CN111255237A - Construction method for controlling overall position of column reinforcement - Google Patents

Construction method for controlling overall position of column reinforcement Download PDF

Info

Publication number
CN111255237A
CN111255237A CN202010169283.8A CN202010169283A CN111255237A CN 111255237 A CN111255237 A CN 111255237A CN 202010169283 A CN202010169283 A CN 202010169283A CN 111255237 A CN111255237 A CN 111255237A
Authority
CN
China
Prior art keywords
column
butterfly
rib
construction method
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010169283.8A
Other languages
Chinese (zh)
Inventor
牛俊平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ruizhou Construction Group Co ltd
Original Assignee
Ruizhou Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ruizhou Construction Group Co ltd filed Critical Ruizhou Construction Group Co ltd
Priority to CN202010169283.8A priority Critical patent/CN111255237A/en
Publication of CN111255237A publication Critical patent/CN111255237A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/18Spacers of metal or substantially of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A construction method for controlling the whole position of a column reinforcement in the construction of constructional engineering. It is at four bights of post suitable for reading, and four butterfly locator cards are established to the nail, come the position of fixed bight post owner muscle, and post bight owner muscle has been fixed a position, and because of the existence of stirrup, whole post muscle position has just also been confirmed.

Description

Construction method for controlling overall position of column reinforcement
Technical Field
The invention relates to an innovative method for controlling the integral deviation of a column bar in the construction of constructional engineering, which is particularly suitable for controlling the integral position of the column bar in a frame structure adopting a wood template.
Background
In the construction of a frame or a frame shear wall structure, a column rib is taken as a vertical continuous transitive connection component, and the integral deviation line outlet of the column rib is a problem which often occurs in the construction. When the edges of the beam and the column are flush, the column rib is integrally displaced due to the collision of the beam and the column rib; deviation caused by cushion block deletion of a protective layer in a column core region due to post-positioning of a beam rib in a construction process; and deviation caused by concrete vibration interference due to dense reinforcing steel bars in the core area, and the like.
Disclosure of Invention
In order to solve the problem that the existing construction process is easy to cause deviation of the column reinforcement, the invention provides a positioning clamp which can position the whole position of the column reinforcement and also plays a role of a cushion block of a column reinforcement protective layer.
The process principle is as follows: the position of the column rib is restricted by the column die, and as long as the position of the column die is correct, the position of the column rib is correct under the condition that the relative position of the column rib and the column die is well controlled.
The technical scheme adopted for solving the technical problem is that a template is used as a fixing base surface, four butterfly-shaped positioning clamps are nailed at four corners of an upper opening of a column to fix the positions of main ribs of the corner column, the main ribs of the corner column are positioned, and the positions of the whole column ribs are determined due to the presence of stirrups.
The invention has the advantages of simple and direct control method, easy operation and effective control of the relative position of the frame column reinforcing steel bar and the column mould, thereby effectively controlling the position of the column reinforcing steel bar.
Drawings
The invention is further illustrated by the following figures and examples.
FIG. 1 is a plan view of the butterfly locator card, the principal component of the present invention.
Fig. 2 is a schematic diagram of a butterfly locator card applied to post position control.
In the figure, 1, a butterfly positioning clamp, 2, a column opening mark, 3, a nail, 4, a column main rib, 5, a column stirrup, 6, a beam main rib, 7, a beam stirrup and 8, a column opening line.
The specific implementation mode is as follows:
process flow
Preparing a butterfly-shaped positioning clamp → installing a floor template → binding beam steel bars in place → nailing butterfly-shaped cushion blocks → binding floor steel bars → pouring concrete → paying off and checking the position of column steel bars.
Preparation of butterfly-shaped positioning card
Selecting a galvanized steel plate or a stainless steel plate with the thickness of 0.5mm, and cutting the galvanized steel plate or the stainless steel plate into the shape shown in the figure 1 by adopting a laser cutting method.
Floor formwork installation
Building a floor formwork support frame, placing a beam bottom formwork, correcting the position of the beam bottom formwork by a suspension wire, installing a beam side formwork after fixing, and then installing a flat plate formwork. The key point of the process is to ensure the correct and square position of the column mouth (8).
Beam reinforcement binding in place
And erecting the beam ribs (6) on the template surface of the floor slab for binding and molding, then lifting the beam ribs, removing the supporting pieces, and placing the beam ribs (6) in the beam mold. In this process, it is necessary to ensure that the column reinforcements are symmetrically distributed with respect to the beam reinforcements when the beam reinforcements pass through the column reinforcements. When the beam edge is parallel and level with the column edge, the beam rib is in the house, the column rib is out of the house, and the beam rib avoids the column rib, so that the thickness of the column rib protective layer is ensured to meet the design requirement.
Butterfly-shaped positioning clip for nail
And correcting the position of the column rib, and nailing the butterfly-shaped positioning cards (1) on four corners of the column opening to enable the clamping openings of the positioning cards to clamp the main ribs (4) at the column corner parts. When the nail is arranged, the notch of the positioning mark (2) on the positioning card is aligned with the column port line (8), and the nail (3) is not less than one on each side. For the condition that the beam edge is flush with the column edge, marking a column opening line on one side without a column opening angle by paying off so as to facilitate nailing; in this case, the positioning clamp can be nailed only on one side, and the number of nails is not less than two.
In order to facilitate the pulling out of the nail after the floor bottom die is dismantled, the nail needs to be driven in a straight line and cannot be anchored in a bent mode.
Binding floor slab reinforcing steel bar
Binding the reinforcing steel bars at the bottom layer of the floor slab, laying water and electric pre-buried pipes, sleeving two layers of stirrups on the column reinforcing steel bars after the binding of the reinforcing steel bars at the surface is finished, and binding the two layers of stirrups at the floor position and the 50cm position on the floor respectively to form a whole.
Pouring concrete
And pouring the floor concrete according to the scheme determined by the construction scheme.
Paying-off inspection column rib position
And (4) copying and placing the floor control lines, releasing each axis according to the control lines, then releasing the column contour lines, and checking the deviation control effect of the column ribs.

Claims (2)

1. A construction method for controlling the whole position of a column reinforcement in constructional engineering construction is characterized in that a butterfly-shaped positioning clamp is arranged at a four-corner nail at a column opening to control the corner reinforcement of a column, and further the position of the whole column reinforcement is controlled.
2. The method is characterized in that: the butterfly-shaped positioning clamp is in a butterfly-shaped plane shape, one end of the butterfly-shaped positioning clamp is nailed on the column port template, and the other end of the butterfly-shaped positioning clamp is clamped on the column rib.
CN202010169283.8A 2020-03-12 2020-03-12 Construction method for controlling overall position of column reinforcement Pending CN111255237A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010169283.8A CN111255237A (en) 2020-03-12 2020-03-12 Construction method for controlling overall position of column reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010169283.8A CN111255237A (en) 2020-03-12 2020-03-12 Construction method for controlling overall position of column reinforcement

Publications (1)

Publication Number Publication Date
CN111255237A true CN111255237A (en) 2020-06-09

Family

ID=70949677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010169283.8A Pending CN111255237A (en) 2020-03-12 2020-03-12 Construction method for controlling overall position of column reinforcement

Country Status (1)

Country Link
CN (1) CN111255237A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2362937Y (en) * 1998-07-16 2000-02-09 同济大学 Steel bar fixing clamp for reinforced concrete structure
JP2005171508A (en) * 2003-12-08 2005-06-30 Toda Constr Co Ltd Method of constructing cast-in-place concrete column and positioning tool for column reinforcement used for the method
CN201649666U (en) * 2010-01-04 2010-11-24 江苏江中集团有限公司 Positioning support for manufacturing cylindrical reinforced frames
CN102383496A (en) * 2011-08-26 2012-03-21 章雪峰 Prefabricated steel hoop barrel of reinforced concrete beam column joint and construction method
CN202227590U (en) * 2011-09-27 2012-05-23 中建七局第三建筑有限公司 Column rib locator for reinforced concrete column
CN204663000U (en) * 2015-06-03 2015-09-23 中国葛洲坝集团第六工程有限公司 A kind of concreting frame column bar reinforcement positioning device
CN205777114U (en) * 2016-05-30 2016-12-07 中建八局第三建设有限公司 A kind of Portable column reinforcing bar location instrument
CN207260599U (en) * 2017-08-01 2018-04-20 中国建筑一局(集团)有限公司 A kind of adjustable frame column bar spacer
CN207597587U (en) * 2017-12-18 2018-07-10 许金根 Column muscle location structure when one kind connects precast beam for PC building cast-in-situ columns
CN208950170U (en) * 2018-07-16 2019-06-07 福建建工集团有限责任公司 A kind of frame column reinforcing bar preventing offsetting device
CN110259114A (en) * 2019-05-28 2019-09-20 中国建筑第八工程局有限公司 The construction method of the mould bases of beam slab rod structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2362937Y (en) * 1998-07-16 2000-02-09 同济大学 Steel bar fixing clamp for reinforced concrete structure
JP2005171508A (en) * 2003-12-08 2005-06-30 Toda Constr Co Ltd Method of constructing cast-in-place concrete column and positioning tool for column reinforcement used for the method
CN201649666U (en) * 2010-01-04 2010-11-24 江苏江中集团有限公司 Positioning support for manufacturing cylindrical reinforced frames
CN102383496A (en) * 2011-08-26 2012-03-21 章雪峰 Prefabricated steel hoop barrel of reinforced concrete beam column joint and construction method
CN202227590U (en) * 2011-09-27 2012-05-23 中建七局第三建筑有限公司 Column rib locator for reinforced concrete column
CN204663000U (en) * 2015-06-03 2015-09-23 中国葛洲坝集团第六工程有限公司 A kind of concreting frame column bar reinforcement positioning device
CN205777114U (en) * 2016-05-30 2016-12-07 中建八局第三建设有限公司 A kind of Portable column reinforcing bar location instrument
CN207260599U (en) * 2017-08-01 2018-04-20 中国建筑一局(集团)有限公司 A kind of adjustable frame column bar spacer
CN207597587U (en) * 2017-12-18 2018-07-10 许金根 Column muscle location structure when one kind connects precast beam for PC building cast-in-situ columns
CN208950170U (en) * 2018-07-16 2019-06-07 福建建工集团有限责任公司 A kind of frame column reinforcing bar preventing offsetting device
CN110259114A (en) * 2019-05-28 2019-09-20 中国建筑第八工程局有限公司 The construction method of the mould bases of beam slab rod structure

Similar Documents

Publication Publication Date Title
CN102510927A (en) Adjustable metal formwork system for concrete structures
JP5965544B2 (en) H-bar, and method for installing form using this H-bar and non-metallic plate
KR101747821B1 (en) construction equipment for drainage way and construction method for drainage way
KR20110128396A (en) Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
WO2024001407A1 (en) Positioning apparatus for prefabricated component connection rebar
CN111255237A (en) Construction method for controlling overall position of column reinforcement
JP6616629B2 (en) Grating mounting structure and method
CN107313587A (en) The template fixed system and the construction method of waterproof construction of buildings waterproof structure
CN217537479U (en) Auxiliary curtain wall embedded part embedded positioning device
JP2005016078A (en) Cast-in-place hollow concrete slab, its construction method and spacer-cum-support used therefor
CN112096096B (en) Positioning device for embedded steel plate and construction method thereof
CN210563413U (en) A indent device for cast-in-place horizontal floor
CN209780239U (en) Beam-penetrating sleeve pre-embedding device
CN109267699B (en) Assembled beam slab and construction method
JP4868627B1 (en) A kit consisting of PCa for forming a solid base rising part.
CN112342929A (en) Continuous beam inclined web circular arc section construction method adopting steel-wood mixed template
JPH06316939A (en) Positioning jig for construction work, and construction of building therewith
CN219298756U (en) Guide wall template fixing device based on canopy face crossbeam
WO2017056602A1 (en) Method for constructing concrete foundation top end, and top end form
CN215671080U (en) Shear force wall secretly buries line box positioner
CN219509161U (en) Concrete placement formwork device and wall system
CN212176097U (en) Temporary fixing system for embedded steel plates on surface of wall
CN219753996U (en) Cast-in-situ stair step reinforcing device and cast-in-situ stair step reinforcing template assembly
CN214061940U (en) Precast concrete assembled structure with rib mold structure
CN211286290U (en) Steel bar formwork for BDF hollow pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200609

RJ01 Rejection of invention patent application after publication