CN111235988A - Energy-saving foundation-changing construction method - Google Patents

Energy-saving foundation-changing construction method Download PDF

Info

Publication number
CN111235988A
CN111235988A CN202010060239.3A CN202010060239A CN111235988A CN 111235988 A CN111235988 A CN 111235988A CN 202010060239 A CN202010060239 A CN 202010060239A CN 111235988 A CN111235988 A CN 111235988A
Authority
CN
China
Prior art keywords
foundation
energy
project
saving
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010060239.3A
Other languages
Chinese (zh)
Other versions
CN111235988B (en
Inventor
姚保文
刘建英
杜国云
胡建保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haixin Construction Development Group Co ltd
Original Assignee
Jiangxi Haixin Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Haixin Construction Co ltd filed Critical Jiangxi Haixin Construction Co ltd
Priority to CN202010060239.3A priority Critical patent/CN111235988B/en
Publication of CN111235988A publication Critical patent/CN111235988A/en
Application granted granted Critical
Publication of CN111235988B publication Critical patent/CN111235988B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/003Foundations for pavings characterised by material or composition used, e.g. waste or recycled material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)

Abstract

The invention discloses an energy-saving construction method for a foundation to be filled, which comprises the following steps: the method comprises the following steps: the project responsible person and the project technical responsible person issue a construction special project according to the survey report of the site soft soil foundation and report to a supervision unit for approval; step two: according to the first approved qualified project technical responsible person, carrying out technical background work on the responsible person of the roadbed construction project, and setting full-time safety personnel for carrying out safety background settlement and field inspection; step three: roughly positioning the position of the road surface below the foundation by using a GPS, marking, carrying out extrusion and silting on the concrete plate block of the old road surface positioned at the ditch and the pond, and layering until the concrete plate block is flush with the side of the ditch and the pond; step four: and excavating the soft soil layer on the side of the ditch and the pond, and vibrating and compacting by using a small vibrating machine to detect the bearing capacity of the foundation. The energy-saving foundation-changing construction method is stable and reliable, simple in equipment, convenient to operate, energy-saving, environment-friendly, strong in practicability and suitable for wide popularization and use.

Description

Energy-saving foundation-changing construction method
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to an energy-saving foundation-changing construction method.
Background
The foundation refers to the soil or rock mass of the supporting foundation under the building. Soil layers as building foundations are divided into rocks, gravel soil, sandy soil, silt soil, cohesive soil and artificial filling soil. The foundation includes a natural foundation and an artificial foundation (composite foundation). Natural foundations are layers of natural soil that do not require human reinforcement. The artificial foundation needs reinforcement treatment by people, and a stone chip cushion layer, a sand cushion layer, mixed lime-soil backfill, tamping and the like are common. The bearing capacity of the foundation is threatened when the water content of the foundation is too large.
The dynamic compaction method and the dynamic compaction replacement method are mainly used for improving the strength of soil, reducing compressibility, improving the vibration liquefaction resistance of soil body and eliminating the collapsibility of soil. The method of adding the filler is generally called vibro-replacement stone pillar method. The vibroflotation method is suitable for treating the foundations of sandy soil, silt soil, silty clay, plain filling soil, miscellaneous filling soil and the like. For treating cohesive soil and saturated loess foundations with non-drainage shear strength of not less than 20kPa, the applicability should be determined by field tests before construction. The method is suitable for treating medium and coarse sand foundations with the clay content not greater than 10% without adding filler and vibroflotation. The vibroflotation gravel pile is mainly used for improving the bearing capacity of a foundation and reducing the settlement of the foundation, and can also be used for improving the anti-skid stability of a soil slope or improving the shear strength of a soil body. Is not suitable for treating the foundation with peat soil, clay with plasticity index more than 25 and ground water with corrosivity and high organic matter content.
If the method needs to be adopted, the applicability of the method needs to be determined through tests, the spring soil phenomenon is easily generated in the treatment process of the existing energy-saving foundation-changing construction method, the bearing capacity is insufficient, and the design concept of energy conservation and environmental protection cannot be revealed in the existing construction method.
Disclosure of Invention
The invention aims to provide an energy-saving type foundation-changing construction method, which aims to solve the problems that the existing energy-saving type foundation-changing construction method proposed in the background art is easy to generate a spring soil phenomenon in the treatment process, so that the bearing capacity is insufficient, and the existing construction method does not show the design concept of energy conservation and environmental protection.
In order to achieve the purpose, the invention provides the following technical scheme: an energy-saving construction method for a foundation to be filled comprises the following steps:
the method comprises the following steps: the project responsible person and the project technical responsible person issue a construction special project according to the survey report of the site soft soil foundation and report to a supervision unit for approval;
step two: according to the first approved qualified project technical responsible person, carrying out technical background work on the responsible person of the roadbed construction project, and setting full-time safety personnel for carrying out safety background settlement and field inspection;
step three: roughly positioning the position of the road surface below the foundation by using a GPS, marking, carrying out extrusion and silting on the concrete plate block of the old road surface positioned at the ditch and the pond, and layering until the concrete plate block is flush with the side of the ditch and the pond;
step four: excavating soft soil layers at the sides of the ditches and ponds, compacting by using a small-sized vibrating machine, detecting the bearing capacity of the foundation, filling road waste and old aggregates in layers after the foundation is qualified, caulking by using mountain flour and slag, rolling for 2-3 times by using a vibratory roller, and rolling for 2-3 times by using a static roller to finish;
step five: spraying cement slurry on the top surface layer of the waste aggregate, and paving a layer of cement soil on the top of the waste aggregate after 24-hour infiltration;
step six: paving lime soil on the top of the cement soil layer by layer until reaching the top surface of the foundation, rolling and compacting layer by layer, and detecting the compactness of the lime soil according to design requirements;
step seven: and manually finishing the foundation, locally filling and compacting the section with unqualified compactness, and detecting the bearing capacity of the section.
Further, the compaction method in the third step is carried out from upstream to downstream from inside to outside, and the concrete slabs for filling the old road surface are rolled for 2-3 times by a 25-ton vibratory roller.
Furthermore, the small-sized vibrating machine in the fourth step is as follows: one of an air rammer, a frog rammer and a flat rammer.
Further, the particle size of the concrete plate on the old pavement in the third step is 20-50cm, and the particle size of the waste granules in the fourth step is 5-10 cm.
Further, the compaction degree of the foundation under one meter in the sixth step is 96%.
Further, the thickness of the cement soil paved in the fifth step is 20 cm.
Compared with the prior art, the invention has the beneficial effects that:
(1) the construction method has the advantages that full-time safety personnel are set for safety end-to-end and field inspection, safety of a construction field is improved, quality safety accidents are avoided, technical project managers carry out technical end-to-end work on managers of special projects for roadbed construction, the technical scheme is perfected, the engineers are constructed according to standards and standards, engineering quality is improved, and accordingly construction level is improved.
(2) The GPS roughly positions the road surface position below the foundation, marks the road surface position, has high accuracy, is convenient to operate, effectively improves the production efficiency, utilizes old road surface concrete plates positioned at the ditches and ponds to carry out extrusion and silting, effectively improves the bearing capacity of the foundation, reuses building waste materials and shows the design concept of energy conservation and environmental protection.
(3) The waste and old aggregate of the road is filled in layers and caulked by stone powder and slag, so that the strength, rigidity and stability of the foundation are improved, cement slurry is sprayed on the top surface layer of the waste and old aggregate, the foundation is reinforced after solidification, and the underground water can be blocked by laying a layer of cement soil, so that the effect of stabilizing the foundation is achieved.
(4) The energy-saving foundation-changing construction method is stable and reliable, simple in equipment, convenient to operate, energy-saving, environment-friendly, strong in practicability and suitable for wide popularization and use. The crushing value of the concrete plate of the middle and old pavement is less than or equal to 20 percent, the porosity of the caulked joint of the stone powder and the slag is 0.5, the bearing capacity after replacement, filling and compaction can reach 120kpa, and the integral strength, the rigidity and the stability of the foundation are effectively improved.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
An energy-saving construction method for a foundation to be filled comprises the following steps:
the method comprises the following steps: the project responsible person and the project technical responsible person issue a construction special project according to the survey report of the site soft soil foundation and report to a supervision unit for approval;
step two: according to the first approved qualified project technical responsible person, carrying out technical background work on the responsible person of the roadbed construction project, and setting full-time safety personnel for carrying out safety background settlement and field inspection;
step three: roughly positioning the position of the road surface below the foundation by using a GPS, marking, carrying out extrusion and silting on the concrete plate block of the old road surface positioned at the ditch and the pond, and layering until the concrete plate block is flush with the side of the ditch and the pond;
step four: excavating soft soil layers at the sides of the ditches and ponds, compacting by using a small-sized vibrating machine, detecting the bearing capacity of the foundation, filling road waste and old aggregates in layers after the foundation is qualified, caulking by using mountain flour and slag, rolling for 2-3 times by using a vibratory roller, and rolling for 2-3 times by using a static roller to finish;
step five: spraying cement slurry on the top surface layer of the waste aggregate, and paving a layer of cement soil on the top of the waste aggregate after 24-hour infiltration;
step six: paving lime soil on the top of the cement soil layer by layer until reaching the top surface of the foundation, rolling and compacting layer by layer, and detecting the compactness of the lime soil according to design requirements;
step seven: and manually finishing the foundation, locally filling and compacting the section with unqualified compactness, and detecting the bearing capacity of the section.
And in the third step, the compaction method is carried out from upstream to downstream from inside to outside, and the concrete slabs for filling the old road surface are rolled for 2-3 times by a 25-ton vibratory roller.
Wherein, the small-size vibrator in step four is: one of an air rammer, a frog rammer and a flat rammer.
Wherein the particle size of the concrete slab on the old pavement in the third step is 20-50cm, and the particle size of the waste granules in the fourth step is 5-10 cm.
Wherein, the compaction degree of the foundation under one meter in the sixth step is 96 percent.
And fifthly, paving cement soil with the thickness of 20 cm.
Example 2
An energy-saving construction method for a foundation to be filled comprises the following steps:
the method comprises the following steps: the project responsible person and the project technical responsible person issue a construction special project according to the survey report of the site soft soil foundation and report to a supervision unit for approval;
step two: according to the first approved qualified project technical responsible person, carrying out technical background work on the responsible person of the roadbed construction project, and setting full-time safety personnel for carrying out safety background settlement and field inspection;
step three: roughly positioning the position of the road surface below the foundation by using a total station, marking, carrying out extrusion and silting on the concrete plate of the old road surface positioned at the ditch and the pond, and layering until the concrete plate is flush with the side of the ditch and the pond;
step four: excavating soft soil layers at the sides of the ditches and ponds, compacting by using a small-sized vibrating machine, detecting the bearing capacity of the foundation, filling road waste and old aggregates in layers after the foundation is qualified, caulking by using mountain flour and slag, rolling for 2-3 times by using a vibratory roller, and rolling for 2-3 times by using a static roller to finish;
step five: spraying cement slurry on the top surface layer of the waste aggregate, and paving a layer of cement soil on the top of the waste aggregate after 24-hour infiltration;
step six: paving lime soil on the top of the cement soil layer by layer until reaching the top surface of the foundation, rolling and compacting layer by layer, and detecting the compactness of the lime soil according to design requirements;
step seven: and manually finishing the foundation, locally filling and compacting the section with unqualified compactness, and detecting the bearing capacity of the section.
And in the third step, the compaction method is carried out from upstream to downstream from inside to outside, and the concrete slabs for filling the old road surface are rolled for 2-3 times by a 25-ton vibratory roller.
Wherein, the small-size vibrator in step four is: one of an air rammer, a frog rammer and a flat rammer.
Wherein the particle size of the concrete slab on the old pavement in the third step is 20-50cm, and the particle size of the waste granules in the fourth step is 5-10 cm.
Wherein, the compaction degree of the foundation under one meter in the sixth step is 96 percent.
And fifthly, paving cement soil with the thickness of 20 cm.
Example 3
An energy-saving construction method for a foundation to be filled comprises the following steps:
the method comprises the following steps: the project responsible person and the project technical responsible person issue a construction special project according to the survey report of the site soft soil foundation and report to a supervision unit for approval;
step two: according to the first approved qualified project technical responsible person, carrying out technical background work on the responsible person of the roadbed construction project, and setting full-time safety personnel for carrying out safety background settlement and field inspection;
step three: roughly positioning the position of the road surface below the foundation by using a GPS, marking, carrying out extrusion and silting on the concrete plate block of the old road surface positioned at the ditch and the pond, and layering until the concrete plate block is flush with the side of the ditch and the pond;
step four: excavating soft soil layers at the sides of the ditches and ponds, compacting by using a small-sized vibrating machine, detecting the bearing capacity of the foundation, filling road waste and old aggregates in layers after the foundation is qualified, caulking by using mountain flour and slag, rolling for 2-3 times by using a vibratory roller, and rolling for 2-3 times by using a static roller to finish;
step five: spraying cement slurry on the top surface layer of the waste aggregate, and paving a layer of cement soil on the top of the waste aggregate after 24-hour infiltration;
step six: laying two-lime soil on the top of the cement soil layer by layer until reaching the top surface of the foundation, rolling and compacting layer by layer, and detecting the compaction degree according to the design requirement;
step seven: and manually finishing the foundation, locally filling and compacting the section with unqualified compactness, and detecting the bearing capacity of the section.
And in the third step, the compaction method is carried out from upstream to downstream from inside to outside, and the concrete slabs for filling the old road surface are rolled for 2-3 times by a 25-ton vibratory roller.
Wherein, the small-size vibrator in step four is: one of an air rammer, a frog rammer and a flat rammer.
Wherein the particle size of the concrete slab on the old pavement in the third step is 20-50cm, and the particle size of the waste granules in the fourth step is 5-10 cm.
Wherein, the compaction degree of the foundation under one meter in the sixth step is 96 percent.
And fifthly, paving cement soil with the thickness of 20 cm.
When the invention works: the construction method has the advantages that full-time safety personnel are set for safety end-to-end and field inspection, safety of a construction field is improved, quality safety accidents are avoided, technical project managers carry out technical end-to-end work on managers of special projects for roadbed construction, the technical scheme is perfected, the engineers are constructed according to standards and standards, engineering quality is improved, and accordingly construction level is improved. The GPS or the total station approximately positions the pavement position below the foundation and marks the pavement position, so that the accuracy is high, the operation is convenient, the production efficiency is effectively improved, the old pavement concrete plate block positioned at the ditch and pond is utilized to carry out the extrusion silting, the bearing capacity of the foundation is effectively improved, the construction waste is recycled, and the design concept of energy conservation and environmental protection is revealed. The waste and old aggregate of the road is filled in layers and caulked by stone powder and slag, so that the strength, rigidity and stability of the foundation are improved, cement slurry is sprayed on the top surface layer of the waste and old aggregate, the foundation is reinforced after solidification, and the underground water can be blocked by laying a layer of cement soil, so that the effect of stabilizing the foundation is achieved. The energy-saving foundation-changing construction method is stable and reliable, simple in equipment, convenient to operate, energy-saving, environment-friendly, strong in practicability and suitable for wide popularization and use. The crushing value of the concrete plate of the middle and old pavement is less than or equal to 20 percent, the porosity of the caulked joint of the stone powder and the slag is 0.5, the bearing capacity after replacement, filling and compaction can reach 120kpa, and the integral strength, the rigidity and the stability of the foundation are effectively improved.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. An energy-saving construction method for a foundation to be filled is characterized by comprising the following steps:
the method comprises the following steps: the project responsible person and the project technical responsible person issue a construction special project according to the survey report of the site soft soil foundation and report to a supervision unit for approval;
step two: according to the first approved qualified project technical responsible person, carrying out technical background work on the responsible person of the roadbed construction project, and setting full-time safety personnel for carrying out safety background settlement and field inspection;
step three: roughly positioning the position of the road surface below the foundation by using a GPS, marking, carrying out extrusion and silting on the concrete plate block of the old road surface positioned at the ditch and the pond, and layering until the concrete plate block is flush with the side of the ditch and the pond;
step four: excavating soft soil layers at the sides of the ditches and ponds, compacting by using a small-sized vibrating machine, detecting the bearing capacity of the foundation, filling road waste and old aggregates in layers after the foundation is qualified, caulking by using mountain flour and slag, rolling for 2-3 times by using a vibratory roller, and rolling for 2-3 times by using a static roller to finish;
step five: spraying cement slurry on the top surface layer of the waste aggregate, and paving a layer of cement soil on the top of the waste aggregate after 24-hour infiltration;
step six: paving lime soil on the top of the cement soil layer by layer until reaching the top surface of the foundation, rolling and compacting layer by layer, and detecting the compactness of the lime soil according to design requirements;
step seven: and manually finishing the foundation, locally filling and compacting the section with unqualified compactness, and detecting the bearing capacity of the section.
2. An energy-saving foundation reclamation method as recited in claim 1, wherein: and in the third step, the sludge squeezing method is carried out from the upstream to the downstream from the inside to the outside, and the concrete slab for filling the old pavement is rolled for 2-3 times by a 25-ton vibratory roller.
3. An energy-saving foundation reclamation method as recited in claim 1, wherein: the small-sized vibrating machine in the fourth step comprises the following steps: one of an air rammer, a frog rammer and a flat rammer.
4. An energy-saving foundation reclamation method as recited in claim 1, wherein: the particle size of the concrete slab on the old pavement in the third step is 20-50cm, and the particle size of the waste granules in the fourth step is 5-10 cm.
5. An energy-saving foundation reclamation method as recited in claim 1, wherein: and in the sixth step, the compaction degree of the foundation below one meter is 96%.
6. An energy-saving foundation reclamation method as recited in claim 1, wherein: and in the fifth step, the thickness of the laid cement soil is 20 cm.
CN202010060239.3A 2020-01-19 2020-01-19 Energy-saving foundation-changing construction method Active CN111235988B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010060239.3A CN111235988B (en) 2020-01-19 2020-01-19 Energy-saving foundation-changing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010060239.3A CN111235988B (en) 2020-01-19 2020-01-19 Energy-saving foundation-changing construction method

Publications (2)

Publication Number Publication Date
CN111235988A true CN111235988A (en) 2020-06-05
CN111235988B CN111235988B (en) 2021-11-09

Family

ID=70864101

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010060239.3A Active CN111235988B (en) 2020-01-19 2020-01-19 Energy-saving foundation-changing construction method

Country Status (1)

Country Link
CN (1) CN111235988B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101418565A (en) * 2007-10-23 2009-04-29 中铁第一勘察设计院集团有限公司 Qinghai-tibet railway permafrost wetland ground treatment technique
CN102747662A (en) * 2012-07-18 2012-10-24 上海城建市政工程(集团)有限公司 Construction method for sand-filling subgrade
CN106436677A (en) * 2016-09-29 2017-02-22 江苏工程职业技术学院 Energy-saving type foundation exchange filling construction method
CN106592362A (en) * 2016-11-28 2017-04-26 北京市政建设集团有限责任公司 Method for utilizing building rubbish to construct bottom layer roadbed
CN107268365A (en) * 2017-06-23 2017-10-20 云南新同程建设集团有限公司 A kind of Construction of Soft Soil Subgrade technique
US9957670B2 (en) * 2012-02-20 2018-05-01 Technisoil Industrial Llc Polyurethane based roadway forming

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101418565A (en) * 2007-10-23 2009-04-29 中铁第一勘察设计院集团有限公司 Qinghai-tibet railway permafrost wetland ground treatment technique
US9957670B2 (en) * 2012-02-20 2018-05-01 Technisoil Industrial Llc Polyurethane based roadway forming
CN102747662A (en) * 2012-07-18 2012-10-24 上海城建市政工程(集团)有限公司 Construction method for sand-filling subgrade
CN106436677A (en) * 2016-09-29 2017-02-22 江苏工程职业技术学院 Energy-saving type foundation exchange filling construction method
CN106592362A (en) * 2016-11-28 2017-04-26 北京市政建设集团有限责任公司 Method for utilizing building rubbish to construct bottom layer roadbed
CN107268365A (en) * 2017-06-23 2017-10-20 云南新同程建设集团有限公司 A kind of Construction of Soft Soil Subgrade technique

Also Published As

Publication number Publication date
CN111235988B (en) 2021-11-09

Similar Documents

Publication Publication Date Title
CN106592608A (en) Differential settlement control method for new foundation and old roadbed of utility tunnel
CN214271530U (en) Soft basic district road structure based on building rubbish is laid
CN210529400U (en) Solidified building residue soil road structure
CN111235988B (en) Energy-saving foundation-changing construction method
CN112813756A (en) Roadbed based on municipal soft soil and construction method
CN111908853A (en) Self-compacting soil, preparation method thereof and construction method for backfilling municipal cavity
CN213115347U (en) Dampproof ground
CN114411921A (en) Method and structure for building roadbed drainage ditch through road reconstruction and extension
CN108824418B (en) Construction method for whole roadbed to penetrate through pond based on in-situ curing technology
CN113700111A (en) Construction method of rainwater permeation, drainage and reuse integrated system
CN111501495A (en) Road construction method
Maher et al. MAT-758: Constructability Benefits of the Use of Lightweight Foamed Concrete Fill (LFCF) in Pavement Applications
CN206916688U (en) A kind of new rammed earth retaining wall
CN212801050U (en) Municipal administration road bad soil foundation stabilization structure
CN1584209A (en) Block pavement constructing method
JP2001193071A (en) Lightweight filling method
CN220318577U (en) Gravity type composite construction retaining wall
CN210947064U (en) Rainwater pipeline backfills structure suitable for silt matter weak soil
CN211922497U (en) River course view dam structure
CN219218563U (en) Sand road surface structure with strong compression resistance and water impermeability
CN217298503U (en) Municipal construction road structure
CN218521536U (en) Road bed construction structures
CN112854841B (en) Civil construction structure construction method of bottom mud treatment plant
Duong et al. Review on treatment methods of soft soil subgrade
CN216075059U (en) Silt basic unit building engineering consolidates foundation structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 330299 Liantang Zhen gengtou Cun Yao Cun Zi Cun, Nanchang County, Nanchang City, Jiangxi Province

Patentee after: Haixin Construction Development Group Co.,Ltd.

Address before: 330299 Liantang Zhen gengtou Cun Yao Cun Zi Cun, Nanchang County, Nanchang City, Jiangxi Province

Patentee before: JIANGXI HAIXIN CONSTRUCTION Co.,Ltd.

CP01 Change in the name or title of a patent holder