CN111255237A - Construction method for controlling overall position of column reinforcement - Google Patents
Construction method for controlling overall position of column reinforcement Download PDFInfo
- Publication number
- CN111255237A CN111255237A CN202010169283.8A CN202010169283A CN111255237A CN 111255237 A CN111255237 A CN 111255237A CN 202010169283 A CN202010169283 A CN 202010169283A CN 111255237 A CN111255237 A CN 111255237A
- Authority
- CN
- China
- Prior art keywords
- column
- butterfly
- rib
- construction method
- post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/18—Spacers of metal or substantially of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A construction method for controlling the whole position of a column reinforcement in the construction of constructional engineering. It is at four bights of post suitable for reading, and four butterfly locator cards are established to the nail, come the position of fixed bight post owner muscle, and post bight owner muscle has been fixed a position, and because of the existence of stirrup, whole post muscle position has just also been confirmed.
Description
Technical Field
The invention relates to an innovative method for controlling the integral deviation of a column bar in the construction of constructional engineering, which is particularly suitable for controlling the integral position of the column bar in a frame structure adopting a wood template.
Background
In the construction of a frame or a frame shear wall structure, a column rib is taken as a vertical continuous transitive connection component, and the integral deviation line outlet of the column rib is a problem which often occurs in the construction. When the edges of the beam and the column are flush, the column rib is integrally displaced due to the collision of the beam and the column rib; deviation caused by cushion block deletion of a protective layer in a column core region due to post-positioning of a beam rib in a construction process; and deviation caused by concrete vibration interference due to dense reinforcing steel bars in the core area, and the like.
Disclosure of Invention
In order to solve the problem that the existing construction process is easy to cause deviation of the column reinforcement, the invention provides a positioning clamp which can position the whole position of the column reinforcement and also plays a role of a cushion block of a column reinforcement protective layer.
The process principle is as follows: the position of the column rib is restricted by the column die, and as long as the position of the column die is correct, the position of the column rib is correct under the condition that the relative position of the column rib and the column die is well controlled.
The technical scheme adopted for solving the technical problem is that a template is used as a fixing base surface, four butterfly-shaped positioning clamps are nailed at four corners of an upper opening of a column to fix the positions of main ribs of the corner column, the main ribs of the corner column are positioned, and the positions of the whole column ribs are determined due to the presence of stirrups.
The invention has the advantages of simple and direct control method, easy operation and effective control of the relative position of the frame column reinforcing steel bar and the column mould, thereby effectively controlling the position of the column reinforcing steel bar.
Drawings
The invention is further illustrated by the following figures and examples.
FIG. 1 is a plan view of the butterfly locator card, the principal component of the present invention.
Fig. 2 is a schematic diagram of a butterfly locator card applied to post position control.
In the figure, 1, a butterfly positioning clamp, 2, a column opening mark, 3, a nail, 4, a column main rib, 5, a column stirrup, 6, a beam main rib, 7, a beam stirrup and 8, a column opening line.
The specific implementation mode is as follows:
process flow
Preparing a butterfly-shaped positioning clamp → installing a floor template → binding beam steel bars in place → nailing butterfly-shaped cushion blocks → binding floor steel bars → pouring concrete → paying off and checking the position of column steel bars.
Preparation of butterfly-shaped positioning card
Selecting a galvanized steel plate or a stainless steel plate with the thickness of 0.5mm, and cutting the galvanized steel plate or the stainless steel plate into the shape shown in the figure 1 by adopting a laser cutting method.
Floor formwork installation
Building a floor formwork support frame, placing a beam bottom formwork, correcting the position of the beam bottom formwork by a suspension wire, installing a beam side formwork after fixing, and then installing a flat plate formwork. The key point of the process is to ensure the correct and square position of the column mouth (8).
Beam reinforcement binding in place
And erecting the beam ribs (6) on the template surface of the floor slab for binding and molding, then lifting the beam ribs, removing the supporting pieces, and placing the beam ribs (6) in the beam mold. In this process, it is necessary to ensure that the column reinforcements are symmetrically distributed with respect to the beam reinforcements when the beam reinforcements pass through the column reinforcements. When the beam edge is parallel and level with the column edge, the beam rib is in the house, the column rib is out of the house, and the beam rib avoids the column rib, so that the thickness of the column rib protective layer is ensured to meet the design requirement.
Butterfly-shaped positioning clip for nail
And correcting the position of the column rib, and nailing the butterfly-shaped positioning cards (1) on four corners of the column opening to enable the clamping openings of the positioning cards to clamp the main ribs (4) at the column corner parts. When the nail is arranged, the notch of the positioning mark (2) on the positioning card is aligned with the column port line (8), and the nail (3) is not less than one on each side. For the condition that the beam edge is flush with the column edge, marking a column opening line on one side without a column opening angle by paying off so as to facilitate nailing; in this case, the positioning clamp can be nailed only on one side, and the number of nails is not less than two.
In order to facilitate the pulling out of the nail after the floor bottom die is dismantled, the nail needs to be driven in a straight line and cannot be anchored in a bent mode.
Binding floor slab reinforcing steel bar
Binding the reinforcing steel bars at the bottom layer of the floor slab, laying water and electric pre-buried pipes, sleeving two layers of stirrups on the column reinforcing steel bars after the binding of the reinforcing steel bars at the surface is finished, and binding the two layers of stirrups at the floor position and the 50cm position on the floor respectively to form a whole.
Pouring concrete
And pouring the floor concrete according to the scheme determined by the construction scheme.
Paying-off inspection column rib position
And (4) copying and placing the floor control lines, releasing each axis according to the control lines, then releasing the column contour lines, and checking the deviation control effect of the column ribs.
Claims (2)
1. A construction method for controlling the whole position of a column reinforcement in constructional engineering construction is characterized in that a butterfly-shaped positioning clamp is arranged at a four-corner nail at a column opening to control the corner reinforcement of a column, and further the position of the whole column reinforcement is controlled.
2. The method is characterized in that: the butterfly-shaped positioning clamp is in a butterfly-shaped plane shape, one end of the butterfly-shaped positioning clamp is nailed on the column port template, and the other end of the butterfly-shaped positioning clamp is clamped on the column rib.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010169283.8A CN111255237A (en) | 2020-03-12 | 2020-03-12 | Construction method for controlling overall position of column reinforcement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010169283.8A CN111255237A (en) | 2020-03-12 | 2020-03-12 | Construction method for controlling overall position of column reinforcement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111255237A true CN111255237A (en) | 2020-06-09 |
Family
ID=70949677
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010169283.8A Pending CN111255237A (en) | 2020-03-12 | 2020-03-12 | Construction method for controlling overall position of column reinforcement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111255237A (en) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2362937Y (en) * | 1998-07-16 | 2000-02-09 | 同济大学 | Steel bar fixing clamp for reinforced concrete structure |
JP2005171508A (en) * | 2003-12-08 | 2005-06-30 | Toda Constr Co Ltd | Method of constructing cast-in-place concrete column and positioning tool for column reinforcement used for the method |
CN201649666U (en) * | 2010-01-04 | 2010-11-24 | 江苏江中集团有限公司 | Positioning support for manufacturing cylindrical reinforced frames |
CN102383496A (en) * | 2011-08-26 | 2012-03-21 | 章雪峰 | Prefabricated steel hoop barrel of reinforced concrete beam column joint and construction method |
CN202227590U (en) * | 2011-09-27 | 2012-05-23 | 中建七局第三建筑有限公司 | Column rib locator for reinforced concrete column |
CN204663000U (en) * | 2015-06-03 | 2015-09-23 | 中国葛洲坝集团第六工程有限公司 | A kind of concreting frame column bar reinforcement positioning device |
CN205777114U (en) * | 2016-05-30 | 2016-12-07 | 中建八局第三建设有限公司 | A kind of Portable column reinforcing bar location instrument |
CN207260599U (en) * | 2017-08-01 | 2018-04-20 | 中国建筑一局(集团)有限公司 | A kind of adjustable frame column bar spacer |
CN207597587U (en) * | 2017-12-18 | 2018-07-10 | 许金根 | Column muscle location structure when one kind connects precast beam for PC building cast-in-situ columns |
CN208950170U (en) * | 2018-07-16 | 2019-06-07 | 福建建工集团有限责任公司 | A kind of frame column reinforcing bar preventing offsetting device |
CN110259114A (en) * | 2019-05-28 | 2019-09-20 | 中国建筑第八工程局有限公司 | The construction method of the mould bases of beam slab rod structure |
-
2020
- 2020-03-12 CN CN202010169283.8A patent/CN111255237A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2362937Y (en) * | 1998-07-16 | 2000-02-09 | 同济大学 | Steel bar fixing clamp for reinforced concrete structure |
JP2005171508A (en) * | 2003-12-08 | 2005-06-30 | Toda Constr Co Ltd | Method of constructing cast-in-place concrete column and positioning tool for column reinforcement used for the method |
CN201649666U (en) * | 2010-01-04 | 2010-11-24 | 江苏江中集团有限公司 | Positioning support for manufacturing cylindrical reinforced frames |
CN102383496A (en) * | 2011-08-26 | 2012-03-21 | 章雪峰 | Prefabricated steel hoop barrel of reinforced concrete beam column joint and construction method |
CN202227590U (en) * | 2011-09-27 | 2012-05-23 | 中建七局第三建筑有限公司 | Column rib locator for reinforced concrete column |
CN204663000U (en) * | 2015-06-03 | 2015-09-23 | 中国葛洲坝集团第六工程有限公司 | A kind of concreting frame column bar reinforcement positioning device |
CN205777114U (en) * | 2016-05-30 | 2016-12-07 | 中建八局第三建设有限公司 | A kind of Portable column reinforcing bar location instrument |
CN207260599U (en) * | 2017-08-01 | 2018-04-20 | 中国建筑一局(集团)有限公司 | A kind of adjustable frame column bar spacer |
CN207597587U (en) * | 2017-12-18 | 2018-07-10 | 许金根 | Column muscle location structure when one kind connects precast beam for PC building cast-in-situ columns |
CN208950170U (en) * | 2018-07-16 | 2019-06-07 | 福建建工集团有限责任公司 | A kind of frame column reinforcing bar preventing offsetting device |
CN110259114A (en) * | 2019-05-28 | 2019-09-20 | 中国建筑第八工程局有限公司 | The construction method of the mould bases of beam slab rod structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102510927A (en) | Adjustable metal formwork system for concrete structures | |
JP5965544B2 (en) | H-bar, and method for installing form using this H-bar and non-metallic plate | |
KR101747821B1 (en) | construction equipment for drainage way and construction method for drainage way | |
KR20110128396A (en) | Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof | |
WO2024001407A1 (en) | Positioning apparatus for prefabricated component connection rebar | |
CN111255237A (en) | Construction method for controlling overall position of column reinforcement | |
JP6616629B2 (en) | Grating mounting structure and method | |
CN107313587A (en) | The template fixed system and the construction method of waterproof construction of buildings waterproof structure | |
CN217537479U (en) | Auxiliary curtain wall embedded part embedded positioning device | |
JP2005016078A (en) | Cast-in-place hollow concrete slab, its construction method and spacer-cum-support used therefor | |
CN112096096B (en) | Positioning device for embedded steel plate and construction method thereof | |
CN210563413U (en) | A indent device for cast-in-place horizontal floor | |
CN209780239U (en) | Beam-penetrating sleeve pre-embedding device | |
CN109267699B (en) | Assembled beam slab and construction method | |
JP4868627B1 (en) | A kit consisting of PCa for forming a solid base rising part. | |
CN112342929A (en) | Continuous beam inclined web circular arc section construction method adopting steel-wood mixed template | |
JPH06316939A (en) | Positioning jig for construction work, and construction of building therewith | |
CN219298756U (en) | Guide wall template fixing device based on canopy face crossbeam | |
WO2017056602A1 (en) | Method for constructing concrete foundation top end, and top end form | |
CN215671080U (en) | Shear force wall secretly buries line box positioner | |
CN219509161U (en) | Concrete placement formwork device and wall system | |
CN212176097U (en) | Temporary fixing system for embedded steel plates on surface of wall | |
CN219753996U (en) | Cast-in-situ stair step reinforcing device and cast-in-situ stair step reinforcing template assembly | |
CN214061940U (en) | Precast concrete assembled structure with rib mold structure | |
CN211286290U (en) | Steel bar formwork for BDF hollow pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200609 |
|
RJ01 | Rejection of invention patent application after publication |