CN111120470A - Cast or forged connecting flange for concrete poles - Google Patents

Cast or forged connecting flange for concrete poles Download PDF

Info

Publication number
CN111120470A
CN111120470A CN202010142712.2A CN202010142712A CN111120470A CN 111120470 A CN111120470 A CN 111120470A CN 202010142712 A CN202010142712 A CN 202010142712A CN 111120470 A CN111120470 A CN 111120470A
Authority
CN
China
Prior art keywords
ring
flange
bearing ring
rib plates
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010142712.2A
Other languages
Chinese (zh)
Inventor
祁锦明
倪荣武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuangong Energy Technology Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010142712.2A priority Critical patent/CN111120470A/en
Publication of CN111120470A publication Critical patent/CN111120470A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B7/00Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections
    • F16B7/18Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements
    • F16B7/182Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements for coaxial connections of two rods or tubes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/12Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B2200/00Constructional details of connections not covered for in other groups of this subclass
    • F16B2200/50Flanged connections
    • F16B2200/506Flanged connections bolted or riveted

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Materials Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

The invention belongs to the technical field of concrete rod manufacturing, and particularly relates to a cast or forged connecting flange for a concrete rod. The invention has simple structure and ingenious design, when the two flanges are connected, the contact surface between the flanges is the contact of the rib plates of the two flanges and the end surfaces of the inner pressure bearing ring and the outer pressure bearing ring, the two flange rings are not in contact, the wrench space when the connecting bolts on the flange rings are fastened is not limited by the position of the rib plates, and the invention can be realized by properly increasing the number of the bolts and the diameter of the bolts when the force transmission needs to be increased.

Description

Cast or forged connecting flange for concrete poles
Technical Field
The invention belongs to the technical field of concrete pole manufacturing, and particularly relates to a cast or forged connecting flange for a concrete pole.
Background
The flange of traditional segmentation concrete pole generally comprises gusset, flange circle, lacing wire circle and protective shroud, and its structural style is that the flange circle is located the link (two flange circles lean on together when two sections are connected), and gusset and protective shroud are located non-link end, and the gusset distributes on the same terminal surface of flange circle with connecting bolt's tip, because the gusset has occupied the spanner space of bolt, causes bolt quantity and size to be limited, and this structure is difficult for meeting the demands when needs transmit great atress.
Disclosure of Invention
The invention aims to provide a casting or forging connecting flange for a concrete rod, which can ensure that the wrench space of bolts is not limited by a rib plate, can properly increase the number of the bolts and the diameters of the bolts and improve the connection stress of the flange.
The purpose of the invention is realized by the following technical scheme:
the cast or forged connecting flange for the concrete rod is characterized by comprising a flange ring, a group of rib plates, an inner pressure bearing ring and an outer pressure bearing ring which are respectively arranged at the connecting end of the flange ring, a lacing ring arranged at the inner side of the inner pressure bearing ring, a group of lacing holes arranged along the circumference of the lacing ring, a protective ring arranged at the back of the connecting end of the flange ring, and a group of bolt holes arranged on the flange ring,
the outer pressure-bearing ring is connected with the outer circle of the flange ring, the inner pressure-bearing ring is connected with the inner circle of the flange ring, the group of rib plates are uniformly distributed along the circumference of the flange ring and connect the inner pressure-bearing ring and the outer pressure-bearing ring into a whole along the radial direction,
and each bolt hole on the flange ring is positioned in a space enclosed by two adjacent rib plates, the inner pressure bearing ring and the outer pressure bearing ring.
The rib plates are as high as the inner bearing ring and the outer bearing ring.
The overhanging end face of the retainer is straight or the inner side of the overhanging end face is provided with a chamfer.
The invention has the advantages that:
the cast or forged connecting flange for the concrete pole has a simple structure and ingenious design, can ensure that when two flanges are connected, the contact surface between the flanges is the contact of the rib plates of the two flanges and the end surfaces of the inner pressure bearing ring and the outer pressure bearing ring, the two flange rings are not in contact, the wrench space when connecting bolts on the flange rings are fastened is not limited by the positions of the rib plates, and the number of the bolts and the diameter of the bolts can be properly increased when force transmission needs to be increased.
Drawings
Fig. 1 is a schematic view of the configuration of the retainer of the present invention in which the overhanging end face is flat.
Fig. 2 is a bottom view of fig. 1 of the present invention.
Fig. 3 is a top view of fig. 1 of the present invention.
Fig. 4 is a schematic view of the retainer of the present invention with a chamfer on the inside of the overhanging end face.
Detailed Description
The following further describes the embodiments of the present invention with reference to the drawings.
As shown in fig. 1 to 4, the cast or forged connection flange for concrete poles of the present invention is characterized by comprising a flange ring 1, a set of rib plates 2, an inner bearing ring 5 and an outer bearing ring 6 respectively provided at the connection end of the flange ring 1, a lacing wire ring 3 provided inside the inner bearing ring 5, a set of lacing wire holes 8 arranged along the circumference of the lacing wire ring 3, a retainer ring 4 provided at the back of the connection end of the flange ring 1, a set of bolt holes 7 provided on the flange ring 1,
the outer bearing ring 6 is connected with the outer circle of the flange ring 1, the inner bearing ring 5 is connected with the inner circle of the flange ring 1, the group of rib plates 2 are uniformly distributed along the circumference of the flange ring 1 and connect the inner bearing ring 5 and the outer bearing ring 6 into a whole along the radial direction,
each bolt hole 7 on the flange ring 1 is positioned in a space enclosed by two adjacent rib plates 2, the inner bearing ring 5 and the outer bearing ring 6.
The rib plate 2 is as high as the inner pressure bearing ring 5 and the outer pressure bearing ring 6.
The overhanging end face of the retainer 4 is straight or the inside of the overhanging end face is chamfered.
The invention is realized by the following scheme. The forming process of the flange is casting or forging, the flange is made of steel or aluminum alloy, and the specific structural form is as follows: the rib plates 2, the inner pressure bearing ring 5 and the outer pressure bearing ring 6 are arranged at the connecting end of the flange ring 1, the outer pressure bearing ring 6 is connected with the outer circle of the flange ring 1, the inner pressure bearing ring 5 is connected with the inner circle of the flange ring 1, the rib plates 2 are as high as the inner pressure bearing ring 5 and the outer pressure bearing ring 6, and the rib plates 2 are uniformly distributed along the circumference and connect the inner pressure bearing ring 5 and the outer pressure bearing ring 6 into a whole along the radial direction. The other end face of the flange ring 1 is not provided with a rib plate and is only connected with the guard ring 4. Be equipped with bolt hole 7 on the flange circle 1, bolt hole 7 is located between two adjacent gusset 2, also is located between interior pressure ring 5 and the outer pressure ring 6, and the spanner space of bolt does not receive the restriction of gusset 2 when two flange joint like this, can suitably increase bolt quantity and increase the bolt diameter, improves the flange joint atress. The hanging rib ring 3 is arranged on the inner side of the inner pressure bearing ring 5 and is in a position which is overlapped with the flange ring 1 to a certain extent, so that the stress of the hanging rib ring 3 is directly transmitted to the flange ring 1, and hanging rib holes 8 which are uniformly distributed along the circumference are formed in the hanging rib ring 3 and are used for being connected with steel bars in the concrete rod body. The outward ends of the retainer 4 may be straight or may be chamfered on the inside to reduce stress concentration. The joints of the rib plates 2 and the inner bearing ring 5, the rib plates 2 and the outer bearing ring 6, and the rib plates 2 and the flange ring 1 can be provided with process fillets, so that the processing and the forming are convenient, and the stress concentration is avoided.
According to the structure, when two flanges are connected, the contact surfaces between the flanges are the contact of the rib plates 2 of the two flanges and the end surfaces of the inner pressure bearing ring 5 and the outer pressure bearing ring 6, the two flange rings 1 are not in contact, the wrench space when connecting bolts on the flange rings 1 are fastened is not limited by the positions of the rib plates, and the number of the bolts and the diameter of the bolts can be increased properly when force transmission needs to be increased.

Claims (3)

1. A cast or forged connecting flange for a concrete pole is characterized by comprising a flange ring, a group of rib plates, an inner pressure bearing ring and an outer pressure bearing ring which are respectively arranged at the connecting end of the flange ring, a lacing ring arranged at the inner side of the inner pressure bearing ring, a group of lacing holes arranged along the circumference of the lacing ring, a protective ring arranged at the back of the connecting end of the flange ring, and a group of bolt holes arranged on the flange ring,
the outer pressure-bearing ring is connected with the outer circle of the flange ring, the inner pressure-bearing ring is connected with the inner circle of the flange ring, the group of rib plates are uniformly distributed along the circumference of the flange ring and connect the inner pressure-bearing ring and the outer pressure-bearing ring into a whole along the radial direction,
and each bolt hole on the flange ring is positioned in a space enclosed by two adjacent rib plates, the inner pressure bearing ring and the outer pressure bearing ring.
2. A cast or forged connecting flange for a concrete pole as claimed in claim 1, wherein said rib is formed to be equal in height to said inner and outer bearing rings.
3. A cast or forged connecting flange for a concrete pole as claimed in claim 1, wherein said overhanging end face of said retainer is flat or chamfered inwardly of the overhanging end face.
CN202010142712.2A 2020-03-04 2020-03-04 Cast or forged connecting flange for concrete poles Pending CN111120470A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010142712.2A CN111120470A (en) 2020-03-04 2020-03-04 Cast or forged connecting flange for concrete poles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010142712.2A CN111120470A (en) 2020-03-04 2020-03-04 Cast or forged connecting flange for concrete poles

Publications (1)

Publication Number Publication Date
CN111120470A true CN111120470A (en) 2020-05-08

Family

ID=70493419

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010142712.2A Pending CN111120470A (en) 2020-03-04 2020-03-04 Cast or forged connecting flange for concrete poles

Country Status (1)

Country Link
CN (1) CN111120470A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204510988U (en) * 2015-03-10 2015-07-29 常州腾远电杆有限公司 Concrete bar inscribed methods is blue
CN204676973U (en) * 2015-05-21 2015-09-30 无锡华润实业公司 For connecting the inner flange of high strength concrete electric pole section
CN205155405U (en) * 2015-10-28 2016-04-13 江阴市恒润重工股份有限公司 Petrochemical equipment uses corrosion -resistant flange
CN107386762A (en) * 2017-09-14 2017-11-24 青海送变电工程公司 A kind of concurrent connected using High-strength flange plate
CN211623898U (en) * 2020-03-04 2020-10-02 祁锦明 Cast or forged connecting flange for concrete poles

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204510988U (en) * 2015-03-10 2015-07-29 常州腾远电杆有限公司 Concrete bar inscribed methods is blue
CN204676973U (en) * 2015-05-21 2015-09-30 无锡华润实业公司 For connecting the inner flange of high strength concrete electric pole section
CN205155405U (en) * 2015-10-28 2016-04-13 江阴市恒润重工股份有限公司 Petrochemical equipment uses corrosion -resistant flange
CN107386762A (en) * 2017-09-14 2017-11-24 青海送变电工程公司 A kind of concurrent connected using High-strength flange plate
CN211623898U (en) * 2020-03-04 2020-10-02 祁锦明 Cast or forged connecting flange for concrete poles

Similar Documents

Publication Publication Date Title
CN211623898U (en) Cast or forged connecting flange for concrete poles
CN111120470A (en) Cast or forged connecting flange for concrete poles
CN201232679Y (en) Axial positioning and connecting device between suspension type speed reducer and shaft spline
CN2073066U (en) Variable aperture joint with multiple connection aperture
CN216617752U (en) Novel split assembly type steel wind power tower connected by section steel flanges
CN214887092U (en) Shield tunnel main body lining segment bolted connection's protruding terminal surface structure
CN102527894B (en) Roll-forging blank making method for G2500 crankshaft
CN215110309U (en) Detachable closely connected structure
CN209041314U (en) A kind of corrosion-resistant crankshaft
CN211081734U (en) Anticorrosion sucker rod
CN202468729U (en) Connecting structure of long shaft and bearing
CN105953006B (en) Quick coupling and quick coupling and the connection method of non-metal composite pipe
CN213326449U (en) Tenon for connecting standard knot
CN216343138U (en) Split pin shaft installed on oil cylinder and oil cylinder
CN219030535U (en) Manhole flange forging of thermal high-pressure separator
CN111267673A (en) Hinge type bending positioning support
CN206170377U (en) Car processing ceramic cartridge idiosome excircle hole anchor clamps
CN209925359U (en) Container binding pull rod
CN219618937U (en) Lightweight location dicyclo
CN211259335U (en) Differential mechanism cross axle
CN208778643U (en) Variable interface sprocket wheel
CN204639304U (en) The positioner of shearing machine and bearing panel thereof
CN204920415U (en) Outer flange joint high strength concrete pole
CN210388026U (en) All-terrain vehicle and pipe fitting joint structure thereof
CN217583081U (en) High-hardness oil quenching type double-wheel body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20220210

Address after: 030024 No. 3101-3103, 31st floor, West Tower, Zhonghai International Center, No. 8, Section 1, Jinci Road, Wanbailin District, Taiyuan City, Shanxi Province

Applicant after: Yuangong Energy Technology Group Co.,Ltd.

Address before: 114001 no.52-300, 219 Road, Tiedong District, Anshan City, Liaoning Province

Applicant before: Qi Jinming

TA01 Transfer of patent application right