CN111400974A CN202010342227.XA CN202010342227A CN111400974A CN 111400974 A CN111400974 A CN 111400974A CN 202010342227 A CN202010342227 A CN 202010342227A CN 111400974 A CN111400974 A CN 111400974A
Authority
CN
China
Prior art keywords
shear stress
bed surface
wall surface
canal
drag force
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010342227.XA
Other languages
English (en)
Other versions
CN111400974B (zh
Inventor
潘佳佳
郭新蕾
王涛
付辉
李甲振
郭永鑫
余弘婧
路锦枝
杨涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Institute of Water Resources and Hydropower Research
Original Assignee
China Institute of Water Resources and Hydropower Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Institute of Water Resources and Hydropower Research filed Critical China Institute of Water Resources and Hydropower Research
Priority to CN202010342227.XA priority Critical patent/CN111400974B/zh
Publication of CN111400974A publication Critical patent/CN111400974A/zh
Application granted granted Critical
Publication of CN111400974B publication Critical patent/CN111400974B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Measuring Volume Flow (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

本发明涉及一种估算矩形河渠壁面和床面切应力的方法,包括:测量参数;计算床面平均切应力;计算壁面平均切应力;计算两侧边壁上的拖曳力与床面拖曳力的比值。本发明所述的方法利用光滑矩形河渠的断面尺寸、水力坡度和宽深比修正系数来计算边壁和床面的平均切应力,能准确计算恒定均匀流条件下水流作用在壁面和床面上的拖曳力。该方法将壁面平均切应力的计算精度提高到7.5%以内,计算精度大幅提高。相比传统的床面切应力计算方法,本发明所述方法综合考虑边壁效应,能更准确地分析河渠阻力系数和河床冲淤变化。所述的方法方便简洁,能适用于不同宽深比的河渠,将宽浅河渠和窄深河渠的壁面切应力计算统一起来,适用范围更广。

Description

一种估算矩形河渠壁面和床面切应力的方法
技术领域
本发明涉及一种估算矩形河渠壁面和床面切应力的方法,是一种水工计算方法,是一种用于实验水槽和河渠阻力分析和泥沙研究的方法。
背景技术
矩形河渠边壁阻力和河床阻力是水槽实验和河道水力学研究的基本要素,是河渠阻力系数研究的基础,也是泥沙沉降和输运计算的前提。矩形河渠边壁和河床的切应力分布与断面流速分布、边壁粗糙度、过水断面形态和二次环流等因素密切相关。现场量测河渠不同断面的非均匀性、边壁粗糙度、流速和二次环流分布是一项耗时耗力的工作,数据采集难度大。即便是针对光滑矩形水槽,也很少有研究详细分析边壁和床面切应力与流速分布、粗糙度、流速和二次环流等因素间的关系。这会影响水槽实验下水流的均匀性,特别是边壁效应会影响床面平均切应力的计算,进而影响推移质输沙率和床面冲刷计算的准确性。光滑矩形河渠壁面切应力分布和非均匀性是水力学研究的重要瓶颈问题,亟待突破解决。因此,有必要提出一种简单有效的方法计算光滑矩形河渠边壁和床面的平均切应力。
针对光滑矩形河渠,传统的壁面切应力计算一般假设河渠是宽浅河道,忽略两侧边壁上的切应力。河床的平均切应力近似为水体重力沿底坡的分力。该计算方法的主要缺陷是:人工河渠或者实验条件下的矩形水槽并不满足宽浅河道假设,忽略边壁切应力的方法计算误差大,不能满足工程设计的需求。国外学者针对大量的实验水槽壁面切应力分布数据,在传统壁面切应力的计算方法上添加了宽深比的影响系数,能够提高一定计算精度。但相应的系数修订方法与实验资料的相关性差,无法采用统一的方程计算不同宽深比的河渠边壁和床面切应力。如何精确且简洁的计算估算矩形河渠壁面和床面切应力是一个需要解决的问题。
发明内容
为了克服现有技术的问题,本发明提出了一种估算矩形河渠壁面和床面切应力的方法。所述的方法在光滑矩形河渠平均边壁切应力的计算中考虑断面形态和宽深比的综合影响,利用水的比重、河宽、水深、湿周和水力坡度分别计算边壁和床面平均切应力。所述的计算方法有利于提高光滑矩形河渠壁面和床面平均切应力的计算精度和准确性。
本发明的目的是这样实现的:一种估算矩形河渠壁面和床面切应力的方法,所述方法的步骤如下:
步骤1,测量参数:实地测量矩形河渠的河宽B、水深H、湿周P和水力坡度s;
步骤2,计算床面平均切应力τb
Figure BDA0002468940600000021
步骤3,计算壁面平均切应力τw
Figure BDA0002468940600000022
式中,γ为水的比重;
步骤4,计算两侧边壁上的拖曳力与床面拖曳力的比值:
Figure BDA0002468940600000023
其中,Fw为水流作用在两侧边壁上的拖曳力,Fb为水流作用在床面上的拖曳力。
本发明的优点和有益效果是:本发明所述的方法利用光滑矩形河渠的断面尺寸、水力坡度和宽深比修正系数来计算边壁和床面的平均切应力,能准确计算恒定均匀流条件下水流作用在壁面和床面上的拖曳力。该方法将壁面平均切应力的计算精度提高到7.5%以内,计算精度大幅提高。相比传统的床面切应力计算方法,本发明所述方法综合考虑边壁效应,能更准确地分析河渠阻力系数和河床冲淤变化。所述的方法方便简洁,能适用于不同宽深比的河渠,将宽浅河渠和窄深河渠的壁面切应力计算统一起来,适用范围更广。
附图说明
图1是本发明实施例所述方法的流程图;
图2是本发明实施例所述方法的边壁水流拖曳力与床面拖曳力的比值与宽深比的关系示意图;
图3是本发明实施例所述方法的方程1计算的无量纲的床面切应力与实测值的对比示意图;
图4是本发明实施例所述方法的方程2计算的无量纲的边壁切应力与实测值的对比示意图。
具体实施方式
实施例:
本实施例是一种估算矩形河渠壁面和床面切应力的方法,所述方法的步骤如下:
步骤1,测量参数:实地测量矩形河渠的河宽B、水深H、湿周P和水力坡度s;
步骤2,计算床面平均切应力τb
Figure BDA0002468940600000031
步骤3,计算壁面平均切应力τw
Figure BDA0002468940600000032
式中,γ为水的比重;
步骤4,计算两侧边壁上的拖曳力与床面拖曳力的比值:
Figure BDA0002468940600000033
其中,Fw为水流作用在两侧边壁上的拖曳力,Fb为水流作用在床面上的拖曳力。
本实施例利用光滑矩形河渠的宽度、水深、湿周和水力坡度分别计算边壁和床面的切应力,其理论原理和数学基础如下:
通过系统收集和整理外光滑矩形河渠边壁和床面切应力的实测资料,相关的数据统计见表1。
表1.光滑矩形河渠边壁和床面切应力资料
Figure BDA0002468940600000034
Figure BDA0002468940600000041
通过系统分析表1中所有的数据,研究发现水流作用在两侧边壁的拖曳力与床面拖曳力的比值仅仅为形态系数宽深比的函数,具体表达式为方程(3)。该方程与各实测资料的对比见图2。结果显示方程(3)能够准确描述不同宽深比下的边壁拖曳力与床面拖曳力的比值,方程与数据的拟合度为95.1%。
而床面水流拖曳力为平均床面切应力在河宽上的积分,可表示为:
Fb=τbB (4)
同理,壁面水流拖曳力为:
Fw=τw2H (5)
其中,光滑矩形河渠的湿周为:
P=B+2H (6)
在恒定均匀流条件下,河渠水流的重力与边壁和河道的阻力平衡,则有:
2Hτw+Bτb=γBHs (7)
引入一个参数
Figure BDA0002468940600000042
来无量纲化边壁和床面切应力,方程(7)变为:
Figure BDA0002468940600000043
联立求解方程(3)、(4)、(5)和(8),可分别得到无量纲的边壁和床面切应力为:
Figure BDA0002468940600000051
Figure BDA0002468940600000052
将方程(1)和(2)分别用于表1中各组观测河渠的壁面切应力计算,结果见图3和4。结果显示方程(2)和(3)与实测值的拟合度高达96.5%和99.0%。因此,本实施例提出的壁面和床面切应力计算方法能很好的计算不同宽深比光滑矩形河渠的边壁与河床平均切应力及水流拖曳力。
最后应说明的是,以上仅用以说明本发明的技术方案而非限制,尽管参照较佳布置方案对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案(比如被研究河道的形态、各种公式的运用、步骤的先后顺序等)进行修改或者等同替换,而不脱离本发明技术方案的精神和范围。

Claims (1)

1.一种估算矩形河渠壁面和床面切应力的方法,其特征在于,所述方法的步骤如下:
步骤1,测量参数:实地测量矩形河渠的河宽B、水深H、湿周P和水力坡度s;
步骤2,计算床面平均切应力τb
Figure FDA0002468940590000011
步骤3,计算壁面平均切应力τw
Figure FDA0002468940590000012
式中,γ为水的比重;
步骤4,计算两侧边壁上的拖曳力与床面拖曳力的比值:
Figure FDA0002468940590000013
其中,Fw为水流作用在两侧边壁上的拖曳力,Fb为水流作用在床面上的拖曳力。
CN202010342227.XA 2020-04-27 2020-04-27 一种估算矩形河渠壁面和床面切应力的方法 Active CN111400974B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010342227.XA CN111400974B (zh) 2020-04-27 2020-04-27 一种估算矩形河渠壁面和床面切应力的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010342227.XA CN111400974B (zh) 2020-04-27 2020-04-27 一种估算矩形河渠壁面和床面切应力的方法

Publications (2)

Publication Number Publication Date
CN111400974A true CN111400974A (zh) 2020-07-10
CN111400974B CN111400974B (zh) 2020-12-08

Family

ID=71431789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010342227.XA Active CN111400974B (zh) 2020-04-27 2020-04-27 一种估算矩形河渠壁面和床面切应力的方法

Country Status (1)

Country Link
CN (1) CN111400974B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112747897A (zh) * 2020-12-07 2021-05-04 河海大学 一种沙泥混合物床面起动切应力计算方法
CN113255030A (zh) * 2021-04-27 2021-08-13 交通运输部天津水运工程科学研究所 一种矩形断面明渠水力最优断面设计方法

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5327984A (en) * 1993-03-17 1994-07-12 Exxon Production Research Company Method of controlling cuttings accumulation in high-angle wells
US20080012345A1 (en) * 2006-06-09 2008-01-17 David Joseph Parker Tethered propgen
CN103808958A (zh) * 2014-01-26 2014-05-21 清华大学 一种测量明渠紊流粘性底层流速的方法及装置
CN106869077A (zh) * 2017-03-17 2017-06-20 云南省水利水电勘测设计研究院 利用畅流期水位流量关系估算寒区河流冰封期流量的方法
CN107816009A (zh) * 2017-10-23 2018-03-20 云南省水利水电勘测设计研究院 一种推求多级复式断面水位流量关系的通用方法
CN108460483A (zh) * 2018-02-09 2018-08-28 中国水利水电科学研究院 一种天然河道流量的定量反演方法
CN108520132A (zh) * 2018-03-30 2018-09-11 湖北省水利水电规划勘测设计院 一种河段阻隔性特征识别及阻隔程度分类的方法
CN109033725A (zh) * 2018-09-14 2018-12-18 中国水利水电科学研究院 一种定床河工模型试验大面积床面切应力的估算方法
CN109932368A (zh) * 2019-04-02 2019-06-25 北京林业大学 一种柔性植被群拖曳力系数的测量方法
CN110046398A (zh) * 2019-03-22 2019-07-23 西北农林科技大学 一种当卡水电站泄洪闸下游冲刷过程三维数值模拟方法
CN110532648A (zh) * 2019-08-09 2019-12-03 西安理工大学 一种堰塞湖风险评估平台
CN110704793A (zh) * 2019-10-12 2020-01-17 中国水利水电科学研究院 一种河渠冰盖糙率的计算方法
CN110705188A (zh) * 2019-10-06 2020-01-17 中水东北勘测设计研究有限责任公司 一维冰水耦合运动的高精度格式模拟方法

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5327984A (en) * 1993-03-17 1994-07-12 Exxon Production Research Company Method of controlling cuttings accumulation in high-angle wells
US20080012345A1 (en) * 2006-06-09 2008-01-17 David Joseph Parker Tethered propgen
CN103808958A (zh) * 2014-01-26 2014-05-21 清华大学 一种测量明渠紊流粘性底层流速的方法及装置
CN106869077A (zh) * 2017-03-17 2017-06-20 云南省水利水电勘测设计研究院 利用畅流期水位流量关系估算寒区河流冰封期流量的方法
CN107816009A (zh) * 2017-10-23 2018-03-20 云南省水利水电勘测设计研究院 一种推求多级复式断面水位流量关系的通用方法
CN108460483A (zh) * 2018-02-09 2018-08-28 中国水利水电科学研究院 一种天然河道流量的定量反演方法
CN108520132A (zh) * 2018-03-30 2018-09-11 湖北省水利水电规划勘测设计院 一种河段阻隔性特征识别及阻隔程度分类的方法
CN109033725A (zh) * 2018-09-14 2018-12-18 中国水利水电科学研究院 一种定床河工模型试验大面积床面切应力的估算方法
CN110046398A (zh) * 2019-03-22 2019-07-23 西北农林科技大学 一种当卡水电站泄洪闸下游冲刷过程三维数值模拟方法
CN109932368A (zh) * 2019-04-02 2019-06-25 北京林业大学 一种柔性植被群拖曳力系数的测量方法
CN110532648A (zh) * 2019-08-09 2019-12-03 西安理工大学 一种堰塞湖风险评估平台
CN110705188A (zh) * 2019-10-06 2020-01-17 中水东北勘测设计研究有限责任公司 一维冰水耦合运动的高精度格式模拟方法
CN110704793A (zh) * 2019-10-12 2020-01-17 中国水利水电科学研究院 一种河渠冰盖糙率的计算方法

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
BAS HOFLAND 等: "Probability Density Function of Instantaneous Drag Forces and Shear Stresses on a Bed", 《JOURNAL OF HYDRAULIC ENGINEERING》 *
JUNKE GUO 等: "Shear Stress in Smooth Rectangular Open-Channel Flows", 《JOURNAL OF HYDRAULIC ENGINEERING》 *
何建京: "明渠非均匀流糙率系数及水力特性研究", 《中国优秀博硕士学位论文全文数据库 (博士)》 *
刘斌: "有植物明渠阻力特性试验研究", 《中国优秀硕士学位论文全文数据库》 *
张胜华: "稳定土渠宽深比的分析与选定", 《科技创新导报》 *
潘文浩: "不同尺度密集粗糙与植被床面明渠流流场与总流特性研究", 《中国博士学位论文全文数据库 基础科学辑》 *
申楠: "黄土坡面细沟水流分离能力对水力学特征的响应过程研究", 《中国优秀硕士学位论文全文数据库 农业科技辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112747897A (zh) * 2020-12-07 2021-05-04 河海大学 一种沙泥混合物床面起动切应力计算方法
CN113255030A (zh) * 2021-04-27 2021-08-13 交通运输部天津水运工程科学研究所 一种矩形断面明渠水力最优断面设计方法

Also Published As

Publication number Publication date
CN111400974B (zh) 2020-12-08

Similar Documents

Publication Publication Date Title
CN110287571B (zh) 一种河流险工冲刷安全分析与岸坡稳定性判定方法
CN111400974B (zh) 一种估算矩形河渠壁面和床面切应力的方法
Liu et al. Two-dimensional kinematic wave model of overland-flow
CN106446411A (zh) 粘性泥石流内部流速、冲击力空间分布测量方法
CN112464584B (zh) 自由表面流的水位和流量推求方法
CN111895979B (zh) 基于gf-1影像和测高卫星的河流存量计算方法
CN113887087B (zh) 潮汐河段底沙输移引起的航道淤积量计算方法及系统
CN109271672A (zh) 一种河-湖-泵站相互影响作用下的河道水面线计算方法
CN104933268A (zh) 一种基于一维非恒定流数值模型的洪水分析方法
Vatankhah et al. Sharp-crested weir located at the end of a circular channel
CN108427654B (zh) 一种中型以上淤地坝已淤积库容快速演算方法
CN114184239A (zh) 一种基于最优收缩度中心圆柱矩形槽的渠道测流法
Fernandes et al. Flow structure in a compound channel with smooth and rough floodplains
CN106320255A (zh) 一种漫滩水流滩槽过流量的计算方法
CN110847112B (zh) 一种基于水力学模拟的河道泄洪预警方法
CN113806851B (zh) 一种疏浚挖槽水动力变化引起的航槽淤积量预测方法
CN109360271A (zh) 一种具有可重复性的基于河段尺度的平滩水位确定方法
CN111639444B (zh) 泥石流拦挡坝拦砂率测算方法、应用
Sachpazis Experimental conceptualisation of the flow net system construction inside the body of homogeneous earth embankment dams
CN113280870A (zh) 一种虚拟二线能坡河渠流量测流法
CN111460357A (zh) 一种凹形坡沟道中泥石流侵蚀深度计算方法
Mohaghegh et al. Evaluation of stage-discharge relationship in compound channels
CN110110455A (zh) 给定流量下调节闸门开度的方法
CN110309607B (zh) 一种闸门过流量计算方法
CN114578088B (zh) 一种强约束河断面或龙口平均流速测量方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant