CN111353202A - Partitioning method for underground pipe network general investigation in municipal administration - Google Patents
Partitioning method for underground pipe network general investigation in municipal administration Download PDFInfo
- Publication number
- CN111353202A CN111353202A CN202010400805.0A CN202010400805A CN111353202A CN 111353202 A CN111353202 A CN 111353202A CN 202010400805 A CN202010400805 A CN 202010400805A CN 111353202 A CN111353202 A CN 111353202A
- Authority
- CN
- China
- Prior art keywords
- node
- pipe
- pipe network
- network
- nodes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 39
- 238000000638 solvent extraction Methods 0.000 title claims abstract description 8
- 238000011835 investigation Methods 0.000 title claims abstract 3
- 238000005192 partition Methods 0.000 claims abstract description 100
- 238000005520 cutting process Methods 0.000 claims abstract description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 14
- 238000007726 management method Methods 0.000 claims description 11
- 238000013316 zoning Methods 0.000 claims description 10
- 238000004220 aggregation Methods 0.000 claims description 7
- 230000002776 aggregation Effects 0.000 claims description 6
- 238000009826 distribution Methods 0.000 claims description 6
- CIWBSHSKHKDKBQ-JLAZNSOCSA-N Ascorbic acid Chemical compound OC[C@H](O)[C@H]1OC(=O)C(O)=C1O CIWBSHSKHKDKBQ-JLAZNSOCSA-N 0.000 claims description 4
- 238000007689 inspection Methods 0.000 claims description 3
- 239000002243 precursor Substances 0.000 claims description 3
- 230000008859 change Effects 0.000 claims description 2
- 238000012946 outsourcing Methods 0.000 claims 2
- 238000004364 calculation method Methods 0.000 claims 1
- 230000007547 defect Effects 0.000 abstract description 3
- 230000004931 aggregating effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 8
- 239000000463 material Substances 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 238000011160 research Methods 0.000 description 3
- 238000013022 venting Methods 0.000 description 3
- 238000004458 analytical method Methods 0.000 description 2
- 238000005457 optimization Methods 0.000 description 2
- 238000013439 planning Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000000704 physical effect Effects 0.000 description 1
- 238000006116 polymerization reaction Methods 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T11/00—2D [Two Dimensional] image generation
- G06T11/20—Drawing from basic elements, e.g. lines or circles
- G06T11/206—Drawing of charts or graphs
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种城市供水管网分区方法,尤其涉及一种市政管理中面向城市地下供水管网普查的分区方法,属于市政工程管理技术领域。The invention relates to a method for partitioning an urban water supply pipe network, in particular to a method for partitioning an urban underground water supply pipe network census in municipal management, and belongs to the technical field of municipal engineering management.
背景技术Background technique
地下管线是城市重要的基础设施,被称为城市“生命线”。随着城市规模的不断扩张,地下管线新旧混杂,网络结构日趋复杂化。由于缺乏全面的管线信息,特别是准确的空间位置信息,各种安全事故常有发生,甚至导致重大经济损失。在加强管线科学规划、信息化管理的同时,对现有城市地下管线的普查和探测工作也越来越受到重视。传统的管网普查时,通常采用人工划定普查区域或者是基于地图图幅的规则格网方式进行分区。不仅仅破坏了管网的整体拓扑连通性,造成了普查管段的不连续。同时忽略了区域内部管网的结构,导致了基于分区的普查工作量分配不均衡。因此,面对地下管网普查时,如何科学、有效地对管网进行区域划分是管网普查具体作业中的关键问题。Underground pipelines are an important urban infrastructure, known as the "lifeline" of the city. With the continuous expansion of the city, the old and new underground pipelines are mixed, and the network structure is becoming more and more complicated. Due to the lack of comprehensive pipeline information, especially accurate spatial location information, various safety accidents often occur and even lead to major economic losses. While strengthening the scientific planning and information management of pipelines, more and more attention has been paid to the census and detection of existing urban underground pipelines. In the traditional pipe network census, the census area is usually demarcated manually or a regular grid based on map sheets is used for division. It not only destroys the overall topology connectivity of the pipe network, but also causes the discontinuity of the census pipe sections. At the same time, the structure of the pipeline network within the region is ignored, which leads to an unbalanced distribution of the workload of the census based on partitions. Therefore, in the face of the census of the underground pipeline network, how to scientifically and effectively divide the pipeline network is the key issue in the specific operation of the pipeline network census.
当前,管网分区的技术主要是针对管网设计、分析等各项问题的研究,出于降低管网的规模和复杂程度,通常建立在管网简化的基础上,重点探讨了管网的主干情况,应用于城市新增管网的规划以及针对已有管网的压力分区优化等方向。但从现势管网普查出发,对城市地下复杂管网进行分析与建模,而进行的管网分区研究鲜有涉及。顾及管网的完整性和拓扑结构特征,以满足普查分区中有特定工作区数量的需求,缺少针对性研究。At present, the technology of pipe network partitioning is mainly aimed at the research of various problems such as pipe network design and analysis. In order to reduce the scale and complexity of the pipe network, it is usually based on the simplification of the pipe network, and the backbone of the pipe network is mainly discussed. It is applied to the planning of new urban pipeline networks and the optimization of pressure zoning for existing pipeline networks. However, starting from the census of the current pipeline network, the analysis and modeling of the urban underground complex pipeline network are carried out, and the research on the partition of the pipeline network is rarely involved. Considering the integrity and topology characteristics of the pipeline network to meet the needs of the number of specific work areas in the census division, there is a lack of targeted research.
发明内容SUMMARY OF THE INVENTION
发明目的:为了克服现有技术中存在的不足,本发明提供一种市政管理中面向地下管网普查的分区方法,实现了管网分区普查总长度、面积大致相等,满足普查工作量的合理分配的需求。适用于绝大多数的管网普查分区问题。充分考虑了管网的实体性质,保持了分区内管网的良好的连通性,避免了分区后管段的割裂。Purpose of the invention: In order to overcome the deficiencies in the prior art, the present invention provides a zoning method for the census of the underground pipe network in municipal management, which realizes that the total length and area of the census of the zoning of the pipe network are approximately equal, and satisfies the reasonable distribution of the census workload. demand. Applicable to the vast majority of pipe network census zoning problems. The physical properties of the pipe network are fully considered, the good connectivity of the pipe network in the partition is maintained, and the split of the pipe section after the partition is avoided.
技术方案:为实现上述目的,本发明采用的技术方案为:Technical scheme: In order to realize the above-mentioned purpose, the technical scheme adopted in the present invention is:
一种市政管理中面向地下管网普查的分区方法,包括以下步骤:A zoning method for underground pipe network census in municipal management, comprising the following steps:
步骤1,收集待普查区域管网信息,根据待普查区域管网信息得到管点数据和管段数据。面向地下管网普查中管网设备具有重要的特征,重点关注管网设备(如三通、阀门井、泄气等设施设备),以及管段的相关信息(如材质、管径等)。本方法需要进行两次抽象,第一次将管网设备抽象为矢量点,管段抽象为矢量线,综合管点数据和管段数据形成管网矢量数据。第二次抽象将管点管段作为统一的空间实体对象,作为整体由欧式空间向拓扑空间进行投影。根据管网矢量数据将管点抽象成节点,将管段抽象成连接节点的边,将管段的长度作为边的权重,构造管网拓扑无向图。Step 1: Collect pipe network information in the area to be surveyed, and obtain pipe point data and pipe section data according to the pipe network information in the area to be surveyed. The pipeline network equipment has important characteristics in the census of the underground pipeline network, focusing on the pipeline network equipment (such as tee, valve well, venting and other facilities and equipment), and the relevant information of the pipe section (such as material, pipe diameter, etc.). This method requires two abstractions. The first time abstracts the pipe network equipment as vector points and the pipe segments as vector lines, and integrates the pipe point data and the pipe segment data to form the pipe network vector data. The second abstraction takes the pipe point and the pipe segment as a unified spatial entity object, and projects from the Euclidean space to the topological space as a whole. According to the pipe network vector data, the pipe points are abstracted into nodes, the pipe segments are abstracted into the edges connecting the nodes, and the length of the pipe segments is used as the weight of the edges to construct the undirected topological graph of the pipe network.
步骤2,步骤1得到的管网拓扑无向图是实际的管网结构,并未通过简化。使用特定裁剪算法将管网进行结构的划分。划分结果包括主干骨架网络结构和分支网络结构,主干骨架网络结构是整个管网的核心,主要由主线管网和部分涉及关键拓扑位置的支线管网构成的。分支网络结构有明显的前驱后继关系,形成有层次的树形结构,其中只有一个前驱节点,而无后继节点的为叶子节点。提取管网拓扑无向图中的供水管网的主干网络结构和分支网络结构。在管网拓扑无向图当中,存在诸多度为1的节点,删除这些节点之后又会出现新的度为1的节点,迭代之后,剩下的拓扑结构即为主干骨架网络结构。记录删除节点的顺序,逆序输出构建为树形结构。The undirected graph of the pipe network topology obtained in step 2 and step 1 is the actual pipe network structure and has not been simplified. The pipe network is structurally divided using a specific tailoring algorithm. The division results include the backbone skeleton network structure and the branch network structure. The backbone skeleton network structure is the core of the entire pipeline network, which is mainly composed of the main pipeline network and some branch pipeline networks involving key topological positions. The branch network structure has obvious predecessor and successor relationship, forming a hierarchical tree structure, in which there is only one predecessor node, and the leaf node without successor node. Extract the backbone network structure and branch network structure of the water supply pipe network in the undirected graph of the pipe network topology. In the undirected graph of pipe network topology, there are many nodes with degree 1. After deleting these nodes, new nodes with degree 1 will appear. After iteration, the remaining topology is the backbone network structure. The order in which nodes are deleted is recorded, and the reverse order output is constructed as a tree structure.
步骤3,根据得到的主干网络结构和分支网络结构将供水管网划分为nc个单元。Step 3: Divide the water supply pipe network into nc units according to the obtained backbone network structure and branch network structure.
步骤31,将主干骨架网络结构中的每个节点看成一个独立的单元,初始单元的数目与节点个数相同。且每一个单元的权重包括挂载在该节点的树状结构的所有长度权重。因管网普查工作量主要是管网长度,故此处将管段的长度属性设为权重。In step 31, each node in the backbone skeleton network structure is regarded as an independent unit, and the number of initial units is the same as the number of nodes. And the weight of each unit includes all length weights of the tree structure mounted on the node. Because the workload of the pipe network census is mainly the length of the pipe network, the length attribute of the pipe segment is set as the weight here.
步骤32,对每个节点i,尝试把节点i分配到其邻接节点所在的单元中,并计算分配前与分配后的模块度差值ΔQ,并记录模块度差值ΔQ最大的那个邻接节点。如果最大的ΔQ>0,则把节点i分配到ΔQ最大的那个邻接节点所在的单元,否则放弃此次划分。模块度差值的计算公式如下:Step 32: For each node i , try to allocate node i to the unit where its adjacent nodes are located, calculate the modularity difference ΔQ before and after allocation, and record the adjacent node with the largest modularity difference ΔQ. If the largest ΔQ>0, then assign node i to the unit where the adjacent node with the largest ΔQ is located, otherwise give up the division. The formula for calculating the modularity difference is as follows:
其中,ΔQ表示模块度差值,TopologySim表示两个相邻节点的拓扑相似度,i,n是节点 编号,i表示第i个节点,n为i的邻接节点,是单元C内的权重之和,表示单元C的内 部权重,是连接单元C的外部连接的权重之和,表示连接单元C的外部权重,C表 示邻接节点n所在的单元,是连接节点i的外部连接的权重之和,是节点i与内部 节点的连接权重相加的和,为整个网络的权重之和。 Among them, ΔQ represents the modularity difference, TopologySim represents the topology similarity of two adjacent nodes, i,n is the node number, i represents the ith node, n is the adjacent node of i , is the sum of the weights within cell C, represents the internal weight of unit C, is the sum of the weights of the outer connections of the connection unit C, represents the external weight of the connection unit C, C represents the unit where the adjacent node n is located, is the sum of the weights of the outer connections connecting node i , is the sum of the connection weights of node i and internal nodes, is the sum of the weights of the entire network.
步骤33,重复步骤32,直到所有节点的所属单元不再发生变化。Step 33: Repeat step 32 until the units to which all nodes belong are no longer changed.
步骤34,将步骤33得到的具有相同的归属的节点,视作一个新的节点,重新构造子图,两个新节点之间的权重为相应两个单元之间所有边的权重之和。In step 34, the node with the same attribution obtained in step 33 is regarded as a new node, and the subgraph is reconstructed, and the weight between the two new nodes is the sum of the weights of all the edges between the corresponding two units.
步骤35,给定最小社区子团分辨率参数,将步骤34得到的子图作为输入,重新执行步骤31到步骤34,直到满足给定的最小子团分辨率参数,得到最小社区子团以及社区子团。Step 35: Given the minimum community subgroup resolution parameter, use the subgraph obtained in step 34 as input, and re-execute steps 31 to 34 until the given minimum subgroup resolution parameter is satisfied, and obtain the minimum community subgroup and community. subgroup.
步骤36,输出最小社区子团以及社区子团的连接关系,将最小社区子团作为管网的最小分区单元,本步骤实现了管网在规定分辨率内的最精细化分割。Step 36 , output the minimum community sub-group and the connection relationship of the community sub-group, and use the minimum community sub-group as the minimum partition unit of the pipe network. This step realizes the most refined segmentation of the pipe network within the specified resolution.
步骤4,在子团连接关系的基础上,根据指定分区数量,以长度相当为主要收敛条件,面积为次要收敛条件,实现管网最小分区单元聚合,达到指定的分区数目。将新节点作为社区子团的可能性,节点i被选为社区子团的可能性的计算具体公式如下:Step 4: On the basis of the subcluster connection relationship, according to the specified number of partitions, the length is the main convergence condition, and the area is the secondary convergence condition, and the minimum partition unit aggregation of the pipe network is realized to reach the specified number of partitions. Taking the new node as the possibility of a community subgroup, the specific formula for calculating the possibility of node i being selected as a community subgroup is as follows:
其中,表示节点i被选为社区子团的概率,D(i)定义为节点i到邻居子团欧氏空 间的质心的距离,表示节点i的所有邻接节点n到节点i的距离平方和。此外,不 同于一般的社区发现算法的收敛条件,本方法还从面积分配的角度,定义空间面积上的收 敛条件: in, represents the probability that node i is selected as a community subgroup, D ( i ) is defined as the distance from node i to the centroid of the Euclidean space of neighbor subgroups, Represents the sum of squared distances from all adjacent nodes n of node i to node i . In addition, different from the convergence conditions of general community discovery algorithms, this method also defines the convergence conditions on the space area from the perspective of area allocation:
其中,表示每个分区面积的最小值,表示分区数,为候选节点,是 第个分区,m i 为邻接节点的质心。根据不同的收敛数,选择取极值点处的数值, 作为最优的子团分配方式。 in, represents the minimum value of the area of each partition, represents the number of partitions, is a candidate node, is the first partitions, where m i is the centroid of adjacent nodes. According to different convergence numbers, choose The value at the extreme point is taken as the optimal subcluster allocation method.
步骤41,将分支网结构的权重赋予其所挂载的主干网络结构的节点上,根据该节点的所属单元,将分支网结构的管段长度赋给所属单元。Step 41: Assign the weight of the branch network structure to the node of the backbone network structure to which it is mounted, and assign the length of the pipe section of the branch network structure to the unit according to the unit to which the node belongs.
步骤42,选择社区子团中权重最小的节点,合并其邻接节点中权重最小的节点为新节点,新节点权重由原节点与原节点之间的边权重的和相加得到。当权重最小的两个节点并不存在直接拓扑关联时,分别计算两节点加入邻居时外包矩形的面积大小,选择面积变化较大的合并方案。Step 42 , select the node with the smallest weight in the community subgroup, merge the node with the smallest weight among its adjacent nodes as a new node, and the new node weight is obtained by adding the sum of the edge weights between the original node and the original node. When the two nodes with the smallest weight do not have direct topological associations, the area of the outer rectangle when the two nodes are added to the neighbors are calculated respectively, and the merging scheme with a larger area change is selected.
步骤43,重复步骤42,直到所有节点合并完成,得到不同分区方案下的各分区。Step 43: Repeat step 42 until all nodes are merged to obtain each partition under different partition schemes.
步骤44,分别计算不同分区方案下的各分区长度的方差,选取方差最小的分区方案。长度方差相等时,使用外包矩形的面积作为判断条件。Step 44: Calculate the variance of each partition length under different partition schemes, and select the partition scheme with the smallest variance. When the length variances are equal, the area of the enclosing rectangle is used as the judgment condition.
步骤5,输出管网分区结果,包括矢量数据以及分区的管网长度信息。
优选的:步骤1中构造管网拓扑无向图的方法如下:Preferably: the method for constructing the undirected graph of the pipe network topology in step 1 is as follows:
步骤11,采集管网设备(如三通、阀门井、泄气等设施设备),以及管段的相关信息(如材质、管径等),管网的对象建模需要将管网矢量数据(包括管点数据和管段数据)进行概念的抽象。首先对管点数据和管段数据进行检查,确保每条管段是两个管点的连线,管段内部没有多余管点设备。对不符合要求的管段和管点进行修正,删除缺少端点管点的管段,打断内部有其他管点的管段。在完成检查的基础上,将管点抽象成节点,将管段抽象成连接节点的边,将管段的长度作为边的权重,构造管网的拓扑图。Step 11: Collect pipe network equipment (such as tee, valve well, venting and other facilities and equipment), and related information of pipe sections (such as material, pipe diameter, etc.) point data and pipe segment data) for conceptual abstraction. First, check the pipe point data and pipe segment data to ensure that each pipe segment is a connection between two pipe points and that there is no redundant pipe point equipment inside the pipe segment. Correct pipe segments and pipe points that do not meet the requirements, delete pipe segments with missing end point pipe points, and break pipe segments with other pipe points inside. On the basis of completing the inspection, the pipe points are abstracted into nodes, the pipe segments are abstracted into edges connecting nodes, and the length of the pipe segments is used as the weight of the edges to construct the topological graph of the pipe network.
步骤12,依次对每个节点进行分析,找到与该节点共边的邻接节点,构造节点的邻 接表,若节点与节点相连,则邻接表中增加一条记录,是节点编 号,、分别表示第个节点。 Step 12: Analyze each node in turn, find the adjacent nodes that share the same edge with the node, and construct the node's adjacency list. with node If connected, add a record to the adjacency list , is the node number, , respectively represent the node.
步骤13,因为对管网构造了无向图,所以管点不区分入度与出度,所以按照节点编号大小规则,删除重复的节点邻接信息,依据邻接表形成管网拓扑无向图G。Step 13: Since an undirected graph is constructed for the pipe network, the pipe points do not distinguish between in-degree and out-degree. Therefore, according to the node number size rule, the duplicate node adjacency information is deleted, and the pipe network topology undirected graph G is formed according to the adjacency table.
优选的:步骤2中提取管网拓扑无向图中的供水管网的主干网络结构和分支网络结构的方法如下:Preferably: the method for extracting the backbone network structure and branch network structure of the water supply pipe network in the undirected graph of the pipe network topology in step 2 is as follows:
步骤21,遍历管网拓扑无向图中的每一节点,若节点没有相邻的节点,则将该节点记录为离散值,并删除该节点。Step 21, traverse each node in the undirected graph of the pipe network topology, if the node has no adjacent node, record the node as a discrete value, and delete the node.
步骤22,遍历管网拓扑无向图中的每一条边,,是边的编号,表示第条边,是节点编号,表示第个节点,若节点的邻接节点数大于 节点的邻接节点数,且节点仅和节点相邻,则为的父节点,更新父子关系表, 并删除边和节点。 Step 22, traverse each edge in the undirected graph of the pipe network topology , , is the edge number, means the first stripe, is the node number, means the first nodes, if the node The number of adjacent nodes is greater than the node the number of adjacent nodes, and the node and node only adjacent, then for the parent node, update the parent-child relationship table, and delete the edge and node .
步骤23,重复步骤21和步骤22,直到没有节点可以简化,管网拓扑无向图中剩下的结构即为管网的主干骨架网络结构R。In step 23, steps 21 and 22 are repeated until no nodes can be simplified, and the remaining structure in the undirected graph of the pipe network topology is the backbone skeleton network structure R of the pipe network.
步骤24,根据父子关系表,对于父子关系表中的任一节点V g1 ,找到其前驱节点V j1 ,若V j1 仍然在父子关系表中,则继续查找V j1 的前驱节点V k1 ,依次类推,直到前驱节点不存在或为主干骨架网络结构中的点,根据此规则构建树形结构T,该树形结构T即为分支网结构,g1、j1、k1是节点编号,分别表示第g1、j1、k1个节点。Step 24: According to the parent-child relationship table, for any node V g1 in the parent-child relationship table, find its predecessor node V j1 , if V j1 is still in the parent-child relationship table, continue to search for the predecessor node V k1 of V j1 , and so on. , until the precursor node does not exist or is a point in the backbone skeleton network structure, build a tree structure T according to this rule, the tree structure T is the branch network structure, g1 , j1 , k1 are the node numbers, representing the first g1 , j1 and k1 nodes.
优选的:步骤5中输出管网分区结果的方法如下:Preferably: the method for outputting the pipe network partition result in
步骤51,将分区编号赋值给最小分区单元,以及单元内部的所有节点,得到管点的分区编号表。Step 51: Assign the partition number to the smallest partition unit and all nodes inside the unit to obtain the partition number table of the pipe point.
步骤52,将分区编号表按照管点的标识字段和矢量数据进行关联。Step 52, associate the partition number table with the vector data according to the identification field of the pipe point.
步骤53,统计不同分区的管段长度,若一个管段两个管点为同一分区,则将此管段的长度记录为此分区的长度。否则忽略此管段长度。Step 53: Count the lengths of pipe sections in different partitions, and if two pipe points in one pipeline section are in the same partition, record the length of this pipeline section as the length of this partition. Otherwise this segment length is ignored.
步骤54,输出关联了分区表的矢量数据和各个分区的长度统计。Step 54, outputting the vector data associated with the partition table and the length statistics of each partition.
优选的:步骤3中管网结构图G=G(V,E),V为管点抽象成的节点,E为管段抽象成的边,社区发现即在管网结构图G中确定nc个单元,nc≥1,使得各个单元的节点集合构成节点V的一个覆盖。Preferably: in step 3, the pipe network structure diagram G=G(V, E), V is the node abstracted by the pipe point, E is the edge abstracted by the pipe segment, and the community discovery is to determine nc units in the pipe network structure diagram G , nc≥1, so that the node set of each unit constitutes a cover of node V.
本发明相比现有技术,具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
(1)本发明划分区域的过程是“离散—聚合”的过程,利用了社区发现算法寻找保持连通性的最小分区单元,顾及长度、面积等约束条件进行分区生成。因此,划分的各分区管网总长度即普查工作量基本保持相当,在普查工作面积方面进行了优化,将有利于普查时工作量的合理分配。(1) The process of dividing the area in the present invention is a "discrete-aggregation" process. The community discovery algorithm is used to find the smallest division unit that maintains connectivity, and the division is generated in consideration of constraints such as length and area. Therefore, the total length of the divided pipeline network, that is, the census workload is basically the same, and the optimization of the census work area will facilitate the rational distribution of the workload during the census.
(2)顾及了管线实体的连接关系,保证了区域内部管网的完整性,传统格网划分分区等方法割裂了管段,增加了普查工作的冗余性。(2) Taking into account the connection relationship of pipeline entities, the integrity of the internal pipeline network in the region is ensured. The traditional grid division and partitioning methods separate the pipeline sections and increase the redundancy of the census work.
(3)传统管网分区方法以管网首尾相连为特征,提取环状管段作为主干网,在城市局部地区管网普查中,由于数据的缺少而该特征表现为不适用。本发明的裁剪算法,能克服该缺陷,获得管网拓扑结构的主、次管段。(3) The traditional pipe network partition method is characterized by the end-to-end connection of the pipe network, and the annular pipe segment is extracted as the backbone network. In the census of the pipe network in local areas of the city, this feature is not applicable due to the lack of data. The clipping algorithm of the invention can overcome this defect and obtain the primary and secondary pipe sections of the pipe network topology structure.
(4)划分区域数量能根据用户灵活设置,具有较强的灵活性,而传统格网划分方法只能取偶数个数。(4) The number of divided areas can be flexibly set according to the user, which has strong flexibility, while the traditional grid division method can only take an even number.
附图说明Description of drawings
图1为管网的主干骨架网络结构示意图。Figure 1 is a schematic diagram of the backbone network structure of the pipe network.
图2为管网的树状结构示意图。FIG. 2 is a schematic diagram of the tree structure of the pipe network.
图3为最小单元的聚合过程示意图。Figure 3 is a schematic diagram of the polymerization process of the minimum unit.
图4为某市给水管网主干骨架网络。Figure 4 shows the backbone skeleton network of a city's water supply network.
图5为将某市管网分为2个分区时的示意图。Fig. 5 is a schematic diagram when a city's pipeline network is divided into two partitions.
图6为将某市管网分为4个分区时的示意图。Fig. 6 is a schematic diagram when a city's pipeline network is divided into 4 partitions.
图7为将某市管网分为5个分区时的示意图。Fig. 7 is a schematic diagram when a city's pipeline network is divided into 5 partitions.
具体实施方式Detailed ways
下面结合附图和具体实施例,进一步阐明本发明,应理解这些实例仅用于说明本发明而不用于限制本发明的范围,在阅读了本发明之后,本领域技术人员对本发明的各种等价形式的修改均落于本申请所附权利要求所限定的范围。Below in conjunction with the accompanying drawings and specific embodiments, the present invention will be further clarified. It should be understood that these examples are only used to illustrate the present invention and are not used to limit the scope of the present invention. Modifications in the form of valence all fall within the scope defined by the appended claims of the present application.
一种市政管理中面向地下管网普查的分区方法,包括以下步骤:A zoning method for underground pipe network census in municipal management, comprising the following steps:
步骤1,收集管网设备(如三通、阀门井、泄气等设施设备),以及管段的相关信息(如材质、管径等)。本方法需要进行二次抽象,第一次将管网设备抽象为矢量点,管段抽象为矢量线,根据综合管点数据和管段数据形成管网矢量数据。第二次抽象将管点管段作为统一的空间实体对象,作为整体由欧式空间向拓扑空间进行投影。根据管网矢量数据将管点抽象成节点,将管段抽象成连接节点的边,将管段的长度作为边的权重,构造管网拓扑无向图。Step 1: Collect pipe network equipment (such as tee, valve well, venting and other facilities and equipment), and related information of pipe sections (such as material, pipe diameter, etc.). This method requires secondary abstraction. For the first time, the pipe network equipment is abstracted as a vector point, and the pipe segment is abstracted as a vector line, and the pipe network vector data is formed according to the comprehensive pipe point data and pipe segment data. The second abstraction takes the pipe point and the pipe segment as a unified spatial entity object, and projects from the Euclidean space to the topological space as a whole. According to the pipe network vector data, the pipe points are abstracted into nodes, the pipe segments are abstracted into the edges connecting the nodes, and the length of the pipe segments is used as the weight of the edges to construct the undirected topological graph of the pipe network.
构造管网拓扑无向图的方法如下:The method of constructing the undirected graph of the pipe network topology is as follows:
步骤11,管网矢量数据(shapefile格式)包括管点数据和管段数据。对管点数据和管段数据进行检查,确保每条管段是两个管点的连线,管段内部没有管点。对不符合要求的管段和管点进行修正,删除缺少端点管点的管段,打断内部有其他管点的管段。在完成检查的基础上,将管点抽象成节点,将管段抽象成连接节点的边,将管段的长度作为边的权重,构造管网的拓扑图。Step 11, the pipe network vector data (shapefile format) includes pipe point data and pipe segment data. Check the pipe point data and pipe segment data to ensure that each pipe segment is a line connecting two pipe points and that there are no pipe points inside the pipe segment. Correct pipe segments and pipe points that do not meet the requirements, delete pipe segments with missing end point pipe points, and break pipe segments with other pipe points inside. On the basis of completing the inspection, the pipe points are abstracted into nodes, the pipe segments are abstracted into edges connecting nodes, and the length of the pipe segments is used as the weight of the edges to construct the topological graph of the pipe network.
步骤12,依次对每个节点进行分析,找到与该节点共边的邻接节点,构造节点的邻 接表,若节点与节点相连,则邻接表中增加一条记录,是节点编 号,、分别表示第个节点。 Step 12: Analyze each node in turn, find the adjacent nodes that share the same edge with the node, and construct the node's adjacency list. with node If connected, add a record to the adjacency list , is the node number, , respectively represent the node.
步骤13,按照节点编号大小规则,删除重复的节点邻接信息,比如邻接表中的两条 记录,若节点编号大,则删除邻接表,依据邻接表形成管网拓扑无向 图G。 Step 13: Delete duplicate node adjacency information, such as two records in the adjacency table, according to the node number size rule ,like If the node number is large, delete the adjacency list , and form the undirected graph G of the pipe network topology according to the adjacency list.
步骤2,步骤1得到的管网拓扑无向图包括主干网络结构和分支网络结构,主干骨架网络结构是整个管网的核心,主要由主线管网和部分涉及关键拓扑位置的支线管网构成的。分支网络结构有明显的前驱后继关系,形成有层次的树形结构,其中只有一个前驱节点,而无后继节点的为叶子节点。如图1、2所示,管网在空间结构上可分为主干网络结构和树状结构。主干管段承载整个管网主要的负载功能,如图1所示。当管道铺设进入居民小区或是新建区域时,往往呈现为树状结构,如图2所示。利用这一特性,执行裁剪算法,迭代删除叶子节点,可以提取管网拓扑无向图中的供水管网的主干网络结构和分支网络结构。Step 2, the undirected graph of the pipe network topology obtained in step 1 includes the backbone network structure and the branch network structure. The backbone skeleton network structure is the core of the entire pipe network, which is mainly composed of the main line pipe network and some branch pipe networks involving key topological positions. . The branch network structure has obvious predecessor and successor relationship, forming a hierarchical tree structure, in which there is only one predecessor node, and the leaf node without successor node. As shown in Figures 1 and 2, the spatial structure of the pipe network can be divided into a backbone network structure and a tree structure. The main pipe section carries the main load functions of the entire pipe network, as shown in Figure 1. When the pipeline is laid into a residential area or a new area, it often presents a tree-like structure, as shown in Figure 2. Using this feature, the cutting algorithm is executed to delete leaf nodes iteratively, and the backbone network structure and branch network structure of the water supply pipe network in the undirected graph of the pipe network topology can be extracted.
提取管网拓扑无向图中的供水管网的主干网络结构和分支网络结构的方法如下:The method of extracting the backbone network structure and branch network structure of the water supply pipe network in the undirected graph of the pipe network topology is as follows:
步骤21,遍历管网拓扑无向图中的每一节点,若节点没有相邻的节点,则将该节点记录为离散值,并删除该节点。Step 21, traverse each node in the undirected graph of the pipe network topology, if the node has no adjacent node, record the node as a discrete value, and delete the node.
步骤22,遍历管网拓扑无向图中的每一条边,,是边的编号,表示第条边,是节点编号,表示第个节点,若节点的邻接节点数大于 节点的邻接节点数,且节点仅和节点相邻,则为的父节点,更新父子关系表, 并删除边和节点 。 Step 22, traverse each edge in the undirected graph of the pipe network topology , , is the edge number, means the first stripe, is the node number, means the first nodes, if the node The number of adjacent nodes is greater than the node the number of adjacent nodes, and the node and node only adjacent, then for the parent node, update the parent-child relationship table, and delete the edge and node .
步骤23,重复步骤21和步骤22,直到没有节点可以删除,管网拓扑无向图中剩下的结构即为管网的主干骨架结构R,该结构是整个管网的核心,主要由主线管网和部分涉及关键拓扑位置的支线管网构成的,是减除可以删除的支线管网之后的结构,有部分边缘的主干线在拓扑结构上并不重要,反之,有一些支线具有重要的拓扑结构上的地位,通过上述步骤,可以减少管线级别对网路结构的影响,构成最适合普查分区的管网结构。Step 23: Repeat steps 21 and 22 until no nodes can be deleted. The remaining structure in the undirected graph of the pipe network topology is the backbone skeleton structure R of the pipe network, which is the core of the entire pipe network and is mainly managed by the main line. It consists of a network and some branch pipelines involving key topological positions. It is a structure after subtracting branch pipelines that can be deleted. There are some edge trunk lines that are not topologically important. On the contrary, some branch lines have important topology. The status of the structure, through the above steps, the influence of the pipeline level on the network structure can be reduced, and the pipeline network structure most suitable for the census division can be formed.
步骤24,根据父子关系表,对于父子关系表中的任一节点V g1 ,可以找到其前驱节点V j1 ,若V j1 仍然在父子关系表中,则继续查找V j1 的前驱节点V k1 ,依次类推,直到前驱节点不存在或为主干骨架结构中的点,根据此规则构建树形结构T,该树形结构T即为分支网结构,g1、j1、k1是节点编号,分别表示第g1、j1、k1个节点。Step 24: According to the parent-child relationship table, for any node V g1 in the parent-child relationship table, its predecessor node V j1 can be found. If V j1 is still in the parent-child relationship table, continue to search for the predecessor node V k1 of V j1 , and sequentially. By analogy, until the predecessor node does not exist or is a point in the backbone skeleton structure, a tree structure T is constructed according to this rule. The tree structure T is the branch network structure, and g1 , j1 , k1 are the node numbers, representing g1 , j1 and k1 nodes.
步骤3,根据得到的主干网络结构和分支网络结构将供水管网划分为nc个单元。Step 3: Divide the water supply pipe network into nc units according to the obtained backbone network structure and branch network structure.
管网结构图G=G(V,E),V为管点抽象成的节点,E为管段抽象成的边,社区发现即在管网结构图G中确定nc个单元,nc≥1,使得各个单元的节点集合构成节点V的一个覆盖。Pipe network structure graph G=G(V, E), V is the node abstracted by the pipe point, E is the edge abstracted by the pipe segment, community discovery is to determine nc units in the pipe network structure graph G, nc≥1, so that The set of nodes of each element constitutes a cover of node V.
将供水管网划分为nc个单元的方法如下:The method of dividing the water supply network into nc units is as follows:
步骤31,将主干网络结构中的每个节点看成一个独立的单元,初始单元的数目与节点个数相同。In step 31, each node in the backbone network structure is regarded as an independent unit, and the number of initial units is the same as the number of nodes.
步骤32,对每个节点i,尝试把节点i分配到其邻接节点所在的单元中,并计算分配前与分配后的模块度差值ΔQ,并记录模块度差值ΔQ最大的那个邻接节点。如果最大的ΔQ>0,则把节点i分配到ΔQ最大的那个邻接节点所在的单元,否则放弃此次划分。模块度差值的计算公式如下:Step 32: For each node i , try to allocate node i to the unit where its adjacent nodes are located, calculate the modularity difference ΔQ before and after allocation, and record the adjacent node with the largest modularity difference ΔQ. If the largest ΔQ>0, then assign node i to the unit where the adjacent node with the largest ΔQ is located, otherwise give up the division. The formula for calculating the modularity difference is as follows:
其中ΔQ表示模块度差值,TopologySim表示两个相邻节点的拓扑相似度,i,n是节点编 号,i表示第i个节点,n为i的邻接节点,是单元C内的权重之和,表示单元C的内 部权重,是连接单元C的外部连接的权重之和,表示连接单元C的外部权重,C 表示邻接节点n所在的单元,是节点i与内部节点的连接权重相加的和,是连接节 点i的外部连接的权重之和,为整个网络的权重之和。 where ΔQ represents the modularity difference, TopologySim represents the topology similarity of two adjacent nodes, i,n is the node number, i represents the ith node, n is the adjacent node of i , is the sum of the weights within cell C, represents the internal weight of unit C, is the sum of the weights of the outer connections of the connection unit C, represents the external weight of the connection unit C, C represents the unit where the adjacent node n is located, is the sum of the connection weights of node i and internal nodes, is the sum of the weights of the outer connections connecting node i , is the sum of the weights of the entire network.
步骤33,重复步骤32,直到所有节点的所属单元不再发生变化。Step 33: Repeat step 32 until the units to which all nodes belong are no longer changed.
步骤34,将步骤33得到的具有相同的归属的节点,视作一个新的节点,重新构造子图,两个新节点之间的权重为相应两个单元之间所有边的权重之和。In step 34, the node with the same attribution obtained in step 33 is regarded as a new node, and the subgraph is reconstructed, and the weight between the two new nodes is the sum of the weights of all the edges between the corresponding two units.
步骤35,给定最小社区子团分辨率参数,将步骤34得到的子图作为输入,重新执行步骤31到步骤34,直到达给定的最小社区子团分辨率参数,得到最小社区子团以及社区子团。Step 35: Given the minimum community subgroup resolution parameter, take the subgraph obtained in step 34 as input, and re-execute steps 31 to 34 until the given minimum community subgroup resolution parameter is reached, and obtain the minimum community subgroup and community subgroup.
步骤36,将最小社区子团作为管网的最小分区单元,输出其及其与社区子团的连接关系。Step 36, take the smallest community subgroup as the smallest partition unit of the pipe network, and output its connection relationship with the community subgroup.
步骤4,根据指定分区数量,以长度相当为收敛条件,实现管网最小分区单元聚合(动态聚合)。当权重较小的邻接节点有多个时,计算此节点分别加入邻居时外包矩形的面积大小,将节点归属于面积较小的邻接节点。通过长度与面积的二元判断,最终确定子团的归属情况。具体公式如下:Step 4: According to the specified number of partitions, and with the length equivalent as the convergence condition, realize the aggregation (dynamic aggregation) of the smallest partition unit of the pipe network. When there are multiple adjacent nodes with smaller weights, calculate the area size of the outer rectangle when this node is added to the neighbor respectively, and assign the node to the adjacent node with smaller area. Through the binary judgment of length and area, the attribution of the subcluster is finally determined. The specific formula is as follows:
其中,表示节点i被选为社区子团的概率,D(i)定义为节点i到邻居子团欧氏空 间的质心的距离,表示节点i的所有邻接节点n到节点i的距离平方和。此外,不 同于一般的社区发现算法的收敛条件,本方法还从面积分配的角度,定义空间面积上的收 敛条件: in, represents the probability that node i is selected as a community subgroup, D ( i ) is defined as the distance from node i to the centroid of the Euclidean space of neighbor subgroups, Represents the sum of squared distances from all adjacent nodes n of node i to node i . In addition, different from the convergence conditions of general community discovery algorithms, this method also defines the convergence conditions on the space area from the perspective of area allocation:
其中,其中,表示每个分区面积的最小值,表示分区数,为候选节点,是第个分区,m i 为邻接节点的质心。根据不同的收敛数,选择取极值点处的 数值,作为最优的子团分配方式。 of which, represents the minimum value of the area of each partition, represents the number of partitions, is a candidate node, is the first partitions, where m i is the centroid of adjacent nodes. According to different convergence numbers, choose The value at the extreme point is taken as the optimal subcluster allocation method.
最小单元的聚合过程如下所示:The aggregation process of the smallest unit is as follows:
步骤41,将分支网结构的权重赋予其所挂载的主干网络结构的节点上,根据该节点的所属单元,将分支网结构的管段长度赋给所属单元。Step 41: Assign the weight of the branch network structure to the node of the backbone network structure to which it is mounted, and assign the length of the pipe section of the branch network structure to the unit according to the unit to which the node belongs.
步骤42,选择社区子团中权重最小的节点,合并其邻接节点中权重最小的节点为新节点,新节点权重由原节点与原节点之间的边权重的和相加得到。Step 42 , select the node with the smallest weight in the community subgroup, merge the node with the smallest weight among its adjacent nodes as a new node, and the new node weight is obtained by adding the sum of the edge weights between the original node and the original node.
步骤43,重复步骤42,直到所有节点合并完成,得到不同分区方案下的各分区。Step 43: Repeat step 42 until all nodes are merged to obtain each partition under different partition schemes.
步骤44,分别计算不同分区方案下的各分区长度的方差,选取方差最小的分区方案。长度方差相等时,使用外包矩形的面积作为判断条件。Step 44: Calculate the variance of each partition length under different partition schemes, and select the partition scheme with the smallest variance. When the length variances are equal, the area of the enclosing rectangle is used as the judgment condition.
如图3所示,一个单元构成的拓扑网络共有a~h共计8个小单元,按照定义的规则,逐次确定每个节点等级。As shown in Figure 3, a topology network composed of a unit has a total of 8 small units a~h, and each node level is determined successively according to the defined rules.
第一次迭代,选择主干骨架节点上挂载有叶子节点的节点,按照裁剪的方式再合并单元,所以c归属于b、g和h归属于e,此时把整个主干骨架网络分成四个部分。In the first iteration, select the node with leaf nodes mounted on the backbone skeleton node, and then merge the units according to the cutting method, so c belongs to b, g and h belong to e, at this time, the entire backbone skeleton network is divided into four parts .
第二次迭代,选择最小的节点a,其归属于权重最低的邻接节点b或d,此时为三份网的方案。以此类推,将d、e合并,形成管网的二分方案。In the second iteration, select the smallest node a, which belongs to the adjacent node b or d with the lowest weight. By analogy, d and e are combined to form a dichotomous scheme of the pipe network.
最终所有小单元收敛到一个代表管网整体的节点。Eventually all the small units converge to a node representing the whole pipe network.
步骤5,输出管网分区结果,包括矢量数据以及分区的管网长度信息以及外包矩形的面积信息。Step 5: Output the pipe network partition result, including vector data, the pipe network length information of the partition, and the area information of the outer rectangle.
输出管网分区结果的方法如下:The method of outputting the pipe network partition results is as follows:
步骤51,将分区编号赋值给最小分区单元,以及单元内部的所有节点,得到管点的分区编号表。Step 51: Assign the partition number to the smallest partition unit and all nodes inside the unit to obtain the partition number table of the pipe point.
步骤52,将分区编号表按照管点的标识字段和矢量数据进行关联。Step 52, associate the partition number table with the vector data according to the identification field of the pipe point.
步骤53,统计不同分区的管段长度,若一个管段两个管点为同一分区,则将此管段的长度记录为此分区的长度。否则忽略此管段长度。Step 53: Count the lengths of pipe sections in different partitions, and if two pipe points in one pipeline section are in the same partition, record the length of this pipeline section as the length of this partition. Otherwise this segment length is ignored.
步骤54,输出关联了分区表的矢量数据和各个分区的长度统计。Step 54, outputting the vector data associated with the partition table and the length statistics of each partition.
示例Example
以示例给水管网数据为例,其覆盖面积约为10.2平方公里,管网数据包含管点12807个,管段15114条,总长度为102.78km。对管网分别进行2分、4分和5分的划分方案。管网结构如图4所示。Taking the sample water supply pipe network data as an example, its coverage area is about 10.2 square kilometers, the pipe network data includes 12,807 pipe points, 15,114 pipe sections, and the total length is 102.78km. The pipeline network is divided into 2 points, 4 points and 5 points respectively. The pipe network structure is shown in Figure 4.
如图5所示,将管网分为2个分区时:分区1共包含6676个管点,7917条管段,管段总长度为58.172km。分区2共包含6131个管点,7197条管段,管段总长度为44.608km,面积分别为4.04km2和3.98km2。As shown in Figure 5, when the pipeline network is divided into two partitions: partition 1 contains a total of 6676 pipeline points and 7917 pipeline segments, and the total length of the pipeline segments is 58.172km. Division 2 contains a total of 6131 pipe points and 7197 pipe sections with a total length of 44.608km and an area of 4.04km 2 and 3.98km 2 respectively.
如图6所示,将管网分为4个分区时:1至4分区分别包含3488个、2833个、3145个、3341个管点。3644条、3698条、3759条、4034条管段。管段总长度分别为24.39km、25.61km、23.34km、30.66km。面积分别为2.01km2、1.99km2、2.15km2和1.99km2。As shown in Figure 6, when the pipe network is divided into 4 partitions: partitions 1 to 4 contain 3488, 2833, 3145 and 3341 pipe points respectively. 3644, 3698, 3759, 4034 pipe sections. The total lengths of the pipe sections are 24.39km, 25.61km, 23.34km and 30.66km respectively. The areas are 2.01km 2 , 1.99km 2 , 2.15km 2 and 1.99km 2 respectively.
如图7所示,将管网分为5个分区时:1至5分区分别包含2760个、2253个、3328个、2106个、2360个管点。2704条、2890条、3892条、2874条、2934条管段。管段总长度分别为25.04km、25.26km、25.21km、25.81km。面积分别为1.24km2、1.16km2、1.33km2、1.40km2和1.52km2。As shown in Figure 7, when the pipe network is divided into 5 partitions: partitions 1 to 5 contain 2760, 2253, 3328, 2106 and 2360 pipe points respectively. 2704, 2890, 3892, 2874, 2934 pipe sections. The total lengths of the pipe sections are 25.04km, 25.26km, 25.21km and 25.81km respectively. The areas are 1.24km 2 , 1.16km 2 , 1.33km 2 , 1.40km 2 and 1.52km 2 respectively.
本发明克服了城市地下管网普查工作中传统规则格网分区方法破坏管网连续性、普查工作量不均等缺陷,实现了以普查公里数为指标的合理管网分区。The invention overcomes the defects of the traditional regular grid partition method in the census work of the urban underground pipeline network, which destroys the continuity of the pipeline network and the census workload is uneven, and realizes the reasonable pipeline network partition with the number of census kilometers as the index.
以上所述仅是本发明的优选实施方式,应当指出:对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above is only the preferred embodiment of the present invention, it should be pointed out that: for those skilled in the art, without departing from the principle of the present invention, several improvements and modifications can also be made, and these improvements and modifications are also It should be regarded as the protection scope of the present invention.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010400805.0A CN111353202B (en) | 2020-05-13 | 2020-05-13 | A zoning method for underground pipe network census in municipal management |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010400805.0A CN111353202B (en) | 2020-05-13 | 2020-05-13 | A zoning method for underground pipe network census in municipal management |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111353202A true CN111353202A (en) | 2020-06-30 |
CN111353202B CN111353202B (en) | 2020-08-28 |
Family
ID=71195094
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010400805.0A Active CN111353202B (en) | 2020-05-13 | 2020-05-13 | A zoning method for underground pipe network census in municipal management |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111353202B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112182861A (en) * | 2020-09-17 | 2021-01-05 | 南昌航空大学 | Fine analysis method for parameter space of structural vibration active control system |
CN113312735A (en) * | 2021-05-19 | 2021-08-27 | 太原理工大学 | DMA partition method for urban water supply pipe network |
CN114648150A (en) * | 2020-12-21 | 2022-06-21 | 中国电建集团华东勘测设计研究院有限公司 | Water supply pipe network optimization partitioning method based on improved modularity index |
CN115134209A (en) * | 2022-05-13 | 2022-09-30 | 中国船舶重工集团公司第七一九研究所 | Pipe network area determination method and device, electronic equipment and storage medium |
CN115795122A (en) * | 2023-01-31 | 2023-03-14 | 中国水利水电科学研究院 | Topological relation carding method for urban drainage pipe network |
CN116504050A (en) * | 2022-09-27 | 2023-07-28 | 东南大学 | A Special Event City Partitioning Method Based on Multimodal Public Transit Trip Data |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024771A (en) * | 2018-09-13 | 2018-12-18 | 上海万朗水务科技有限公司 | Underground pipe network monitoring management system |
CN109214549A (en) * | 2018-08-01 | 2019-01-15 | 武汉众智鸿图科技有限公司 | A kind of water supply network auxiliary DMA partition method and system based on graph theory |
CN109660596A (en) * | 2018-11-12 | 2019-04-19 | 中国恩菲工程技术有限公司 | Monitoring method, device, server, storage medium and the system of pipeline O&M |
CN110334850A (en) * | 2019-05-30 | 2019-10-15 | 中国地质大学(武汉) | A design and optimization method for valve layout of water supply network |
-
2020
- 2020-05-13 CN CN202010400805.0A patent/CN111353202B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109214549A (en) * | 2018-08-01 | 2019-01-15 | 武汉众智鸿图科技有限公司 | A kind of water supply network auxiliary DMA partition method and system based on graph theory |
CN109024771A (en) * | 2018-09-13 | 2018-12-18 | 上海万朗水务科技有限公司 | Underground pipe network monitoring management system |
CN109660596A (en) * | 2018-11-12 | 2019-04-19 | 中国恩菲工程技术有限公司 | Monitoring method, device, server, storage medium and the system of pipeline O&M |
CN110334850A (en) * | 2019-05-30 | 2019-10-15 | 中国地质大学(武汉) | A design and optimization method for valve layout of water supply network |
Non-Patent Citations (5)
Title |
---|
XUEHONG ZHU等: "Modeling the high-resolution dynamic exposure to flooding in a city region", 《HYDROLOGY AND EARTH SYSTEM SCIENCES》 * |
李化雨 等: "供水管网计算分区方法的比较分析", 《哈尔滨工业大学学报》 * |
赵元正 等: "基于MapX的区域规划信息系统的设计与实现", 《基于MAPX的区域规划信息系统的设计与实现》 * |
飞翔: "智慧水务供水管网远程监测系统", 《HTTP://JZ.DOCIN.COM/P-1972317730.HTML》 * |
高金良 等: "结合图论的供水管网PMA分区方法", 《哈尔滨工业大学学报》 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112182861A (en) * | 2020-09-17 | 2021-01-05 | 南昌航空大学 | Fine analysis method for parameter space of structural vibration active control system |
CN112182861B (en) * | 2020-09-17 | 2022-05-13 | 南昌航空大学 | A Fine Analysis Method of Parameter Space of Active Control System for Structural Vibration |
CN114648150A (en) * | 2020-12-21 | 2022-06-21 | 中国电建集团华东勘测设计研究院有限公司 | Water supply pipe network optimization partitioning method based on improved modularity index |
CN114648150B (en) * | 2020-12-21 | 2023-02-14 | 中国电建集团华东勘测设计研究院有限公司 | Water supply pipe network optimization partitioning method based on improved modularity index |
CN113312735A (en) * | 2021-05-19 | 2021-08-27 | 太原理工大学 | DMA partition method for urban water supply pipe network |
CN113312735B (en) * | 2021-05-19 | 2022-06-03 | 太原理工大学 | A method of DMA partitioning of urban water supply network |
CN115134209A (en) * | 2022-05-13 | 2022-09-30 | 中国船舶重工集团公司第七一九研究所 | Pipe network area determination method and device, electronic equipment and storage medium |
CN115134209B (en) * | 2022-05-13 | 2023-10-27 | 中国船舶重工集团公司第七一九研究所 | Pipe network area determining method and device, electronic equipment and storage medium |
CN116504050A (en) * | 2022-09-27 | 2023-07-28 | 东南大学 | A Special Event City Partitioning Method Based on Multimodal Public Transit Trip Data |
CN115795122A (en) * | 2023-01-31 | 2023-03-14 | 中国水利水电科学研究院 | Topological relation carding method for urban drainage pipe network |
CN115795122B (en) * | 2023-01-31 | 2023-05-12 | 中国水利水电科学研究院 | Urban drainage pipe network topological relation carding method |
Also Published As
Publication number | Publication date |
---|---|
CN111353202B (en) | 2020-08-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111353202B (en) | A zoning method for underground pipe network census in municipal management | |
Agarwal et al. | Parametric and kinetic minimum spanning trees | |
CN107330030B (en) | A hierarchical network construction method for massive road network data compression storage | |
CN105630988A (en) | Method and system for rapidly detecting space data changes and updating data | |
CN110728305A (en) | Mining method of taxi passenger hot spot area based on grid information entropy clustering algorithm | |
CN117235950B (en) | Natural gas pipe network steady-state simulation method, medium and equipment based on Newton iteration method | |
CN112966385A (en) | Method and system for identifying topology weak points of power distribution network frame | |
CN111190955B (en) | Management, distribution and dispatching through checking method based on knowledge graph | |
CN113706333A (en) | Method and system for automatically generating topology island of power distribution network | |
Basaraner et al. | A structure recognition technique in contextual generalisation of buildings and built-up areas | |
CN112925784A (en) | Actual population data multi-scale spatialization method | |
CN111814528A (en) | A city-level classification method for night-light images based on connectivity analysis | |
CN115081910A (en) | Robustness evaluation method for urban multimodal public transport network | |
CN104318501A (en) | Pipeline network topological relation establishment method, device and system | |
Zheng et al. | Topic model-based road network inference from massive trajectories | |
Bakalov et al. | A network model for the utility domain | |
CN111226254A (en) | Reliability of web maps | |
Tian et al. | Multilevel partitioning with multiple strategies for complex water distribution network | |
CN118313099A (en) | Pipe network pipe explosion comprehensive analysis system based on 3DGIS platform | |
CN113821550B (en) | Road network topological graph dividing method, device, equipment and computer program product | |
Zhao et al. | A framework for group converging pattern mining using spatiotemporal trajectories | |
CN113343565B (en) | Neighborhood effect mode construction and CA simulation method and system considering spatial heterogeneity | |
CN112287052B (en) | River network relation expression method for river length system informatization application | |
CN109242132A (en) | Subregion peak load prediction technique based on MapReduce frame | |
CN102142000A (en) | Multi-scale triangulated irregular network (TIN) library coupled storage method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |