CN111428950A - Scheduling method and device - Google Patents

Scheduling method and device Download PDF

Info

Publication number
CN111428950A
CN111428950A CN201910020067.4A CN201910020067A CN111428950A CN 111428950 A CN111428950 A CN 111428950A CN 201910020067 A CN201910020067 A CN 201910020067A CN 111428950 A CN111428950 A CN 111428950A
Authority
CN
China
Prior art keywords
scheduling
information
elements
rule
data corresponding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910020067.4A
Other languages
Chinese (zh)
Inventor
单增琪
李嘉欣
金晶
陈秋丽
李昆
李志华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SF Technology Co Ltd
SF Tech Co Ltd
Original Assignee
SF Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SF Technology Co Ltd filed Critical SF Technology Co Ltd
Priority to CN201910020067.4A priority Critical patent/CN111428950A/en
Publication of CN111428950A publication Critical patent/CN111428950A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses a scheduling method and a device, wherein the method comprises the following steps: creating a plurality of scheduling elements required by scheduling in a scheduling system; respectively inputting data corresponding to the scheduling factors into the scheduling system to serve as an information base generated by a scheduling rule; establishing a matching relation between data corresponding to the scheduling factors as a scheduling rule; creating scheduling information aiming at each scheduling element based on service requirements, and respectively importing the scheduling information into a scheduling system; and checking the data corresponding to the scheduling information one by one according to the scheduling rule to generate a scheduling list according with the scheduling rule. The scheduling system can flexibly configure the scheduling elements and the data corresponding to the scheduling elements according to the scheduling rules, and can verify the scheduling information according to the scheduling rules, so that the scheduling list of each employee is reasonable and correct.

Description

Scheduling method and device
Technical Field
The invention relates to the technical field of management, in particular to a scheduling method and a scheduling device.
Background
The comprehensive enterprise similar to the logistics industry has a plurality of stations and different scheduling modes, wherein some stations only need to arrange the working time elements of the personnel, and some stations need to arrange the working time and the working content of the personnel and other elements. The conventional scheduling system mostly fixes the scheduling rule and can only meet the scheduling requirement of a certain post. The internal of the company needs to be provided with a shift arrangement system for each post, which consumes a great deal of manpower and capital.
As the enterprise steps into a fine management stage, more management and control requirements are provided for the elements of manpower resource management, the original scheduling system has poor expansibility, and if the change of the management requirements needs to be supported, the scheduling check rules need to be redeveloped and modified, so that the process speed of enterprise innovation is reduced, and the research and development expenditure is increased.
The existing scheduling mode is to bind people with data such as working time, working content, working area, etc., and if a certain element in the binding relationship is adjusted or temporarily moved, the binding relationship needs to be modified. The matching relationship between the personnel and the service scene needs to be adjusted and matched through a manual binding relationship, and cannot be restricted through system rule verification, so that scheduling errors are easily caused, the working time of the scheduling personnel is omitted and consumed, and the requirement of planning and scheduling in advance is not met.
Disclosure of Invention
In view of the above-mentioned drawbacks and deficiencies of the prior art, it is desirable to provide a scheduling method and apparatus.
In order to overcome the defects of the prior art, the technical scheme provided by the invention is as follows:
in a first aspect, the present invention provides a scheduling method, which is characterized in that the method comprises:
creating a plurality of scheduling elements required by scheduling in a scheduling system;
respectively inputting data corresponding to the scheduling elements into a scheduling system, and storing the data as an information base generated by a scheduling rule;
establishing a matching relation based on the data corresponding to the scheduling elements as a scheduling rule;
creating scheduling information aiming at each scheduling element based on service requirements, and respectively importing the scheduling information into a scheduling system;
and checking the data corresponding to the scheduling information one by one according to the scheduling rule to generate a scheduling list according with the scheduling rule.
Further, the scheduling element comprises work time, work content and work area;
and establishing a matching relation between one item in the working time, the working content and the working area and any one of the remaining two items or the remaining two items, and using the matching relation as the scheduling rule to verify the scheduling information.
And further, adding, reducing or modifying data corresponding to the scheduling elements so as to expand or maintain the information base.
Further, the scheduling elements in the scheduling list or the scheduling information corresponding to the scheduling elements may be increased, decreased or modified.
Further, the shift information can be viewed and/or downloaded based on a designated single or plurality of the shift elements.
In a second aspect, the present invention further provides a shift scheduling apparatus, which is characterized in that the shift scheduling apparatus comprises:
the system comprises a first processing module, a second processing module and a scheduling module, wherein the first processing module is used for creating a plurality of scheduling elements required by scheduling in a scheduling system;
the second processing module is used for respectively inputting data corresponding to the scheduling factors into the scheduling system to serve as an information base generated by a scheduling rule;
the third processing module is used for establishing a matching relation between data corresponding to the scheduling factors as a scheduling rule;
the fourth processing module is used for creating scheduling information aiming at each scheduling element based on the service requirement and respectively importing the scheduling information into the scheduling system;
and the fifth processing module is used for checking the data corresponding to the scheduling information one by one according to the scheduling rule and generating a scheduling list according with the scheduling rule.
Further, the scheduling element comprises work time, work content and work area;
and establishing a matching relation between one item in the working time, the working content and the working area and any one of the remaining two items or the remaining two items, and using the matching relation as the scheduling rule to verify the scheduling information.
And further, adding, reducing or modifying data corresponding to the scheduling elements so as to expand or maintain the information base.
Further, the scheduling elements in the scheduling list or the scheduling information corresponding to the scheduling elements may be increased, decreased or modified.
Further, the shift information can be viewed and/or downloaded based on a designated single or plurality of the shift elements.
Compared with the prior art, the invention has the beneficial effects that:
the invention creates a plurality of scheduling elements required by scheduling in a scheduling system; respectively inputting data corresponding to the scheduling factors into the scheduling system to serve as an information base generated by a scheduling rule; establishing a matching relation between data corresponding to the scheduling factors as a scheduling rule; creating scheduling information aiming at each scheduling element based on service requirements, and respectively importing the scheduling information into a scheduling system; and checking the data corresponding to the scheduling information one by one according to the scheduling rule to generate a scheduling list according with the scheduling rule. The scheduling system can flexibly configure the scheduling elements and the data corresponding to the scheduling elements according to the scheduling rules, realize the scheduling requirements of different posts through one set of system, and simultaneously provide flexibly configurable scheduling function support for enterprises to gradually reach different development stages of refined management, thereby saving the expenditure of enterprise research and development cost. The system is used for checking the scheduling rule, so that enterprise loss caused by manual errors is reduced, and the management efficiency of human resources is improved.
Drawings
Other features, objects and advantages of the present application will become more apparent upon reading of the following detailed description of non-limiting embodiments thereof, made with reference to the accompanying drawings in which:
fig. 1 is a schematic flow chart of a scheduling method according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a shift scheduling device according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of a computer device according to an embodiment of the present invention.
Detailed Description
The present application will be described in further detail with reference to the following drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the relevant invention and not restrictive of the invention. It should be noted that, for convenience of description, only the portions related to the present invention are shown in the drawings.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
As mentioned in the background art, there are many stations and different scheduling modes for a comprehensive enterprise similar to the logistics industry, and some stations only need to arrange the working time elements of the personnel, and some stations need to arrange the working time and the working content of the personnel. The conventional scheduling system mostly fixes the scheduling rule and can only meet the scheduling requirement of a certain post. The internal of the company needs to be provided with a shift arrangement system for each post, which consumes a great deal of manpower and capital.
As the enterprise steps into a fine management stage, more management and control requirements are provided for the elements of manpower resource management, the original scheduling system has poor expansibility, and if the change of the management requirements needs to be supported, the scheduling check rules need to be redeveloped and modified, so that the process speed of enterprise innovation is reduced, and the research and development expenditure is increased.
The existing scheduling mode is to bind people with data such as working time, working content, working area, etc., and if a certain element in the binding relationship is adjusted or temporarily moved, the binding relationship needs to be modified. The matching relationship between the personnel and the service scene needs to be adjusted and matched through a manual binding relationship, and cannot be restricted through system rule verification, so that scheduling errors are easily caused, the working time of the scheduling personnel is omitted and consumed, and the requirement of planning and scheduling in advance is not met.
Referring to fig. 1, a flow chart of a scheduling method provided by the present invention is shown.
The basic concept of the invention is to create a scheduling element required by scheduling in a scheduling system; importing data corresponding to each scheduling element, and establishing a scheduling rule according to the data corresponding to the scheduling elements to serve as a scheduling constraint condition; and respectively creating scheduling information of each scheduling element, deriving the scheduling information of each scheduling element according with the scheduling rule, and generating a scheduling list.
The above-described scheduling method is explained in detail in the following examples.
As shown in fig. 1, in step 110, a plurality of shift elements required for shift are created in the shift scheduling system;
the shift scheduling elements are multiple and at least comprise two shift scheduling elements. For example: the working time and the working content are used as the scheduling elements to establish a matching relationship, or the working time, the working content and the working area are simultaneously used as the scheduling elements to establish the matching relationship, or the scheduling elements can be added on the existing basis, and the matching relationship between the scheduling elements and other scheduling elements is established.
In step 120, the data corresponding to the scheduling elements are respectively entered into the scheduling system as an information base generated by the scheduling rules;
here, data corresponding to shift schedule elements are described as an example, and for example: the data corresponding to the working area is as follows: 010R, 011R, 012R; the data corresponding to the working content is as follows: AP1, AP2, AP3, AS1, AS2, AS3, ADS1, ADS2, ADS 3.
In step 130, a matching relationship is established between the data corresponding to the scheduling elements as a scheduling rule;
for example: and establishing a scheduling rule according to the matching relation of the data corresponding to the two elements of the working time and the working area, wherein the working content corresponding to the working area 010R comprises AP1, AP3, AS1, AS2 and AS3, and if the working area of the post is 010R, the working content cannot be arranged to be ADS 1.
When scheduling, the matching relationship between the data corresponding to the scheduling elements must be followed to ensure that the scheduling list of each employee is reasonable and correct.
In step 140, creating scheduling information for each scheduling element based on the service requirement, and importing the scheduling information into a scheduling system respectively;
the shift information of each element is specifically described here, for example: when the scheduling element is working time, the scheduling information is specifically a working schedule; when the scheduling element is the work content, the scheduling information is specifically a work content table; when the scheduling element is a work area, the scheduling information is specifically a work area table.
In step 150, the data corresponding to the scheduling information is checked one by one according to the scheduling rule, and a scheduling table conforming to the scheduling rule is generated.
For example: generate a shift schedule for employee a.
(1) Firstly, arranging the working time of the person for 1-30 days by importing a working time schedule;
(2) secondly, arranging the work content of the person in 1-30 days by importing a work content table; at the moment, whether the skill of the employee A can meet the requirement of the work content is checked; if the result can be satisfied, the import is successful, and if the result cannot be satisfied, the import fails and the work content needs to be modified.
(3) Finally, arranging the working area of the person for 1-30 days by importing a working area table; at the moment, whether the work content of the employee A meets the requirements of the work area is verified according to the scheduling rule; if the condition can be met, the import is successful, and if the condition cannot be met, the import fails and the working area needs to be modified.
In one embodiment, the shift schedule elements include, but are not limited to, work hours, work content, and work areas;
and establishing a matching relation between one item in the working time, the working content and the working area and any one of the remaining two items or the remaining two items, and using the matching relation as the scheduling rule to verify the scheduling information.
Because the management requirements of the post or the enterprise on the same post required to be scheduled change, for example, the management requirements of the company on the post where the employee A is located change, and the management requirements on the working area are increased, the data corresponding to the working area and the data matching relationship between the data and other scheduling elements can be increased, and a new scheduling rule meeting the requirements can be established.
In one embodiment, data corresponding to the shift schedule elements is added, subtracted, or modified to extend or maintain the information base.
In the actual shift scheduling process, if the data requirement corresponding to one or several shift scheduling elements is changed, the working content is taken as an example for explanation, and the data corresponding to the working content before the change is as follows: AP1, AP2, AP3, AS1, AS2, AS3, ADS1, ADS2 and ADS3, wherein the process of forming the scheduling rule is that the 9 data and the data corresponding to other scheduling elements establish a matching relationship; the data corresponding to the changed work content is as follows: the process of forming the scheduling rule by the AP1, the AS1 and the ADS1 is to establish a matching relationship between the 3 data and the data corresponding to other scheduling elements.
In one embodiment, the shift schedule element or the shift schedule information corresponding to the shift schedule element in the shift schedule may be increased, decreased or modified.
For example, when the scheduling requirement of the company on the post where the employee A is located changes and the management requirement of the work area is canceled, deleting the work area table can meet the new scheduling requirement of the company.
For example, the work area of employee a needs to be adjusted in 15 days of the month, and the work area is changed from the X1 area to the X2 area, so that the 15-day work area table is only needed to be updated, the X1 area is changed to the X2 area, and whether the work area conforms to the scheduling rule is checked again.
In one embodiment, the shift information can be viewed and/or downloaded based on a designated single or multiple of the shift elements.
The shift list specifies a single element view for viewing and downloading, such as: only the working time is checked, and then the shift schedule only displays the information of the working time.
Multiple elements may also be designated for conversion into a combined view for viewing and downloading. The scheduling information of each element is displayed by the scheduling table cluster, statistics can be carried out according to the manpower of each element, and whether omission exists or the situation that personnel arrangement is unreasonable is checked.
Fig. 2 is a schematic structural diagram of a shift scheduling apparatus 200 according to an embodiment of the present invention. As shown in fig. 2, the apparatus may implement the method shown in fig. 1, and the apparatus may include:
a first processing module 210, configured to create a plurality of shift scheduling elements required for shift scheduling in a shift scheduling system;
the second processing module 220 is configured to enter data corresponding to the scheduling factors into the scheduling system, respectively, and use the data as an information base generated by a scheduling rule;
a third processing module 230, configured to establish a matching relationship between data corresponding to the shift scheduling elements as a shift scheduling rule;
the fourth processing module 240 is configured to create scheduling information for each scheduling element based on a service requirement, and import the scheduling information into a scheduling system respectively;
the fifth processing module 250 is configured to perform one-to-one verification on the data corresponding to the scheduling information according to the scheduling rule, and generate a scheduling list meeting the scheduling rule.
Optionally, the shift scheduling element includes work time, work content and work area;
and establishing a matching relation between one item in the working time, the working content and the working area and any one of the remaining two items or the remaining two items, and using the matching relation as the scheduling rule to verify the scheduling information.
Optionally, data corresponding to the shift schedule elements is added, reduced or modified to extend or maintain the information base.
Optionally, the shift schedule element or the shift schedule information corresponding to the shift schedule element in the shift schedule may be increased, decreased, or modified.
Optionally, the shift information can be viewed and/or downloaded based on a designated single or multiple of the shift elements.
The in-city express delivery device provided by this embodiment may implement the embodiments of the method described above, and the implementation principle and technical effect are similar, which are not described herein again.
Fig. 3 is a schematic structural diagram of a computer device according to an embodiment of the present invention. As shown in fig. 3, a schematic structural diagram of a computer system 300 suitable for implementing a terminal device or a server of the embodiment of the present application is shown.
As shown in fig. 3, the computer system 300 includes a Central Processing Unit (CPU)301 that can perform various appropriate actions and processes in accordance with a program stored in a Read Only Memory (ROM)302 or a program loaded from a storage section 308 into a Random Access Memory (RAM) 303. In the RAM 303, various programs and data necessary for the operation of the system 300 are also stored. The CPU 301, ROM 302, and RAM 303 are connected to each other via a bus 304. An input/output (I/O) interface 306 is also connected to bus 304.
To the I/O interface 305, AN input section 306 including a keyboard, a mouse, and the like, AN output section 307 including a network interface card such as a Cathode Ray Tube (CRT), a liquid crystal display (L CD), and the like, a speaker, and the like, a storage section 308 including a hard disk, and the like, and a communication section 309 including a network interface card such as a L AN card, a modem, and the like, the communication section 309 performs communication processing via a network such as the internet, a drive 310 is also connected to the I/O interface 306 as necessary, a removable medium 311 such as a magnetic disk, AN optical disk, a magneto-optical disk, a semiconductor memory, and the like is mounted on the drive 310 as necessary, so that a computer program read out therefrom is mounted into the storage section 308 as necessary.
In particular, the process described above with reference to fig. 2 may be implemented as a computer software program, according to an embodiment of the present disclosure. For example, embodiments of the present disclosure include a computer program product comprising a computer program tangibly embodied on a machine-readable medium, the computer program comprising program code for performing the above-described method of stand allocation for a plurality of aircraft. In such an embodiment, the computer program may be downloaded and installed from a network through the communication section 309, and/or installed from the removable medium 311.
The flowchart and block diagrams in the figures illustrate the architecture, functionality, and operation of possible implementations of systems, methods and computer program products according to various embodiments of the present invention. In this regard, each block in the flowchart or block diagrams may represent a module, segment, or portion of code, which comprises one or more executable instructions for implementing the specified logical function(s). It should also be noted that, in some alternative implementations, the functions noted in the block may occur out of the order noted in the figures. For example, two blocks shown in succession may, in fact, be executed substantially concurrently, or the blocks may sometimes be executed in the reverse order, depending upon the functionality involved. It will also be noted that each block of the block diagrams and/or flowchart illustration, and combinations of blocks in the block diagrams and/or flowchart illustration, can be implemented by special purpose hardware-based systems which perform the specified functions or acts, or combinations of special purpose hardware and computer instructions.
The units or modules described in the embodiments of the present application may be implemented by software or hardware. The described units or modules may also be provided in a processor. The names of these units or modules do not in some cases constitute a limitation of the unit or module itself.
As another aspect, the present application also provides a computer-readable storage medium, which may be the computer-readable storage medium included in the foregoing device in the foregoing embodiment; or it may be a separate computer readable storage medium not incorporated into the device. The computer readable storage medium stores one or more programs for use by one or more processors in performing the method for stand allocation for a plurality of aircraft described herein.
The above description is only a preferred embodiment of the application and is illustrative of the principles of the technology employed. It will be appreciated by a person skilled in the art that the scope of the invention as referred to in the present application is not limited to the embodiments with a specific combination of the above-mentioned features, but also covers other embodiments with any combination of the above-mentioned features or their equivalents without departing from the inventive concept. For example, the above features may be replaced with (but not limited to) features having similar functions disclosed in the present application.

Claims (10)

1. A scheduling method, comprising:
creating a plurality of scheduling elements required by scheduling in a scheduling system;
respectively inputting data corresponding to the scheduling factors into the scheduling system to serve as an information base generated by a scheduling rule;
establishing a matching relation between data corresponding to the scheduling factors as a scheduling rule;
creating scheduling information aiming at each scheduling element based on service requirements, and respectively importing the scheduling information into a scheduling system;
and checking the data corresponding to the scheduling information one by one according to the scheduling rule to generate a scheduling list according with the scheduling rule.
2. The scheduling method according to claim 1, wherein:
the scheduling element comprises working time, working content and a working area;
and establishing a matching relation between one item in the working time, the working content and the working area and any one of the remaining two items or the remaining two items, and using the matching relation as the scheduling rule to verify the scheduling information.
3. The scheduling method according to claim 1 or 2, characterized in that:
and adding, reducing or modifying data corresponding to the scheduling elements so as to expand or maintain the information base.
4. The scheduling method according to claim 3, wherein:
the scheduling elements in the scheduling list or the scheduling information corresponding to the scheduling elements can be increased, reduced or modified.
5. The scheduling method according to claim 4, wherein:
the shift information can be viewed and/or downloaded based on a designated single or plurality of the shift elements.
6. A scheduling device, which is characterized in that,
the system comprises a first processing module, a second processing module and a scheduling module, wherein the first processing module is used for creating a plurality of scheduling elements required by scheduling in a scheduling system;
the second processing module is used for respectively inputting data corresponding to the scheduling factors into the scheduling system to serve as an information base generated by a scheduling rule;
the third processing module is used for establishing a matching relation between data corresponding to the scheduling factors as a scheduling rule;
the fourth processing module is used for creating scheduling information aiming at each scheduling element based on the service requirement and respectively importing the scheduling information into the scheduling system;
and the fifth processing module is used for checking the data corresponding to the scheduling information one by one according to the scheduling rule and generating a scheduling list according with the scheduling rule.
7. The scheduling method according to claim 6, wherein:
the scheduling element comprises working time, working content and a working area;
and establishing a matching relation between one item in the working time, the working content and the working area and any one of the remaining two items or the remaining two items, and using the matching relation as the scheduling rule to verify the scheduling information.
8. The scheduling method according to claim 6 or 7, wherein:
and adding, reducing or modifying data corresponding to the scheduling elements so as to expand or maintain the information base.
9. The scheduling method according to claim 8, wherein:
the scheduling elements in the scheduling list or the scheduling information corresponding to the scheduling elements can be increased, reduced or modified.
10. The scheduling method according to claim 9, wherein:
the shift information can be viewed and/or downloaded based on a designated single or plurality of the shift elements.
CN201910020067.4A 2019-01-09 2019-01-09 Scheduling method and device Pending CN111428950A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910020067.4A CN111428950A (en) 2019-01-09 2019-01-09 Scheduling method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910020067.4A CN111428950A (en) 2019-01-09 2019-01-09 Scheduling method and device

Publications (1)

Publication Number Publication Date
CN111428950A true CN111428950A (en) 2020-07-17

Family

ID=71545643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910020067.4A Pending CN111428950A (en) 2019-01-09 2019-01-09 Scheduling method and device

Country Status (1)

Country Link
CN (1) CN111428950A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112396387A (en) * 2020-09-02 2021-02-23 贵阳朗玛信息技术股份有限公司 System management device and method for scheduling management
CN112711682A (en) * 2021-01-08 2021-04-27 携程计算机技术(上海)有限公司 Class data management method, system, electronic device and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106548274A (en) * 2016-10-19 2017-03-29 平安科技(深圳)有限公司 A kind of personnel's scheduling method and device
CN107316119A (en) * 2016-04-27 2017-11-03 上海劳勤信息技术有限公司 A kind of the smart shift scheduling algorithm and system of foundation post capability and mission requirements
JP6395140B1 (en) * 2017-12-28 2018-09-26 ナノズ株式会社 Working time matching system, working time sharing system, and working time matching method
CN108764669A (en) * 2018-05-15 2018-11-06 万翼科技有限公司 Scheduling method, system and computer readable storage medium

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107316119A (en) * 2016-04-27 2017-11-03 上海劳勤信息技术有限公司 A kind of the smart shift scheduling algorithm and system of foundation post capability and mission requirements
CN106548274A (en) * 2016-10-19 2017-03-29 平安科技(深圳)有限公司 A kind of personnel's scheduling method and device
JP6395140B1 (en) * 2017-12-28 2018-09-26 ナノズ株式会社 Working time matching system, working time sharing system, and working time matching method
CN108764669A (en) * 2018-05-15 2018-11-06 万翼科技有限公司 Scheduling method, system and computer readable storage medium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112396387A (en) * 2020-09-02 2021-02-23 贵阳朗玛信息技术股份有限公司 System management device and method for scheduling management
CN112711682A (en) * 2021-01-08 2021-04-27 携程计算机技术(上海)有限公司 Class data management method, system, electronic device and storage medium

Similar Documents

Publication Publication Date Title
US20090204463A1 (en) Method, tool, and system for analyzing a project
CN103019684A (en) Dynamic template-based business page configuring method
CN111858615A (en) Database table generation method, system, computer system and readable storage medium
CN111428950A (en) Scheduling method and device
US9595014B1 (en) System and method for executing workflow instance and modifying same during execution
CN101661586A (en) Method of optimized data processing procedure and device thereof
CN113537943A (en) Universal workflow engine and construction method thereof
CN113282425A (en) Immersive robot process automation application system, platform and method
CN115167785B (en) Label-based network disk file management method and device, network disk and storage medium
CN115222480B (en) Purchase order generation method, system, equipment and computer readable storage medium
US11775893B2 (en) Method and apparatus for cell-based workforce scheduling
CN114138752B (en) Quantum vehicle type accessory basic database creating method and device, electronic equipment and storage medium
CN111626650A (en) Logistics site equipment efficiency optimization method and system
CN115168778A (en) Website page generation method and system, electronic equipment and readable storage medium
CN114648309A (en) Project node control method, device, equipment, storage medium and program product
CN112328656B (en) Service query method, device, equipment and storage medium based on middle platform architecture
CN114282078A (en) Project data processing method and device, electronic equipment and storage medium
US20180240210A1 (en) System and method for transportation scheduling and planning
CN113312420A (en) Flight data processing method, device, equipment and storage medium
CN110852700A (en) Data sorting method and device for workflow system
CN109582330A (en) Data model upgrade method, device, equipment and readable storage medium storing program for executing
CN115543969B (en) Data migration method, device, equipment and medium
CN117135050B (en) Application deployment method and device
CN113553092A (en) Project processing method and device, electronic equipment and computer readable storage medium
CN118093698A (en) Data processing method, device, electronic equipment and computer storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination