CN105645691A (en) Multifunctional and ecological tree pool
CN202990090U (en) Control device for controlling to flow equally under condition of water level change
CN111535416B (en) Sponge urban rainwater source control system and process based on delay adjustment technology
CN111456188A (en) A regulation structure for sponge urban road construction
CN108571050A (en) Underground type road rain water runoff collection processing system implementing
CN102767226A (en) Separate active road edge type pipe drainage system for managing and utilizing urban rainwater
CN209798949U (en) A regulation structure for sponge urban road construction
CN109372085B (en) Shunt well
CN201952879U (en) Cutoff apparatus used in municipal rainwater pipe network for cutting off the rainwater flow of the initial period
CN109836017A (en) A kind of residential area rainwater-collecting and the system of utilizing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination