CN111236290A - Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method - Google Patents

Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method Download PDF

Info

Publication number
CN111236290A
CN111236290A CN202010065956.5A CN202010065956A CN111236290A CN 111236290 A CN111236290 A CN 111236290A CN 202010065956 A CN202010065956 A CN 202010065956A CN 111236290 A CN111236290 A CN 111236290A
Authority
CN
China
Prior art keywords
pile foundation
pile
protection device
cavity
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010065956.5A
Other languages
Chinese (zh)
Inventor
周航
王增亮
丁选明
刘汉龙
申航
童龙勇
余昊
殷峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University
Original Assignee
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University filed Critical Chongqing University
Priority to CN202010065956.5A priority Critical patent/CN111236290A/en
Publication of CN111236290A publication Critical patent/CN111236290A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/06Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against corrosion by soil or water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bridges Or Land Bridges (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a simple environment-friendly device suitable for preventing a bridge pier foundation from scouring and a construction method, and relates to the technical field of bridge pile foundation reinforcement and protection. The utility model provides a simple and easy environment-friendly device suitable for pier pile foundation scour prevention, is including the protector that is the loudspeaker form. The inside of the protection device is a cavity S, a plurality of through holes are formed in a top plate above the cavity S, and gravel or water flows into the cavity S through the through holes. The protection device is provided with a pile hole penetrating through the upper plate surface and the lower plate surface of the protection device, the protection device is sleeved on the pile foundation through the pile hole, and the circular bottom plate is attached to the bottom surface of the riverbed. If the pile foundation is the pile foundation of the built bridge, the protection device is divided into a plurality of assembly parts, and the plurality of assembly parts are assembled on site to realize that the protection device is sleeved on the pile foundation. This novel protector can restrain the destruction of horseshoe vortex and wake vortex to the pile foundation, and the device can protect the pile foundation not receive the erosion and corrosion of water with pile foundation contact segment. Meanwhile, the protective device is suitable for the built and non-built bridge pile foundations.

Description

Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method
Technical Field
The invention relates to the technical field of bridge pile foundation reinforcement and protection.
Background
In recent years, the economy of China is rapidly developed, and a large number of large bridges spanning the rivers of the great river, such as a Hongzhu Australian bridge, an east-sea bridge, a Hangzhou Bay bridge, a Lijiatuo bridge in Chongqing city, and the like, are built immediately. Most of the bridges across rivers adopt deep water pile group foundations, and the size and the water blocking area are large. The safety and stability of the bridge pile foundation in the complex water flow environment depend on the stress condition of the bridge pile foundation in the complex water area environment, and are also related to the reduction of the bearing capacity of the pile foundation caused by the shallow burying depth of the bridge pile foundation caused by water flow scouring. And a large number of investigation statistical results also show that one of the main causes of bridge damage is caused by the reduction of the embedded depth of the bridge pier due to the local scouring of the bridge pier foundation.
The existence of bridge pile foundation has changed the rivers environment around the pile foundation, and research shows: when a pile-column structure is built in a water flow environment, the flow field around the structure can be obviously changed, a complex and changeable three-dimensional flow state is formed, a descending flow and a horseshoe vortex can be formed in front of a pile, and a wake vortex can be formed behind the pile. The formation and movement of the horseshoe vortex and the wake vortex enhance the transport capacity of the material on the surface of the riverbed, so that an obvious local scouring pit is formed on the bridge pile foundation, the effective embedding depth of the bridge pile foundation in the bottom bed soil body is reduced, the bearing capacity of the pile foundation is reduced, the safety and the stability of the bridge are greatly influenced, in the mountain city, the water flow velocity is larger, and the influence of water flow scouring on the safety and the stability of the bridge is stronger.
Therefore, it is highly desirable to develop a pier foundation protection device capable of resisting water flow scouring.
Disclosure of Invention
The invention aims to provide a pier foundation protection device capable of resisting water flow scouring and prolonging the service life of a bridge.
The technical scheme adopted for achieving the purpose of the invention is that the simple environment-friendly device suitable for preventing the pier foundation from scouring comprises a trumpet-shaped protective device.
The protection device is characterized in that a cavity S is formed inside the protection device, the part of the protection device above the cavity S is marked as a top plate, and the part of the protection device below the cavity S is marked as a circular bottom plate. The part of the top plate close to the bottom plate is flat.
A plurality of through holes are formed in the top plate, and sand or concrete mortar flows into the cavity S through the through holes.
And a pile foundation is arranged along the axis of the protection device to penetrate through the pile hole, and the pile hole penetrates through the top plate, the cavity S and the circular bottom plate.
The pile foundation poured into the river bed penetrates through the pile hole, and the circular bottom plate is attached to the surface of the river bed.
Further, the pile foundation is a bridge pile foundation which is built or not.
If the pile foundation is the bridge pile foundation of building completion, then protector is formed by a plurality of built-up pieces concatenation. When the protective device is installed, the plurality of assembly parts surround the pile foundation to form a circle, and the plurality of assembly parts are connected with each other, so that the pile foundation penetrates through the pile hole of the spliced protective device.
If the pile foundation is the bridge pile foundation that is not built, during the installation, the pile foundation that has built the completion passes the stake hole from the top.
Furthermore, the shape of the pile hole is matched with the cross section shape of the pile foundation, and a movable gap exists between the pile foundation and the pile hole.
Furthermore, the maximum water depth of the river where the pile foundation is located is a, the height of the protection device is b, a is larger than 0, and b is larger than 0.
When a is less than or equal to 3m, b is 0.5 a. When a is more than 3m, b is more than or equal to 1.5m and less than or equal to 2.5 m.
Furthermore, the thickness of the top plate is 4-7 cm, and the thickness of the circular bottom plate is 5-7 cm.
Based on the construction method of the simple environment-friendly device suitable for preventing the pier foundation from scouring, the construction method comprises the following steps:
1) and surrounding a plurality of the assembly parts into a circle around the pile foundation of the built bridge, and connecting the plurality of the assembly parts by adopting a mortise and tenon structure so that the pile foundation penetrates through the pile holes of the spliced protective device.
2) Gravel or concrete mortar is added into the cavity S through the through holes, and the protection device sinks along the pile foundation under the action of gravity until the circular bottom plate is attached to the surface of the river bed.
Further, the step 2) is followed by a step of fixing the protection device and the pile foundation together by using concrete.
Based on the construction method of the simple environment-friendly device suitable for preventing the pier foundation from scouring, the construction method comprises the following steps:
1) in an unfinished bridge, the cast pile foundation is passed through the pile hole of the protective device from the top.
2) Gravel or concrete mortar is added into the cavity S through the through holes, and the protection device sinks along the pile foundation under the action of gravity until the circular bottom plate is attached to the surface of the river bed.
Further, the step 2) is followed by a step of fixing the protection device and the pile foundation together by using concrete.
The technical effect of the invention is undoubted, the novel protection device can effectively inhibit the damage of horseshoe-shaped vortex and wake vortex to the pile foundation, and the contact part of the device and the pile foundation can protect the pile foundation from erosion corrosion of water. Meanwhile, the protective device can be suitable for bridge pile foundations which are built and planned to be built, and has the characteristics of simple and rapid construction, low cost, safety and environmental protection.
Drawings
FIG. 1 is a schematic view of a protector mounted with a circular section pile foundation;
fig. 2 is a cross-sectional view of a protective device suitable for use with a circular section pile foundation;
FIG. 3 is a schematic view of a protection device for a square section pile foundation for a constructed bridge;
fig. 4 is a schematic view of the installation of the protection device and the square section pile foundation.
In the figure: pile foundation 1, shield 2, top plate 201, through-hole 2011, circular base plate 202, pile hole 203, and assembly 204.
Detailed Description
The present invention is further illustrated by the following examples, but it should not be construed that the scope of the above-described subject matter is limited to the following examples. Various substitutions and alterations can be made without departing from the technical idea of the invention and the scope of the invention is covered by the present invention according to the common technical knowledge and the conventional means in the field.
Example 1:
this embodiment discloses a simple and easy environment-friendly device suitable for pier pile foundation scour prevention, including the protector 2 that is the loudspeaker form.
Referring to fig. 2, the inside of the guard 2 is a cavity S, a portion of the guard 2 above the cavity S is denoted as a top plate 201, and the thickness of the top plate 201 is 4 cm.
The part of the guard 2 below the cavity S is denoted as a circular bottom plate 202, and the thickness of the circular bottom plate 202 is 5 cm. The diameter of the circular base plate 202 is 2-3 times of the cross-sectional area of the pile foundation, namely the action range of the horseshoe vortex and the wake vortex. The top plate 201 is flat near the bottom plate 202.
Referring to fig. 1, a plurality of through holes 2011 are formed in the top plate 201.
Referring to fig. 2, pile holes 203 for pile foundations 1 to pass through are arranged along the axis of the protection device 2, and the pile holes 201 penetrate through the top plate 201, the cavity S and the circular bottom plate 202.
Referring to fig. 1, the pile foundation 1 poured into the river bed passes through the pile hole 203, and the circular bottom plate 202 is attached to the surface of the river bed. The cross-section of stake hole 203 and pile foundation 1 is circular, and the diameter of stake hole 203 is 2cm more than the diameter of pile foundation 1, and stake hole 203 can slide on pile foundation 1 promptly.
In this embodiment, the pile foundation 1 is an unfinished bridge pile foundation, and the maximum water depth of the river in which the pile foundation 1 is located is 3 m. The height of the protection device 2 is 1.5m, and the protection device 2 is made of polytetrafluoroethylene fiber materials. During installation, the top of the poured pile foundation 1 passes through the pile hole 203 from the bottom plate 202, sand flows into the cavity S through the plurality of through holes 2011, and the protection device 2 sinks to the bottom of the pile foundation 1 along the pile foundation 1 under the action of gravity.
Example 2:
this embodiment discloses a simple and easy environment-friendly device suitable for pier pile foundation scour prevention, including the protector 2 that is the loudspeaker form.
The inner part of the protection device 2 is a cavity S, the part of the protection device 2 above the cavity S is marked as a top plate 201, and the thickness of the top plate 201 is 7 cm.
The part of the guard 2 below the cavity S is denoted as a circular bottom plate 202, and the thickness of the circular bottom plate 202 is 7 cm. The diameter of the circular base plate 202 is 2-3 times of the cross-sectional area of the pile foundation, namely the action range of the horseshoe vortex and the wake vortex. The top plate 201 is flat near the bottom plate 202.
A plurality of through holes 2011 are formed in the top plate 201.
Referring to fig. 3, pile holes 203 for pile foundations 1 to pass through are arranged along the axis of the protection device 2, and the pile holes 201 penetrate through the top plate 201, the cavity S and the circular bottom plate 202.
Referring to fig. 4, the pile foundation 1 poured into the river bed passes through the pile hole 203, and the circular bottom plate 202 is attached to the surface of the river bed. The sections of the pile hole 203 and the pile foundation 1 are both square, the side length of the section of the pile hole 203 is 3cm longer than that of the pile foundation 1, namely the pile hole 203 can slide on the pile foundation 1.
In this embodiment, the pile foundation 1 is a constructed bridge pile foundation, the maximum water depth of a river in which the pile foundation 1 is located is 5m, and the height of the protection device 2 is 2 m. Referring to fig. 3, the shielding device 2 is formed by splicing four assembly members 204, and the assembly members 204 are made of high-strength plastic. During the installation, four built-up member 204 encloses into a week around pile foundation 1 to connect four built-up members 204 through the mortise and tenon structure, make pile foundation 1 pass the pile hole 201 of protector 2 that splices, grit or water flow into cavity S through a plurality of through-holes 2011, protector 2 receives the action of gravity to sink to the bottom of pile foundation 1 along pile foundation 1. The top plate 201 is approximately flat closer to the circular bottom plate 202, so that the action range of horseshoe-shaped vortex and wake vortex is changed, the force range is enlarged a little, the influence of concentrated force on the device is avoided, and the influence of contraction scouring on the device is reduced.
Example 3:
the embodiment discloses a construction method of a simple environment-friendly device suitable for preventing erosion of a pier pile foundation based on the device in embodiment 1, and the construction method comprises the following steps:
1) in an unfinished bridge, the top of the cast pile foundation 1 is passed from the floor 202 through the pile hole 201 of the protective device 2.
2) Through a plurality of grit is added to cavity S in through-hole 2011, protector 2 receives the action of gravity along pile foundation 1 to sink until circular bottom plate 202 and riverbed surface laminating.
3) Under special environment or condition, adopt the concrete will protector 2 is together fixed with pile foundation 1, prevents that protector 2 and pile foundation 1 from producing relative slip.
Example 4:
the embodiment is based on the device in embodiment 2, and discloses a construction method of a simple environment-friendly device suitable for preventing erosion of a pier pile foundation, which comprises the following steps:
1) the four assembly parts 204 are surrounded into a circle around the pile foundation 1 of the built bridge, and the four assembly parts 204 are connected with each other by adopting a mortise and tenon structure, so that the pile foundation 1 passes through the pile holes 201 of the spliced protection device 2, and the bottom plate 202 is positioned below the top plate 201.
2) Through a plurality of concrete mortar is added to cavity S in through-hole 2011, and protector 2 receives the action of gravity to sink to the bottom of pile foundation 1 along pile foundation 1.
3) Under special environment or condition, adopt the concrete will protector 2 is together fixed with pile foundation 1, prevents that protector 2 and pile foundation 1 from producing relative slip.
Example 5:
this embodiment discloses a simple and easy environment-friendly device suitable for pier pile foundation scour prevention, including the protector 2 that is the loudspeaker form.
Referring to fig. 2, the inside of the guard 2 is a cavity S, a portion of the guard 2 above the cavity S is denoted as a top plate 201, and a portion of the guard 2 below the cavity S is denoted as a circular bottom plate 202. The top plate 201 is flat near the bottom plate 202.
Referring to fig. 1, a plurality of through holes 2011 are formed in the top plate 201, and concrete mortar flows into the cavity S through the plurality of through holes 2011.
Referring to fig. 2, pile holes 203 for pile foundations 1 to pass through are arranged along the axis of the protection device 2, and the pile holes 201 penetrate through the top plate 201, the cavity S and the circular bottom plate 202.
Referring to fig. 1, the pile foundation 1 poured into the river bed passes through the pile hole 203, and the circular bottom plate 202 is attached to the surface of the river bed.
Example 6:
the main structure of this embodiment is the same as that of embodiment 5, and further, the pile foundation 1 is a bridge pile foundation which is not completely built, and during installation, the pile foundation 1 which is completely built passes through the pile hole 203 from the top.
Example 7:
the main structure of this embodiment is the same as that of embodiment 6, and further, the cross sections of pile hole 203 and pile foundation 1 are circular, and the diameter of pile hole 203 is 1cm greater than the diameter of pile foundation 1, i.e. pile hole 203 can slide on pile foundation 1.
Example 8:
the main structure of this embodiment is the same as that of embodiment 7, and further, the maximum water depth of the river in which the pile foundation 1 is located is 5m, and the height of the protection device 2 is 2 m.
Example 9:
the main structure of this embodiment is the same as that of embodiment 8, and further, the thickness of the top plate 201 is 6cm, and the thickness of the circular bottom plate 202 is 6 cm.

Claims (9)

1. The utility model provides a simple and easy environment-friendly device suitable for pier pile foundation scour prevention, its characterized in that: comprises a trumpet-shaped protection device (2);
the protection device comprises a protection device (2), a top plate (201) and a circular bottom plate (202), wherein a cavity S is formed inside the protection device (2), the part of the protection device (2) above the cavity S is marked as the top plate (201), and the part of the protection device (2) below the cavity S is marked as the circular bottom plate (202); the part of the top plate (201) close to the bottom plate (202) is flat;
a plurality of through holes (2011) are formed in the top plate (201), and sand or concrete mortar flows into the cavity S through the through holes (2011);
a pile foundation (1) is arranged along the axis of the protective device (2) to penetrate through a pile hole (203), and the pile hole (201) penetrates through the top plate (201), the cavity S and the circular bottom plate (202);
the pile foundation (1) poured into the river bed penetrates through the pile hole (203), and the circular base plate (202) is attached to the surface of the river bed.
2. The simple and easy environment-friendly device suitable for pier pile foundation scour prevention of claim 1, characterized in that: the pile foundation (1) is a bridge pile foundation which is built or not;
if the pile foundation (1) is a built bridge pile foundation, the protection device (2) is formed by splicing a plurality of assembly parts (204); when the protective device is installed, the plurality of assembly parts (204) surround the pile foundation (1) to form a circle, and the plurality of assembly parts (204) are connected with each other, so that the pile foundation (1) penetrates through pile holes (201) of the spliced protective device (2);
if pile foundation (1) is the bridge pile foundation of not building the completion, during the installation, pile hole (203) is passed from the top to pile foundation (1) of having built the completion.
3. The simple and easy environment-friendly device suitable for pier pile foundation scour prevention of claim 1 or 2, characterized in that: the shape of pile hole (201) and the cross-sectional shape phase-match of pile foundation (1), there is the clearance that moves between pile foundation (1) and pile hole (201).
4. The simple and easy environment-friendly device suitable for pier pile foundation scour prevention of claim 1 or 3, characterized in that: the maximum water depth of a river where the pile foundation (1) is located is a, the height of the protection device (2) is b, a is larger than 0, and b is larger than 0;
when a is less than or equal to 3m, b is 0.5 a; when a is more than 3m, b is more than or equal to 1.5m and less than or equal to 2.5 m.
5. The simple and easy environment-friendly device suitable for pier pile foundation scour prevention of claim 1 or 3, characterized in that: the thickness of roof (201) is 4 ~ 7cm, and the thickness of circular bottom plate (202) is 5 ~ 7 cm.
6. The construction method of the simple environment-friendly device suitable for preventing the pier pile foundation from scouring based on claim 1 is characterized in that: the method comprises the following steps:
1) surrounding a plurality of assembly parts (204) into a circle around a pile foundation (1) of the built bridge, and connecting the plurality of assembly parts (204) by adopting a mortise and tenon structure to enable the pile foundation (1) to penetrate through pile holes (201) of the spliced protection device (2);
2) through a plurality of grit or concrete mortar are added to cavity S through-hole (2011), protector (2) receive the action of gravity along pile foundation (1) to sink until circular bottom plate (202) and riverbed surface laminating.
7. The construction method of the simple environment-friendly device suitable for preventing the pier pile foundation from being scoured according to claim 6, wherein the construction method comprises the following steps: and 2) fixing the protection device (2) and the pile foundation (1) together by adopting concrete.
8. The construction method of the simple environment-friendly device suitable for preventing the pier pile foundation from scouring based on claim 1 is characterized in that: the method comprises the following steps:
1) in an unfinished bridge, the poured pile foundation (1) penetrates through a pile hole (201) of a protective device (2) from the top;
2) through a plurality of grit or concrete mortar are added to cavity S through-hole (2011), protector (2) receive the action of gravity along pile foundation (1) to sink until circular bottom plate (202) and riverbed surface laminating.
9. The construction method of the simple environment-friendly device suitable for preventing the pier pile foundation from being scoured according to claim 8, wherein the construction method comprises the following steps: and 2) fixing the protection device (2) and the pile foundation (1) together by adopting concrete.
CN202010065956.5A 2020-01-20 2020-01-20 Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method Pending CN111236290A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010065956.5A CN111236290A (en) 2020-01-20 2020-01-20 Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010065956.5A CN111236290A (en) 2020-01-20 2020-01-20 Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method

Publications (1)

Publication Number Publication Date
CN111236290A true CN111236290A (en) 2020-06-05

Family

ID=70879779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010065956.5A Pending CN111236290A (en) 2020-01-20 2020-01-20 Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method

Country Status (1)

Country Link
CN (1) CN111236290A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827367A (en) * 2020-07-29 2020-10-27 湖南工程学院 Scour prevention structure of offshore wind power pile foundation
CN112160288A (en) * 2020-07-31 2021-01-01 浙江大学 Pier local scouring protection device with rotating normal curved surface
CN112227188A (en) * 2020-10-07 2021-01-15 代潇男 Bridge leg depth limiter suitable for emergency rescue and disaster relief at breach of dam in yellow river water conservancy
CN112746556A (en) * 2021-01-12 2021-05-04 浙江大学 Pier scouring protection method combining concave rotating normal curved surface and granular particles
CN112854313A (en) * 2021-01-15 2021-05-28 天津水运工程勘察设计院 Assembled offshore wind power pile foundation scouring protection device and installation method thereof
CN113338348A (en) * 2021-05-10 2021-09-03 华北电力大学 Foundation pile anti-scouring device for ocean currents
CN114197299A (en) * 2022-01-07 2022-03-18 中铁大桥勘测设计院集团有限公司 Pier and scour prevention assembled protective shroud with subregion whirlpool that disappears

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100560390B1 (en) * 2005-11-26 2006-03-13 (주)정도엔지니어링 Breaking prevention structure of well box basis for bridge
CN203487564U (en) * 2013-09-30 2014-03-19 山东电力工程咨询院有限公司 Anti-flushing device of offshore wind power base structure
DE102015102065A1 (en) * 2015-02-12 2016-08-18 Anton Kanand Transition device for anti-collapse devices of offshore structures
CN106812159A (en) * 2017-03-14 2017-06-09 天津大学 A kind of offshore wind farm single-pile foundation protection against erosion sleeve
CN106968277A (en) * 2017-04-06 2017-07-21 天津大学 A kind of assembled offshore pile scour protection device and its construction method
EP2643526B1 (en) * 2010-11-23 2017-11-01 Technip France Anti-scour disk and method
CN109372006A (en) * 2018-11-27 2019-02-22 中国电建集团华东勘测设计研究院有限公司 Offshore wind turbine foundation scour protection structure and its construction method
CN110056013A (en) * 2018-04-19 2019-07-26 湖南工程学院 A kind of Anti-scouring device of offshore wind farm pile foundation

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100560390B1 (en) * 2005-11-26 2006-03-13 (주)정도엔지니어링 Breaking prevention structure of well box basis for bridge
EP2643526B1 (en) * 2010-11-23 2017-11-01 Technip France Anti-scour disk and method
CN203487564U (en) * 2013-09-30 2014-03-19 山东电力工程咨询院有限公司 Anti-flushing device of offshore wind power base structure
DE102015102065A1 (en) * 2015-02-12 2016-08-18 Anton Kanand Transition device for anti-collapse devices of offshore structures
CN106812159A (en) * 2017-03-14 2017-06-09 天津大学 A kind of offshore wind farm single-pile foundation protection against erosion sleeve
CN106968277A (en) * 2017-04-06 2017-07-21 天津大学 A kind of assembled offshore pile scour protection device and its construction method
CN110056013A (en) * 2018-04-19 2019-07-26 湖南工程学院 A kind of Anti-scouring device of offshore wind farm pile foundation
CN109372006A (en) * 2018-11-27 2019-02-22 中国电建集团华东勘测设计研究院有限公司 Offshore wind turbine foundation scour protection structure and its construction method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827367A (en) * 2020-07-29 2020-10-27 湖南工程学院 Scour prevention structure of offshore wind power pile foundation
CN112160288A (en) * 2020-07-31 2021-01-01 浙江大学 Pier local scouring protection device with rotating normal curved surface
CN112227188A (en) * 2020-10-07 2021-01-15 代潇男 Bridge leg depth limiter suitable for emergency rescue and disaster relief at breach of dam in yellow river water conservancy
CN112227188B (en) * 2020-10-07 2022-03-11 代潇男 Bridge leg depth limiter suitable for emergency rescue and disaster relief at breach of dam in yellow river water conservancy
CN112746556A (en) * 2021-01-12 2021-05-04 浙江大学 Pier scouring protection method combining concave rotating normal curved surface and granular particles
CN112746556B (en) * 2021-01-12 2022-04-19 浙江大学 Pier scouring protection method combining concave rotating normal curved surface and granular particles
US11987941B2 (en) 2021-01-12 2024-05-21 Zhejiang University Pier scour protection method by combinating a downward bivariate normal distribution surface and granular mixture
CN112854313A (en) * 2021-01-15 2021-05-28 天津水运工程勘察设计院 Assembled offshore wind power pile foundation scouring protection device and installation method thereof
CN113338348A (en) * 2021-05-10 2021-09-03 华北电力大学 Foundation pile anti-scouring device for ocean currents
CN114197299A (en) * 2022-01-07 2022-03-18 中铁大桥勘测设计院集团有限公司 Pier and scour prevention assembled protective shroud with subregion whirlpool that disappears
CN114197299B (en) * 2022-01-07 2024-01-26 中铁大桥勘测设计院集团有限公司 Pier with subregion vortex that disappears and scour protection assembled guard ring

Similar Documents

Publication Publication Date Title
CN111236290A (en) Simple environment-friendly device suitable for preventing pier pile foundation from scouring and construction method
CN112523266A (en) Fabricated offshore wind power foundation anti-scouring energy dissipation structure and installation method thereof
CN108360547B (en) Bridge composite foundation suitable for deep water and strong earthquake conditions
KR100819624B1 (en) Waterproof open caisson assembly and concrete foundation construction method using the same
CN104775392B (en) The submerged breakwater rigidifying structure of a kind of wave that disappears in conjunction with flexible vegetation
CN213805503U (en) Underwater pile foundation scouring protection device with scouring prevention hole
KR101169023B1 (en) Method for installing soil nailing and tunnel prevent hole for tidal plant
KR101256265B1 (en) Construction method of the pier without the temporary dike
CN216948458U (en) Fixed pile foundation of offshore wind turbine erodees protective structure
CN111350205B (en) Construction method suitable for underwater pile group pile foundation anti-scouring pit device
JP2015151684A (en) Floating body-type artificial ground
CN216360715U (en) Photovoltaic pile suitable for intertidal zone photovoltaic power station
CN111236291B (en) Anti-scouring NACA type water injection device for serial pier foundation and construction method thereof
CN210887090U (en) Breakwater with energy dissipation function
CN214738307U (en) High-seepage-prevention anti-floating pile raft foundation structure in ultra-soft land area
Perham Ice sheet retention structures
CN214738236U (en) Offshore wind power single pile foundation mud surface resistance enhancing structure based on plate soil friction effect
CN212714803U (en) Hydraulic engineering protects bearing structure with ecological bank protection
Sen Spillway scour and design of plunge pool
CN114182765B (en) Marine fan fixed pile foundation scour protection structure and construction method thereof
CN206723592U (en) For protecting the structural member of submerged pipeline
CN111236289A (en) Bridge group pile foundation anti-scouring bearing platform and construction method thereof
KR100743550B1 (en) Scour prevention block
CN220266574U (en) A prestressed anchorage cable structure for foundation ditch support
CN114991221A (en) Novel stone throwing shaft collar protective structure's offshore wind power pile foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200605