CN111445205A - Electrical load control system - Google Patents

Electrical load control system Download PDF

Info

Publication number
CN111445205A
CN111445205A CN202010216048.1A CN202010216048A CN111445205A CN 111445205 A CN111445205 A CN 111445205A CN 202010216048 A CN202010216048 A CN 202010216048A CN 111445205 A CN111445205 A CN 111445205A
Authority
CN
China
Prior art keywords
load control
electricity utilization
power
data
electricity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010216048.1A
Other languages
Chinese (zh)
Inventor
唐斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianna Energy Technology Shanghai Co ltd
Original Assignee
Tianna Energy Technology Shanghai Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianna Energy Technology Shanghai Co ltd filed Critical Tianna Energy Technology Shanghai Co ltd
Priority to CN202010216048.1A priority Critical patent/CN111445205A/en
Publication of CN111445205A publication Critical patent/CN111445205A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention provides an electrical load control system. The system comprises: the power utilization acquisition modules are respectively connected with the power utilization equipment and used for acquiring multiple types of power utilization data of the corresponding power utilization equipment every preset acquisition period; the electricity utilization control module is configured to acquire the historical electricity utilization data and the current electricity utilization data, generate actual electricity utilization data, determine that the actual electricity utilization data is larger than a safety load threshold value preset by a management user, set electricity utilization data of at least one electric device in the plurality of electric devices to be zero in a simulation mode to calculate simulated electricity utilization data of the plurality of electric devices, and form an electricity utilization load control scheme based on the simulated electricity utilization data and the identifier of the at least one electric device.

Description

Electrical load control system
Technical Field
The invention relates to the field of power control, in particular to an electric load control system.
Background
With the development of the current society, the demand for electric power energy is continuously increasing, and it is more and more important to stabilize safe power utilization to strengthen the load control of the electric power energy. The existing power load control is to obtain the service condition of the power load in a manual meter reading mode of a power consumer for a long time, and the power consumer can master the power load condition according to the data reflected by an actual energy consumption equipment meter, so that the power consumption distribution of the power consumer can be realized according to the load condition, the reasonable supply of resources is realized, the cost is reduced, the efficiency is improved, and the possibility of power accidents is reduced.
However, such electrical load control by manual meter reading is not only heavy in workload, but also has a high possibility of occurrence of estimated reading, misreading, and missing reading. The low accuracy of the data prevents rapid and accurate control of the electrical load, which may result in loss to the power consumer. In particular, in an industrial enterprise in which a large number of electric devices are present, it is particularly difficult to quickly and accurately control an electric load because of a large number of kinds and numbers of electric devices, different importance of various electric devices due to different process stages, and the like. For example, in the current situation, the way for power consumption management of a power consumption enterprise is to collect engineers of various departments to conduct conference discussion when emergency load regulation is needed, generate a preliminary load control scheme, and evaluate the preliminary load control scheme in combination with the operation efficiency, production plan and the like of various power consumption equipment to form a final load control scheme. And then, on the premise that each department ensures that the scheme is feasible, the power guarantee department appoints an engineer to the site to start and stop certain electric equipment according to the final load control scheme. Obviously, such a solution is inefficient, labor-intensive, requires engineers to be very familiar with the operating conditions of the distribution network and to have a rich field experience, and after the load control is completed, engineers also need to go to the field to see whether the operating conditions of the power supply equipment and the power consumption equipment are normal.
In addition, although some automatic schemes for remote meter reading exist, for power consumers using the schemes, although the accuracy and integrity of data are guaranteed by storing the data in a database, the power load control still needs an experienced engineer to perform autonomous analysis and judgment on the basis of a data field, and the control mode is highly subjective and greatly depends on personal experience of the engineer, so that the effect of load control is very unreliable.
Disclosure of Invention
In order to solve the problems, the invention provides an electric load control system. The system comprises: the power utilization acquisition modules are respectively connected with the power utilization equipment and used for acquiring multiple types of power utilization data of the corresponding power utilization equipment every preset acquisition period; the electricity utilization control module comprises a buffer, the buffer is used for buffering the electricity utilization data of the corresponding electricity utilization equipment acquired by the electricity utilization acquisition modules in the current acquisition period as current electricity utilization data, the electricity utilization control module stores the electricity utilization data of a plurality of types acquired by the electricity utilization acquisition modules in the acquisition period before the current acquisition period in a database of a management server connected with the electricity utilization control module as historical electricity utilization data, the electricity utilization control module is configured to acquire the historical electricity utilization data specified in the load control command from the database and acquire the current electricity utilization data specified in the load control command from the buffer when receiving the load control command from a management user, and the historical electricity utilization data and the current electricity utilization data are combined to generate actual electricity utilization data of the electricity utilization equipment, determining whether the actual power consumption data is greater than a safety load threshold preset by the management user, if the actual power consumption data is greater than the safety load threshold preset by the management user, simulatively setting power consumption data of at least one power consumption device in the plurality of power consumption devices to zero to calculate simulative power consumption data of the plurality of power consumption devices, wherein the simulative power consumption data is smaller than or equal to the safety load threshold, and forming a power consumption control scheme based on the simulative power consumption data and the identifier of the at least one power consumption device.
By utilizing the scheme of the invention, the reasonable power utilization plan can be more surely formulated by related responsible persons of a power user by visually displaying the load condition of the power utilization equipment and simulating the load condition in the power system, the optimized configuration in the aspect of power resource supply is realized by effectively controlling power energy, the future development trend of the power system is met, and the cost reduction, the efficiency improvement and the reasonable power utilization of the power user are ensured by effectively monitoring and reasonably applying the power load.
Drawings
FIG. 1 shows a schematic diagram of an electrical load control system according to the present invention; and
fig. 2 shows a schematic structural diagram of a monitoring module of the electrical load control system according to an embodiment of the present invention.
Detailed Description
The embodiments of the present invention will be described in detail below with reference to the accompanying drawings in order to more clearly understand the objects, features and advantages of the present invention. It should be understood that the embodiments shown in the drawings are not intended to limit the scope of the present invention, but are merely intended to illustrate the spirit of the technical solution of the present invention.
In the following description, for the purposes of illustrating various inventive embodiments, certain specific details are set forth in order to provide a thorough understanding of the various inventive embodiments. One skilled in the relevant art will recognize, however, that the embodiments may be practiced without one or more of the specific details. In other instances, well-known devices, structures and techniques associated with this application may not be shown or described in detail to avoid unnecessarily obscuring the description of the embodiments.
Throughout the specification and claims, the word "comprise" and variations thereof, such as "comprises" and "comprising," are to be understood as an open, inclusive meaning, i.e., as being interpreted to mean "including, but not limited to," unless the context requires otherwise.
Reference throughout this specification to "one embodiment" or "an embodiment" means that a particular feature, structure, or characteristic described in connection with the embodiment is included in at least one embodiment. Thus, the appearances of the phrases "in one embodiment" or "in an embodiment" in various places throughout this specification are not necessarily all referring to the same embodiment. Furthermore, the particular features, structures, or characteristics may be combined in any suitable manner in one or more embodiments.
As used in the specification and the appended claims, the singular forms "a", "an", and "the" include plural referents unless the context clearly dictates otherwise. It should be noted that the term "or" is generally employed in its sense including "and/or" unless the context clearly dictates otherwise.
Fig. 1 shows a schematic structural diagram of an electrical load control system 1 according to the invention. As shown in fig. 1, the electrical load control system 1 includes a plurality of electrical load acquisition modules 10 (only one is schematically shown in fig. 1). Each power consumption collecting module 10 may be connected to one power consumption device 60, and is configured to collect a plurality of types of power consumption data of the corresponding power consumption device 60 every predetermined collecting period. For example, the predetermined collection period may be 1 minute, so that the electricity collection module 10 collects electricity data of the electricity consumption device 60 connected thereto every one minute.
The electrical load control system 1 further includes an electrical utilization control module 20, which includes a buffer (not shown in the figure) for buffering the electrical utilization data, also referred to as current electrical utilization data, of the corresponding electrical equipment 60 collected by the plurality of electrical utilization collection modules 10 in the current collection period. For example, the power consumption control module 20 may be configured to write current power consumption data of the power consumption devices 60 collected by the power consumption collection modules 10 into a redis cache based on the modbus protocol.
In addition, each time new power consumption data acquired by the power consumption acquisition module 10 is received, the power consumption control module 20 further transfers the current power consumption data in the buffer to a database (e.g., a hard disk) of the management server 30 connected to the power consumption control module 20. For example, the electricity consumption control module 20 may execute a binning program once per minute, store the data in the buffer in the hard disk mysql database of the management server 30, and request the management server 30 for the data when requested by the management user, for example, through websocket. In this way, at any particular time, the electricity control module 20 stores current electricity data of the current sampling period, and the database of the management server 30 stores electricity data collected by the plurality of electricity collection modules 10 in the collection period before the current collection period, which is also referred to as historical electricity data.
In practical operation, the management user of the power utilization enterprise may monitor the power utilization condition of each power utilization device, for example, the management user may visually check the power utilization condition of each power utilization device through the portable management terminal 40 as shown in the figure or through the management server 30. Here, the power consumption of each power consumption device may be represented by the power consumption data collected by each power consumption collection module as described above, or may be represented by the monitoring signal/digital parameter collected by the monitoring module 50 as described below, or may be represented by a combination of the two. Furthermore, the management user can request the electrical load control system 1 to perform load control as needed. In this case, the management user can issue a load control request to the utility control module 20 by operating the management terminal 40 or directly operating the management server 30, for example. The load control request may specify, for example, a target range (which electric devices) of the load control, such as specifying that a certain production line of a plurality of production lines is subjected to the load control, specifying that electric devices of a certain link of all the production lines are subjected to the load control, or specifying other electric devices that a user wants to control. The load control request may also specify a time range for load control, such as specifying how long in the future to perform load control, etc.
Upon receiving a load control request from a management user, the electricity consumption control module 20 acquires corresponding historical electricity consumption data from the database of the management server 30 according to an instruction in the load control request, and acquires corresponding current electricity consumption data from the buffer of the electricity consumption control module 20. The power consumption control module 20 may acquire current power consumption data and historical power consumption data of some or all of the power consumption devices 60 according to the load control request. Here, it is assumed that the electricity consumption control module 20 acquires the current electricity consumption data and the historical electricity consumption data of all of the plurality of electric devices 60. The power usage control module 20 may combine the acquired historical power usage data and the current power usage data to generate actual power usage data for the plurality of powered devices 60. The electricity consumption control module 20 determines whether the actual electricity consumption data is greater than a safety load threshold preset by a management user.
In some embodiments, if it is determined that the actual power usage data is greater than the safety load threshold preset by the administrative user, the power control module 20 may simulatively set the power usage data of at least one powered device 60 of the plurality of powered devices 60 to zero (i.e., simulate turning off the powered device) to calculate the simulated power usage data of the plurality of powered devices 60. Specifically, the power consumption control module 20 may count the simulated operating currents after unloading some power consumption devices 60 by simulating unloading some power consumption devices 60 from the current operating currents or count the simulated operating currents after loading some power consumption devices 60 by loading some power consumption devices 60 to the current operating currents.
Here, the power consumption control module 20 may sequentially turn off each of the power consumers 60 in a simulation manner according to a rule (e.g., power consumption priority of each power consumer 60) preset by a user until the obtained simulated power consumption data is less than or equal to the safety load threshold. The identifier of the at least one consumer 60 that is switched off in an analog manner can now be known. The power utility control module 20 may form a power utility load control scheme based on the obtained simulated power utility data and the identifier of the at least one power consumer 60.
In one embodiment, the decision of the load control scheme is performed by the management server 30. In this case, the power consumption control module 20 may transmit the power load management scheme to the management server 30, and the management server 30 determines whether to shut down the at least one powered device 60 based on the power load management scheme. If it is determined to shut down the at least one powered device 60, the management server 30 transmits a load control command to the powered control module 20 to shut down the at least one powered device 60. The management server 30 may include hardware devices and software devices such as a server, a workstation, and a switch, and the management server 30 may receive and display the load condition of the electric equipment 60 from the electric control module 20 in real time, and may transmit the load condition to the management terminal 40 in real time for display.
In another embodiment, the decision of the load control scheme is performed by the management terminal 40 connected to the management server 30 by wire or wirelessly. In this case, the electricity control module 20 may transmit the electricity load management scheme to the management server 30, and the management server 30 forwards the electricity load management scheme to the management terminal 40. The management terminal 40 determines whether to shut down the at least one electric device 60 based on the electric load control scheme, and transmits a load control command to the management server 30 if it is determined to shut down the at least one electric device 60. The management server 30 forwards the load control command to the power consumption control module 20 to shut down the at least one powered device 60. Herein, the management terminal 40 may be a portable mobile terminal, and the management user may view the power consumption of each power consumption device 60 whenever and wherever necessary, and may receive a message transmitted by the system whenever and wherever possible, thereby providing higher operational flexibility. Further, although the management terminal 40 is shown as 1 in fig. 1, in other examples, the electrical load control system 1 may include a plurality of management terminals 40, each management terminal 40 being controlled by one management user.
In other embodiments, the power consumption control module 20 may apply different rules to simulate the power consumption data of different power consumption devices 60 of the plurality of power consumption devices 60 to 0 respectively to calculate a plurality of simulated power consumption data smaller than or equal to the safety load threshold, and form a plurality of power consumption load control schemes according to the plurality of simulated power consumption data and the identifiers of the corresponding turned-off power consumption devices 60 respectively.
In this case, in an embodiment, the power usage control module 20 may transmit all of the plurality of power load management schemes to the management server 30, and the management server 30 may select one power load control scheme from the plurality of power load control schemes based on an instruction of a management user and determine whether to shut down the power device 60 corresponding to the selected power load scheme based on the selected power load control scheme. If it is determined to shut down the electric devices 60 corresponding to the selected electric load scheme, the management server 30 transmits a load control command to the electric control module 20 to shut down the electric devices 60 corresponding to the selected electric load scheme.
In another embodiment, the power utilization control module 20 may transmit all of the plurality of power utilization load management schemes to the management server 30, and the management server 30 transmits the plurality of power utilization load management schemes to the management terminal 40. The management terminal 40 selects one electric load control scheme from the plurality of electric load control schemes based on an instruction of the management user, and determines whether to shut down the electric devices 60 corresponding to the selected electric load scheme based on the selected electric load control scheme. If it is determined to shut down the electric devices 60 corresponding to the selected electric load scenario, the management terminal 40 transmits a load control command to the management server 30. The management server 30 forwards the load control command to the electricity usage control module 20 to shut down the electricity usage device 60 corresponding to the selected electricity usage load scheme.
In some embodiments, the electrical load control system 1 may further include a monitoring module 50. Fig. 2 shows a schematic diagram of a monitoring module 50 of the electrical load control system 1 according to an embodiment of the invention. As shown in fig. 2, the monitoring module 50 includes a plurality of monitoring terminals 52 (only one shown in fig. 2 by way of example) and an intelligent gateway 54. Each monitoring terminal 52 is connected to a corresponding one of the plurality of electric devices 60, and is configured to obtain a plurality of monitoring signals of the corresponding electric device. The plurality of monitoring signals includes, for example, voltage, current, relay input, and the like. The monitoring terminal 52 may also convert the plurality of monitoring signals into digital parameters, respectively, including, for example, three-phase voltage, three-phase current, power factor, frequency, power usage, and the like. For example, the monitoring terminal 52 may convert the obtained voltage sampled by the voltage transformer and the current sampled by the current transformer into digital parameters for calculation at the terminal, read out the calculated data through the serial interface, display various parameters according to the preset values, perform communication transmission through the infrared or RS485 interface, complete the monitoring of the operating parameters, and record and store various data.
The intelligent gateway 54 classifies the digital parameters of the plurality of electric devices 60 according to device types and data identification manners, and packages the classified digital parameters according to a predetermined communication protocol to transmit to the connected management server 30. For example, intelligent gateway 54 may classify the digital parameters of each powered device 60 according to the device type of the powered device 60, such as gateway, channel, or power consumer, and the data identification of the obtained device data item.
In some embodiments, monitoring module 50 may also include a fiber optic transceiver 56 that may transmit the digital parameters packaged by intelligent gateway 54 to management server 30 over fiber.
As described above, both the power consumption collection module 10 and the monitoring terminal 52 may be configured to obtain power consumption data of the powered device 60, and the power consumption control module 20 may further determine whether the powered device 60 is safely powered by comparing the obtained data.
In the embodiment according to the present invention, the collection accuracy of the electricity consumption collection module 10 is greater than that of the monitoring terminal 52. For example, the acquisition accuracy of the monitoring terminal 52 is 0.2 level, while the acquisition accuracy of the power consumption acquisition module 10 is 0.2s level, and the lower the number is, the higher the acquisition accuracy is represented by + s. This is because the data collected by the power consumption collecting module 10 is the main data source of the power consumption load control scheme, and therefore the data accuracy requirement is higher.
To further determine the data accuracy, for a specific electric device 60, the electricity control module 20 may determine whether the electricity data collected by the electricity collection module 10 is consistent with the monitoring signal obtained by the monitoring terminal 52, and send an alarm signal to the management server 30 if it is determined that the electricity data collected by the electricity collection module 10 is inconsistent with the monitoring signal obtained by the monitoring terminal 52. Here, depending on the type or parameters of the electricity collection module 10 and the monitoring terminal 52 used, the comparison between the electricity data and the monitoring signal may be performed directly or after conversion into a comparable amount.
To further determine the accuracy of the commands from the administrative user, the powered control module 20 is further configured to, upon receiving a load control command from the administrative user, acknowledge the load control command and transmit the load control command back to the administrative server 30 for the administrative user to acknowledge again. Here, the load control command transmitted back to the management server 30 may highlight, for example, an identifier of the electric device 60 to be turned off by the load control command. The management user may confirm directly at the management server 30 or may receive and confirm the load control command from the management server 30 through the management terminal 40. The power consumption control module 20 may turn off the power consumption device 60 specified in the load control command according to the load control command when receiving the load control command confirmed again by the management user.
In some embodiments according to the present invention, the management server 30 may also perform power integration on the respective electric devices 60. Specifically, since it is known from the formula P — UIcos θ that the powers of the upper voltage class and the lower voltage class are equal (on the premise of neglecting the loss), the power and the current of the low voltage class can be converted into the power and the current of the high voltage class according to the calculation formula, so that different voltage classes (e.g., 35KV, 10KV, 6KV, etc.) can be integrated into the same voltage class. By the method, the information data island effect can be broken through, the data integrity and accuracy are greatly improved, and the problems of low information data integration level, poor interconnectivity and information management dispersion are solved.
The present invention may be methods, apparatus, systems and/or computer program products. The computer program product may include a computer-readable storage medium having computer-readable program instructions embodied therein for carrying out aspects of the present invention.
The computer readable storage medium may be a tangible device that can hold and store the instructions for use by the instruction execution device. The computer readable storage medium may be, for example, but not limited to, an electronic memory device, a magnetic memory device, an optical memory device, an electromagnetic memory device, a semiconductor memory device, or any suitable combination of the foregoing. More specific examples (a non-exhaustive list) of the computer readable storage medium would include the following: a portable computer diskette, a hard disk, a Random Access Memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a Static Random Access Memory (SRAM), a portable compact disc read-only memory (CD-ROM), a Digital Versatile Disc (DVD), a memory stick, a floppy disk, a mechanical coding device, such as punch cards or in-groove projection structures having instructions stored thereon, and any suitable combination of the foregoing. Computer-readable storage media as used herein is not to be construed as transitory signals per se, such as radio waves or other freely propagating electromagnetic waves, electromagnetic waves propagating through a waveguide or other transmission medium (e.g., optical pulses through a fiber optic cable), or electrical signals transmitted through electrical wires.
The computer-readable program instructions described herein may be downloaded from a computer-readable storage medium to a respective computing/processing device, or to an external computer or external storage device via a network, such as the internet, a local area network, a wide area network, and/or a wireless network. The network may include copper transmission cables, fiber optic transmission, wireless transmission, routers, firewalls, switches, gateway computers and/or edge servers. The network adapter card or network interface in each computing/processing device receives computer-readable program instructions from the network and forwards the computer-readable program instructions for storage in a computer-readable storage medium in the respective computing/processing device.
Computer program instructions for carrying out operations of the present invention may be assembler instructions, Instruction Set Architecture (ISA) instructions, machine-related instructions, microcode, firmware instructions, state setting data, or source or object code written in any combination of one or more programming languages, including AN object oriented programming language such as Smalltalk, C + +, or the like, as well as conventional procedural programming languages, such as the "C" language or similar programming languages.
Aspects of the present invention are described herein with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems) and computer program products according to embodiments of the invention. It will be understood that each block of the flowchart illustrations and/or block diagrams, and combinations of blocks in the flowchart illustrations and/or block diagrams, can be implemented by computer-readable program instructions.
These computer-readable program instructions may be provided to a processing unit of a general purpose computer, special purpose computer, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processing unit of the computer or other programmable data processing apparatus, create means for implementing the functions/acts specified in the flowchart and/or block diagram block or blocks. These computer-readable program instructions may also be stored in a computer-readable storage medium that can direct a computer, programmable data processing apparatus, and/or other devices to function in a particular manner, such that the computer-readable medium storing the instructions comprises an article of manufacture including instructions which implement the function/act specified in the flowchart and/or block diagram block or blocks.
The computer readable program instructions may also be loaded onto a computer, other programmable data processing apparatus, or other devices to cause a series of operational steps to be performed on the computer, other programmable apparatus or other devices to produce a computer implemented process such that the instructions which execute on the computer, other programmable apparatus or other devices implement the functions/acts specified in the flowchart and/or block diagram block or blocks.
The flowchart and block diagrams in the figures illustrate the architecture, functionality, and operation of possible implementations of systems, methods and computer program products according to various embodiments of the present invention. In this regard, each block in the flowchart or block diagrams may represent a module, segment, or portion of instructions, which comprises one or more executable instructions for implementing the specified logical function(s). In some alternative implementations, the functions noted in the block may occur out of the order noted in the figures. For example, two blocks shown in succession may, in fact, be executed substantially concurrently, or the blocks may sometimes be executed in the reverse order, depending upon the functionality involved. It will also be noted that each block of the block diagrams and/or flowchart illustration, and combinations of blocks in the block diagrams and/or flowchart illustration, can be implemented by special purpose hardware-based systems which perform the specified functions or acts, or combinations of special purpose hardware and computer instructions.
Having described embodiments of the present invention, the foregoing description is intended to be exemplary, not exhaustive, and not limited to the embodiments disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The terms used herein were chosen in order to best explain the principles of the embodiments, the practical application, or technical improvements to the techniques in the marketplace, or to enable others of ordinary skill in the art to understand the embodiments disclosed herein.

Claims (12)

1. An electrical load control system comprising:
the power utilization acquisition modules are respectively connected with the power utilization equipment and used for acquiring multiple types of power utilization data of the corresponding power utilization equipment every preset acquisition period;
the electricity utilization control module comprises a buffer used for buffering the electricity utilization data of the corresponding electricity utilization equipment acquired by the electricity utilization acquisition modules in the current acquisition period as the current electricity utilization data, and the electricity utilization control module stores a plurality of categories of electricity utilization data acquired by the electricity utilization acquisition modules in the acquisition period before the current acquisition period in a database of a management server connected with the electricity utilization control module as historical electricity utilization data, and is configured to
Upon receiving a load control request from a management user, acquiring historical electricity usage data specified in the load control request from the database, and acquiring current electricity usage data specified in the load control request from the cache,
combining the historical power usage data and the current power usage data to generate actual power usage data for the plurality of powered devices,
determining whether the actual electricity utilization data is larger than a safety load threshold preset by the management user,
if the actual electricity utilization data is determined to be larger than a safety load threshold value preset by the management user, simulating and setting electricity utilization data of at least one electric equipment in the plurality of electric equipment to be zero to calculate simulated electricity utilization data of the plurality of electric equipment, wherein the simulated electricity utilization data is smaller than or equal to the safety load threshold value, and
forming an electrical load control scheme based on the simulated electrical usage data and an identifier of the at least one powered device.
2. The system of claim 1, further comprising:
a management server configured to
Receiving a power load control scheme from the power consumption control module,
determining whether to shut down the at least one powered device based on the power load control scheme, an
Upon determining to shut down the at least one powered device, sending a load control command to the power consumption control module to shut down the at least one powered device.
3. The system of claim 1, further comprising a management server and a management terminal connected to the management server, wherein
The management server is configured to receive a power load control scheme from the power consumption control module and transmit the power load control scheme to the management terminal,
the management terminal determines whether to shut down the at least one powered device based on the power load control scheme,
the management terminal sends a load control command to the management server when it is determined to shut down the at least one electric device, an
The management server forwards the load control command to the power utilization control module to shut down the at least one power utilization device.
4. The system of claim 1, wherein the power consumption control module is further configured to:
if the actual electricity utilization data is determined to be larger than a safety load threshold value preset by the management user, respectively setting the electricity utilization data of different electric equipment in the plurality of electric equipment to be zero in a simulation mode to calculate a plurality of simulated electricity utilization data, wherein each simulated electricity utilization data is smaller than or equal to the safety load threshold value, and
a plurality of electricity load control schemes are respectively formed based on the plurality of simulated electricity usage data and an identifier of the electricity usage device corresponding to each simulated electricity usage data.
5. The system of claim 4, further comprising:
a management server configured to
Receive the plurality of electrical load control schemes from the electrical load control module,
selecting one electric load control scheme from the plurality of electric load control schemes based on the indication of the management user,
determining whether to shut down the electric devices corresponding to the selected electric load scheme based on the selected electric load control scheme, an
Upon determining to shut down the electrical equipment corresponding to the selected electrical load scenario, sending a load control command to the electrical usage control module to shut down the electrical equipment corresponding to the selected electrical load scenario.
6. The system of claim 4, further comprising a management server and a management terminal connected to the management server, wherein
The management server is configured to receive the plurality of electric load control schemes from the electric load control module and transmit the plurality of electric load control schemes to the management terminal,
the management terminal selects one electric load control scheme from the plurality of electric load control schemes based on an instruction of the management user,
the management terminal determines whether to shut down the electric devices corresponding to the selected electric load scheme based on the selected electric load control scheme,
upon determining to shut down the electric devices corresponding to the selected electric load scenario, the management terminal transmits a load control command to the management server,
the management server forwards the load control command to the electricity utilization control module to shut down the electricity utilization equipment corresponding to the selected electricity utilization load scheme.
7. The system of claim 1, further comprising:
a monitoring module, which comprises a plurality of monitoring terminals and an intelligent gateway,
wherein each monitoring terminal is respectively connected with a corresponding one of the plurality of electric devices and is used for acquiring a plurality of monitoring signals of the corresponding electric device and respectively converting the monitoring signals into digital parameters,
and the intelligent gateway classifies the digital parameters of the electric equipment according to equipment types and data identification modes, and packages the classified digital parameters according to a preset communication protocol to send to a connected management server.
8. The system of claim 7, wherein the monitoring module further comprises a fiber optic transceiver that transmits the intelligent gateway packaged digital parameters to the management server over a fiber optic.
9. The system of claim 7, wherein the plurality of monitoring signals comprise voltages, currents, relay inputs, and the digital parameters comprise three-phase voltages, three-phase currents, power factor, frequency, power usage.
10. The system of claim 7, wherein the acquisition accuracy of the electricity usage acquisition module is greater than the acquisition accuracy of the monitoring terminal, and wherein the electricity usage control module is further configured to:
for specific electric equipment, determining whether the electricity utilization data acquired by the electricity utilization acquisition module is consistent with the monitoring signals acquired by the monitoring terminal, and
and if the electricity utilization data acquired by the electricity utilization acquisition module is determined to be inconsistent with the monitoring signals acquired by the monitoring terminal, sending an alarm signal to the management server.
11. The system of claim 1, wherein the power consumption control module is further configured to:
upon receiving a load control command from the administrative user, acknowledging the load control command and transmitting the load control command back to the administrative server for further acknowledgment by the administrative user, an
And when the load control command confirmed again by the management user is received, the electric equipment specified in the load control command is shut down according to the load control command.
12. The system of claim 1, wherein the power consumption control module is further configured to: caching the current electricity utilization data of the plurality of electricity utilization equipment into the cache based on a modbus protocol.
CN202010216048.1A 2020-03-25 2020-03-25 Electrical load control system Pending CN111445205A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010216048.1A CN111445205A (en) 2020-03-25 2020-03-25 Electrical load control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010216048.1A CN111445205A (en) 2020-03-25 2020-03-25 Electrical load control system

Publications (1)

Publication Number Publication Date
CN111445205A true CN111445205A (en) 2020-07-24

Family

ID=71655716

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010216048.1A Pending CN111445205A (en) 2020-03-25 2020-03-25 Electrical load control system

Country Status (1)

Country Link
CN (1) CN111445205A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117495056A (en) * 2023-12-28 2024-02-02 西安民为电力科技有限公司 Power consumption data monitoring and optimizing method and system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101951027A (en) * 2010-09-01 2011-01-19 中国电力科学研究院 Uniform data acquisition and monitoring system of low-medium voltage power distribution network
CN104734351A (en) * 2015-03-09 2015-06-24 兴义供电局 Network distribution large user intelligent split terminal controller
CN105046360A (en) * 2015-07-20 2015-11-11 国网天津市电力公司 Power load weight management system based on peak-valley time period and peak-valley time period management method
CN106124852A (en) * 2016-06-13 2016-11-16 国网天津宝坻供电有限公司 Non-intrusion type load monitor system
CN109494876A (en) * 2018-11-28 2019-03-19 国网江苏省电力有限公司南京供电分公司 A kind of distribution web information system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101951027A (en) * 2010-09-01 2011-01-19 中国电力科学研究院 Uniform data acquisition and monitoring system of low-medium voltage power distribution network
CN104734351A (en) * 2015-03-09 2015-06-24 兴义供电局 Network distribution large user intelligent split terminal controller
CN105046360A (en) * 2015-07-20 2015-11-11 国网天津市电力公司 Power load weight management system based on peak-valley time period and peak-valley time period management method
CN106124852A (en) * 2016-06-13 2016-11-16 国网天津宝坻供电有限公司 Non-intrusion type load monitor system
CN109494876A (en) * 2018-11-28 2019-03-19 国网江苏省电力有限公司南京供电分公司 A kind of distribution web information system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117495056A (en) * 2023-12-28 2024-02-02 西安民为电力科技有限公司 Power consumption data monitoring and optimizing method and system

Similar Documents

Publication Publication Date Title
CN112069247B (en) Power system operation data visualization system and method based on digital twin technology
CN111131480A (en) Cloud edge cooperative service system for smart power plant
US10164431B2 (en) Outage management and prediction for a power grid system
CN110020967B (en) Information processing method and device for intelligent alarm of power grid dispatching end transformer substation
CN100481672C (en) Power supply device
CN102998562B (en) Power quality monitoring system based on International Electrotechnical Commission (IEC) 61850 communication protocol
CN110071577A (en) Supervisory control of substation information acceptance method and system
CN103427489A (en) Intelligent substation comprehensive monitoring system
JP5523577B2 (en) Monitoring control system communication method and monitoring control system
CN104917845A (en) UPS (Uninterruptible Power Supply) intelligent monitoring network
CN105203887A (en) Prewarning method, device and system for overload of transformer
CN105978140B (en) Information fusion method of power equipment
CN108875103B (en) Power grid online simulation system and method
Duarte et al. Substation-based self-healing system with advanced features for control and monitoring of distribution systems
CN111445205A (en) Electrical load control system
CN206712547U (en) Low voltage distribution monitoring apparatus and system
CN104461627B (en) Intelligent substation test equipment SV and GOOSE configuration parameter introduction method
CN203587709U (en) Intelligent transformer station integrated monitoring system
CN103545805A (en) Modeling-based railway power supply arm monitoring method
CN107482783B (en) Comprehensive intelligent system for monitoring and controlling service power
CN104539045A (en) Intelligent fault-analysis-prevention system and working method thereof
CN212229020U (en) Three-phase safety electric meter
CN111369172A (en) Power system load power protection control method, system, equipment and storage medium
CN112491101A (en) Control method and system of storage battery pack, storage medium and electronic device
CN111900800B (en) Remote switching-on and switching-off method and system for electric meter

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200724