CN111101413A - Device applied to salinized soil subgrade in seasonal frozen soil area and construction method - Google Patents
Device applied to salinized soil subgrade in seasonal frozen soil area and construction method Download PDFInfo
- Publication number
- CN111101413A CN111101413A CN202010079233.0A CN202010079233A CN111101413A CN 111101413 A CN111101413 A CN 111101413A CN 202010079233 A CN202010079233 A CN 202010079233A CN 111101413 A CN111101413 A CN 111101413A
- Authority
- CN
- China
- Prior art keywords
- soil
- facility
- layer
- roadbed
- hydrothermal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000002689 soil Substances 0.000 title claims abstract description 166
- 238000010276 construction Methods 0.000 title claims abstract description 52
- 230000001932 seasonal effect Effects 0.000 title claims abstract description 37
- 239000010410 layer Substances 0.000 claims abstract description 98
- 239000004576 sand Substances 0.000 claims abstract description 86
- 238000005192 partition Methods 0.000 claims abstract description 56
- 239000011241 protective layer Substances 0.000 claims abstract description 40
- 238000000034 method Methods 0.000 claims abstract description 33
- 238000005056 compaction Methods 0.000 claims abstract description 31
- 150000003839 salts Chemical class 0.000 claims abstract description 31
- 235000008733 Citrus aurantifolia Nutrition 0.000 claims abstract description 19
- 235000011941 Tilia x europaea Nutrition 0.000 claims abstract description 19
- 239000004571 lime Substances 0.000 claims abstract description 19
- 230000000087 stabilizing effect Effects 0.000 claims abstract description 18
- 230000008569 process Effects 0.000 claims abstract description 10
- 230000002093 peripheral effect Effects 0.000 claims abstract description 4
- 238000012544 monitoring process Methods 0.000 claims description 31
- 238000004321 preservation Methods 0.000 claims description 21
- 239000000523 sample Substances 0.000 claims description 20
- 238000011049 filling Methods 0.000 claims description 16
- 239000000463 material Substances 0.000 claims description 8
- 238000012806 monitoring device Methods 0.000 claims description 7
- 238000003825 pressing Methods 0.000 claims description 6
- 230000001681 protective effect Effects 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 238000005096 rolling process Methods 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000004140 cleaning Methods 0.000 claims description 3
- 238000013461 design Methods 0.000 claims description 3
- 239000003864 humus Substances 0.000 claims description 3
- 239000003550 marker Substances 0.000 claims description 3
- 239000002344 surface layer Substances 0.000 claims description 3
- 238000003860 storage Methods 0.000 claims 2
- 238000000926 separation method Methods 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 29
- 238000009413 insulation Methods 0.000 abstract description 12
- 230000000694 effects Effects 0.000 description 12
- FAPWRFPIFSIZLT-UHFFFAOYSA-M Sodium chloride Chemical compound [Na+].[Cl-] FAPWRFPIFSIZLT-UHFFFAOYSA-M 0.000 description 10
- 239000011780 sodium chloride Substances 0.000 description 9
- 230000005012 migration Effects 0.000 description 8
- 238000013508 migration Methods 0.000 description 8
- 239000004795 extruded polystyrene foam Substances 0.000 description 7
- 230000008859 change Effects 0.000 description 5
- 239000004927 clay Substances 0.000 description 5
- 230000008014 freezing Effects 0.000 description 5
- 238000007710 freezing Methods 0.000 description 5
- 230000008961 swelling Effects 0.000 description 5
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 4
- 239000000945 filler Substances 0.000 description 4
- 239000004746 geotextile Substances 0.000 description 4
- 230000002265 prevention Effects 0.000 description 4
- 230000005540 biological transmission Effects 0.000 description 3
- 201000010099 disease Diseases 0.000 description 3
- 239000012774 insulation material Substances 0.000 description 3
- 230000007774 longterm Effects 0.000 description 3
- 230000035699 permeability Effects 0.000 description 3
- 239000000843 powder Substances 0.000 description 3
- QAOWNCQODCNURD-UHFFFAOYSA-L Sulfate Chemical compound [O-]S([O-])(=O)=O QAOWNCQODCNURD-UHFFFAOYSA-L 0.000 description 2
- 238000010521 absorption reaction Methods 0.000 description 2
- 239000010426 asphalt Substances 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 2
- 239000006260 foam Substances 0.000 description 2
- 239000008187 granular material Substances 0.000 description 2
- 238000002156 mixing Methods 0.000 description 2
- 239000002245 particle Substances 0.000 description 2
- 239000010451 perlite Substances 0.000 description 2
- 235000019362 perlite Nutrition 0.000 description 2
- 239000004814 polyurethane Substances 0.000 description 2
- 230000008092 positive effect Effects 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000012266 salt solution Substances 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 238000002791 soaking Methods 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 238000010257 thawing Methods 0.000 description 2
- 239000010409 thin film Substances 0.000 description 2
- VEXZGXHMUGYJMC-UHFFFAOYSA-M Chloride anion Chemical compound [Cl-] VEXZGXHMUGYJMC-UHFFFAOYSA-M 0.000 description 1
- PMZURENOXWZQFD-UHFFFAOYSA-L Sodium Sulfate Chemical compound [Na+].[Na+].[O-]S([O-])(=O)=O PMZURENOXWZQFD-UHFFFAOYSA-L 0.000 description 1
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000005856 abnormality Effects 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000001311 chemical methods and process Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 239000013078 crystal Substances 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000008020 evaporation Effects 0.000 description 1
- 238000001704 evaporation Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 230000002427 irreversible effect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 239000007769 metal material Substances 0.000 description 1
- 239000012466 permeate Substances 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 229920006327 polystyrene foam Polymers 0.000 description 1
- 229920002635 polyurethane Polymers 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000001556 precipitation Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 229910052938 sodium sulfate Inorganic materials 0.000 description 1
- 235000011152 sodium sulphate Nutrition 0.000 description 1
- 238000007711 solidification Methods 0.000 description 1
- 230000008023 solidification Effects 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
- -1 sulfate is higher Chemical class 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/04—Foundations produced by soil stabilisation
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/06—Methods or arrangements for protecting foundations from destructive influences of moisture, frost or vibration
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a device and a construction method applied to a salinized soil subgrade in a seasonal frozen soil area, belongs to the technical field of subgrade foundations, and aims to solve the problems that the salinized soil subgrade in the seasonal frozen soil area is easy to frost heaving, salt heaving and solution sink and the problem that a cushion layer is thick and is not easy to compact when the traditional subgrade gravel soil is used as a water-permeable partition layer. The device comprises an earthwork roadbed, a heat stabilizing facility and a partition facility, wherein the partition facility comprises a middle coarse sand lower protective layer, a modified desert sand partition layer and a middle coarse sand upper protective layer which are sequentially arranged from bottom to top; the heat-stabilizing facility comprises a bottom roadbed stabilizing facility and an upper layer heat-insulating facility, wherein the bottom roadbed stabilizing facility comprises an lime soil compaction pile and a lime soil cushion layer which are sequentially arranged from bottom to top. The method comprises the following steps of constructing a bottom roadbed stabilizing facility, constructing a partition facility, constructing an earthwork roadbed and an upper layer heat insulation facility, and constructing a peripheral water-stop wall. The invention can maintain the stability of water, heat and salt of the roadbed for a long time through the combination of the structure and the construction method; the cost is low, and the construction process is few, and it is simple to maintain.
Description
Technical Field
The invention belongs to the technical field of roadbed foundations, and particularly relates to a device and a construction method applied to a salinized soil roadbed in a seasonal frozen soil area.
Background
(1) The mechanism of saline soil subgrade settlement and salt expansion and frost heaving in the seasonal frozen soil area is as follows:
the cause of the saline soil can be summarized as follows: the method has the advantages that the method is arid in climate, rare in precipitation, strong in evaporation, and more salt is contained in the parent rock of the formed soil, the distribution of the parent rock is particularly wide in northwest provinces of China, the northwest provinces are mostly located in seasonal frozen soil regions, and the thickness of the movable layer is about 1.5-2.0 m; soil in the range of a salinized soil subgrade active layer in a seasonal frozen soil area is accompanied with various physical and chemical processes in the freezing and thawing cycle process, such as: water salt migration, salt phase change, energy transmission and the like; after the warm season is finished and the soil enters the cold season, the ground surface begins to freeze in the whole range of the movable layer, the freezing surface develops downwards, water moves from bottom to top towards the freezing surface, and simultaneously along with salt migration, when groundwater is active, the dissolving and moving effects on soluble salts such as sodium chloride, sodium sulfate and the like in the soil body are obvious, and the dissolving and moving diseases are easily induced; after the soil enters a warm season, the ground surface begins to melt, the frozen surface is transferred downwards, water moves towards the frozen surface from top to bottom, simultaneously, along with salt migration, in a seasonal frozen soil area, when the local temperature rises, the solubility of a salt solution is gradually improved, and precipitated crystals begin to melt; along with the alternate change of the air temperature of the seasonal frozen soil area, the roadbed soil undergoes repeated salt swelling, frost swelling and settlement processes, and soil body is repeatedly swelled and loosened to cause loose and swollen surface, unstable side slope or deformation and damage of highway roadbed and road surface; years of construction experience shows that the content of salts such as sulfate is higher, the loosening and swelling diseases are more serious, and the salt swelling and the solution collapse deformation of the soil body are irreversible.
In order to relieve and prevent the diseases of frost heaving, salt heaving and collapse of the salinized soil earthwork roadbed in the freezing region of the season, the effective way is to control the processes of water and salt migration, salt phase change, energy transmission and the like in the soil body.
(2) Measures for controlling water and salt migration in the prior art:
the traditional method for preventing and controlling the salt swelling and the sinking diseases of the salinized soil subgrade is to arrange a partition layer, wherein the partition layer is divided into an impermeable partition layer and a permeable partition layer. The traditional impervious partition layer is mainly made of geotextiles such as waterproof geotextile and waterproof boards, and the geotextiles such as waterproof geotextile are easy to be punctured by granular fillers under the action of external load, temperature load and the like in a construction rolling stage or an operation stage, so that the service life is influenced, and the like; the permeable partition layer is generally filled with gravel, aeolian sand, river sand or desert sand and the like with good permeability, and the basic principle of partition is that the thickness of the partition layer is larger than or equal to the rising height of capillary water containing salt, so that the partition effect is achieved.
But gravel or river sand is used as a water permeability partition layer, so as to play a role of partition, the paving thickness is larger, the capillary water of gravel soil and sand is increased to a height of between 40 and 110cm, more fillers are needed, and the method is suitable for road sections with the roadbed filling height of more than 1.8m and the fillers are available; the capillary water of the aeolian sand is increased to a strong height of 80-90cm, and when the aeolian sand is used as a water permeable partition layer, the laying thickness is at least 90cm, so that the problems that the compactness is difficult to control, the filler demand is large and the like exist; when the silty soil and the clay soil are used as water-permeable partition layers, the capillary water rises strongly to a height of 200-400cm, and if the silty soil and the clay soil contain more powder and clay particles, and thin film water exists between the powder and the clay particles, salt migration can occur along with the existence of the thin film water, secondary salinization is caused, and the partition layers gradually lose efficacy; therefore, the content of powder and clay should be strictly controlled during construction, which makes construction difficult.
(3) The current situation about roadbed thermal insulation and stability in the prior art:
in road engineering in permafrost regions or seasonal frozen soil regions, a heat preservation method is generally used in frost heaving prevention roadbed, and a heat preservation layer is laid in the roadbed, so that the variation range of a roadbed soil temperature field in an active layer range can be effectively reduced, and the positive effects of frost heaving prevention, water seepage prevention and thaw settlement prevention are achieved.
The existing heat insulation materials for the roadbed mainly comprise a Polyurethane (PU) plate, a polystyrene foam (EPS) plate, an extruded polystyrene foam plastic (XPS) plate and the like, the performance indexes of the heat insulation materials for the road engineering require that the thermal resistance, the strength and the rigidity need to reach certain standards, the thermal resistance rate and the compressive strength of the XPS plate are superior to those of the PU plate and the EPS plate, but the mechanical property of the XPS heat insulation plate material is greatly different from the roadbed filling, the thickness of the XPS heat insulation plate is in positive correlation with the heat insulation effect, but the excessive thickness of the XPS heat insulation plate can influence the overall rigidity of the roadbed, the problem that the deflection value exceeds the standard and the like can occur possibly, and the heat insulation plates such as the XPS and the like.
The application of the side slope heat preservation in road engineering of permafrost regions has proved that the side slope heat preservation can play a role in reaction, and when the side slope heat preservation material is applied in construction of seasonal frozen regions, the blocky heat preservation material is found to be easy to slide downwards, and bulge or slab staggering and local deformation are caused; the heat conductivity coefficients of the asphalt expanded perlite, the fine granular soil and the live turf soil are larger, and the heat insulation performance is poorer when the asphalt expanded perlite, the fine granular soil and the live turf soil are used as a slope heat insulation material.
The saline soil subgrade in the seasonal frozen soil region is required to solve the problem of the settlement caused by double reasons of frost heaving and salt heaving, the requirement of subgrade basement stability is considered in the basement treatment, and the soaking pre-dissolving method, the filling and replacing method, the dynamic compaction method, the compaction pile method and the like in the prior art are obviously limited.
The soaking pre-dissolving method is suitable for soil layers with small thickness and large permeability coefficient; the effect of treating the saline soil foundation by the dynamic compaction method is not ideal; the pile foundation construction process has various pile foundation types, in a saline soil area, soil body pore water is rich in salt solution, the specific gravity is high, the viscosity is high, the discharging is very difficult and slow, the drainage period is long, the construction period is long, and the compaction effect of the gravel pile is not ideal; chloride ions and sulfate which are rich in the saline soil have certain corrosion effect on metal materials and concrete, so that the driven steel sheet pile, the prefabricated square pile, the immersed tube cast-in-place pile, the CFG pile and the cast-in-place pile are not suitable for being applied to the treatment of the roadbed of the saline soil area.
Based on the problems in the background art, the technical personnel in the field research and develop a device and a construction method applied to the salinized soil subgrade in the seasonal frozen soil area in the construction of highway engineering with the thickness of the movable layer of the seasonal frozen soil area of more than northwest of 1.5m-2.0 m.
Disclosure of Invention
The invention aims to provide a device applied to a salinized soil subgrade in a seasonal frozen soil area, and aims to solve the problems that the salinized soil area and the subgrade in the salinized soil area are easy to frost heaving, salt heaving, sinking and the like.
The invention also aims to provide a construction method of the device applied to the salinized soil roadbed in the seasonal frozen soil area, so as to solve the problem that the cushion layer is thick and not easy to compact when the traditional roadbed gravel soil is used as a water-permeable partition layer.
In order to solve the problems, the technical scheme of the invention is as follows:
a device applied to a salinized soil subgrade in a seasonal frozen soil area comprises an earthwork subgrade, a heat-stabilizing facility and a partition facility, wherein the partition facility comprises a middle coarse sand lower protective layer, a modified desert sand partition layer and a middle coarse sand upper protective layer which are sequentially arranged from bottom to top; the heat-stabilizing facility comprises a bottom roadbed stabilizing facility and an upper heat-insulating facility, the bottom roadbed stabilizing facility comprises an ash soil compaction pile and a lime soil cushion layer which are sequentially arranged from bottom to top, the lime soil cushion layer is positioned below a middle coarse sand lower protective layer, and an earthwork roadbed and a road surface are sequentially paved above a middle coarse sand upper protective layer.
The system further comprises hydrothermal monitoring facilities, wherein the hydrothermal monitoring facilities are distributed in a group at intervals of 10-50 Km kilometers, each group of hydrothermal monitoring facilities is 1.5-2.5 m in length, and the hydrothermal monitoring facilities are laid in an upper protective layer of the earthwork roadbed and the medium coarse sand along the roadbed in a half width mode.
Furthermore, the horizontal arrangement interval of the hydrothermal probes is 1m, the vertical arrangement interval of the hydrothermal probes is 0.5m, one group of the hydrothermal probes is paved to a depth which exceeds the bottom end of the lime-soil compaction pile by 0.5m, and the rest groups of the hydrothermal probes are only paved in the earth roadbed and the upper protective layer of the medium coarse sand.
Furthermore, the hydrothermal monitoring facility comprises a thermistor cable and a hydrothermal probe which are connected with each other, the thermistor cable is connected with a monitoring device, the monitoring device comprises an information collector and a power supply device which are connected with each other, and the power supply device is connected with the thermistor cable.
Furthermore, modified desert sand water-proof walls are arranged on the outer sides of the lime-soil compaction piles.
Furthermore, the upper-layer heat-insulating facility comprises a bubble mixed light soil base layer and heat-insulating protective roads, wherein the bubble mixed light soil base layer is positioned above the earthwork roadbed and below the road surface, and the heat-insulating protective roads are positioned at two sides of the earthwork roadbed.
Furthermore, sand and soil surrounding areas with trapezoidal sections are arranged on two sides of the partition facility, and the sand and soil surrounding areas encapsulate the peripheries of the middle coarse sand lower protective layer, the modified desert sand partition layer and the middle coarse sand upper protective layer.
Furthermore, the lime-soil compaction pile is a quincuncial pile.
Furthermore, power supply unit includes solar battery and solar panel interconnect, connects through the dc-to-ac converter between solar battery and the solar panel.
A construction method of a device applied to a salinized soil subgrade in a seasonal frozen soil area is characterized by comprising the following steps: the method comprises the following steps:
step A, constructing a bottom roadbed stabilizing facility:
firstly, cleaning the surface by using an excavator, wherein the treatment depth is not less than 0.3m, and the humus soil is guaranteed to be excavated;
the pipe sinking method is adopted to form the lime-soil compaction pile, and the pile forming process comprises the following steps: the pile driver is put in place, the steel pipe is driven to the design requirement, the material is added, the pipe is pulled out, the pile is formed, the pile top is compacted, the heavy hammer is tamped and sealed, the base is fully compacted and leveled by a road roller and a leveler after the pile is formed, and the flatness meets the standard requirement;
adopting a marker post method to control the paving thickness, paving a 5% lime soil cushion layer with the thickness of 30-50cm, and layering and compacting;
after the pile is formed, a group of hydrothermal monitoring facilities are buried in a drilled hole, the lowest hydrothermal probe is ensured to be positioned at the position of 0.5m of the bottom end of the lime-soil compaction pile, and then the pile is fully compacted and leveled;
step B, partition facility construction:
filling sand soil edge-covered areas in a layered mode;
sequentially laying a middle coarse sand lower protective layer with the thickness of 5 cm;
a modified desert sand partition layer with the thickness of 3cm-5 cm;
a 5 cm-thick medium coarse sand upper protective layer, and embedding a hydrothermal monitoring facility with a corresponding depth when the layer is filled;
layering and primarily pressing, leveling and secondarily pressing, and finally rolling the surface layer;
step C, construction of an earthwork roadbed and an upper layer heat preservation facility:
filling an upper earthwork roadbed and a heat-insulating protective road of the partition facility in layers, constructing in full scale, and ensuring that the thickness of a road pavement is not more than 0.3 m; ensuring that the compactness meets the requirements of construction specifications after each layer of filling, and burying a hydrothermal monitoring facility with a corresponding depth during each layer of filling;
paving a bubble mixed light soil base layer, and curing for 7 days according to the standard;
d, constructing a peripheral water-stop wall:
building the modified desert sand water-proof wall, and fully compacting by adopting a rammer;
step E, pavement construction:
the standard requires the construction of a pavement.
The invention has the following beneficial effects:
(1) according to the invention, the partition facilities are arranged below the earthwork roadbed, and the modified desert sand is used as the impervious partition layer, so that the paving thickness is small, the compaction is easy, and the construction is convenient; its self has the characteristics of flexible selfreparing, belongs to flexible selfreparing impervious barrier, replaces traditional aeolian sand large thickness partition layer that permeates water, lays the data display of on-the-spot monitoring at the experimental section: the modified desert sand partition layer can directly partition capillary water, and soluble salts dissolved in the capillary water can be simultaneously partitioned, so that the water-resisting and salt-separating effects are remarkable, and the problems of settlement and secondary salinization are fundamentally solved.
(2) The heat-stabilizing facility comprises a bottom roadbed stabilizing facility and an upper-layer heat-insulating facility, wherein the upper-layer heat-insulating facility is arranged above and around the earthwork roadbed, and in a seasonal frozen soil area, the thickness of a movable layer is about 1.5-2.0 m in the northwest direction, so that the good heat-insulating facility can ensure that the movable layer is not completely frozen below the earthwork roadbed when the earthwork roadbed comes in severe winter, and the problems of frost heaving of the lower roadbed and wet sinking after salt heaving are fundamentally solved; the foam mixed light soil is selected as the heat insulation layer paved above the earthwork roadbed, and the foam mixed light soil is characterized in that the density is smaller than that of common concrete, the strength and the rigidity even exceed those of a soil body with good performance, the heat conductivity coefficient, the strength and the density can be adjusted, and the heat conductivity coefficient can be reduced by adjusting the density under the condition of meeting the requirements of the strength and the durability, so that the heat insulation performance is improved; the bubble mixed light soil has high porosity, small heat conductivity coefficient, good shock resistance, heat insulation and freeze-thaw resistance; after the bubble mixed light soil is mixed according to a certain mixing proportion, the fluidity, the water retention property and the workability are good, the construction is convenient, and the initial strength of curing for 7 days after solidification is high; the bubble mixed light soil belongs to cement stable granules, can be used for construction of a base layer subbase layer, has good shock resistance, heat insulation and freeze-thaw resistance, and meets the requirement of strength and rigidity.
And when the thickness of the slope heat-preservation protecting channel is larger than the thickness of the movable layer, the ground temperature of the roadbed outside the widening section is always at the normal temperature, the range of the movable layer outside the widening section can be reduced, the occurrence and development of frost heaving, salt heaving and thawing damage of the roadbed are controlled, and the problem of soil body bulking caused by salt phase change is avoided.
As the upper heat preservation facility of the seasonal frozen soil area, the combination of the bubble mixed light soil and the heat preservation guard way, the data monitored on the laying site in the test section are displayed as follows: good heat-stabilizing effect can be achieved; and confirming the data of the field detection of the test section in the construction.
A bottom layer roadbed stabilizing facility is laid below the middle coarse sand lower protective layer, the bottom layer roadbed stabilizing facility selects the combination of a lime soil compaction pile and a lime soil cushion layer, the combination is specially specific to the characteristics of saline soil in a seasonal frozen soil area, and various factors such as compaction effect, water consumption, heat supply and the like are considered, the lime soil compaction pile can react to consume water and release heat and expand in volume in construction, a quincunx pile group reacts with the lower foundation soil, water absorption, expansion and compaction are realized, the bearing capacity of the foundation can be remarkably improved, and a large amount of reaction heat is emitted, so that the bottom layer roadbed stabilizing facility has a positive effect on the thermal stability of the upper roadbed; the combined lime soil cushion layer can ensure that the excessive capillary water below the lime soil cushion layer can be absorbed in later use, and the application effect is good.
(3) The hydrothermal probe in the hydrothermal monitoring facility can timely detect the hydrothermal current situation of the earthwork roadbed and the corresponding position below the earthwork roadbed, and can collect data, so that the monitoring is convenient, the whole solar energy is adopted for power supply, and the hydrothermal monitoring facility is more suitable for the current situation of the salinized soil road section in the northwest seasonal frozen soil area; the paving mode adopts half-width road width, the half-width road width is generally arranged at one end of a negative slope in consideration of freezing depth, one group of the half-width road width is arranged at intervals of 10-50 Km kilometers, the half-width road width is flexibly adjusted according to the geological condition of a construction field road section, when the geological structure similarity of the construction field road section is higher, the arrangement interval is widened, and when the geological structure similarity of the construction field road section is low and the condition above a road surface is complex, the arrangement interval is shortened; the hydrothermal monitoring facility can monitor the hydrothermal condition inside the roadbed in real time, monitor abnormality in time and ensure long-term healthy operation of the roads in the salinized land area in the seasonal frozen area; and a module with a function of forecasting hydrothermal abnormal conditions can be additionally arranged according to the requirement, so that intelligent monitoring is realized.
(4) The method of the invention highlights that the middle coarse sand lower protective layer, the modified desert sand partition layer and the middle coarse sand upper protective layer are wrapped by using layered filling sand granule soil, and meanwhile, the lower protective layer, the modified desert sand partition layer and the middle coarse sand upper protective layer are paved and compacted in a layered manner, thus ensuring the stability of the middle coarse sand lower protective layer, the modified desert sand partition layer and the middle coarse sand upper; meanwhile, the earthwork roadbed and the heat-preservation guard way are integrally paved, so that the stability of the heat-preservation guard way is ensured, the integrated construction process is less, and the cost is low; and finally, constructing the modified desert sand water-stop wall, further preventing the migration of water and salt on two sides of the roadbed, and comprehensively ensuring the stability of the roadbed.
(5) According to the invention, by combining the structure and the construction method, the upward migration of underground capillary water and soluble salt can be effectively isolated, and the processes of salt phase change, energy transmission and the like can be effectively controlled; the effects of water absorption, heat supplement and expansion compaction on the lower substrate are achieved, and the long-term water, heat and salt stability of the roadbed soil is maintained; and timely monitoring the water and heat conditions of the roadbed; the related part materials are common geotechnical materials, so that the construction cost is low, the construction procedures are few, and the later maintenance is simple; the whole facility construction and the roadbed construction are carried out simultaneously, and the long-term healthy operation effect of the constructed highway is obvious.
Drawings
FIG. 1 is a schematic view of a device applied to a salinized soil subgrade in a seasonal frozen soil area;
fig. 2 is a top view of fig. 1.
The reference numbers are as follows: 1. mixing the bubbles with a light soil base layer; 2. insulating and protecting the road; 3. a lime soil cushion layer; 4. compacting the piles by using lime soil; 5. modifying a desert sand partition layer; 6. a protective layer is arranged on the medium coarse sand; 7. a middle coarse sand lower protective layer; 8. modifying the desert sand water-proof wall; 9. a sand soil edge covering area; 10. a thermistor cable; 11. a hydrothermal probe; 12. a monitoring device; 13. an information collector; 14. a power supply device; 15. a pavement; 16. an earthwork roadbed.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
As shown in fig. 1-2, the device applied to the salinized soil subgrade in the seasonal frozen soil area comprises an earthwork subgrade 16, a heat stabilizing facility, a partition facility and a hydrothermal monitoring facility.
Specifically, the method comprises the following steps: the partition facility comprises a middle coarse sand lower protective layer 7, a modified desert sand partition layer 5 and a middle coarse sand upper protective layer 6 which are arranged from bottom to top in sequence; and sand soil surrounding areas 9 with trapezoidal sections are arranged on two sides of the partition facility, and the sand soil surrounding areas 9 encapsulate the peripheries of the middle coarse sand lower protective layer 7, the modified desert sand partition layer 5 and the middle coarse sand upper protective layer 6.
The heat-stabilizing facility comprises a bottom roadbed stabilizing facility and an upper layer heat-insulating facility:
the bottom roadbed stabilizing facility comprises an ash soil compaction pile 4 and a lime soil cushion layer 3 which are sequentially arranged from bottom to top, the lime soil cushion layer 3 is positioned below a middle coarse sand lower protective layer 7, and an earthwork roadbed 16 and a road surface 15 are sequentially paved above a middle coarse sand upper protective layer 6; the lime-soil compaction pile 4 is a quincuncial pile; and modified desert sand water-proof walls 8 are arranged on the outer sides of the lime soil compaction piles 4.
The upper-layer heat preservation facility comprises a bubble mixed light soil base layer 1 and a heat preservation guard way 2, the bubble mixed light soil base layer 1 is located above the earthwork roadbed 16 and below the road surface 15, and the heat preservation guard way 2 is located on two sides of the earthwork roadbed 16.
The hydrothermal monitoring facility comprises a thermistor cable 10 and a hydrothermal probe 11 which are connected with each other, the thermistor cable 10 is connected with a monitoring device 12, the monitoring device 12 comprises an information collector 13 and a power supply device 14 which are connected with each other, and the power supply device 14 is connected with the thermistor cable 10; the power supply device 14 includes a solar battery and a solar panel connected to each other, and the solar battery and the solar panel are connected through an inverter.
The hydrothermal monitoring facilities are arranged in a group at intervals of 10-50 Km, the length of each group of hydrothermal monitoring facilities is 1.5-2.5 m, and the hydrothermal monitoring facilities are laid in an earth roadbed 16 and a medium grit upper protective layer 6 along the roadbed in a half-width mode; the horizontal arrangement interval of the hydrothermal probes 11 is 1m, the vertical arrangement interval of the hydrothermal probes 11 is 0.5m, one group of the hydrothermal probes 11 is paved with a depth which exceeds the bottom end of the lime-soil compaction pile 4 by 0.5m, and the rest groups of the hydrothermal probes 11 are only paved in the earth roadbed 16 and the upper coarse sand protective layer 6.
The construction method of the device applied to the salinized soil subgrade in the seasonal frozen soil area comprises the following steps:
step A, constructing a bottom roadbed stabilizing facility:
firstly, cleaning the surface by using an excavator, wherein the treatment depth is determined according to the geological conditions of the construction site, so that humus is removed, and the treatment depth is not less than 0.3m in the construction;
the lime-soil compaction piles 4 are formed by a pipe sinking method, the lime-soil compaction piles 4 are arranged into quincuncial piles, and the pile forming process comprises the following steps: the pile driver is put in place, the steel pipe is driven to the design requirement, the material is added, the pipe is pulled out, the pile is formed, the pile top is compacted, the heavy hammer is tamped and sealed, the base is fully compacted and leveled by a road roller and a leveler after the pile is formed, and the flatness meets the standard requirement;
the paving thickness is controlled by adopting a marker post method, a 5% lime soil cushion layer 3 is paved, and the lime soil cushion layer is compacted in a layered mode, wherein the paving thickness is determined according to geological conditions of a construction site, and is generally 30cm-50 cm;
after the pile is formed, a group of hydrothermal monitoring facilities are buried in a drilled hole, the lowest hydrothermal probe is ensured to be positioned at the position of 0.5m at the bottom end of the lime-soil compaction pile 4, and then the complete compaction and leveling are carried out;
step B, partition facility construction:
filling a sand soil edge-covered area 6 in a layered manner;
sequentially laying a middle coarse sand lower protective layer 7 with the thickness of 5 cm;
a modified desert sand partition layer 5 with the thickness of 3cm-5 cm;
a 5 cm-thick medium coarse sand upper protective layer 6, wherein a hydrothermal monitoring facility with a corresponding depth is buried when the layer is filled;
the thickness of the modified desert sand partition layer 5 is determined according to geological conditions of a construction site, when the contents of underground capillary water and salt are high, the paving thickness of the modified desert sand partition layer 5 is properly increased, otherwise, the paving thickness is up to 3cm, so that partition can be realized, and the construction cost is lower;
layering and primarily pressing, leveling and secondarily pressing, and finally rolling the surface layer;
step C, construction of an earthwork roadbed and an upper layer heat preservation facility:
filling an upper earthwork roadbed 16 and a heat-insulating protective road 2 of the partition facility in layers, constructing in full scale, and ensuring that the thickness of a ripping layer is not more than 0.3 m; ensuring that the compactness meets the requirements of construction specifications after each layer of filling, and burying a hydrothermal monitoring facility with a corresponding depth during each layer of filling;
paving a bubble mixed light soil base layer 1, and curing for 7 days according to the standard;
d, constructing a peripheral water-stop wall:
building a modified desert sand water-stop wall 8, and fully compacting by adopting a tamper;
step E, pavement construction:
standards require the pavement 15 to be constructed.
Claims (10)
1. The utility model provides a be applied to device of seasonal frozen soil district salt soil road bed, includes earthwork road bed (16), its characterized in that: the sand-based sand separation system further comprises a heat-stabilizing facility and a partition facility, wherein the partition facility comprises a middle coarse sand lower protective layer (7), a modified desert sand partition layer (5) and a middle coarse sand upper protective layer (6) which are sequentially arranged from bottom to top; heat-stabilizing facility includes bottom road bed stabilizing facilities and upper heat preservation facility, bottom road bed stabilizing facilities includes lime-soil compaction stake (4) and lime-soil bed course (3) that set gradually from bottom to top, lime-soil bed course (3) are located protective layer (7) below under the medium coarse sand, earthwork road bed (16) and road surface (15) are laid in proper order to medium coarse sand upper protective layer (6) top.
2. The device of claim 1, applied to a salinized soil subgrade in a seasonal frozen soil area, wherein: the system also comprises hydrothermal monitoring facilities, wherein the hydrothermal monitoring facilities are arranged in a group at intervals of 10-50 Km kilometers, the length of each group of hydrothermal monitoring facilities is 1.5-2.5 m, and the hydrothermal monitoring facilities are laid in the earth roadbed (16) and the medium coarse sand upper protective layer (6) along the roadbed in a half-width mode.
3. The device of claim 2, applied to a salinized soil subgrade in a seasonal frozen soil area, wherein: the horizontal arrangement distance of the hydrothermal probes (11) is 1m, the vertical arrangement distance of the hydrothermal probes (11) is 0.5m, one group of the hydrothermal probes (11) is paved with a depth exceeding the bottom end of the lime-soil compaction pile (4) by 0.5m, and the rest groups of hydrothermal probes (11) are only paved in the earthwork roadbed (16) and the upper protective layer (6) of medium and coarse sand.
4. A device for application to a salinized soil subgrade in seasonal frozen soil areas according to claim 2 or 3, wherein: the hydrothermal monitoring facility comprises a thermistor cable (10) and a hydrothermal probe (11) which are connected with each other, the thermistor cable (10) is connected with a monitoring device (12), the monitoring device (12) comprises an information collector (13) and a power supply device (14) which are connected with each other, and the power supply device (14) is connected with the thermistor cable (10).
5. The device of claim 1, applied to a salinized soil subgrade in a seasonal frozen soil area, wherein: and modified desert sand water-stop walls (8) are arranged on the outer sides of the lime soil compaction piles (4).
6. The device of claim 1, applied to a salinized soil subgrade in a seasonal frozen soil area, wherein: the upper heat preservation facility comprises a bubble mixed light soil base layer (1) and a heat preservation guardrail (2), the bubble mixed light soil base layer (1) is located above an earthwork roadbed (16) and below a pavement (15), and the heat preservation guardrail (2) is located on two sides of the earthwork roadbed (16).
7. The device of claim 1, applied to a salinized soil subgrade in a seasonal frozen soil area, wherein: and sand and soil surrounding areas (9) with trapezoidal sections are arranged on two sides of the partition facility, and the sand and soil surrounding areas (9) encapsulate the peripheries of the middle coarse sand lower protective layer (7), the modified desert sand partition layer (5) and the middle coarse sand upper protective layer (6) therein.
8. The device of claim 1, applied to a salinized soil subgrade in a seasonal frozen soil area, wherein: the lime-soil compaction piles (4) adopt quincuncial piles.
9. The device of claim 4, wherein the device is applied to a salinized soil subgrade in a seasonal frozen soil area, and comprises: the power supply device (14) comprises a solar storage battery and a solar panel which are connected with each other, and the solar storage battery and the solar panel are connected through an inverter.
10. A construction method of a device applied to a salinized soil subgrade in a seasonal frozen soil area is characterized by comprising the following steps: the method comprises the following steps:
step A, constructing a bottom roadbed stabilizing facility:
firstly, cleaning the surface by using an excavator, wherein the treatment depth is not less than 0.3m, and the humus soil is guaranteed to be excavated;
the pipe sinking method is adopted to form the lime-soil compaction pile 4, and the pile forming process comprises the following steps: the pile driver is put in place, the steel pipe is driven to the design requirement, the material is added, the pipe is pulled out, the pile is formed, the pile top is compacted, the heavy hammer is tamped and sealed, the base is fully compacted and leveled by a road roller and a leveler after the pile is formed, and the flatness meets the standard requirement;
the paving thickness is controlled by adopting a marker post method, a 5 percent lime soil cushion layer 3 with the thickness of 30-50cm is paved, and the layers are compacted;
after the pile is formed, a group of hydrothermal monitoring facilities are buried in a drilled hole, the lowest hydrothermal probe is ensured to be positioned at the position of 0.5m at the bottom end of the lime-soil compaction pile (4), and then the pile is fully compacted and leveled;
step B, partition facility construction:
filling sand and soil surrounding areas (6) in a layered manner;
sequentially paving middle coarse sand lower protective layers (7) with the thickness of 5 cm;
a modified desert sand partition layer (5) with the thickness of 3cm-5 cm;
a middle coarse sand upper protective layer (6) with the thickness of 5cm, and a hydrothermal monitoring facility with the corresponding depth is buried when the layer is filled;
layering and primarily pressing, leveling and secondarily pressing, and finally rolling the surface layer;
step C, construction of an earthwork roadbed and an upper layer heat preservation facility:
filling an upper earthwork roadbed (16) and a heat-insulating protective road (2) of the partition facility in layers, constructing in full scale, and ensuring that the thickness of the road pavement is not more than 0.3 m; ensuring that the compactness meets the requirements of construction specifications after each layer of filling, and burying a hydrothermal monitoring facility with a corresponding depth during each layer of filling;
paving a bubble mixed light soil base layer (1), and curing for 7 days according to the standard;
d, constructing a peripheral water-stop wall:
building a modified desert sand water-stop wall (8), and fully compacting by adopting a tamper;
step E, pavement construction:
the standard requires the construction of a pavement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010079233.0A CN111101413A (en) | 2020-02-03 | 2020-02-03 | Device applied to salinized soil subgrade in seasonal frozen soil area and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010079233.0A CN111101413A (en) | 2020-02-03 | 2020-02-03 | Device applied to salinized soil subgrade in seasonal frozen soil area and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111101413A true CN111101413A (en) | 2020-05-05 |
Family
ID=70428000
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010079233.0A Pending CN111101413A (en) | 2020-02-03 | 2020-02-03 | Device applied to salinized soil subgrade in seasonal frozen soil area and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111101413A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111830235A (en) * | 2020-06-17 | 2020-10-27 | 安徽理工大学 | Frozen soil body model and construction method of frozen soil body water migration model |
CN112176814A (en) * | 2020-10-12 | 2021-01-05 | 西藏大学 | Water accumulation preventing plateau asphalt highway and construction method |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103774515A (en) * | 2014-02-20 | 2014-05-07 | 中铁第四勘察设计院集团有限公司 | High speed railway embankment structure in salty soil regions |
RU2536538C1 (en) * | 2013-07-18 | 2014-12-27 | Виктор Анатольевич Бабелло | Method for reduction of deformations of motor and railway roads on permafrost soils that thaw out in process of operation |
CN205557220U (en) * | 2016-02-03 | 2016-09-07 | 中国科学院寒区旱区环境与工程研究所 | Wind amasss husky berm frozen soil roadbed structure |
CN106147779A (en) * | 2016-07-14 | 2016-11-23 | 甘肃工业技术研究院 | The preparation of drift-sand antiseepage saline and alkaline barrier material and salt-soda soil through engineering approaches in situ is administered and restorative procedure |
CN206529760U (en) * | 2017-02-22 | 2017-09-29 | 中铁二院工程集团有限责任公司 | High-speed railway embankment substrate salinized soil resists molten sunken construction |
CN208415233U (en) * | 2018-06-21 | 2019-01-22 | 北京市勘察设计研究院有限公司 | A kind of foundation structure of saline soil area |
CN109958120A (en) * | 2019-04-10 | 2019-07-02 | 国网新疆电力有限公司经济技术研究院 | Method of the cold anti-salt of drought-hit area salinized soil every salt |
CN110273341A (en) * | 2019-07-19 | 2019-09-24 | 西南交通大学 | A kind of frozen ground regions heating road structure and its construction method |
CN212000424U (en) * | 2020-02-03 | 2020-11-24 | 甘肃省公路工程质量试验检测中心有限公司 | Be applied to device of seasonal frozen soil district salt soil road bed |
-
2020
- 2020-02-03 CN CN202010079233.0A patent/CN111101413A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2536538C1 (en) * | 2013-07-18 | 2014-12-27 | Виктор Анатольевич Бабелло | Method for reduction of deformations of motor and railway roads on permafrost soils that thaw out in process of operation |
CN103774515A (en) * | 2014-02-20 | 2014-05-07 | 中铁第四勘察设计院集团有限公司 | High speed railway embankment structure in salty soil regions |
CN205557220U (en) * | 2016-02-03 | 2016-09-07 | 中国科学院寒区旱区环境与工程研究所 | Wind amasss husky berm frozen soil roadbed structure |
CN106147779A (en) * | 2016-07-14 | 2016-11-23 | 甘肃工业技术研究院 | The preparation of drift-sand antiseepage saline and alkaline barrier material and salt-soda soil through engineering approaches in situ is administered and restorative procedure |
CN206529760U (en) * | 2017-02-22 | 2017-09-29 | 中铁二院工程集团有限责任公司 | High-speed railway embankment substrate salinized soil resists molten sunken construction |
CN208415233U (en) * | 2018-06-21 | 2019-01-22 | 北京市勘察设计研究院有限公司 | A kind of foundation structure of saline soil area |
CN109958120A (en) * | 2019-04-10 | 2019-07-02 | 国网新疆电力有限公司经济技术研究院 | Method of the cold anti-salt of drought-hit area salinized soil every salt |
CN110273341A (en) * | 2019-07-19 | 2019-09-24 | 西南交通大学 | A kind of frozen ground regions heating road structure and its construction method |
CN212000424U (en) * | 2020-02-03 | 2020-11-24 | 甘肃省公路工程质量试验检测中心有限公司 | Be applied to device of seasonal frozen soil district salt soil road bed |
Non-Patent Citations (4)
Title |
---|
张亚萍;周彦芳;仁增茂;赵玺;胡有权;魏玉杰;张靖;张兆萍;施志国;: "河西荒漠地区铺设改性荒漠砂枸杞高产高效栽培技术研究", 安徽农业科学, vol. 47, no. 24, 31 December 2019 (2019-12-31), pages 54 - 56 * |
张珍, 王介民, 曲凤云: "换土法及防渗裙法处理基础下盐渍土层的探讨", 山西水利科技, no. 02, 31 May 2001 (2001-05-31), pages 82 * |
杨仲全: "盐渍土地区路基隔断层设置研究", 中国水运(下半月), vol. 12, no. 11, 30 November 2012 (2012-11-30), pages 218 - 220 * |
陈昌富等: "地基基础 新版", 28 February 2010, 武汉理工大学出版社, pages: 206 - 207 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111830235A (en) * | 2020-06-17 | 2020-10-27 | 安徽理工大学 | Frozen soil body model and construction method of frozen soil body water migration model |
CN111830235B (en) * | 2020-06-17 | 2022-07-12 | 安徽理工大学 | Frozen soil model and method for constructing frozen soil moisture migration model |
CN112176814A (en) * | 2020-10-12 | 2021-01-05 | 西藏大学 | Water accumulation preventing plateau asphalt highway and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110485228B (en) | Hydrothermal closed type anti-frost-heaving slurry-turning high-strength highway subgrade structure and construction method | |
CN111979866B (en) | Roadbed anti-freezing structure in seasonal frozen soil area and construction method thereof | |
CN204875410U (en) | High and cold permafrost region active service road bed adds face structure of paving | |
CN107747261A (en) | A kind of new Soft Clay seasonal frozen soil region highway subgrade structure and construction method | |
CN204212018U (en) | A kind of road structure preventing and treating the soft soil roadbed freeze thawing disease of high and cold mountain area cheuch section | |
CN111101413A (en) | Device applied to salinized soil subgrade in seasonal frozen soil area and construction method | |
CN101418565A (en) | Qinghai-tibet railway permafrost wetland ground treatment technique | |
CN204825539U (en) | Control difference in temperature prevents roadbed structure of cold mountain area highway inhomogeneous deformation | |
Wu et al. | Freeze-thaw erosion mechanism and preventive actions of highway subgrade soil in an alpine meadow on the Qinghai-Tibet Plateau | |
CN212000424U (en) | Be applied to device of seasonal frozen soil district salt soil road bed | |
CN113323017B (en) | Construction method of side wall fertilizer groove foam concrete backfill system | |
CN102877543B (en) | Heat-preservation blind trench facility applicable to multi-year permafrost region and construction method | |
CN112195965A (en) | Expansive soil cutting retaining wall | |
CN208151798U (en) | A kind of seasonal frozen soil region high-speed rail roadbed water cut infiltration ditch system | |
Zornberg | Ingenuity in geotechnical design using geosynthetics | |
CN113529785B (en) | Soil retaining structure suitable for eliminating frost heaving effect in cold region and construction method | |
CN102587399B (en) | Salivary flow ice prevention and management structure in cold zone | |
CN213896585U (en) | Fill roadbed structure suitable for water-rich low-lying permafrost region | |
CN210238158U (en) | Plateau high-ice-content frozen soil section railway cutting structure | |
CN111749073A (en) | Water permeable reconstruction technology based on existing road base layer | |
CN221052795U (en) | Open-type roadbed drainage structure under cold district environment | |
CN111396678A (en) | Through-laying type rubble tube dike cooling structure | |
RU2283910C2 (en) | Heat-insulation layer of road structure | |
CN217378985U (en) | Anti-freezing and anti-expansion gravity retaining wall structure | |
CN214657118U (en) | Block stone roadbed with slope wind and sand prevention effect |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |