CN111042412A - Novel large-area terrace concrete pouring process - Google Patents
Novel large-area terrace concrete pouring process Download PDFInfo
- Publication number
- CN111042412A CN111042412A CN201911192393.XA CN201911192393A CN111042412A CN 111042412 A CN111042412 A CN 111042412A CN 201911192393 A CN201911192393 A CN 201911192393A CN 111042412 A CN111042412 A CN 111042412A
- Authority
- CN
- China
- Prior art keywords
- strickling
- steel bar
- terrace
- cross
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
- E04G21/10—Devices for levelling, e.g. templates or boards
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention provides a novel large-area terrace concrete pouring process, which comprises the following specific steps of: cutting a steel bar with the diameter of 12mm into two specifications of 40cm and 10 cm; welding the middle part of a 10cm steel bar at a position 3cm away from the upper end of the 40cm steel bar to form a cross-shaped iron piece; driving the crossed iron pieces into the foundation on the terrace according to a plurality of roads, wherein the distance between every two roads is 6m, and the distance between every two roads is 2 m; placing a ruler on the upper part of the 10cm steel bar, leveling each cross-shaped iron piece by using a level gauge, and measuring data which is 48mm lower than the surface of the poured terrace; placing straight steel pipes with the length of 6m on the left side and the right side of the upper part of the cross-shaped iron piece, and firmly binding the steel pipes by binding wires; and (3) pouring concrete at one time, strickling off along the steel pipe by using a 6m strickling-off tool, taking out the steel pipe and the binding wire after strickling off, and strickling off by using a 2m strickling-off tool. The invention has the beneficial effects that: the terrace is not influenced by the area and times, can be poured in place at one time, and saves more than one time at least.
Description
Technical Field
The invention relates to the technical field of concrete pouring, in particular to a novel large-area terrace concrete pouring process.
Background
Along with the increasing scale of industrial plants, the building area of the plants is larger, and the difficulty and the cost of building floor pouring of the plants are increased. How to realize the 'good' and 'province' of terrace pouring becomes the core problem of terrace pouring. The traditional terrace pouring construction process is limited by the operation of the roller, so long as the terrace width is larger than 6m, the terrace can be poured twice or more, the second pouring can be continued only by requiring the first pouring concrete surface layer to bear the load of the next construction procedure, and the construction speed is difficult to improve.
Disclosure of Invention
In order to solve the problems, the invention discloses a novel large-area terrace concrete pouring process.
In order to achieve the above purpose, the invention provides the following technical scheme:
the utility model provides a novel large tracts of land terrace concrete pouring technology which characterized in that, concrete step is:
step 1: cutting the steel bar with the diameter of 12mm into two specifications of 40cm and 10cm, wherein the number is determined according to the floor area;
step 2: welding the middle part of a 10cm steel bar at a position 3cm away from the upper end of a 40cm steel bar, wherein the 10cm steel bar is vertical to the 40cm steel bar to form a cross-shaped iron piece;
and step 3: driving the crossed iron pieces into the foundation on the terrace according to a plurality of roads, wherein the distance between every two roads is 6m, the interval distance between every two roads is 2m, and the driving depth is specifically determined according to the thickness of the terrace;
and 4, step 4: placing a ruler on the upper part of a 10cm reinforcing steel bar, leveling each cross-shaped iron piece by using a level gauge, measuring data which is 48mm lower than the surface of the poured terrace, and reinforcing the concrete of each cross-shaped iron piece after each measurement;
and 5: placing straight steel pipes with the length of 6m on the left side and the right side of the upper part of the cross-shaped iron piece, and firmly binding the steel pipes by binding wires;
step 6: and (3) pouring concrete at one time, strickling off along the steel pipe by using a 6m strickling-off tool, taking out the steel pipe and the binding wire after strickling off, and strickling off by using a 2m strickling-off tool.
Compared with the prior art, the invention has the beneficial effects that: the floor is not affected by the area and times, the whole workshop floor can be poured in place at one time, and the time is saved by more than one time at least.
Drawings
FIG. 1 is a partial schematic view of three paths with a spacing of 6m and a cross-shaped iron piece with a spacing of 2 m.
Fig. 2 is a cross-sectional view of the cross-shaped iron member and the steel pipe after being fixed and formed.
List of reference numerals:
the steel bar is 1-10cm, the steel bar is 2-40cm, the steel pipe is 3-steel pipe, and the floor foundation is 4-terrace foundation.
Detailed Description
The present invention will be further illustrated with reference to the accompanying drawings and specific embodiments, which are to be understood as merely illustrative of the invention and not as limiting the scope of the invention. It should be noted that the terms "front," "back," "left," "right," "upper" and "lower" used in the following description refer to directions in the drawings, and the terms "inner" and "outer" refer to directions toward and away from, respectively, the geometric center of a particular component.
As shown in the figure, the concrete pouring process of the novel large-area terrace comprises the following specific steps:
step 1: cutting the steel bar with the diameter of 12mm into two specifications of 40cm and 10cm, wherein the number is determined according to the floor area;
step 2: welding the middle part of a 10cm steel bar at a position 3cm away from the upper end of a 40cm steel bar, wherein the 10cm steel bar is vertical to the 40cm steel bar to form a cross-shaped iron piece;
and step 3: driving the crossed iron pieces into the foundation on the terrace according to a plurality of roads, wherein the distance between every two roads is 6m, the interval distance between every two roads is 2m, and the driving depth is specifically determined according to the thickness of the terrace;
and 4, step 4: placing a ruler on the upper part of a 10cm reinforcing steel bar, leveling each cross-shaped iron piece by using a level gauge, measuring data which is 48mm lower than the surface of the poured terrace, and reinforcing the concrete of each cross-shaped iron piece after each measurement;
and 5: placing straight steel pipes with the length of 6m on the left side and the right side of the upper part of the cross-shaped iron piece, and firmly binding the steel pipes by binding wires;
step 6: and (3) pouring concrete at one time, strickling off along the steel pipe by using a 6m strickling-off tool, taking out the steel pipe and the binding wire after strickling off, and strickling off by using a 2m strickling-off tool.
The horizontal point of the traditional terrace method is determined on the channel steel, the concrete is poured on the surface layer of a single strip, and leveling can be achieved, but elevation of the concrete after the concrete is condensed on the concrete surface layers of more than two paths has errors due to various reasons, such as the proportion of water in the concrete, deviation of a template and the like, the terrace pouring between the two paths of the second time is completely based on the concrete height after the concrete is poured on two sides, the elevation point has errors, and because the terrace is not poured once, errors are bound to exist in the joint position after the concrete surface layer poured for the second time is condensed, the traditional method is not well controlled, the unevenness of the concrete surface is easy to occur, the joint position is obvious and other defects. According to the method, firstly, straight 6m steel pipes are placed on three iron pieces with flat elevations at intervals of 2m, the tops of all the steel pipes are on the same horizontal plane, the intersection positions of the two steel pipes can be checked to be more accurately adjusted, then the whole workshop terrace can be integrally cast, dense elevation control points enable the surface flatness to reach 100%, and the connection flatness can also reach 100% due to the fact that the steel pipes are not cast successively.
The technical means disclosed in the invention scheme are not limited to the technical means disclosed in the above embodiments, but also include the technical scheme formed by any combination of the above technical features. It should be noted that those skilled in the art can make various improvements and modifications without departing from the principle of the present invention, and such improvements and modifications are also considered to be within the scope of the present invention.
Claims (1)
1. The utility model provides a novel large tracts of land terrace concrete pouring technology which characterized in that, concrete step is:
step 1: cutting a steel bar with the diameter of 12mm into two specifications of 40cm and 10 cm;
step 2: welding the middle part of a 10cm steel bar at a position 3cm away from the upper end of a 40cm steel bar, wherein the 10cm steel bar is vertical to the 40cm steel bar to form a cross-shaped iron piece;
and step 3: driving the crossed iron pieces into the foundation on the terrace according to a plurality of roads, wherein the distance between every two roads is 6m, and the distance between every two roads is 2 m;
and 4, step 4: placing a ruler on the upper part of a 10cm reinforcing steel bar, leveling each cross-shaped iron piece by using a level gauge, measuring data which is 48mm lower than the surface of the poured terrace, and reinforcing the concrete of each cross-shaped iron piece after each measurement;
and 5: placing straight steel pipes with the length of 6m on the left side and the right side of the upper part of the cross-shaped iron piece, and firmly binding the steel pipes by binding wires;
step 6: and (3) pouring concrete at one time, strickling off along the steel pipe by using a 6m strickling-off tool, taking out the steel pipe and the binding wire after strickling off, and strickling off by using a 2m strickling-off tool.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911192393.XA CN111042412A (en) | 2019-11-28 | 2019-11-28 | Novel large-area terrace concrete pouring process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911192393.XA CN111042412A (en) | 2019-11-28 | 2019-11-28 | Novel large-area terrace concrete pouring process |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111042412A true CN111042412A (en) | 2020-04-21 |
Family
ID=70233485
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911192393.XA Withdrawn CN111042412A (en) | 2019-11-28 | 2019-11-28 | Novel large-area terrace concrete pouring process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111042412A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4314773A (en) * | 1979-12-21 | 1982-02-09 | Allen Engineering Corporation | High density concrete placer |
CN202266038U (en) * | 2011-09-20 | 2012-06-06 | 福建工程学院 | Device for controlling flatness of concrete plate |
CN107268854A (en) * | 2016-04-06 | 2017-10-20 | 五冶集团上海有限公司 | Industrial premises high-flatness large-area concrete construction method of ground |
CN206784951U (en) * | 2017-05-03 | 2017-12-22 | 中建一局集团第六建筑有限公司 | A kind of concreting floorslab thickness control device |
CN108104478A (en) * | 2017-12-27 | 2018-06-01 | 中国建筑第八工程局有限公司 | Large area concrete bed course and surface layer divide storehouse smoother and its construction method |
-
2019
- 2019-11-28 CN CN201911192393.XA patent/CN111042412A/en not_active Withdrawn
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4314773A (en) * | 1979-12-21 | 1982-02-09 | Allen Engineering Corporation | High density concrete placer |
CN202266038U (en) * | 2011-09-20 | 2012-06-06 | 福建工程学院 | Device for controlling flatness of concrete plate |
CN107268854A (en) * | 2016-04-06 | 2017-10-20 | 五冶集团上海有限公司 | Industrial premises high-flatness large-area concrete construction method of ground |
CN206784951U (en) * | 2017-05-03 | 2017-12-22 | 中建一局集团第六建筑有限公司 | A kind of concreting floorslab thickness control device |
CN108104478A (en) * | 2017-12-27 | 2018-06-01 | 中国建筑第八工程局有限公司 | Large area concrete bed course and surface layer divide storehouse smoother and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209636847U (en) | A kind of adjustable tower crane built-in fitting accurate positioning tool | |
CN100552170C (en) | Height adjustable type super flat floor divided seam protection template system | |
CN104612700B (en) | A kind of Longitudinal Settlement deformation causes the determination method of shield tunnel additional internal force | |
CN103669562A (en) | Cantilever bay window board concrete overall pouring structure and construction method thereof | |
CN206503141U (en) | A kind of overlength casing in bridge pile foundation construction is accurately positioned mounting tool | |
CN103696369A (en) | Four-point locating and installing method of steel box beam sections | |
CN203755655U (en) | Shear wall formwork column base leveling device | |
CN111042412A (en) | Novel large-area terrace concrete pouring process | |
CN105735228B (en) | High-lift tooth climbs formula ship lift rack system construction method and installation accuracy control method | |
CN105544982B (en) | A kind of hyperboloid reverses steel column construction method | |
CN204510806U (en) | The longitudinal edge cover bracket of building plain form rack system | |
CN103953194B (en) | A kind of variable-section variable gradient concrete in mass guiding gutter construction method | |
CN108951883B (en) | High-precision embedded part installation method for nuclear power station | |
CN203462765U (en) | Floor flatness control system of large-area concrete building | |
CN102021915A (en) | Method for constructing large plate type foundation of line | |
CN106123873B (en) | Upright projection positioning measuring device positions cultellation construction method | |
CN104132644A (en) | Device for tunnel section measuring point lofting | |
CN105421780A (en) | Construction method of prefabricated concrete structure | |
CN204983312U (en) | Novel precast concrete coincide floor | |
CN105064681B (en) | Installing method of steel structure foundation screw bolt | |
CN205856988U (en) | A kind of flat kerbstone of town road that improves paves the horizon rule device of quality | |
CN202938826U (en) | Tunnel inflected arch lining steel bar scale distance ruler | |
CN204115719U (en) | Tunnel cross-section measurement point laying out apparatus | |
CN204510481U (en) | Shaped steel junction plate vertical in steel building | |
CN204311345U (en) | Interdigitated electrode structure shrinkage joint erecting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20200421 |
|
WW01 | Invention patent application withdrawn after publication |