CN111091307A - Power distribution network resource processing method, storage medium and processor - Google Patents

Power distribution network resource processing method, storage medium and processor Download PDF

Info

Publication number
CN111091307A
CN111091307A CN201911399352.8A CN201911399352A CN111091307A CN 111091307 A CN111091307 A CN 111091307A CN 201911399352 A CN201911399352 A CN 201911399352A CN 111091307 A CN111091307 A CN 111091307A
Authority
CN
China
Prior art keywords
distribution network
power distribution
power
layer model
investment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911399352.8A
Other languages
Chinese (zh)
Inventor
孙钦斐
陈平
宫成
曾爽
王瀚秋
丁屹峰
李香龙
杨烁
王钊
梁安琪
李干
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Beijing Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Beijing Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201911399352.8A priority Critical patent/CN111091307A/en
Publication of CN111091307A publication Critical patent/CN111091307A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a power distribution network resource processing method, a storage medium and a processor. Wherein, the method comprises the following steps: acquiring a pre-increased load of the power distribution network; establishing a target model, wherein the target model is used for evaluating the adjustment of the resources of the power distribution network under the condition that the power distribution network meets the load requirement; inputting at least one constraint to the target model, wherein the constraint is indicative of a limited range of a predetermined parameter of the distribution network if the load requirement is met; and obtaining a mode for adjusting the resources of the power distribution network according to the target model. The invention solves the technical problem of unreasonable resource optimization configuration of the power distribution network in the prior art.

Description

Power distribution network resource processing method, storage medium and processor
Technical Field
The invention relates to the technical field of power distribution network resource processing, in particular to a power distribution network resource processing method, a storage medium and a processor.
Background
The power consumption characteristics of the electric heating equipment are influenced by various factors such as equipment types, power consumption time, geographical positions and the like, the characteristics of high power, randomness, intermittence, dispersity, centralized concurrency and the like are shown, along with the deep process of changing coal into electricity, a series of problems are brought to a power grid by large-scale distributed electric heating load access, and the heating effect of a user changing coal into electricity and the transformation, planning and construction effects of a power distribution network are directly influenced.
A mathematical model used for researching the problem of the optimal configuration of the power distribution network resources abroad is mainly a power distribution network extended construction resource optimal configuration model. Related researches on optimal configuration and operation of power distribution network resources in China comprise research results in theoretical aspects and mature planning technical standards. However, the characteristics of the electric heating load and the planning and operation problems of the power distribution network are not considered in the current researches.
In view of the above problems, no effective solution has been proposed.
Disclosure of Invention
The embodiment of the invention provides a power distribution network resource processing method, a storage medium and a processor, which are used for at least solving the technical problem that the optimal configuration of power distribution network resources is unreasonable in the prior art.
According to an aspect of the embodiments of the present invention, a method for processing power distribution network resources is provided, including: acquiring a pre-increased load of the power distribution network; establishing a target model, wherein the target model is used for evaluating the adjustment needed to be carried out on the resources of the power distribution network under the condition that the power distribution network meets the load requirement; inputting at least one constraint to the target model, wherein the constraint is indicative of a limited range of a predetermined parameter of the distribution grid if the load requirement is met; and obtaining a mode for adjusting the resources of the power distribution network according to the target model.
Optionally, the target model comprises two layers, wherein a first layer model of the two layers is used for adjusting the installation location and/or capacity of the resource in the power distribution network; the second of the two layers is used to adjust the configuration of resources in the power distribution network.
Optionally, the method further comprises: the second layer model feeds back the adjustment result of the configuration of the resource to the first layer model as one of the bases for the first layer model to evaluate the installation position and/or capacity adjustment of the resource.
Optionally, the method further comprises: and the first layer model feeds back the adjustment result of the resource installation position and/or capacity of the first layer model to the second layer model to serve as a constraint condition for the second layer model to adjust the configuration of the resource.
Optionally, the first layer model uses the following objective function: fupper=min(ω1f12f23f3) (ii) a Wherein f is1Annual loss charge of distribution line, f2For the efficiency of utilization of the distribution network equipment, f3For operating maintenance costs, omega, of distribution network equipment1、ω2、ω3Are respectively f1、f2、f3The weight occupied.
Optionally, the constraints of the first layer model include at least one of: node voltage, power balance, reliability, network topology, investment of distribution lines, wire cross sections, power supply radius, switch allowable action times, investment of switch equipment, investment of reactive compensation devices and investment of three-phase unbalance adjusting devices.
Optionally, the first layer model uses the following objective function: flower=min(ω3f34f4) (ii) a Wherein f is3For annual power loss of the distribution line, f4Is the annual voltage deviation minimum, omega3、ω4Are respectively f3、f4The weight occupied.
Optionally, the constraints of the second layer model include at least one of: node voltage, power balance, branch power, network topology, the number of allowed actions of the switch, and the number of three-phase imbalance adjusting devices.
According to another aspect of the embodiments of the present invention, there is also provided a storage medium, where the storage medium includes a stored program, and when the program runs, a device in which the storage medium is located is controlled to execute any one of the above methods.
According to another aspect of the embodiments of the present invention, there is also provided a processor, configured to execute a program, where the program executes to perform the method of any one of the above.
In the embodiment of the invention, the method comprises the steps of acquiring the pre-increased load of the power distribution network; establishing a target model, wherein the target model is used for evaluating the adjustment needed to be carried out on the resources of the power distribution network under the condition that the power distribution network meets the load requirement; inputting at least one constraint to the target model, wherein the constraint is indicative of a limited range of a predetermined parameter of the distribution grid if the load requirement is met; the method for adjusting the resources of the power distribution network is obtained according to the target model, and the resources of the power distribution network are adjusted through the target model, so that the purposes of lowest power distribution loss, least investment and highest utilization efficiency of power grid equipment, namely the optimal comprehensive target, are achieved, the technical effect of effectively reducing power grid investment and power distribution loss is achieved, and the technical problem of unreasonable resource optimization configuration of the power distribution network in the prior art is solved.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the invention without limiting the invention. In the drawings:
fig. 1 is a flowchart of a power distribution network resource processing method according to an embodiment of the present invention.
Detailed Description
In order to make the technical solutions of the present invention better understood, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that the terms "first," "second," and the like in the description and claims of the present invention and in the drawings described above are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It is to be understood that the data so used is interchangeable under appropriate circumstances such that the embodiments of the invention described herein are capable of operation in sequences other than those illustrated or described herein. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
Example 1
In accordance with an embodiment of the present invention, there is provided an embodiment of a method for processing power distribution grid resources, it should be noted that the steps illustrated in the flowchart of the drawings may be performed in a computer system such as a set of computer executable instructions, and that while a logical order is illustrated in the flowchart, in some cases, the steps illustrated or described may be performed in an order different than that described herein.
Fig. 1 is a flowchart of a power distribution network resource processing method according to an embodiment of the present invention, as shown in fig. 1, the method includes the following steps:
step S102, acquiring a pre-increased load of the power distribution network;
the power distribution network includes but is not limited to a 10kV line, and the pre-increased load of the power distribution network can be from electric heating equipment, and of course, can also be from other electric equipment, such as an air conditioner and the like.
Step S104, establishing a target model, wherein the target model is used for evaluating the adjustment of the resources of the power distribution network under the condition that the power distribution network meets the load requirement;
the target model can improve the voltage quality of the power distribution network, guarantee the power supply reliability and power supply capacity of the power distribution network, and realize economic and safe operation of the power distribution network.
Step S106, inputting at least one constraint condition to the target model, wherein the constraint condition is used for indicating the limited range of the preset parameter of the power distribution network under the condition of meeting the load requirement;
the constraint conditions relate to topological constraint, relevant regulations, energy balance and guarantee of voltage quality, power supply reliability and power supply capacity of the power grid.
And S108, obtaining a mode for adjusting the resources of the power distribution network according to the target model.
In the specific implementation process, the power distribution network resources such as the wiring mode, the line model, the line power supply radius, the distribution transformer model, the distribution transformer capacity, the reactive power compensation device, the three-phase imbalance adjusting device and the like can be adjusted to be reasonably and optimally utilized. Optionally, the adjusting manner includes at least one of the following: and additionally installing a three-phase unbalance adjusting device, configuring a distribution transformer reactive compensation device and a capacity regulating transformer.
Through the steps, the method can realize the adoption of the method for acquiring the pre-increased load of the power distribution network; establishing a target model, wherein the target model is used for evaluating the adjustment of the resources of the power distribution network under the condition that the power distribution network meets the load requirement; inputting at least one constraint to the target model, wherein the constraint is indicative of a limited range of a predetermined parameter of the distribution network if the load requirement is met; the method for adjusting the resources of the power distribution network is obtained according to the target model, and the resources of the power distribution network are adjusted through the target model, so that the purpose of optimal comprehensive target with lowest power distribution loss, lowest investment and highest utilization efficiency of power grid equipment is achieved, the technical effect of effectively reducing power grid investment and power distribution loss is achieved, and the technical problem of unreasonable resource optimization configuration of the power distribution network in the prior art is solved.
Optionally, the target model comprises two layers, wherein a first layer model of the two layers is used for adjusting the installation location and/or capacity of the resource in the power distribution network; the second of the two layers is used to adjust the configuration of resources in the power distribution network.
The first layer model may be an upper layer model, and the second layer model may be a lower layer model.
For example, a two-layer planning method can be adopted to perform integrated planning on the power distribution network resources, and a general model of the two-layer planning is as follows:
Figure BDA0002347104620000041
wherein, F (x, w) and F (x, y) are respectively an upper layer objective function and a lower layer objective function; g (x) and g (x, y) are respectively upper and lower layer constraint conditions; x and y are decision variables of an upper layer and a lower layer respectively.
The upper layer is an investment decision problem, and a multi-target model is established by considering the investment cost of equipment such as a distribution line, a distribution transformer, a reactive power compensation device, a switch device, a three-phase imbalance adjusting device and the like and the economic and safe promotion effect of the equipment on the distribution network. The method is characterized in that the installation positions and the capacities of various resources of the power distribution network are optimized by taking the minimum investment cost and annual network loss cost of various power distribution network resources and the highest utilization efficiency of power grid equipment as optimization targets.
The lower layer is an operation optimization problem, the network reconstruction is considered, reactive compensation equipment and a three-phase imbalance adjusting device are additionally arranged, the effects of reducing the network loss and improving the voltage quality are considered, and a multi-objective optimization model is also established. And optimizing the configuration conditions of various power distribution network resources by taking the minimum network loss and voltage deviation after the heating load is accessed as an optimization target.
As an optional embodiment, according to seasonal characteristics of the electric heating load, the whole year can be divided into 3 typical energy supply seasons, namely a heating season (11 months to 3 months in the next year), a cooling season (6 months to 9 months) and a transition season (4 months, 5 months and 10 months), the whole year is divided into 3 typical seasons, 1 representative day is selected for each season, and the operation fee of the system in each typical day can be calculated firstly and then multiplied by corresponding days to obtain the annual operation fee.
Optionally, the method further comprises: the second layer model feeds back the adjustment result of the configuration of the resource to the first layer model as one of the bases for the first layer model to evaluate the installation position and/or capacity adjustment of the resource.
Optionally, the method further comprises: and the first layer model feeds back the adjustment result of the resource installation position and/or capacity to the second layer model as a constraint condition for adjusting the configuration of the resource by the second layer model.
The upper layer investment decision result acts on the lower layer objective function and the constraint condition, and the lower layer operation optimization is fed back to the upper layer by an optimal value, so that the interaction between the upper layer and the lower layer is realized. The planning model constraint relates to topology constraint, relevant regulations, energy balance and guarantee of voltage quality, power supply reliability and power supply capacity of the power grid.
Optionally, the first layer model uses the following objective function: fupper=min(ω1f12f23f3) (ii) a Wherein f is1Annual loss charge of distribution line, f2For the efficiency of utilization of the distribution network equipment, f3For distribution network equipmentOperating maintenance costs of omega1、ω2、ω3Are respectively f1、f2、f3The weight occupied.
The annual loss of the distribution line is used
Figure BDA0002347104620000051
Wherein, taTotal days for season a; KS is the total time period obtained after the equivalent load curve is segmented; t is tjIs the duration of the jth period; plossjThe line loss electric quantity is the j time period; ceIs the electricity price.
The annual power loss cost
Figure BDA0002347104620000052
Wherein N isaThe total number of the power distribution network resources is; mu.siIndicating the utilization of the ith grid resource.
The operation and maintenance cost of the distribution network resources
Figure BDA0002347104620000053
Wherein, CIiInvestment cost for the ith grid resource unit; CO 2iThe operation and maintenance cost of the ith power grid resource unit.
After the large-scale electric heating equipment is connected to the power distribution network, the objective function comprehensively considers the line model, the wiring mode, the power supply radius, the positions of the contact and section switches, the configuration of the reactive compensation equipment and the configuration of the three-phase unbalance adjusting device to improve the line loss and the reliability, so that the investment and maintenance cost of the power distribution network resources and the annual network loss cost are reduced, and the utilization efficiency of the power distribution network equipment is improved to serve as an optimization target. In a specific implementation process, the resources can be optimized by the objective function, and the resources can be calculated in seasons and time intervals and then superposed.
Optionally, the constraints of the first layer model comprise at least one of: node voltage, power balance, reliability, network topology, investment of distribution lines, wire cross sections, power supply radius, switch allowable action times, investment of switch equipment, investment of reactive compensation devices and investment of three-phase unbalance adjusting devices.
The above node voltage constraints are: u shapemin≤Uk≤Umax
The power balance constraint is:
Figure BDA0002347104620000061
Figure BDA0002347104620000062
wherein, Pi、QiRespectively injecting active power and reactive power into the node i; gij、Bij、δijSequentially setting the conductance, susceptance and voltage phase angle difference between the nodes i and j; u shapei、UjThe voltage amplitudes of nodes i, j, respectively.
The above reliability constraints are: r is not less than R0Wherein R is0Is a predetermined achieved reliability index. The power supply reliability requirements are different for different power supply regions, the grid reliability requirement is higher than 99.83% for urban areas, and the grid reliability requirement is higher than 99.72% for rural areas.
The network topology constraint is that a network structure needs to meet a radiation structure and a connectivity structure, and each load point needs to be connected with a power grid, namely, a power supply supplies power; in the case of normal power supply, each load point can be supplied by only one power supply.
Above-mentioned distribution lines's investment constraint, wherein, distribution lines is 10kV distribution lines, and 10kV distribution lines's construction transformation principle is investment and working costs minimum principle, satisfies certain load requirement and safe and reliable constraint condition under, confirms the circuit construction scheme, and the constraint function is:
Figure BDA0002347104620000063
wherein, FNL1Annual investment and total running cost for newly building a 10kV medium-voltage line; fNL2Annual investment for expanding capacity of existing 10kV medium-voltage lineAnd total operating costs; fNKAnnual investment and total running cost of equipment such as switches, β is the price of electricity, i is the load point in the system, j is the possible power failure accident, npIs the set of all load points in the system; n iseThe set of all power outage events that may occur; l isiIs the load point λjThe load value of (d); the occurrence probability of the power failure time j; r isjThe duration of the power outage.
Annual investment and operating costs for the plant FNL1、FNL2And FNKThe comprehensive investment can be converted into the investment cost which is evenly distributed in each year by adopting a current value-to-year value method, and the specific calculation formula is as follows:
Figure BDA0002347104620000064
wherein, FNi、ZiAnd YiRespectively the annual comprehensive cost, the comprehensive investment and the annual operation cost (yuan/year) of each device; n isiThe economic service life of the equipment; r is0The investment recovery rate of the power industry is high.
The annual operating cost Yi mainly includes the annual energy loss cost of the equipment and the maintenance cost, and the like, as shown in the following formula:
Yi=βΔAi+Wi
wherein, WiAnnual overhaul and maintenance cost of the equipment, β power generation ratio, delta AiThe total annual electric energy loss value of the equipment; the annual energy loss cost of the switch is negligible, i.e. Δ aK=0。
The above-mentioned constraints on the section of the conductor, for example, the section of the trunk of a 10kV cable line in the "coal to electricity" region, is 300mm2The cross section of the branch line is 185mm2(ii) a The section of a 10kV overhead line trunk line is 240mm2The cross section of the branch line is 70mm2
The above power supply radius constraint, for example, the power supply radius of the 10kV line in the "coal to electricity" area in the town is preferably controlled within 5km, and the power supply radius of the 10kV line in the "coal to electricity" area in the rural area is preferably controlled within 15 km.
Generally, the operation department has a corresponding limit to the number of switch operations in a day according to the "operation guide rule" rule, and the allowable number of switch actions is constrained by the following formula:
Nstotal≤Nstmax
Nsk≤Nskmax,k=1,2,...,ns
wherein N isstotalRefers to the total operation times of the tie switch and the section switch in a fixed time period, and the upper limit is Nstmax;NskThe number of times of actions of the kth switch in the action switch set in one day is N, and the corresponding upper limit value is Nstmax,nsThe number of switches participating in the action.
The investment constraints of switchgear, such as the cost of line construction, are usually limited, and the investment constraints of the interconnection switches are introduced to limit the number of interconnection switches installed. Specifically, the following formula:
N·Cs≤Cinv
wherein N is the number of installation units of the interconnection switch; csThe current value of single investment for the interconnection switch; cinvIs the investment limit.
The investment constraints of the reactive power compensation device and the three-phase imbalance adjusting device, for example, the investment costs of the reactive power compensation device and the three-phase imbalance adjusting device are limited, the number of equipment required to be equipped is reduced as much as possible under the condition of ensuring the voltage quality, and the investment constraints of the reactive power compensation device and the three-phase imbalance adjusting device are introduced to limit the number of the equipment to be installed. Specifically, the following formula:
A·RS≤Rinv
B·SPCS≤SPCinv
wherein A is the number of groups of reactive compensation devices; b is the number of the three-phase unbalance adjusting devices; rsFor the present value of investment, R, of a single group of reactive power compensation devicesinvIs the investment limit of the reactive compensation device; SPCSThe investment current value of a single three-phase unbalance adjusting device is obtained; SPCinvIs a single three-phaseBalancing the investment limits of the regulating device.
Optionally, the first layer model uses the following objective function: flower=min(ω3f34f4) (ii) a Wherein f is3For annual power loss of the distribution line, f4Is the annual voltage deviation minimum, omega3、ω4Are respectively f3、f4The weight occupied.
The annual power loss and power consumption of the distribution line:
Figure BDA0002347104620000081
wherein the content of the first and second substances,
Figure BDA0002347104620000082
for the electricity price in the time period t, the value of the electricity price is combined with the peak-valley electricity price policies of users in different heating areas, and the average value of the peak-valley electricity price is taken, for example, the average value of the electricity prices in Beijing is selected according to 0.26 yuan/kilowatt hour (the subsidy policy of the electricity price in Beijing is comprehensively considered);
Figure BDA0002347104620000083
is the power loss over time period t; Δ t is the time interval of each time interval; t is the number of time segments.
The voltage deviation described above:
Figure BDA0002347104620000084
wherein the content of the first and second substances,
Figure BDA0002347104620000085
the voltage of node k for a period t; vNIs the node rated voltage; n is a radical ofrIs a collection of nodes.
Optionally, the constraints of the second layer model include at least one of: node voltage, power balance, branch power, network topology, the number of allowed actions of the switch, and the number of three-phase imbalance adjusting devices.
The node voltage constraint is as follows:
Vmin≤Vk≤Vmax
wherein, Vmin、VmaxRespectively an upper limit and a lower limit of the node voltage; vkIs the voltage at node k.
The above power balance constraint:
Figure BDA0002347104620000086
Figure BDA0002347104620000087
wherein, Pi、QiRespectively injecting active power and reactive power into the node i; gij、Bij、δijSequentially setting the conductance, susceptance and voltage phase angle difference between the nodes i and j; n is the total number of system nodes; vi、VjThe voltage amplitudes of nodes i, j, respectively.
The branch power constraint:
Pj≤Pj max
wherein, PjIs the active power value of branch j; pj maxThe maximum value is allowed for the active power of branch j.
The above network architecture operation constraints are:
g∈G
wherein g is a reconstructed network topology structure; g is the set of network radial topologies.
The number of switching operations is limited due to the manufacturing process and the difference in current and capacity of the switch. Therefore, in the dynamic reconfiguration process, in addition to satisfying the power flow constraint, the branch capacity constraint, the node voltage constraint and the network topology constraint, the constraint of the number of switching actions must be satisfied, which is shown in the following formula:
Figure BDA0002347104620000091
wherein, WjmaxThe maximum number of actions of a single switch; wmaxThe maximum number of actions for all switches.
The configuration number constraint of the three-phase unbalance adjustment device aims at a lower-layer model, in optimization variables, the configuration number constraint of the three-phase unbalance adjustment device needs to be considered, and the following constraints are added to constraint conditions:
Figure BDA0002347104620000092
it should be noted that, in both the first layer model and the second layer model, there are multiple optimization targets, and a decision matrix method is used to realize the conversion from a multi-target function to a single-target function. The multilayer model is solved by mainly adopting a hybrid algorithm based on an ant colony algorithm and cone optimization. In the first layer model, the ant colony algorithm is adopted to rapidly plan the positions of the power distribution network lines and the positions of the interconnection switches, and the cone optimization algorithm is adopted to plan the positions of the reactive compensation equipment and the three-phase imbalance adjusting device; in the second layer model, the cone optimization algorithm is adopted to carry out optimization scheduling on the reactive compensation equipment, the number of groups of three-phase unbalance adjusting devices and the state of the interconnection switch. According to different requirements of different layer models on an algorithm, the multi-layer model is decomposed and calculated, and finally the fast and accurate solution of the large-scale mixed integer nonlinear programming problem is achieved.
Example 2
According to another aspect of the embodiments of the present invention, there is also provided a storage medium, where the storage medium includes a stored program, and where the program is executed to control a device in which the storage medium is located to perform any one of the above methods.
Example 3
According to another aspect of the embodiments of the present invention, there is also provided a processor, configured to execute a program, where the program executes to perform any one of the methods described above.
The above-mentioned serial numbers of the embodiments of the present invention are merely for description and do not represent the merits of the embodiments.
In the above embodiments of the present invention, the descriptions of the respective embodiments have respective emphasis, and for parts that are not described in detail in a certain embodiment, reference may be made to related descriptions of other embodiments.
In the embodiments provided in the present application, it should be understood that the disclosed technology can be implemented in other ways. The above-described embodiments of the apparatus are merely illustrative, and for example, the division of the units may be a logical division, and in actual implementation, there may be another division, for example, multiple units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, units or modules, and may be in an electrical or other form.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present invention may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a form of hardware, and can also be realized in a form of a software functional unit.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present invention may be embodied in the form of a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, or a network device) to execute all or part of the steps of the method according to the embodiments of the present invention. And the aforementioned storage medium includes: a U-disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a removable hard disk, a magnetic or optical disk, and other various media capable of storing program codes.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, various modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.

Claims (10)

1. A power distribution network resource processing method is characterized by comprising the following steps:
acquiring a pre-increased load of the power distribution network;
establishing a target model, wherein the target model is used for evaluating the adjustment needed to be carried out on the resources of the power distribution network under the condition that the power distribution network meets the load requirement;
inputting at least one constraint to the target model, wherein the constraint is indicative of a limited range of a predetermined parameter of the distribution grid if the load requirement is met;
and obtaining a mode for adjusting the resources of the power distribution network according to the target model.
2. The method of claim 1, wherein the target model comprises two layers, wherein a first layer model of the two layers is used to adjust an installation location and/or capacity of a resource in the power distribution grid; the second of the two layers is used to adjust the configuration of resources in the power distribution network.
3. The method of claim 2, further comprising:
the second layer model feeds back the adjustment result of the configuration of the resource to the first layer model as one of the bases for the first layer model to evaluate the installation position and/or capacity adjustment of the resource.
4. The method of claim 2, further comprising:
and the first layer model feeds back the adjustment result of the resource installation position and/or capacity of the first layer model to the second layer model to serve as a constraint condition for the second layer model to adjust the configuration of the resource.
5. The method of any of claims 2 to 4, wherein the first layer model uses the following objective function:
Fupper=min(ω1f12f23f3)
wherein f is1Annual loss charge of distribution line, f2For the efficiency of utilization of the distribution network equipment, f3For operating maintenance costs, omega, of distribution network equipment1、ω2、ω3Are respectively f1、f2、f3The weight occupied.
6. The method of claim 5, wherein the constraints of the first layer model comprise at least one of:
node voltage, power balance, reliability, network topology, investment of distribution lines, wire cross sections, power supply radius, switch allowable action times, investment of switch equipment, investment of reactive compensation devices and investment of three-phase unbalance adjusting devices.
7. The method of any of claims 2 to 4, wherein the first layer model uses the following objective function:
Flower=min(ω3f34f4);
wherein f is3For annual power loss of the distribution line, f4Is the annual voltage deviation minimum, omega3、ω4Are respectively f3、f4The weight occupied.
8. The method of claim 7, wherein the constraints of the second layer model comprise at least one of:
node voltage, power balance, branch power, network topology, the number of allowed actions of the switch, and the number of three-phase imbalance adjusting devices.
9. A storage medium comprising a stored program, wherein the program, when executed, controls an apparatus in which the storage medium is located to perform the method of any one of claims 1 to 8.
10. A processor configured to execute a program, wherein the program executes to perform the method of any one of claims 1 to 8.
CN201911399352.8A 2019-12-30 2019-12-30 Power distribution network resource processing method, storage medium and processor Pending CN111091307A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911399352.8A CN111091307A (en) 2019-12-30 2019-12-30 Power distribution network resource processing method, storage medium and processor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911399352.8A CN111091307A (en) 2019-12-30 2019-12-30 Power distribution network resource processing method, storage medium and processor

Publications (1)

Publication Number Publication Date
CN111091307A true CN111091307A (en) 2020-05-01

Family

ID=70397978

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911399352.8A Pending CN111091307A (en) 2019-12-30 2019-12-30 Power distribution network resource processing method, storage medium and processor

Country Status (1)

Country Link
CN (1) CN111091307A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112200401A (en) * 2020-08-17 2021-01-08 国网上海市电力公司 Electric automobile ordered charging method based on improved NSGA-II algorithm
CN112734593A (en) * 2020-12-24 2021-04-30 国网北京市电力公司 Power distribution network planning method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106230026A (en) * 2016-08-30 2016-12-14 华北电力大学(保定) The power distribution network bilayer coordinated planning method containing distributed power source analyzed based on temporal characteristics
CN107451670A (en) * 2016-05-30 2017-12-08 中国电力科学研究院 A kind of hierarchical coordinative dispatching method a few days ago for active distribution network
CN107528345A (en) * 2017-09-30 2017-12-29 国电南瑞科技股份有限公司 A kind of net source lotus storage control method for coordinating of Multiple Time Scales
CN110110893A (en) * 2019-04-03 2019-08-09 国网新疆电力有限公司昌吉供电公司 The distribution network structure optimization method of extensive electric heating equipment access
CN110348048A (en) * 2019-05-31 2019-10-18 国网河南省电力公司郑州供电公司 Based on the power distribution network optimal reconfiguration method for considering tropical island effect load prediction
CN110570327A (en) * 2019-08-07 2019-12-13 广东电网有限责任公司 active power distribution network double-layer planning method considering source-load interactive response

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107451670A (en) * 2016-05-30 2017-12-08 中国电力科学研究院 A kind of hierarchical coordinative dispatching method a few days ago for active distribution network
CN106230026A (en) * 2016-08-30 2016-12-14 华北电力大学(保定) The power distribution network bilayer coordinated planning method containing distributed power source analyzed based on temporal characteristics
CN107528345A (en) * 2017-09-30 2017-12-29 国电南瑞科技股份有限公司 A kind of net source lotus storage control method for coordinating of Multiple Time Scales
CN110110893A (en) * 2019-04-03 2019-08-09 国网新疆电力有限公司昌吉供电公司 The distribution network structure optimization method of extensive electric heating equipment access
CN110348048A (en) * 2019-05-31 2019-10-18 国网河南省电力公司郑州供电公司 Based on the power distribution network optimal reconfiguration method for considering tropical island effect load prediction
CN110570327A (en) * 2019-08-07 2019-12-13 广东电网有限责任公司 active power distribution network double-layer planning method considering source-load interactive response

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112200401A (en) * 2020-08-17 2021-01-08 国网上海市电力公司 Electric automobile ordered charging method based on improved NSGA-II algorithm
CN112200401B (en) * 2020-08-17 2024-02-27 国网上海市电力公司 Ordered charging method for electric automobile based on improved NSGA-II algorithm
CN112734593A (en) * 2020-12-24 2021-04-30 国网北京市电力公司 Power distribution network planning method

Similar Documents

Publication Publication Date Title
Jayasekara et al. Optimal operation of distributed energy storage systems to improve distribution network load and generation hosting capability
Millar et al. Impact of MV connected microgrids on MV distribution planning
Pamshetti et al. Coordinated allocation of BESS and SOP in high PV penetrated distribution network incorporating DR and CVR schemes
CN110490376B (en) Intelligent soft switch planning method for improving reliability and economy of power distribution network
CN107038530A (en) A kind of power distribution network overall planning method and system
Jiang et al. Two-step optimal allocation of stationary and mobile energy storage systems in resilient distribution networks
CN105096207B (en) Important power user power supply reliability assessment method based on analytic hierarchy process
CN107134787A (en) Urgent accurate cutting load control system and cutting load method based on distributed feeder automation
CN109948868A (en) High permeability distribution type renewable energy power generation cluster Method for optimized planning
CN108304972B (en) Active power distribution network frame planning method based on supply and demand interaction and DG (distributed generation) operation characteristics
CN107492908A (en) A kind of feeder line Method for optimized planning based on distributed power source access
CN111682585A (en) Comprehensive planning method and system for intelligent energy storage soft switch of power distribution network
CN108808664A (en) A kind of urban power network planning method considering sub-area division optimization operation
CN112018790B (en) Method for participating in demand response adjustment control based on layered distributed energy storage
Astero et al. Improvement of RES hosting capacity using a central energy storage system
CN111091307A (en) Power distribution network resource processing method, storage medium and processor
CN111563691B (en) Performance evaluation method of AC/DC hybrid power distribution network connected with new energy
CN104156531A (en) Fault current limiter distribution point optimization and capacity selection method taking operation loss into consideration
CN111105089B (en) Urban power grid planning method considering coordination of main and distribution networks
CN116707023A (en) Active power distribution network layering and partitioning comprehensive optimization method based on source-load correlation clustering
CN111242389A (en) Intelligent energy storage soft switch planning method, system, equipment and medium
CN115496427B (en) Flexible interconnection investment planning decision method for multi-microgrid system
Li et al. A two-stage multi-objective optimal power flow algorithm for hybrid AC/DC grids with VSC-HVDC
CN114580127A (en) High-voltage distribution network planning method considering medium-voltage transfer supply and wiring group division
Lu et al. Planning of Soft Open Point Considering Demand Response

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200501