CN111350368A - A kind of high-altitude edge protection safety railing for steel structure construction - Google Patents

A kind of high-altitude edge protection safety railing for steel structure construction Download PDF

Info

Publication number
CN111350368A
CN111350368A CN202010206369.3A CN202010206369A CN111350368A CN 111350368 A CN111350368 A CN 111350368A CN 202010206369 A CN202010206369 A CN 202010206369A CN 111350368 A CN111350368 A CN 111350368A
Authority
CN
China
Prior art keywords
edge protection
steel
protection safety
structure construction
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010206369.3A
Other languages
Chinese (zh)
Inventor
蔡静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202010206369.3A priority Critical patent/CN111350368A/en
Publication of CN111350368A publication Critical patent/CN111350368A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3223Means supported by building floors or flat roofs, e.g. safety railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及钢结构施工技术领域,尤其涉及一种钢结构施工用高空临边防护安全栏杆,通过于筒状立柱与钢平台之间采用磁力座连接,从而可在钢平台上快速安装和拆除该栏杆,快速转移场地;且该栏杆具有可以实行标准化加工,经济性好,可多次重复使用,使用中安全稳定性高,制作及组装简单,能实现标准化生产的优点,可广泛用于钢结构高空施工的临边防护作业中。

Figure 202010206369

The invention relates to the technical field of steel structure construction, in particular to a high-altitude edge protection safety railing for steel structure construction. The railing can quickly transfer the site; and the railing has the advantages of standardized processing, good economy, repeated use, high safety and stability in use, simple production and assembly, and can realize standardized production. It can be widely used in steel structures In the edge protection operation of high-altitude construction.

Figure 202010206369

Description

一种钢结构施工用高空临边防护安全栏杆A kind of high-altitude edge protection safety railing for steel structure construction

技术领域technical field

本发明涉及建筑施工技术领域,尤其涉及一种钢结构施工用高空临边防护安全栏杆。The invention relates to the technical field of building construction, in particular to a high-altitude edge protection safety railing for steel structure construction.

背景技术Background technique

随着国民经济的发展,出现了越来越多的钢结构高层建筑、钢结构桥梁、钢结构设备等,在高空钢结构施工时,施工人员经常需要在高空平台上行走,必须在钢平台边缘设置高空临边防护栏杆来保证高空作业人员的安全。With the development of the national economy, more and more steel structure high-rise buildings, steel structure bridges, steel structure equipment, etc. have appeared. During the construction of high-altitude steel structures, construction workers often need to walk on the high-altitude platform and must walk on the edge of the steel platform. Set up high-altitude border guardrails to ensure the safety of high-altitude workers.

传统的钢结构施工用高空临边防护栏杆采用与钢平台焊接的连接方式,焊接连接方式虽然牢固可靠,但存在以下缺点:1)临时栏杆移动不便,由于临时栏杆与钢平台焊接,若施工位置改变,只能重新制作安装新的临时栏杆,或将原有的临时栏杆切割后重新移至新的位置焊接,费时费力。2)临时栏杆与钢平台焊接,当拆除临时栏杆时,需切割掉临时栏杆与钢平台之间的连接焊缝,后续需对该钢平台的切割处进行打磨、补漆处理,浪费大量的财力。3)临时栏杆与钢平台母材焊接,不可避免的将损伤原有钢平台母材的性能,降低结构性能,在一些重要结构上设计是不允许焊接临时结构的。4)临时栏杆在使用完成后由于切割,栏杆立柱会变短,临时栏杆的高度已不满足要求,这些临时栏杆往往报废或将立杆重新接长,造成大量的浪费;这些都是本领域技术人员所不希望见到的。The traditional high-altitude protective railing for steel structure construction adopts the welding connection method with the steel platform. Although the welding connection method is firm and reliable, it has the following disadvantages: 1) The temporary railing is inconvenient to move. Because the temporary railing is welded with the steel platform, if the construction location If it is changed, it can only be re-fabricated and installed with a new temporary railing, or the original temporary railing can be cut and moved to a new location for welding, which is time-consuming and labor-intensive. 2) The temporary railing is welded to the steel platform. When the temporary railing is removed, the welding seam between the temporary railing and the steel platform needs to be cut off, and then the cutting part of the steel platform needs to be polished and painted, which wastes a lot of financial resources. . 3) Welding the temporary railings with the base metal of the steel platform will inevitably damage the performance of the original steel platform base metal and reduce the structural performance. In some important structures, the welding of temporary structures is not allowed. 4) After the temporary railing is cut, the railing column will be shortened, and the height of the temporary railing does not meet the requirements. These temporary railings are often scrapped or the vertical rails are re-lengthened, causing a lot of waste; these are all skilled in the art people do not want to see.

发明内容SUMMARY OF THE INVENTION

针对上述存在的问题,本发明公开了一种钢结构施工用高空临边防护安全栏杆,其中,包括磁力座、立柱结构、吊环、螺杆,垫板,调节螺母,钢丝绳和横杆;In view of the above existing problems, the present invention discloses a high-altitude edge protection safety railing for steel structure construction, which includes a magnetic base, a column structure, a lifting ring, a screw rod, a backing plate, an adjusting nut, a steel wire rope and a cross bar;

所述立柱结构包括空心底座和筒状立柱,所述筒状立柱的下端固定在所述空心底座上并与所述空心底座相连通,所述空心底座设置于所述钢平台上,且所述磁力座吸附在所述钢平台上并位于所述空心底座内;The column structure includes a hollow base and a cylindrical column, the lower end of the cylindrical column is fixed on the hollow base and communicated with the hollow base, the hollow base is arranged on the steel platform, and the The magnetic base is adsorbed on the steel platform and located in the hollow base;

所述调节螺母通过所述垫板设置于所述筒状立柱的上端,所述螺杆与所述调节螺母相适配,所述螺杆的下端依次穿过所述调节螺母和所述垫板设置于所述筒状立柱内,所述吊环设置于所述螺杆的下端,所述钢丝绳的两端分别连接所述吊环和所述磁力座;The adjusting nut is arranged on the upper end of the cylindrical column through the backing plate, the screw rod is matched with the adjusting nut, and the lower end of the screw rod is arranged on the adjusting nut and the backing plate in sequence. In the cylindrical column, the lifting ring is arranged at the lower end of the screw rod, and the two ends of the wire rope are respectively connected to the lifting ring and the magnetic base;

所述横杆垂直连接在所述筒状立柱上。The cross bar is vertically connected to the cylindrical column.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述磁力座的顶部设置有吊耳,所述钢丝绳的下端与所述吊耳连接。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, a lifting lug is provided on the top of the magnetic base, and the lower end of the steel wire rope is connected with the lifting lug.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述吊环和所述螺杆为一体式结构。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, the lifting ring and the screw rod are an integral structure.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述空心底座呈倒U形结构,且所述倒U形结构开口部的两侧均设置有折边。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, the hollow base has an inverted U-shaped structure, and both sides of the opening of the inverted U-shaped structure are provided with folded edges.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述筒状立柱的外侧等间距焊接有固定环,所述横杆通过所述固定环与所述筒状立柱连接。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, the outer side of the cylindrical column is welded with fixed rings at equal intervals, and the cross bar is connected to the cylindrical column through the fixed ring.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述钢丝绳的两端均连接有绳夹。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, both ends of the steel wire rope are connected with rope clips.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述磁力座为手动起重式永磁磁力座。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, the magnetic base is a manual lifting type permanent magnet magnetic base.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述钢丝绳为镀锌钢丝绳。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, the steel wire rope is a galvanized steel wire rope.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述栏杆的相邻立柱结构之间的间距为0.8~1.2m。In the above-mentioned high-altitude edge protection safety railing for steel structure construction, the distance between adjacent column structures of the railing is 0.8-1.2 m.

上述的钢结构施工用高空临边防护安全栏杆,其中,所述空心底座侧壁与所述磁力座之间的间距小于10mm。In the above-mentioned high-altitude edge protection safety rail for steel structure construction, the distance between the side wall of the hollow base and the magnetic base is less than 10 mm.

上述发明具有如下优点或者有益效果:The above invention has the following advantages or beneficial effects:

本发明公开了一种钢结构施工用高空临边防护安全栏杆,通过于筒状立柱与钢平台之间采用磁力座连接,从而可在钢平台上快速安装和拆除该栏杆,快速转移场地;且该栏杆具有可以实行标准化加工,经济性好,可多次重复使用,使用中安全稳定性高,制作及组装简单,能实现标准化生产的优点,可广泛用于钢结构高空施工的临边防护作业中。The invention discloses a high-altitude edge protection safety railing for steel structure construction. By connecting a cylindrical column and a steel platform with a magnetic base, the railing can be quickly installed and removed on the steel platform, and the site can be quickly transferred; and The railing has the advantages of standardized processing, good economy, repeated use, high safety and stability in use, simple production and assembly, and standardized production. It can be widely used for edge protection operations in high-altitude construction of steel structures middle.

附图说明Description of drawings

通过阅读参照以下附图对非限制性实施例所作的详细描述,本发明及其特征、外形和优点将会变得更加明显。在全部附图中相同的标记指示相同的部分。并未可以按照比例绘制附图,重点在于示出本发明的主旨。The present invention and its features, features, and advantages will become more apparent upon reading the detailed description of non-limiting embodiments with reference to the following drawings. Like numbers refer to like parts throughout the drawings. The drawings may not be drawn to scale, emphasis instead being placed upon illustrating the subject matter of the present invention.

图1为本发明实施例中钢结构施工用高空临边防护安全栏杆的结构示意图;Fig. 1 is the structural representation of high-altitude edge protection safety railing for steel structure construction in the embodiment of the present invention;

图2为本发明实施例中立柱结构的结构示意图;2 is a schematic structural diagram of a column structure in an embodiment of the present invention;

图3为本发明实施例中立柱结构的透视图;3 is a perspective view of a column structure in an embodiment of the present invention;

图4为本发明实施例中磁力座的结构示意图;4 is a schematic structural diagram of a magnetic base in an embodiment of the present invention;

图中:1是筒状立柱、2是空心底座、3是固定环,4是横杆,11是磁力座,111是吊耳,12是绳夹,13是螺杆,14是吊环,15是活动垫板,16是调节螺母,17是钢丝绳。In the figure: 1 is a cylindrical column, 2 is a hollow base, 3 is a fixed ring, 4 is a cross bar, 11 is a magnetic base, 111 is a lifting lug, 12 is a rope clip, 13 is a screw, 14 is a lifting ring, and 15 is a movable Backing plate, 16 is the adjusting nut, 17 is the wire rope.

具体实施方式Detailed ways

下面结合附图和具体的实施例对本发明中的结构作进一步的说明,但是不作为本发明的限定。The structure of the present invention will be further described below with reference to the accompanying drawings and specific embodiments, but it is not intended to limit the present invention.

如图1~4所示,本发明公开了一种钢结构施工用高空临边防护安全栏杆,具体的,该高空临边防护安全栏杆包括磁力座11,立柱结构、吊环14、螺杆13,垫板15,调节螺母16,钢丝绳17和横杆4;该立柱结构包括空心底座2和筒状立柱1,该筒状立柱1的下端固定在空心底座2上并与该空心底座2相连通(即筒状立柱1的内腔与空心底座2的内腔相连通),该空心底座2设置于钢平台上且与该钢平台之间不固定,该磁力座11吸附在钢平台上并位于该空心底座2内;该调节螺母16通过垫板15设置于筒状立柱1的上端,该螺杆13与调节螺母16相适配,该螺杆13的下端依次穿过调节螺母16和垫板15设置于筒状立柱1内,该吊环14设置于该螺杆13的下端,该钢丝绳17的两端分别连接吊环14和磁力座11,从而可以通过螺杆13上的调节螺母16来调整钢丝绳17的张拉力,以将该筒状立柱1紧紧压紧在钢平台上,进而实现了筒状立柱1与钢平台间的固定连接;另外,该筒状立柱1上焊接有用于放置横杆4的固定环3(圆环),该横杆4通过固定环3垂直连接在该筒状立柱1上,成片的筒状立柱1与横杆4即组成了一个高空临边安全栏杆体系。As shown in Figures 1 to 4, the present invention discloses a high-altitude edge protection safety railing for steel structure construction. Plate 15, adjusting nut 16, wire rope 17 and cross bar 4; the column structure includes a hollow base 2 and a cylindrical column 1, and the lower end of the cylindrical column 1 is fixed on the hollow base 2 and communicated with the hollow base 2 (ie The inner cavity of the cylindrical column 1 is communicated with the inner cavity of the hollow base 2), the hollow base 2 is arranged on the steel platform and is not fixed with the steel platform, and the magnetic base 11 is adsorbed on the steel platform and located in the hollow Inside the base 2; the adjusting nut 16 is arranged on the upper end of the cylindrical column 1 through the backing plate 15, the screw 13 is matched with the adjusting nut 16, and the lower end of the screw 13 is arranged in the barrel through the adjusting nut 16 and the backing plate 15 in turn. In the vertical column 1, the lifting ring 14 is arranged at the lower end of the screw 13, and the two ends of the wire rope 17 are respectively connected to the lifting ring 14 and the magnetic base 11, so that the tension of the wire rope 17 can be adjusted by the adjusting nut 16 on the screw rod 13 to The cylindrical column 1 is tightly pressed on the steel platform, thereby realizing the fixed connection between the cylindrical column 1 and the steel platform; in addition, the cylindrical column 1 is welded with a fixing ring 3 ( The cross bar 4 is vertically connected to the cylindrical column 1 through the fixing ring 3, and the cylindrical column 1 and the cross bar 4 form a high-altitude edge safety railing system.

在本发明的一个优选的实施例中,上述空心底座2呈倒U形结构,且该倒U形结构开口部的两侧均设置有折边,具体的,该空心底座2采用8mm钢板焊接而成,该空心底座2与钢平台接触处外翻50mm宽度的90度折边,以增大该空心底座2与钢平台之间的接触面积,上述结构所用材质均为Q235钢材,该空心底座2所围的空间与磁力座11外观尺寸相匹配,具体的,该空心底座2侧壁与磁力座11之间的间距小于或等于10mm。In a preferred embodiment of the present invention, the hollow base 2 has an inverted U-shaped structure, and both sides of the opening of the inverted U-shaped structure are provided with folded edges. Specifically, the hollow base 2 is welded with 8mm steel plates. The hollow base 2 and the steel platform contact place with a 90-degree folded edge with a width of 50mm to increase the contact area between the hollow base 2 and the steel platform. The materials used in the above structure are Q235 steel, and the hollow base 2 The enclosed space matches the external size of the magnetic base 11 . Specifically, the distance between the side wall of the hollow base 2 and the magnetic base 11 is less than or equal to 10 mm.

具体的,上述筒状立柱1和底座2的总高度为1.2m,该筒状立柱1采用规格规格D48*3的圆管。Specifically, the total height of the above-mentioned cylindrical column 1 and the base 2 is 1.2 m, and the cylindrical column 1 adopts a circular tube with a specification of D48*3.

在本发明的一个优选的实施例中,上述筒状立柱1的外侧等间距焊接有固定环3(圆环)以便于安装横杆4,上述横杆4通过固定环3与筒状立柱1连接。In a preferred embodiment of the present invention, the outer side of the cylindrical column 1 is welded with fixed rings 3 (circular rings) at equal intervals to facilitate the installation of the cross bar 4 , and the cross bar 4 is connected to the cylindrical column 1 through the fixed ring 3 .

在本发明的一个优选的实施例中,上述磁力座11的顶部设置有吊耳,该钢丝绳17的下端与吊耳连接。In a preferred embodiment of the present invention, the top of the magnetic base 11 is provided with a lifting lug, and the lower end of the wire rope 17 is connected to the lifting lug.

在本发明的一个优选的实施例中,上述吊环14和螺杆13为一体式结构,即该吊环14和螺杆13可采用一体式的吊环螺杆。In a preferred embodiment of the present invention, the above-mentioned lifting ring 14 and the screw rod 13 have an integral structure, that is, the lifting ring 14 and the screw rod 13 may adopt an integral lifting ring screw.

在本发明的一个优选的实施例中,上述钢丝绳17的两端均连接有绳夹12。In a preferred embodiment of the present invention, both ends of the wire rope 17 are connected with rope clips 12 .

在本发明的一个优选的实施例中,上述磁力座11为手动起重式永磁磁力座11,优选400KG磁力的磁力座11,以保证栏杆底座2与钢平台足够的压紧力。In a preferred embodiment of the present invention, the above-mentioned magnetic base 11 is a manual lifting type permanent magnet magnetic base 11 , preferably a magnetic base 11 of 400KG magnetic force, to ensure sufficient pressing force between the railing base 2 and the steel platform.

在本发明的一个优选的实施例中,上述钢丝绳17为镀锌钢丝绳,具体的,该镀锌钢丝绳的直径为8mm。In a preferred embodiment of the present invention, the above-mentioned steel wire rope 17 is a galvanized steel wire rope. Specifically, the diameter of the galvanized steel wire rope is 8 mm.

在本发明的一个优选的实施例中,上述栏杆的相邻立柱结构之间的间距为0.8~1.2m(例如0.8m、1m、1.1m或者1.2m等)。In a preferred embodiment of the present invention, the spacing between adjacent column structures of the above-mentioned railing is 0.8-1.2m (eg, 0.8m, 1m, 1.1m or 1.2m, etc.).

在本发明的一个优选的实施例中,上述垫板15的厚度为8mm。In a preferred embodiment of the present invention, the thickness of the above-mentioned backing plate 15 is 8 mm.

具体的,上述钢结构施工用高空临边防护安全栏杆的安装方法具体为:Specifically, the installation method of the above-mentioned high-altitude edge protection safety railing for steel structure construction is as follows:

首先在钢平台上放上磁力座11,然后将包括筒状立柱1和空心底座2的立柱结构放置在钢平台上,该筒状立柱1上焊接有等间距的固定环3,该筒状立柱1顶部设置有吊环螺杆,且该吊环螺杆吊环端位于下方,螺杆端位于上方,该磁力座11位于该空心底座2内,之后将钢丝绳17穿过筒状立柱1,并将钢丝绳17的一端与磁力座11上的吊耳连接,钢丝绳17的另一端与吊环螺杆的吊环端连接,且该钢丝绳17端部采用相应的绳夹12绑扎;于该筒状立柱1顶部设置有活动垫板15,并将吊环螺杆的螺杆端穿过活动垫板15,调节螺母16套设于吊环螺杆的螺杆端上并位于活动垫板15之上,旋转调节螺母16时,吊环螺杆沿筒状立柱1轴线向上移动,钢丝绳17被逐渐张紧,从而可以将空心底座2紧紧压紧在钢平台上,由于磁力座11拉力的作用,筒状立柱1顶部不能左右摆动,且由于空心底座2与钢平台之间较大的接触面积,从而使得空心底座2也不能在水平方向上移动,从而可以将立柱结构紧紧固定在钢平台上。之后将多立柱结构在钢平台上按间距1m均匀布置,然后将横杆4穿过筒状立柱1上的固定环3,横杆4可采用D33.5*3的圆管,或直径8mm的镀锌钢丝绳,该横杆4与立柱上的固定环3可采用U型绳卡固定;多个立柱与横杆4连接成空间稳定结构,使该安全栏杆能非常牢固的固定在钢平台上。成片的立柱结构与横杆4组成了一个高空临边安全栏杆体系。First, put the magnetic base 11 on the steel platform, and then place the column structure including the cylindrical column 1 and the hollow base 2 on the steel platform. The cylindrical column 1 is welded with fixed rings 3 at equal intervals. 1. A lifting ring screw is arranged on the top, and the lifting ring end of the lifting ring screw is located below, the screw end is located above, the magnetic base 11 is located in the hollow base 2, and then the wire rope 17 is passed through the cylindrical column 1, and one end of the wire rope 17 is connected to the hollow base 2. The lifting lugs on the magnetic base 11 are connected, the other end of the steel wire rope 17 is connected with the lifting ring end of the lifting ring screw, and the end of the steel wire rope 17 is bound by the corresponding rope clip 12; the top of the cylindrical column 1 is provided with a movable pad 15, The screw end of the lifting ring screw is passed through the movable backing plate 15, and the adjusting nut 16 is sleeved on the screw end of the lifting ring screw and located on the movable backing plate 15. When the adjusting nut 16 is rotated, the lifting ring screw is upward along the axis of the cylindrical column 1. Moving, the wire rope 17 is gradually tensioned, so that the hollow base 2 can be tightly pressed on the steel platform. Due to the pulling force of the magnetic base 11, the top of the cylindrical column 1 cannot swing left and right. Therefore, the hollow base 2 cannot move in the horizontal direction, so that the column structure can be tightly fixed on the steel platform. After that, the multi-column structure is evenly arranged on the steel platform at a distance of 1m, and then the cross bar 4 is passed through the fixing ring 3 on the cylindrical column 1. Galvanized steel wire rope, the cross bar 4 and the fixing ring 3 on the column can be fixed by U-shaped rope clips; multiple columns and the cross bar 4 are connected to form a spatially stable structure, so that the safety railing can be very firmly fixed on the steel platform. The piece of column structure and the cross bar 4 form a high-altitude side-by-side safety railing system.

本实施例中该栏杆的立柱结构和横杆可采用工厂定型化制作,现场安装方便,无需动用焊接设备,气割设备,不需动火作业,不会对原有的钢平台母材造成任何损伤,移动时只需将磁力座的手动开关置于关的状态就可移动栏杆的立柱,移动或拆除快速方便。In this embodiment, the column structure and the horizontal bars of the railing can be made by factory stereotypes, which is convenient for on-site installation, does not need to use welding equipment, gas cutting equipment, does not need hot work, and will not cause any damage to the original steel platform base material. , When moving, just put the manual switch of the magnetic base in the off state to move the column of the railing, which is quick and convenient to move or remove.

本领域技术人员应该理解,本领域技术人员在结合现有技术以及上述实施例可以实现变化例,在此不做赘述。这样的变化例并不影响本发明的实质内容,在此不予赘述。It should be understood by those skilled in the art that those skilled in the art can implement variations in combination with the prior art and the above-mentioned embodiments, which will not be repeated here. Such variations do not affect the essential content of the present invention, and will not be repeated here.

以上对本发明的较佳实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,其中未尽详细描述的设备和结构应该理解为用本领域中的普通方式予以实施;任何熟悉本领域的技术人员,在不脱离本发明技术方案范围情况下,都可利用上述揭示的方法和技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例,这并不影响本发明的实质内容。因此,凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均仍属于本发明技术方案保护的范围内。The preferred embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in ordinary ways in the art; any person skilled in the art, without departing from the present invention Within the scope of the technical solution of the invention, many possible changes and modifications can be made to the technical solution of the present invention by using the methods and technical contents disclosed above, or modified into equivalent embodiments with equivalent changes, which does not affect the essence of the present invention. . Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solutions of the present invention still fall within the protection scope of the technical solutions of the present invention.

Claims (10)

1.一种钢结构施工用高空临边防护安全栏杆,其特征在于,包括磁力座、立柱结构、吊环、螺杆,垫板,调节螺母,钢丝绳和横杆;1. a high-altitude edge protection safety railing for steel structure construction, is characterized in that, comprises magnetic base, column structure, lifting ring, screw rod, backing plate, adjusting nut, wire rope and cross bar; 所述立柱结构包括空心底座和筒状立柱,所述筒状立柱的下端固定在所述空心底座上并与所述空心底座相连通,所述空心底座设置于所述钢平台上,且所述磁力座吸附在所述钢平台上并位于所述空心底座内;The column structure includes a hollow base and a cylindrical column, the lower end of the cylindrical column is fixed on the hollow base and communicated with the hollow base, the hollow base is arranged on the steel platform, and the The magnetic base is adsorbed on the steel platform and located in the hollow base; 所述调节螺母通过所述垫板设置于所述筒状立柱的上端,所述螺杆与所述调节螺母相适配,所述螺杆的下端依次穿过所述调节螺母和所述垫板设置于所述筒状立柱内,所述吊环设置于所述螺杆的下端,所述钢丝绳的两端分别连接所述吊环和所述磁力座;The adjusting nut is arranged on the upper end of the cylindrical column through the backing plate, the screw rod is matched with the adjusting nut, and the lower end of the screw rod is arranged on the adjusting nut and the backing plate in sequence. In the cylindrical column, the lifting ring is arranged at the lower end of the screw rod, and the two ends of the wire rope are respectively connected to the lifting ring and the magnetic base; 所述横杆垂直连接在所述筒状立柱上。The cross bar is vertically connected to the cylindrical column. 2.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述磁力座的顶部设置有吊耳,所述钢丝绳的下端与所述吊耳连接。2 . The high-altitude edge protection safety railing for steel structure construction according to claim 1 , wherein a lifting lug is provided on the top of the magnetic base, and the lower end of the steel wire rope is connected with the lifting lug. 3 . 3.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述吊环和所述螺杆为一体式结构。3 . The high-altitude edge protection safety railing for steel structure construction according to claim 1 , wherein the lifting ring and the screw rod are integral structures. 4 . 4.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述空心底座呈倒U形结构,且所述倒U形结构开口部的两侧均设置有折边。4. The high-altitude edge protection safety railing for steel structure construction according to claim 1, wherein the hollow base is in an inverted U-shaped structure, and both sides of the opening of the inverted U-shaped structure are provided with folds. side. 5.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述筒状立柱的外侧等间距焊接有固定环,所述横杆通过所述固定环与所述筒状立柱连接。5. The high-altitude edge protection safety railing for steel structure construction according to claim 1, characterized in that, fixed rings are welded at equal intervals on the outer side of the cylindrical column, and the cross bar is connected to the Tubular column connection. 6.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述钢丝绳的两端均连接有绳夹。6 . The high-altitude edge protection safety railing for steel structure construction according to claim 1 , wherein both ends of the steel wire rope are connected with rope clips. 7 . 7.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述磁力座为手动起重式永磁磁力座。7 . The high-altitude edge protection safety rail for steel structure construction according to claim 1 , wherein the magnetic base is a manual lifting type permanent magnet magnetic base. 8 . 8.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述钢丝绳为镀锌钢丝绳。8 . The high-altitude edge protection safety railing for steel structure construction according to claim 1 , wherein the steel wire rope is a galvanized steel wire rope. 9 . 9.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述栏杆的相邻立柱结构之间的间距为0.8~1.2m。9 . The high-altitude edge protection safety railing for steel structure construction according to claim 1 , wherein the distance between adjacent column structures of the railing is 0.8-1.2 m. 10 . 10.如权利要求1所述的钢结构施工用高空临边防护安全栏杆,其特征在于,所述空心底座侧壁与所述磁力座之间的间距小于或等于10mm。10 . The high-altitude edge protection safety railing for steel structure construction according to claim 1 , wherein the distance between the side wall of the hollow base and the magnetic base is less than or equal to 10 mm. 11 .
CN202010206369.3A 2020-03-23 2020-03-23 A kind of high-altitude edge protection safety railing for steel structure construction Pending CN111350368A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010206369.3A CN111350368A (en) 2020-03-23 2020-03-23 A kind of high-altitude edge protection safety railing for steel structure construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010206369.3A CN111350368A (en) 2020-03-23 2020-03-23 A kind of high-altitude edge protection safety railing for steel structure construction

Publications (1)

Publication Number Publication Date
CN111350368A true CN111350368A (en) 2020-06-30

Family

ID=71193096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010206369.3A Pending CN111350368A (en) 2020-03-23 2020-03-23 A kind of high-altitude edge protection safety railing for steel structure construction

Country Status (1)

Country Link
CN (1) CN111350368A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065082A (en) * 2020-07-21 2020-12-11 太原重工股份有限公司 Protective fence device for construction
CN116876866A (en) * 2023-08-31 2023-10-13 中建四局建设发展有限公司 A pole double-channel safety device with intelligent reminder and its control method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009167492A (en) * 2008-01-18 2009-07-30 Ulvac Japan Ltd Film deposition source, and sputtering system
CN204238149U (en) * 2014-07-18 2015-04-01 高长恩 Flexible protection movable isolation guardrail
CN204775842U (en) * 2015-05-28 2015-11-18 沪东中华造船(集团)有限公司 A railing post for boats and ships hatch edge
CN108104494A (en) * 2017-12-28 2018-06-01 中车建设工程有限公司 Electromagnetism edge protection device
CN208899895U (en) * 2018-08-24 2019-05-24 云南建投第二建设有限公司 A kind of construction is with can epicyclic-type protective device
CN110205957A (en) * 2019-06-10 2019-09-06 南京广奥景观装饰工程有限公司 Novel flexible anticollision barrier

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009167492A (en) * 2008-01-18 2009-07-30 Ulvac Japan Ltd Film deposition source, and sputtering system
CN204238149U (en) * 2014-07-18 2015-04-01 高长恩 Flexible protection movable isolation guardrail
CN204775842U (en) * 2015-05-28 2015-11-18 沪东中华造船(集团)有限公司 A railing post for boats and ships hatch edge
CN108104494A (en) * 2017-12-28 2018-06-01 中车建设工程有限公司 Electromagnetism edge protection device
CN208899895U (en) * 2018-08-24 2019-05-24 云南建投第二建设有限公司 A kind of construction is with can epicyclic-type protective device
CN110205957A (en) * 2019-06-10 2019-09-06 南京广奥景观装饰工程有限公司 Novel flexible anticollision barrier

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065082A (en) * 2020-07-21 2020-12-11 太原重工股份有限公司 Protective fence device for construction
CN116876866A (en) * 2023-08-31 2023-10-13 中建四局建设发展有限公司 A pole double-channel safety device with intelligent reminder and its control method
CN116876866B (en) * 2023-08-31 2025-05-23 中建四局建设发展有限公司 A pole double-lane safety device with intelligent reminder and control method thereof

Similar Documents

Publication Publication Date Title
CN111350368A (en) A kind of high-altitude edge protection safety railing for steel structure construction
CN206873307U (en) Movable type bridge justifies pier stud work high above the ground operating platform
CN209193460U (en) A kind of movable lifting Large-size rebar cage weld job operating platform
CN108252218A (en) A kind of large span cable-carried arch bridge steel lagging jack external wrapping concrete bed die slide device
CN204225471U (en) A kind of cantilever steel girder structure through walls
CN201125536Y (en) Window construction protection device
CN106012834A (en) A special-shaped anti-symmetrical steel main tower internal support and tensioning system with space-distorted curves
CN213573124U (en) Simple and easy integration entrance to a cave protector
CN207633866U (en) A kind of municipal works fence easy to remove
CN110593553A (en) End template reinforcement device
CN206397211U (en) A kind of bridge construction deposits protector with steel reinforcement cage
CN204059920U (en) Shaped steel roof beam fixed ground anchor structure
CN207314793U (en) Operating platform between a kind of regularization precast stair
CN212077954U (en) A Portable Assembled and Turnable Deep Foundation Pit Steel Box Supporting Structure
CN204571266U (en) A kind of anchor structure for builder's jack i iron
CN211775082U (en) A kind of tire frame for large-span tubular truss
CN203222981U (en) Suspended platform for steel reinforced concrete cantilever structure construction
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN104652837B (en) A kind of method and structure for increasing steel pipe frame newly on former concrete pipe support
CN210151590U (en) Highway bridge cylindrical mold top operation platform
CN209429521U (en) A prefabricated steel structure integrated floor concrete pouring molding tool
CN109763663B (en) A kind of frame column steel reinforcement protection device and construction method thereof
CN206337823U (en) A kind of dismantled and assembled, adjustable supporting height pump line support and setting tool
CN220580041U (en) A caisson formwork platform
CN221346369U (en) Steel member installation, dismantlement auxiliary fixtures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200630

RJ01 Rejection of invention patent application after publication