- CN111125635B CN111125635B CN201911219552.0A CN201911219552A CN111125635B CN 111125635 B CN111125635 B CN 111125635B CN 201911219552 A CN201911219552 A CN 201911219552A CN 111125635 B CN111125635 B CN 111125635B
- Authority
- CN
- China
- Prior art keywords
- data
- filling
- date
- day
- electric quantity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 33
- 230000005611 electricity Effects 0.000 claims abstract description 43
- 238000009825 accumulation Methods 0.000 claims description 12
- 238000012545 processing Methods 0.000 claims description 3
- 150000001875 compounds Chemical class 0.000 claims 2
- 230000008569 process Effects 0.000 description 4
- 230000002159 abnormal effect Effects 0.000 description 3
- 230000006399 behavior Effects 0.000 description 3
- 230000008859 change Effects 0.000 description 3
- 230000008878 coupling Effects 0.000 description 3
- 238000010168 coupling process Methods 0.000 description 3
- 238000005859 coupling reaction Methods 0.000 description 3
- 238000004891 communication Methods 0.000 description 2
- 230000007774 longterm Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 230000003203 everyday effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/10—Complex mathematical operations
- G06F17/18—Complex mathematical operations for evaluating statistical data, e.g. average values, frequency distributions, probability functions, regression analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02D—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
- Y02D10/00—Energy efficient computing, e.g. low power processors, power management or thermal management
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Business, Economics & Management (AREA)
- Data Mining & Analysis (AREA)
- Mathematical Optimization (AREA)
- Mathematical Analysis (AREA)
- Pure & Applied Mathematics (AREA)
- Computational Mathematics (AREA)
- Mathematical Physics (AREA)
- Economics (AREA)
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Human Resources & Organizations (AREA)
- Tourism & Hospitality (AREA)
- Strategic Management (AREA)
- Bioinformatics & Cheminformatics (AREA)
- Bioinformatics & Computational Biology (AREA)
- Primary Health Care (AREA)
- Marketing (AREA)
- Evolutionary Biology (AREA)
- General Business, Economics & Management (AREA)
- General Health & Medical Sciences (AREA)
- Operations Research (AREA)
- Probability & Statistics with Applications (AREA)
- Water Supply & Treatment (AREA)
- Algebra (AREA)
- Public Health (AREA)
- Databases & Information Systems (AREA)
- Software Systems (AREA)
- General Engineering & Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The application discloses a method, a device, a terminal and a storage medium for filling user table data, wherein the method comprises the following steps: determining a first data filling date according to the acquired user table data; acquiring data of a summary table; calculating the accumulated sum of the first data filling date and the first total table electric quantity of the day before the first data filling date according to the total table data; and obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the single-day total meter electric quantity corresponding to the first data filling date to the sum of the first total meter electric quantity, and according to the product of the ratio and the electric quantity in the first data filling date. According to the method and the device, the electricity consumption of the user data on the day of the loss of the user data is calculated by combining the electricity consumption of the general meter according to the electricity consumption of the user code during the loss period, so that the filling is performed, the phenomenon that the filled electricity is obviously not in accordance with the metering rule of the electricity meter is avoided, and the technical problem that the line loss rate calculation error is overlarge in the prior art is solved.
Description
Technical Field
The application relates to the technical field of power metering, in particular to a user table data filling method, a device, a terminal and a storage medium.
Background
For a low-voltage distribution area or a feeder line, under the conditions of correct topological relation, correct metering and no electricity stealing behavior of a user, the line loss rate is relatively stable in long-term data, and the change of the line loss rate is mainly caused by fluctuation of load distribution, so that the line loss rate under normal use is relatively gentle in change; the abnormal electricity utilization behavior of the user can cause drastic changes of the line loss rate. According to the principle, abnormal electricity utilization behavior analysis of the user based on line loss data (namely long-term data of the electricity quantity of the user and the electricity quantity of the total meter) can locate abnormal electricity utilization users.
However, in practical application, the situation that the user electricity data is missing in the same day often occurs, which causes a technical problem that the antenna loss rate calculation error is too large in the same day.
Disclosure of Invention
The application provides a method, a device, a terminal and a storage medium for filling user table data, which are used for solving the technical problem that in the prior art, in practical application, the situation that the user electric quantity data is lost in the same day often occurs, so that the calculation error of the antenna loss rate is overlarge.
In view of the above, a first aspect of the present application provides a method for padding user table data, including:
determining a first data filling date according to the acquired user table code data, wherein the first data filling date is a date when table code data is missing in the acquired user table code data;
acquiring summary table code data, wherein the summary table code data comprises: summary table code data for the first data fill date and a day prior to the first data fill date;
calculating the accumulated sum of the first data filling date and the first total table electric quantity of the day before the first data filling date according to the total table data;
and obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the single-day total table electric quantity corresponding to the first data filling date to the sum of the first total table electric quantity, and the product of the ratio and the power consumption in the first data filling date, so as to fill the user table data according to the single-day filling electric quantity.
Optionally, the obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the sum of the single-day total table electric quantity corresponding to the first data filling date and the first total table electric quantity, and according to the product of the ratio and the electric quantity used in the first data filling date specifically includes:
obtaining the single-day filling electric quantity of the first data filling date through a filling electric quantity calculation formula according to the single-day total table electric quantity corresponding to the first data filling date, the first total table electric quantity accumulation and the power consumption in the first data filling date, wherein the filling electric quantity calculation formula specifically comprises the following steps:
in the formula, e i Filling up the power for the day i, day i i The electricity quantity of the single-day total table of the ith day, n is the number of days for filling up the date of the first data, e after -e before Filling up the first data with electricity consumption in the date, e after The day after the date is filled in for the first data, e before Filling the first data with the day before the date.
A second aspect of the present application provides a user-table data padding apparatus, including:
the data filling date determining unit is used for determining a first data filling date according to the acquired user table code data, wherein the first data filling date is a date when the table code data is missing in the acquired user table code data;
the device comprises a summary table data acquisition unit, a summary table data acquisition unit and a summary table data processing unit, wherein the summary table data acquisition unit is used for acquiring summary table data, and the summary table data comprises: summary table code data for the first data fill date and a day prior to the first data fill date;
the summary table electric quantity accumulation and calculation unit is used for calculating the first summary table electric quantity accumulation sum of the first data filling date and the day before the first data filling date according to the summary table data;
and the filling electric quantity calculating unit is used for obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the single-day total table electric quantity corresponding to the first data filling date to the first total table electric quantity accumulation sum and the product of the ratio and the user electric quantity in the first data filling date so as to fill the user table code data according to the single-day filling electric quantity.
Optionally, the obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the sum of the single-day total table electric quantity corresponding to the first data filling date and the first total table electric quantity, and according to the product of the ratio and the electric quantity used in the first data filling date specifically includes:
obtaining the single-day filling electric quantity of the first data filling date through a filling electric quantity calculation formula according to the single-day total table electric quantity corresponding to the first data filling date, the first total table electric quantity accumulation and the power consumption in the first data filling date, wherein the filling electric quantity calculation formula specifically comprises the following steps:
in the formula, e i Filling up the power for the day i, day i i The electricity quantity of the single-day total table of the ith day, n is the number of days for filling up the date of the first data, e after -e before Filling up the first data with electricity consumption in the date, e after The day after the date is filled in for the first data, e before Filling the first data with the day before the date.
A third aspect of the present application provides a terminal, comprising: a processor and a memory;
the memory is used for storing program codes corresponding to the user table data padding method according to the first aspect of the application;
the processor is configured to execute the program code.
A fourth aspect of the present application provides a storage medium, where the storage medium stores program codes corresponding to the user table data padding method according to the first aspect of the present application.
According to the technical scheme, the method has the following advantages:
a first aspect of the present application provides a method for filling user table data, including:
determining a first data filling date according to the acquired user table code data, wherein the first data filling date is a date when table code data is missing in the acquired user table code data; acquiring summary table code data, wherein the summary table code data comprises: summary table code data for the first data fill date and a day prior to the first data fill date; calculating the first total table electric quantity accumulated sum of the first data filling date and the day before the first data filling date according to the total table code data; and obtaining the single-day filling electricity quantity of the first data filling date according to the ratio of the single-day total meter electricity quantity corresponding to the first data filling date to the sum of the first total meter electricity quantity, and the product of the ratio and the electricity consumption quantity in the first data filling date, so as to fill the user meter code data according to the single-day filling electricity quantity.
According to the method and the device, the electricity consumption of the user data on the day of the loss of the user data is calculated by combining the electricity consumption of the general meter according to the electricity consumption of the user code during the loss period, and the electricity consumption is filled, so that the calculation result is closer to the actual electricity consumption, the phenomenon that the filled electricity is obviously not consistent with the electricity meter metering rule is avoided, and the technical problem that the line loss rate calculation error is overlarge in the prior art is solved.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the description below are only some embodiments of the present application, and for those skilled in the art, other drawings can be obtained according to the drawings without inventive labor.
Fig. 1 is a schematic flowchart of a first embodiment of a method for padding user-table data according to the present application;
fig. 2 is a schematic structural diagram of a user-table data padding apparatus according to a first embodiment of the present application.
Detailed Description
The embodiment of the application provides a method, a device, a terminal and a storage medium for filling user table data, which are used for solving the technical problem that in practical application in the prior art, the user electric quantity data is often lost in the same day, so that the calculation error of the antenna loss rate is overlarge.
It should be noted that an isolated and complete part of the distribution network, such as a low-voltage distribution area or a feeder line, can be seen as an isolated tree structure from the perspective of the metering system, in this isolated tree structure, the incoming electric energy and the outgoing electric energy are determined, and the electric energy flows from the root node, is mostly consumed in each leaf node, and is consumed in the line in a small amount (theoretical line loss). In the measurement, the root node is a general table (load terminal for low-voltage transformer area, and assessment general table for feeder), and the leaf node is a user electric meter (low-voltage electric meter for low-voltage transformer area, and measurement terminal or load terminal for feeder). Under the premise of correct topological relation (user-variable relation and line-variable relation) and correct metering, the total electricity consumption = sum of user electricity consumption + line loss electricity consumption.
The records of the electricity meter codes are increased along with time, that is, "the code (d + 1) > = the code (d)" holds for every day, where d is the date, and the electricity consumption = the code (d + 1) — the code (d), but in practical application, a method of "calculating the electricity quantity of the user by using the change rate of the total electricity quantity to fill up" is commonly used, so that the error of a filling result is too large, and a logic error that "the code calculated according to the filling electricity quantity is larger than the code in the later period or smaller than the code in the earlier period" may even occur.
In order to make the objects, features and advantages of the present invention more apparent and understandable, the following embodiments of the present invention are clearly and completely described with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the embodiments described below are only a part of the embodiments of the present invention, and not all of the embodiments of the present invention. All other embodiments obtained by a person of ordinary skill in the art based on the embodiments in the present application without making any creative effort belong to the protection scope of the present application.
Referring to fig. 1, a first embodiment of the present application provides a method for padding user table data, including:
The first data padding date is the date that table code data are missing in the acquired user table code data.
And 102, acquiring data of the summary table.
Wherein the summary table code data includes: the first data padding date and summary table code data of a day prior to the first data padding date.
It should be noted that, because the calculation of the power consumption is based on the difference between the table code at the time of day and the table code at the time of the next day, that is, the table code of one day is missing, the power consumption data of the day and the previous day will be missing, and therefore, when the data of the summary table is obtained, the data of the summary table at the previous day of the filling date of the first data should also be obtained.
And 103, calculating the accumulated sum of the first data filling date and the first total table electric quantity of the day before the first data filling date according to the total table code data.
And 104, obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the single-day total table electric quantity corresponding to the first data filling date to the sum of the first total table electric quantity and the product of the ratio and the power consumption in the first data filling date so as to fill the user table data according to the single-day filling electric quantity.
It should be noted that the single-day filling power amount of the first data filling date is obtained through a filling power amount calculation formula according to the single-day total table power amount corresponding to the first data filling date, the first total table power amount accumulation and the power consumption amount in the first data filling date, where the filling power amount calculation formula specifically is:
in the formula, e i Filling up the power for the day i, day i i The electricity amount of the single-day summary of the ith day, n is the number of days for filling up the date of the first data, e after -e before Filling up the first data with the electricity consumption in the date, e after The day after the date is filled in for the first data, e before The day before the date is filled with the first data.
The fill-in test results are shown in table 1:
wherein the blank cells represent missing data.
After the filling electric quantity of the electric quantity missing date is calculated, the number 10 missing meter code can be reversely deduced to be 991 based on the filled electric quantity, the calculated result is closer to the actual power consumption, the phenomenon that the filled electric quantity obviously does not accord with the metering rule of an electric meter can be avoided, and the technical problem that the line loss rate calculation error is overlarge in the prior art is solved.
The above is a detailed description of a first embodiment of a method for filling user-table data provided in the present application, and the following is a detailed description of a device for filling user-table data provided in the present application.
Referring to fig. 2, a second embodiment of the present application provides a user table data padding apparatus, including:
a data padding date determining unit 201, configured to determine a first data padding date according to the obtained user table data, where the first data padding date is a date when table data is missing in the obtained user table data;
a summary table data obtaining unit 202, configured to obtain summary table data, where the summary table data includes: the first data filling date and the summary list code data of the day before the first data filling date;
the summary table electric quantity accumulation and calculation unit 203 is used for calculating the first summary table electric quantity accumulation sum of the first data filling date and the day before the first data filling date according to the summary table data;
and the padding electric quantity calculating unit 204 is used for obtaining the single-day padding electric quantity of the first data padding date according to the ratio of the single-day total table electric quantity corresponding to the first data padding date to the first total table electric quantity accumulation sum and the product of the ratio and the user electric quantity in the first data padding date so as to pad the user table data according to the single-day padding electric quantity.
Optionally, the shim power calculating unit 204 is specifically configured to:
obtaining the single-day filling electric quantity of the first data filling date through a filling electric quantity calculation formula according to the single-day total table electric quantity corresponding to the first data filling date, the first total table electric quantity accumulation and the electric quantity used in the first data filling date, wherein the filling electric quantity calculation formula specifically comprises the following steps:
in the formula, e i Filling up the power for the day i, day i i The electricity amount of the single-day summary of the ith day, n is the number of days for filling up the date of the first data, e after -e before Filling up the first data with the electricity consumption in the date, e after The day after the date is filled in for the first data, e before The day before the date is filled with the first data.
In addition, the present application also provides an embodiment of a terminal and a storage medium storing corresponding program codes for applying the method of the first embodiment of the present application.
A third embodiment of the present application provides a terminal, including: a processor and a memory;
the memory is used for storing program codes corresponding to the user table data padding method according to the first embodiment of the application;
the processor is configured to execute the program code.
A fourth embodiment of the present application provides a storage medium, where the storage medium stores a program code corresponding to the user table data padding method according to the first embodiment of the present application.
It is clear to those skilled in the art that, for convenience and brevity of description, the specific working processes of the above-described systems, apparatuses and units may refer to the corresponding processes in the foregoing method embodiments, and are not described herein again.
In the several embodiments provided in the present application, it should be understood that the disclosed system, apparatus and method may be implemented in other ways. For example, the above-described apparatus embodiments are merely illustrative, and for example, the division of the units is only one logical division, and other divisions may be realized in practice, for example, a plurality of units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, devices or units, and may be in an electrical, mechanical or other form.
The terms "first," "second," "third," "fourth," and the like in the description of the application and the above-described figures, if any, are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It is to be understood that the data so used is interchangeable under appropriate circumstances such that the embodiments of the application described herein are, for example, capable of operation in sequences other than those illustrated or otherwise described herein. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present invention may be embodied in the form of a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, or a network device) to execute all or part of the steps of the method according to the embodiments of the present invention. And the aforementioned storage medium includes: a U-disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk or an optical disk, and other various media capable of storing program codes.
The above embodiments are only used for illustrating the technical solutions of the present application, and not for limiting the same; although the present application has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions in the embodiments of the present application.
Claims (4)
1. A method for padding user table data, comprising:
determining a first data filling date according to the acquired user table code data, wherein the first data filling date is a date when table code data is missing in the acquired user table code data;
acquiring summary table code data, wherein the summary table code data comprises: summary table code data for the first data fill date and a day prior to the first data fill date;
calculating the accumulated sum of the first data filling date and the first total table electric quantity of the day before the first data filling date according to the total table data;
obtaining the single-day filling amount of the first data filling date according to the ratio of the single-day total table electricity quantity corresponding to the first data filling date to the first total table electricity quantity accumulated sum and the product of the ratio and the electricity consumption in the first data filling date so as to fill the user table data according to the single-day filling amount;
the obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the single-day total table electric quantity corresponding to the first data filling date to the sum of the first total table electric quantity and according to the product of the ratio and the electric quantity used in the first data filling date specifically comprises:
obtaining the single-day filling electric quantity of the first data filling date through a filling electric quantity calculation formula according to the single-day total meter electric quantity corresponding to the first data filling date, the accumulated first total meter electric quantity and the electric consumption in the first data filling date, wherein the filling electric quantity calculation formula specifically comprises the following steps:
in the formula (I), the compound is shown in the specification,is charged on a single day on day i, is charged>The electric quantity of the single-day summary of the ith day, n is the number of days of the filling date of the first data, and is greater than or equal to>Filling the first data with the power consumption in the date @>The day after the date is filled for the first data, based on the status of the sensor>Filling the first data with the day before the date.
2. A user-table data padding apparatus, comprising:
the data filling date determining unit is used for determining a first data filling date according to the acquired user table code data, wherein the first data filling date is a date when the table code data is missing in the acquired user table code data;
the device comprises a summary table data acquisition unit, a summary table data acquisition unit and a summary table data processing unit, wherein the summary table data acquisition unit is used for acquiring summary table data, and the summary table data comprises: summary table code data for the first data fill date and a day prior to the first data fill date;
the summary table electric quantity accumulation and calculation unit is used for calculating the first summary table electric quantity accumulation sum of the first data filling date and the day before the first data filling date according to the summary table data;
the filling electric quantity calculating unit is used for obtaining the single-day filling electric quantity of the first data filling date according to the ratio of the single-day total table electric quantity corresponding to the first data filling date to the first total table electric quantity accumulated sum and the product of the ratio and the user electric quantity in the first data filling date so as to fill the user table code data according to the single-day filling electric quantity;
wherein the padding power calculating unit is specifically configured to:
obtaining the single-day filling electric quantity of the first data filling date through a filling electric quantity calculation formula according to the single-day total meter electric quantity corresponding to the first data filling date, the accumulated first total meter electric quantity and the electric consumption in the first data filling date, wherein the filling electric quantity calculation formula specifically comprises the following steps:
in the formula (I), the compound is shown in the specification,is charged on a single day on day i, is charged>The electric quantity of the single-day summary of the ith day, n is the number of days of the filling date of the first data, and is greater than or equal to>Filling the first data with the power consumption in the date @>The day after the date is filled for the first data, based on the status of the sensor>Filling the first data with the day before the date.
3. A terminal comprising a processor and a memory;
the memory for storing program code corresponding to the user table data padding method of claim 1;
the processor is configured to execute the program code.
4. A storage medium storing program code corresponding to the user table data padding method according to claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911219552.0A CN111125635B (en) | 2019-11-29 | 2019-11-29 | User table data filling method, device, terminal and storage medium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911219552.0A CN111125635B (en) | 2019-11-29 | 2019-11-29 | User table data filling method, device, terminal and storage medium |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111125635A CN111125635A (en) | 2020-05-08 |
CN111125635B true CN111125635B (en) | 2023-04-18 |
Family
ID=70497187
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911219552.0A Active CN111125635B (en) | 2019-11-29 | 2019-11-29 | User table data filling method, device, terminal and storage medium |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111125635B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117932246B (en) * | 2024-03-21 | 2024-08-20 | 广东鹰视能效科技有限公司 | Electric quantity data recalculation method and system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106169160A (en) * | 2016-06-01 | 2016-11-30 | 国网河北省电力公司电力科学研究院 | A kind of electricity abnormity diagnosis based on critical point power system and electricity complementing method |
CN106651651A (en) * | 2016-12-12 | 2017-05-10 | 全球能源互联网研究院 | Data filling method and device for utilization power curve of grid user |
WO2017088444A1 (en) * | 2015-11-24 | 2017-06-01 | 深圳Tcl数字技术有限公司 | Method and device for prompting electric quantity information of terminal |
CN108519989A (en) * | 2018-02-27 | 2018-09-11 | 国网冀北电力有限公司电力科学研究院 | The reduction retroactive method and device of a kind of day electricity missing data |
CN109033454A (en) * | 2018-08-27 | 2018-12-18 | 广东电网有限责任公司 | Data filling method, apparatus, equipment and storage medium based on attributes similarity |
CN109445972A (en) * | 2018-09-21 | 2019-03-08 | 深圳供电局有限公司 | Data recovery method, device, equipment and storage medium |
-
2019
- 2019-11-29 CN CN201911219552.0A patent/CN111125635B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2017088444A1 (en) * | 2015-11-24 | 2017-06-01 | 深圳Tcl数字技术有限公司 | Method and device for prompting electric quantity information of terminal |
CN106169160A (en) * | 2016-06-01 | 2016-11-30 | 国网河北省电力公司电力科学研究院 | A kind of electricity abnormity diagnosis based on critical point power system and electricity complementing method |
CN106651651A (en) * | 2016-12-12 | 2017-05-10 | 全球能源互联网研究院 | Data filling method and device for utilization power curve of grid user |
CN108519989A (en) * | 2018-02-27 | 2018-09-11 | 国网冀北电力有限公司电力科学研究院 | The reduction retroactive method and device of a kind of day electricity missing data |
CN109033454A (en) * | 2018-08-27 | 2018-12-18 | 广东电网有限责任公司 | Data filling method, apparatus, equipment and storage medium based on attributes similarity |
CN109445972A (en) * | 2018-09-21 | 2019-03-08 | 深圳供电局有限公司 | Data recovery method, device, equipment and storage medium |
Also Published As
Publication number | Publication date |
---|---|
CN111125635A (en) | 2020-05-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110705107B (en) | Power distribution network voltage evaluation method, system, equipment and storage medium | |
David et al. | Consumer rationality assumptions in the real-time pricing of electricity | |
CN109103874A (en) | Consider the distribution network reliability evaluation method of part throttle characteristics and distributed generation resource access | |
CN109308552A (en) | A kind of business game appraisal procedure, device and electronic equipment | |
CN109118012B (en) | Industrial dynamic multi-dimensional energy consumption cost prediction method, system, storage medium and terminal | |
CN106780112A (en) | Electric service interactive system and method | |
CN115267644A (en) | Method and device for detecting misalignment of electric energy meter | |
CN110262959B (en) | Bottom layer service pressure testing method and device, electronic equipment and storage medium | |
CN109409559B (en) | Method and device for determining oilfield output reduction rate | |
CN113283096B (en) | Method for acquiring distribution network line account data and analyzing abnormal data and related device | |
CN108764699A (en) | Scheduling method, server and computer readable storage medium | |
CN111125635B (en) | User table data filling method, device, terminal and storage medium | |
CN114814708A (en) | Electric energy meter metering error estimation method and device based on floating line loss model | |
CN110781449A (en) | Estimation method for user data loss in distribution area line loss calculation | |
CN114328647A (en) | Method, system, terminal and storage medium for generating material demand quantity | |
CN108228679A (en) | Time series data metering method and time series data metering device | |
CN113777398A (en) | Electric energy meter electric quantity recording method, electric energy meter and readable storage medium | |
CN112596020A (en) | Method and related device for correcting running errors of intelligent electric meters in transformer area | |
CN110308644B (en) | Smart electric meter clock timing precision compensation method, device and equipment | |
CN111428197A (en) | Data processing method, device and equipment | |
CN107562695B (en) | Load data processing method and device for distribution transformer | |
CN111478311A (en) | Line loss calculation method and system for any partition of power grid | |
CN113780625B (en) | User electricity charge prediction method, system, terminal and storage medium | |
CN114614509A (en) | Analysis method for influence of photovoltaic access on electric energy quality and related device | |
US9528854B1 (en) | Determining downstream load in a distribution network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |