CN110991834A - Scheduling system of electric power overhaul task - Google Patents

Scheduling system of electric power overhaul task Download PDF

Info

Publication number
CN110991834A
CN110991834A CN201911142766.2A CN201911142766A CN110991834A CN 110991834 A CN110991834 A CN 110991834A CN 201911142766 A CN201911142766 A CN 201911142766A CN 110991834 A CN110991834 A CN 110991834A
Authority
CN
China
Prior art keywords
maintenance
overhaul
work
group
dispatching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911142766.2A
Other languages
Chinese (zh)
Inventor
赵威
崔丙锋
孙绍辉
曹勇
李岳泽
齐枫
王哲吉
刘扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Electric Power Dispatching Industry Co ltd
Hongfujin Precision Industry Shenzhen Co Ltd
State Grid Corp of China SGCC
Original Assignee
Heilongjiang Electric Power Dispatching Industry Co ltd
Hongfujin Precision Industry Shenzhen Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Electric Power Dispatching Industry Co ltd, Hongfujin Precision Industry Shenzhen Co Ltd, State Grid Corp of China SGCC filed Critical Heilongjiang Electric Power Dispatching Industry Co ltd
Priority to CN201911142766.2A priority Critical patent/CN110991834A/en
Publication of CN110991834A publication Critical patent/CN110991834A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

A dispatching system of electric power overhaul tasks improves the work efficiency of overhaul work and belongs to the field of electric power overhaul dispatching. The invention comprises the following steps: each maintenance project corresponds to one maintenance project scheduling sub-control platform and one maintenance group queue, and each maintenance worker corresponds to one handheld terminal; each maintenance group queue stores idle maintenance groups in the current maintenance project according to the time sequence; the master dispatching platform receives the work orders, carries out numbering on the work orders corresponding to all maintenance items according to the maintenance items and the maintenance time in the work orders, and distributes the work orders and the numbers to the corresponding maintenance item dispatching sub-control platforms; the sub-control platform distributes the maintenance groups according to the sequence of the queue number and the current maintenance group queue; the corresponding handheld terminal works according to the received work allocation list; when a handheld terminal of a certain maintenance group sends a signal for completing maintenance work, the corresponding maintenance group is added into the maintenance group queue and is positioned at the tail of the current maintenance group queue.

Description

Scheduling system of electric power overhaul task
Technical Field
The invention relates to a scheduling system, in particular to a power overhaul task scheduling system, and belongs to the field of power overhaul scheduling.
Background
The electric power system is an electric energy production and consumption system which consists of links such as a power plant, a power transmission and transformation line, a power supply and distribution station, power utilization and the like. The function of the device is to convert the primary energy of the nature into electric energy through a power generation device, and then supply the electric energy to each user through power transmission, power transformation and power distribution. In order to realize the function, the power system is also provided with corresponding information and control systems at each link and different levels, and the production process of the electric energy is measured, regulated, controlled, protected, communicated and scheduled so as to ensure that users obtain safe and high-quality electric energy. In order to ensure normal operation of the power system, operation, maintenance and repair work needs to be performed on the power equipment. The overhaul work has multiple projects, including the whole body nature of disassembling of equipment inspection, maintenance, change and experimental, and the maintenance of equipment locality, the disassembly inspection, maintenance, change and experimental of part, and equipment conventional nature inspection, maintenance and experimental, and the electrified test, outward appearance inspection and the maintenance that equipment carried out under the state of not cutting off the power supply. The current maintenance is that the work order of maintenance with power equipment uploads dispatch center, and dispatch center will overhaul the work order and dispatch the work order and divide into the maintenance staff, if the maintenance work is more, the dispatch is untimely, can influence maintenance work and power equipment's normal operating, so need improve the work efficiency of maintenance work.
Disclosure of Invention
In order to improve the working efficiency of maintenance work, the invention provides a scheduling system of an electric power maintenance task.
The invention discloses a dispatching system of an electric power overhaul task, which comprises a total dispatching platform, a plurality of overhaul project dispatching platforms, a plurality of handheld terminals and a plurality of overhaul group queues;
the general scheduling platform, each overhaul project scheduling sub-control platform and each handheld terminal are all a wireless access point AP and form a wireless sensor network;
each maintenance project corresponds to one maintenance project scheduling sub-control platform and one maintenance group queue, and each maintenance worker corresponds to one handheld terminal;
each maintenance group queue is used for storing idle maintenance groups in the current maintenance project according to the time sequence;
the main dispatching platform is used for receiving the dispatching list, respectively numbering the dispatching list corresponding to each overhaul item according to the overhaul items and the overhaul time in the dispatching list, and distributing the dispatching list and the numbers to the corresponding overhaul item dispatching sub-control platforms;
the maintenance project scheduling sub-control platform is used for distributing maintenance groups according to the sequence of the queue number and the current maintenance group queue;
the handheld terminal is used for receiving the dispatching list, sending a signal for starting maintenance work and a signal for finishing maintenance work, and sending a maintenance report;
when a handheld terminal of a certain maintenance group sends a signal for completing maintenance work, the corresponding maintenance group is added into the maintenance group queue and is positioned at the tail of the current maintenance group queue.
Preferably, the dispatch list further comprises a maintenance work importance degree prejudgment level, the maintenance work importance degree prejudgment level is used for carrying out preliminary judgment on maintenance work by a worker of equipment to be maintained, and the maintenance work importance degree prejudgment level comprises general and emergency;
the general dispatching platform is used for respectively numbering the work orders corresponding to the maintenance items according to the maintenance items, the maintenance time and the maintenance work importance degree pre-judgment levels in the work orders, and distributing the work orders and the numbers to the corresponding maintenance item dispatching sub-control platforms;
and in the dispatching lists with the same or similar maintenance time, the row number of the dispatching list with the emergency maintenance work importance degree pre-judgment level is in front.
Preferably, the overhaul item scheduling sub-control platform is configured to allocate overhaul groups according to the queue number and the sequence of the current overhaul group queue:
when the pre-judging level of the importance degree of the maintenance work in the dispatching list is urgent, and when a free maintenance group is available in the maintenance group queue, distributing the free maintenance group in the maintenance group queue, if no free maintenance group is available in the maintenance group queue, sending the information of the group needing to be maintained urgently to the handheld terminals of all maintenance groups in each maintenance project, selecting the required maintenance group from the handheld terminals corresponding to the received response signal, and distributing the dispatching list to the handheld terminals of the maintenance groups;
the handheld terminal is further used for receiving information of the maintenance group in need of maintenance, and sending a response signal if the current maintenance work can be finished.
Preferably, the handheld terminal is further configured to receive information of an urgent maintenance group, and send a response signal indicating that there is a spare maintenance worker if the current maintenance work cannot be finished but there is a spare maintenance worker;
and the maintenance project scheduling sub-control platform builds a new maintenance group according to the received response signal of the idle maintenance worker, and sends the dispatching list to the handheld terminal of the maintenance group.
Preferably, the method for allocating the free service groups in the service group queue comprises the following steps:
and distributing the idle maintenance groups according to the first-in first-out sequence of the idle maintenance groups in the maintenance group queue.
Or distributing the idle maintenance groups according to the levels of the idle maintenance groups in the maintenance group queue and the first-in first-out sequence.
Or distributing the idle maintenance groups according to the working time of the idle maintenance groups in the maintenance group queue.
The invention distributes the maintenance work through the general scheduling platform, the maintenance project scheduling platform, the handheld terminal and the maintenance group queue and schedules the maintenance groups, thereby ensuring the timely completion of the maintenance work, simultaneously responding to emergency, maximally utilizing maintenance resources and improving the work efficiency of the maintenance work.
Drawings
Fig. 1 is a schematic diagram of a scheduling system of a power overhaul task of the present invention.
Fig. 2 is a schematic flow chart of power overhaul task scheduling in a specific embodiment.
Detailed Description
The present embodiment is described with reference to fig. 1, and the scheduling system for power overhaul tasks in the present embodiment includes a total scheduling platform, a plurality of overhaul project scheduling platforms, a plurality of handheld terminals, and a plurality of overhaul group queues;
the general scheduling platform, each overhaul project scheduling sub-control platform and each handheld terminal are all a wireless access point AP and form a wireless sensor network;
each maintenance project corresponds to one maintenance project scheduling sub-control platform and one maintenance group queue, and each maintenance worker corresponds to one handheld terminal;
each maintenance group queue is used for storing idle maintenance groups in the current maintenance project according to the time sequence;
the main dispatching platform is used for receiving the dispatching list, respectively numbering the dispatching list corresponding to each overhaul item according to the overhaul items and the overhaul time in the dispatching list, and distributing the dispatching list and the numbers to the corresponding overhaul item dispatching sub-control platforms;
the dispatch list of the present embodiment includes: the method comprises the steps that overhaul content, overhaul number, overhaul finish latest time and overhaul required time are estimated, when a total dispatching platform carries out numbering, overhaul work starting time needs to be determined according to the overhaul finish latest time and the overhaul required time estimation, and numbering is carried out according to the starting time;
each maintenance project corresponds to a maintenance project scheduling sub-control platform and a maintenance group queue, the maintenance project scheduling sub-control platform distributes maintenance work for maintenance groups in the maintenance group queue, recovers maintenance reports of all groups, and reports the maintenance reports to the general scheduling platform after the maintenance work is summarized; the maintenance project scheduling sub-control platform distributes maintenance groups according to the row number and the sequence of the current maintenance group queue; each maintenance worker is provided with a handheld terminal, the handheld terminal receives a dispatching order, needs to arrive at a maintenance site immediately after receiving the dispatching order, sends a maintenance starting working signal and a maintenance finishing working signal, and sends a maintenance report after the maintenance is finished;
when a handheld terminal of a certain maintenance group sends a signal for completing maintenance work, the corresponding maintenance group is added into the maintenance group queue and is positioned at the tail of the current maintenance group queue. According to the maintenance task scheduling sub-control platform, the maintenance group queue is used for recording current idle maintenance workers in sequence, the maintenance project scheduling sub-control platform distributes the work orders to the idle maintenance workers in the maintenance group queue, and the work efficiency of the maintenance workers is improved.
In the preferred embodiment, the dispatch list of the embodiment also includes a maintenance work importance degree prejudgment level, which is a preliminary judgment of the maintenance work by the staff of the equipment to be maintained, aiming at that individual emergency power equipment can be maintained in time without influencing the normal operation of the power system;
the master dispatching platform respectively performs number ranking on the work orders corresponding to all the overhaul items according to overhaul items, overhaul time and overhaul work importance degree pre-judging levels in the work orders, and distributes the work orders and the number rankings to corresponding overhaul item dispatching sub-control platforms;
and in the dispatching lists with the same or similar maintenance time, the row number of the dispatching list with the emergency maintenance work importance degree pre-judgment level is in front.
The embodiment preferentially distributes maintenance groups for the urgent maintenance tasks, and the maintenance is carried out in time, so that the operation of the power system is prevented from being influenced.
The maintenance project scheduling sub-control platform of the embodiment is used for allocating maintenance groups according to the sequence of the queue number and the current maintenance group queue:
as shown in fig. 2, when the pre-determined level of importance of the maintenance work in the dispatch list is urgent, and when there is a free maintenance group in the maintenance group queue, assigning a free maintenance group in the maintenance group queue, if there is no free maintenance group in the maintenance group queue, sending the information of the group needing to be maintained urgently to the handheld terminals of all maintenance groups in each maintenance project, and selecting a required maintenance group from the handheld terminals corresponding to the received response signal, and assigning the dispatch list to the handheld terminals of the maintenance groups;
the handheld terminal of the embodiment sends a response signal if the current maintenance work can be finished when receiving the information of the maintenance group in need of maintenance.
Aiming at the maintenance group capable of completing maintenance work in advance, the maintenance project scheduling sub-control platform can be responded in time, the maintenance project scheduling sub-control platform is scheduled, and the work efficiency is improved.
In a preferred embodiment, the handheld terminal is further configured to receive information of an urgent maintenance group, and send a response signal indicating that there is a spare maintenance worker if the current maintenance work cannot be finished but there is a spare maintenance worker;
and the maintenance project scheduling sub-control platform builds a new maintenance group according to the received response signal of the idle maintenance worker, and sends the dispatching list to the handheld terminal of the maintenance group.
According to the embodiment, as the maintenance work is carried out, some work does not need all the workers of the maintenance group to participate in the work, and at the moment, idle workers can be recombined into a group to be scheduled by the maintenance project scheduling sub-control platform, so that the working efficiency is improved.
In a preferred embodiment, the method for allocating the free maintenance groups in the maintenance group queue in this embodiment is as follows:
and distributing the idle maintenance groups according to the first-in first-out sequence of the idle maintenance groups in the maintenance group queue.
Or distributing the idle maintenance groups according to the levels of the idle maintenance groups in the maintenance group queue and the first-in first-out sequence.
Or distributing the idle maintenance groups according to the working time of the idle maintenance groups in the maintenance group queue.
In the embodiment, the levels of the maintenance groups are the levels obtained in the usual work assessment process, the priority distribution with high levels is realized, and the first-in first-out distribution is considered in the same level.
Although the invention herein has been described with reference to particular embodiments, it is to be understood that these embodiments are merely illustrative of the principles and applications of the present invention. It is therefore to be understood that numerous modifications may be made to the illustrative embodiments and that other arrangements may be devised without departing from the spirit and scope of the present invention as defined by the appended claims. It should be understood that features described in different dependent claims and herein may be combined in ways different from those described in the original claims. It is also to be understood that features described in connection with individual embodiments may be used in other described embodiments.

Claims (5)

1. A scheduling system of an electric power overhaul task is characterized by comprising a total scheduling platform, a plurality of overhaul project scheduling platforms, a plurality of handheld terminals and a plurality of overhaul group queues;
the general scheduling platform, each overhaul project scheduling sub-control platform and each handheld terminal are all a wireless access point AP and form a wireless sensor network;
each maintenance project corresponds to one maintenance project scheduling sub-control platform and one maintenance group queue, and each maintenance worker corresponds to one handheld terminal;
each maintenance group queue is used for storing idle maintenance groups in the current maintenance project according to the time sequence;
the main dispatching platform is used for receiving the dispatching list, respectively numbering the dispatching list corresponding to each overhaul item according to the overhaul items and the overhaul time in the dispatching list, and distributing the dispatching list and the numbers to the corresponding overhaul item dispatching sub-control platforms;
the maintenance project scheduling sub-control platform is used for distributing maintenance groups according to the sequence of the queue number and the current maintenance group queue;
the handheld terminal is used for receiving the dispatching list, sending a signal for starting maintenance work and a signal for finishing maintenance work, and sending a maintenance report;
when a handheld terminal of a certain maintenance group sends a signal for completing maintenance work, the corresponding maintenance group is added into the maintenance group queue and is positioned at the tail of the current maintenance group queue.
2. The scheduling system of the electric power overhaul task of claim 1, wherein the dispatch list further comprises an overhaul work importance degree prejudgment level, the overhaul work importance degree prejudgment level is used for preliminarily judging the overhaul work by a worker of equipment to be overhauled, and the overhaul work importance degree prejudgment level comprises normal and emergency;
the general dispatching platform is used for respectively numbering the work orders corresponding to the maintenance items according to the maintenance items, the maintenance time and the maintenance work importance degree pre-judgment levels in the work orders, and distributing the work orders and the numbers to the corresponding maintenance item dispatching sub-control platforms;
and in the dispatching lists with the same or similar maintenance time, the row number of the dispatching list with the emergency maintenance work importance degree pre-judgment level is in front.
3. The power overhaul task scheduling system of claim 2, wherein the overhaul project scheduling subcontrol platform is configured to assign the overhaul groups according to the queue number and the current order of the overhaul group queue:
when the pre-judging level of the importance degree of the maintenance work in the dispatching list is urgent, and when a free maintenance group is available in the maintenance group queue, distributing the free maintenance group in the maintenance group queue, if no free maintenance group is available in the maintenance group queue, sending the information of the group needing to be maintained urgently to the handheld terminals of all maintenance groups in each maintenance project, selecting the required maintenance group from the handheld terminals corresponding to the received response signal, and distributing the dispatching list to the handheld terminals of the maintenance groups;
the handheld terminal is further used for receiving information of the maintenance group in need of maintenance, and sending a response signal if the current maintenance work can be finished.
4. The power overhaul task scheduling system of claim 3,
the handheld terminal is also used for receiving the information of the maintenance group in need of urgent maintenance, and if the current maintenance work cannot be finished but idle maintenance workers are available, a response signal of the idle maintenance workers is sent;
and the maintenance project scheduling sub-control platform builds a new maintenance group according to the received response signal of the idle maintenance worker, and sends the dispatching list to the handheld terminal of the maintenance group.
5. The power overhaul task scheduling system of claim 2 or 3 wherein the method of allocating free overhaul panels in the overhaul panel queue is:
and distributing the idle maintenance groups according to the first-in first-out sequence of the idle maintenance groups in the maintenance group queue.
Or distributing the idle maintenance groups according to the levels of the idle maintenance groups in the maintenance group queue and the first-in first-out sequence.
Or distributing the idle maintenance groups according to the working time of the idle maintenance groups in the maintenance group queue.
CN201911142766.2A 2019-11-20 2019-11-20 Scheduling system of electric power overhaul task Pending CN110991834A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911142766.2A CN110991834A (en) 2019-11-20 2019-11-20 Scheduling system of electric power overhaul task

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911142766.2A CN110991834A (en) 2019-11-20 2019-11-20 Scheduling system of electric power overhaul task

Publications (1)

Publication Number Publication Date
CN110991834A true CN110991834A (en) 2020-04-10

Family

ID=70085449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911142766.2A Pending CN110991834A (en) 2019-11-20 2019-11-20 Scheduling system of electric power overhaul task

Country Status (1)

Country Link
CN (1) CN110991834A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113392291A (en) * 2021-07-06 2021-09-14 山东电力工程咨询院有限公司 Service recommendation method and system based on data center
CN113421002A (en) * 2021-06-30 2021-09-21 中国航空油料有限责任公司 Automatic dispatching method and device, electronic equipment and storage medium
CN113504769A (en) * 2021-05-24 2021-10-15 温州大学 Injection molding equipment state monitoring system based on industry 4.0

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2579995A1 (en) * 2007-03-01 2008-09-01 Harmon Solutions Group, Llc System and method for monitoring the restoration of damaged property within a drying chamber
EP2046007A1 (en) * 2007-04-17 2009-04-08 Huawei Technologies Co., Ltd. Method, system and device for call scheduling
EP2455897A2 (en) * 2010-11-18 2012-05-23 General Electric Company Methods and systems involving power system grid management
CN205541135U (en) * 2016-02-02 2016-08-31 广州斯迈尔特智能科技有限公司 Public bicycle management system's hand -held type does not have stake and borrows still scheduling transportation machine
CN106535350A (en) * 2016-12-30 2017-03-22 燕山大学 Medical dynamic scheduling system based on wireless sensor network
CN107392502A (en) * 2017-08-16 2017-11-24 国家电网公司 Management method, managing device and the terminal device of electric power apparatus examination
CN107977743A (en) * 2017-11-29 2018-05-01 合肥工业大学 Multiple no-manned plane cotasking distribution method and device
CN108471168A (en) * 2018-05-23 2018-08-31 山东广域科技有限责任公司 A kind of substation's wireless data transmission and inspection base and method
CN110096014A (en) * 2019-05-29 2019-08-06 黑龙江电力调度实业有限公司 A kind of intelligence control system and control method based on power communication
CN110264036A (en) * 2019-05-10 2019-09-20 阿里巴巴集团控股有限公司 Method for scheduling task and device
CN110287347A (en) * 2019-07-05 2019-09-27 黑龙江电力调度实业有限公司 Using the method for big data detection electric power computer room failure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2579995A1 (en) * 2007-03-01 2008-09-01 Harmon Solutions Group, Llc System and method for monitoring the restoration of damaged property within a drying chamber
EP2046007A1 (en) * 2007-04-17 2009-04-08 Huawei Technologies Co., Ltd. Method, system and device for call scheduling
EP2455897A2 (en) * 2010-11-18 2012-05-23 General Electric Company Methods and systems involving power system grid management
CN205541135U (en) * 2016-02-02 2016-08-31 广州斯迈尔特智能科技有限公司 Public bicycle management system's hand -held type does not have stake and borrows still scheduling transportation machine
CN106535350A (en) * 2016-12-30 2017-03-22 燕山大学 Medical dynamic scheduling system based on wireless sensor network
CN107392502A (en) * 2017-08-16 2017-11-24 国家电网公司 Management method, managing device and the terminal device of electric power apparatus examination
CN107977743A (en) * 2017-11-29 2018-05-01 合肥工业大学 Multiple no-manned plane cotasking distribution method and device
CN108471168A (en) * 2018-05-23 2018-08-31 山东广域科技有限责任公司 A kind of substation's wireless data transmission and inspection base and method
CN110264036A (en) * 2019-05-10 2019-09-20 阿里巴巴集团控股有限公司 Method for scheduling task and device
CN110096014A (en) * 2019-05-29 2019-08-06 黑龙江电力调度实业有限公司 A kind of intelligence control system and control method based on power communication
CN110287347A (en) * 2019-07-05 2019-09-27 黑龙江电力调度实业有限公司 Using the method for big data detection electric power computer room failure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杜雪灵等: "考虑公平性的面向多灾点需求应急资源调度", 《计算机应用》 *
薛东斌: "电力通信网络管理系统的设计探析", 《通信电源技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113504769A (en) * 2021-05-24 2021-10-15 温州大学 Injection molding equipment state monitoring system based on industry 4.0
CN113421002A (en) * 2021-06-30 2021-09-21 中国航空油料有限责任公司 Automatic dispatching method and device, electronic equipment and storage medium
CN113392291A (en) * 2021-07-06 2021-09-14 山东电力工程咨询院有限公司 Service recommendation method and system based on data center
CN113392291B (en) * 2021-07-06 2024-01-23 山东电力工程咨询院有限公司 Service recommendation method and system based on data center

Similar Documents

Publication Publication Date Title
CN110991834A (en) Scheduling system of electric power overhaul task
CN105354762B (en) Power customer service work order identification and distribution system and method
CN111311116B (en) Intelligent park-based vehicle scheduling method, device, equipment and storage medium
CN103714437A (en) Power line repair commanding method based on CIS and movable operation
CN106682743A (en) Operation and maintenance work order scheduling management method and system in electric power telecommunication field
CN101488204A (en) Task optimization scheduling system
CN111178773A (en) Factory production scheduling planning system and method
CN102594433B (en) Dynamic priority dispatching method of satellite network many-to-one communication conflicts
CN110825510A (en) Task-driven multi-satellite cooperative task allocation method and system
CN104915819A (en) Production planning-based vehicle allocation method
CN101510280A (en) Platform for optimizing and scheduling task
CN103678860A (en) Dispatching optimization method and device
CN106845809A (en) A kind of engineering course line work dispatching method, system and device, dispatching system
CN110350655A (en) One kind is ordered system with grid operation ticket sequencing
CN110599023A (en) Battery replacement scheduling method for electric vehicle group and cloud management server
CN103595654A (en) HQoS implementation method, device and network equipment based on multi-core CPUs
Pappis et al. Scheduling in a multi-processor environment with deteriorating job processing times and decreasing values: the case of forest fires
CN101364107A (en) Dynamic dispatching method with prediction in complex large system environment
CN104950684A (en) Swarm robot collaborative scheduling measurement and control method and system platform
CN109190995B (en) Multi-agent-based maintenance resource bidirectional joint scheduling strategy decision method
JP5527712B2 (en) Distributed power control method and distributed power control system
CN110049047A (en) A kind of power communication maintenance is self-service to permit to handle system
CN110322232A (en) A kind of distribution scheduling task ticket automatic generation method, apparatus and system
CN115829538A (en) Terminal operation and maintenance service management system
CN110581598A (en) Intelligent command and scheduling system for power system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200410