CN110886158A - Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system - Google Patents
Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system Download PDFInfo
- Publication number
- CN110886158A CN110886158A CN201911294917.6A CN201911294917A CN110886158A CN 110886158 A CN110886158 A CN 110886158A CN 201911294917 A CN201911294917 A CN 201911294917A CN 110886158 A CN110886158 A CN 110886158A
- Authority
- CN
- China
- Prior art keywords
- track
- branch
- main
- track beam
- rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012546 transfer Methods 0.000 claims abstract description 77
- 238000004891 communication Methods 0.000 claims description 60
- 230000007246 mechanism Effects 0.000 claims description 38
- 238000003032 molecular docking Methods 0.000 claims description 20
- 210000001503 joint Anatomy 0.000 claims description 12
- 230000007704 transition Effects 0.000 claims description 10
- 230000001154 acute effect Effects 0.000 claims description 7
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 230000000875 corresponding effect Effects 0.000 description 42
- 230000036961 partial effect Effects 0.000 description 25
- 230000009471 action Effects 0.000 description 21
- 230000008859 change Effects 0.000 description 13
- 238000010586 diagram Methods 0.000 description 13
- 239000000725 suspension Substances 0.000 description 12
- 230000000670 limiting effect Effects 0.000 description 7
- 230000033001 locomotion Effects 0.000 description 7
- 230000001276 controlling effect Effects 0.000 description 6
- 238000010276 construction Methods 0.000 description 4
- 230000001360 synchronised effect Effects 0.000 description 4
- 230000002457 bidirectional effect Effects 0.000 description 3
- 230000002441 reversible effect Effects 0.000 description 3
- 230000009466 transformation Effects 0.000 description 3
- 238000013461 design Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 238000006467 substitution reaction Methods 0.000 description 2
- 241000721047 Danaus plexippus Species 0.000 description 1
- 241001465754 Metazoa Species 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012806 monitoring device Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B25/00—Tracks for special kinds of railways
- E01B25/22—Tracks for railways with the vehicle suspended from rigid supporting rails
- E01B25/26—Switches; Crossings
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Train Traffic Observation, Control, And Security (AREA)
Abstract
The invention belongs to the technical field of rail transit, and aims to solve the problem that a suspended air-rail cannot be interconnected and run among a plurality of running rail beams, and the invention provides a multi-line rail beam based on a multi-branch structure, which comprises a guide rail, a rail changing device and four main rails which are not crossed with each other, wherein three branch rail beams in the guide rail are sequentially arranged between the main rails at one side and the other side, the other three branch rail beams in the guide rail are sequentially and oppositely arranged, and a pair of branch rail beams are crossed with each other; the track transfer device comprises a fork track transfer device arranged at the connecting part of the fork track beam and the main track and a fork track transfer device arranged at the intersection part of the fork track beam and is used for communicating the corresponding track beams; the invention has the beneficial effects that: the rapid and stable line changing operation of the train among the plurality of tracks can be realized through the arrangement of the plurality of forked track beams, the main line track and the rail changing device.
Description
Technical Field
The invention belongs to the technical field of rail transit, and particularly relates to a multi-line rail beam and a suspension type air-rail system based on a multi-track turnout structure.
Background
The aerial rail train belongs to urban fast public transport, and is a suspension type rail transit system, which comprises rail buttresses, a rail beam, an aerial rail train and a vehicle bogie, wherein the vehicle bogie is used for driving the aerial rail train to longitudinally walk along the rail beam, the aerial rail train, namely a suspension type aerial railway, the rail of the suspension type aerial railway is arranged above the rail, the space construction under a bridge and near the ground can be utilized, the construction cost is low, the construction period is short, the traffic pressure can be effectively relieved when the aerial railway is constructed in a crowded place, and meanwhile, the rail lines also become mutually staggered and diversified along with the rapid development of the aerial railway technology.
In the prior art, a plurality of turnout structures are generally adopted when a suspended air-rail is used for changing tracks in a complex running track beam system, and are supported through a stand column fixedly arranged on the ground, so that the track change of a train in the complex track system is realized, the turnout has longer length, larger occupied area and higher construction cost, and for the track change among a plurality of bidirectional track lines, a plurality of turnout structures are needed for carrying out cross reversing, the safety and the working efficiency when a plurality of trains run and reverse simultaneously are influenced, so that a system which can be used as a transfer line among the plurality of lines is needed for realizing the interconnection and intercommunication among the plurality of running track beams.
Disclosure of Invention
In order to solve the above problems in the prior art, that is, to solve the problem that the suspended air-rail cannot be interconnected and run among a plurality of running track beams, the invention provides a multi-track turnout structure-based multi-track beam, which comprises a first main track, a second main track, a third main track, a fourth main track, a guide track and a track changing device for switching the track communication direction; the first, second, third, and fourth main line tracks do not cross each other; the guide track comprises a first bifurcation track beam, a second bifurcation track beam, a third bifurcation track beam, a fourth bifurcation track beam, a fifth bifurcation track beam and a sixth bifurcation track beam; from a first end to a second end of the multi-track beam, the first branch track beam, the second branch track beam, and the third branch track beam are sequentially disposed between the first main track and the fourth main track, the fourth branch track beam, the fifth branch track beam, and the sixth branch track beam are sequentially disposed between the fourth main track and the first main track, and the second branch track beam and the fifth branch track beam are disposed in a crossing manner; the rail transfer device comprises a fork rail transfer device and a fork rail transfer device, the fork rail transfer device is arranged at a connecting part of the fork track beam and the main track beam, and the fork rail transfer device is arranged at a crossing part of the second fork track beam and the fifth fork track beam.
In some preferred embodiments, the first branch track beam and the sixth branch track beam are disposed between the first mainline track and the second mainline track and are tangentially disposed at an acute angle to both the first mainline track and the second mainline track; the second branch track beam and the fifth branch track beam are arranged between the second main track and the third main track and are tangentially arranged at acute angles with the second main track and the third main track; the third branch track beam and the fourth branch track beam are disposed between the third main track and the fourth main track, and are tangentially disposed at acute angles to the third main track and the fourth main track; the first bifurcated track beam, the second bifurcated track beam, and the third bifurcated track beam, which are sequentially disposed between the first mainline track and the fourth mainline track, are sequentially disposed to form a first cross track line; the fourth branch track beam, the fifth branch track beam and the sixth branch track beam which are sequentially arranged between the fourth mainline track and the first mainline track are sequentially arranged to form a second cross track line; the fork track-changing device is arranged at the connecting parts of the first track-crossing line, the second track-crossing line and the corresponding main track in a lifting manner; the fork track-changing device is arranged at the intersection part of the second branch track beam and the fifth branch track beam so as to switch a first passage and a second passage; the first path is communication of the first track crossing line, and the second path is communication of the second track crossing line.
In some preferred embodiments, the fork track-changing device includes a first track-changing device and a second track-changing device, the first track-changing device is liftably provided at a connecting portion of the first branch track beam and the first main track and the second main track, and/or a connecting portion of the second branch track beam and the second main track and the third main track, and/or a connecting portion of the third branch track beam and the third main track and the fourth main track; the second track transfer device is arranged at a connecting part of the sixth diverging track beam and the first main track and the second main track in a liftable and lowerable manner, and/or a connecting part of the fifth diverging track beam and the second main track and the third main track, and/or a connecting part of the fourth diverging track beam and the third main track and the fourth main track.
In some preferred embodiments, the first transfer device includes a first communicating member, a second communicating member, and a first drive mechanism; the first connecting component comprises a first connecting part and a first track part, and the first track part is fixedly connected with the first connecting part and is connected with the driving mechanism through the first connecting part; the second communicating member comprises a second connecting part and a second track part, and the second track part is fixedly connected with the second connecting part and is connected with the driving mechanism through the second connecting part; the first driving mechanism drives one of the first communicating member and the second communicating member to move downwards to be in butt joint with the running track beam, and simultaneously drives the other communicating member to ascend to a set height so as to construct a unique passage at the turnout part.
In some preferred embodiments, the second orbital transfer device includes a third communicating member, a fourth communicating member, a second drive mechanism; the third communicating member comprises a third connecting part and a third track part, and the third track part is fixedly connected with the third connecting part and is connected with the second driving mechanism through the third connecting part; the fourth communicating member comprises a fourth connecting part and a fourth track part, and the fourth track part is fixedly connected with the fourth connecting part and is connected with the second driving mechanism through the fourth connecting part; the second driving mechanism drives one of the third communicating member and the fourth communicating member to move downwards to be in butt joint with the running track beam, and simultaneously drives the other communicating member to ascend to a set height so as to construct a unique passage at the turnout part.
In some preferred embodiments, the fork track transfer device comprises a third track transfer device, the third track transfer device comprises a transition track beam and a third driving device; both ends of the transition track beam can be butted with the second branch track beam and the fifth branch track beam which establish a passage; the third driving device is used for driving the transition track beam to rotate so as to establish a passage.
In some preferred embodiments, the first branch track beam, the second branch track beam, the third branch track beam, the fourth branch track beam, the fifth branch track beam, and the sixth branch track beam are all curved track beams, and a curve radius of the curved track beams is a set turning radius value.
In some preferred embodiments, the multi-line track beam further comprises a docking track section, the docking track section comprises a first docking track section, a second docking track section, a third docking track section and a fourth docking track section, and one end of the first docking track section and one end of the second docking track section are fixedly connected with or integrally formed with one end of the first main line track; one end of the third connection track section and one end of the fourth connection track section are fixedly connected with one end of the fourth main line track or are integrally formed; the other ends of the first connection track section, the second connection track section, the third connection track section and the fourth connection track section are connected with a running track beam.
In some preferred embodiments, the first, second, third and fourth docking track segments are all linear track beams.
The utility model provides a suspension type air-railway system, includes many track roof beams that traveles, suspension type air-railway system is provided with one or more above arbitrary the multi-thread track roof beam based on multichannel fork structure, the multi-thread track roof beam with the track roof beam fixed connection that traveles for realize the interconnection of train in different complicated orbital operation.
The invention has the beneficial effects that:
1) the multi-track-fork-structure-based multi-track beam provided by the invention is sequentially arranged in the four main track tracks for passing in different directions through the six fork tracks, so that bidirectional interconnection and intercommunication of trains in different main track tracks can be realized, and rapid cross-track operation among different tracks can be realized.
2) The multi-line track beam based on the multi-track fork structure is matched with the third track-changing device through the group of fork track beams arranged in a cross mode, and each main line track is in a length range formed by only three sections of standard track beams in the longitudinal direction, so that stable and rapid interconnection and intercommunication of the multi-line track under the condition of the least occupied space can be realized.
3) According to the multi-track rail beam based on the multi-track fork structure, the first track transfer device and the second track transfer device are in a state of being in butt joint with the corresponding main track in a default state, namely when track transfer is not needed, the first track transfer device and the second track transfer device can achieve communication of the plurality of main tracks without driving movement; can realize vehicle transform track and double-line vehicle operation fast through first device and the second device of becoming the rail, improve whole operating efficiency, practice thrift the track transform time.
4) According to the multi-track-fork-structure-based multi-track beam, the first rail transfer device and the second rail transfer device are in quick lifting type movable butt joint through the first driving mechanism and the second driving mechanism respectively, and the third rail transfer device is driven to rotate and butt joint through the third driving mechanism, so that the track conversion time is shortened, and the overall practicability and the efficiency are improved; the driving mechanism can be any one of mechanical driving, motor driving, pressure driving and magnetic driving.
5) The suspended air-railway system can realize interconnection and intercommunication of track transformation in the staggered cross-track complex track system through combination of two or more multi-line track beams or combination of the multi-line track beams and the running track beams.
6) The invention is not only suitable for the inner suspension type monorail traffic system, but also suitable for the outer suspension type monorail traffic system.
7) The invention has simple and novel structure, low cost and convenient popularization.
Drawings
Other features, objects and advantages of the present application will become more apparent upon reading of the following detailed description of non-limiting embodiments thereof, made with reference to the accompanying drawings in which:
fig. 1 is a schematic perspective view of a multi-track beam based on a multi-track turnout structure in the invention;
fig. 2 is a schematic perspective view of a first track-changing device in a multi-track rail beam based on a multi-track fork structure;
fig. 3 is a schematic perspective view of a second track-changing device in the multi-track beam based on the multi-switch structure;
fig. 4 is a schematic perspective view of a third track-changing device in the multi-track beam based on the multi-switch structure;
fig. 5 is a partial structural view of a connection portion between a first main track and a first branch track beam in a multi-track beam based on a multi-track branch structure according to the present invention;
fig. 6 is a partial structural view of a connection portion between a first main track and a sixth diverging track beam in the multi-track beam based on the multi-track diverging structure according to the present invention;
fig. 7 is a partial structural view of a connecting portion between a second main track and a first branch track beam in a multi-track beam based on a multiple track branch structure according to the present invention;
fig. 8 is a partial structural view of a connection portion between a second main track and a sixth diverging track beam in the multi-track beam based on the multi-track diverging structure according to the present invention;
fig. 9 is a partial structural view of a connecting portion between a second main track and a second branch track beam in the multi-track beam based on the multi-switch structure according to the present invention;
fig. 10 is a partial structural view of a connecting portion between a second main track and a fifth branch track beam in the multi-track beam based on the multi-branch structure according to the present invention;
fig. 11 is a partial structural view of a connecting portion between a third main track and a fifth branch track beam in the multi-track beam based on the multi-branch structure according to the present invention;
fig. 12 is a partial structural view of a connecting portion between a third main track and a second branch track beam in the multi-track beam based on the multiple track branch structure according to the present invention;
fig. 13 is a partial structural view of a connecting portion between a third main track and a fourth branch track beam in the multi-track beam based on the multiple track branch structure according to the present invention;
fig. 14 is a partial structural view of a connecting portion of a third main track and a third branch track beam in the multi-track beam based on the multi-switch structure according to the present invention;
fig. 15 is a partial structural view of a connecting portion between a fourth main line track and a fourth branch track beam in the multi-track beam based on the multiple track branch structure according to the present invention;
fig. 16 is a partial structural schematic view of a connecting portion between a fourth main track and a third branch track beam in the multi-track beam based on the multi-track branch structure according to the present invention.
Description of reference numerals: 1. a first main line track; 2. a second main line track; 3. a third main line track; 4. a fourth main line track; 5. a first track transfer device 51, a first communicating member 52, a second communicating member; 6. a second track transfer device 61, a third communicating member 62, a fourth communicating member; 7. a third track transfer device; 8. a first branch rail beam; 9. a second branch rail beam; 10. a third branch rail beam; 11. a fourth switch track beam; 12. a fifth switch track beam; 13. a sixth diverging track beam; 14. a first docking track segment; 15. a second docking track segment; 16. a third docking track section; 17. and a fourth docking track segment.
Detailed Description
The preferred embodiments of the present invention will be described below with reference to the accompanying drawings, and it will be understood by those skilled in the art that these embodiments are merely illustrative of the technical principles of the present invention and are not intended to limit the scope of the present invention.
The invention provides a multi-line track beam based on a multi-track fork structure, which comprises a first main line track, a second main line track, a third main line track, a fourth main line track, a guide track for fork operation and a track changing device for switching the communication direction of the tracks; the four main line tracks are not crossed, namely if the four main line tracks are linear tracks, the four main line tracks are arranged in parallel, and if the four main line tracks are curve tracks, the four main line tracks are not crossed; the guide track comprises a first bifurcation track beam, a second bifurcation track beam, a third bifurcation track beam, a fourth bifurcation track beam, a fifth bifurcation track beam and a sixth bifurcation track beam; the first branch track beam, the second branch track beam and the third branch track beam are sequentially arranged between the first main line track and the fourth main line track from the first end to the second end of the multi-line track beam to form a first cross-line passage capable of running in a cross-line mode; the fourth branch track beam, the fifth branch track beam and the sixth branch track beam are sequentially arranged between the fourth main line track and the first main line track to form a second overline passage capable of operating in an overline mode, and the second branch track beam and the fifth branch track beam are arranged in a crossed mode; the first overline passage and the second overline passage realize the overline communication in opposite directions; the three forked track beams in the first overline passage and the three forked track beams in the second overline passage can be arranged adjacently and sequentially, and also can be arranged sequentially at intervals, different length specifications can be set according to various terrains or rail changing requirements, and the rapid, safe and stable rail changing operation of the train in a plurality of tracks is realized.
The rail transfer device comprises a fork rail transfer device and a fork rail transfer device, wherein the fork rail transfer device is arranged at the connecting part of the fork track beam and the main track beam and is used for realizing the communication of the main track beam or the communication of the fork track beam at a fork; the fork track-changing device is arranged at the intersection part of the second branch track beam and the fifth branch track beam and is used for realizing the self communication of the second branch track beam or the fifth branch track beam, and the fork track-changing device controls the second branch track beam and the fifth branch track beam to have only one branch track beam in a communication state at the same time; the fork track-changing device and the fork track-changing device can be swing arm track-changing devices, rotary track-changing devices or lifting track-changing devices, as long as the track line change of the corresponding track can be realized.
In the invention, two forked track beams are arranged in a crossed manner, so that the length specification of the whole multi-line track beam can be shortened, the occupied area of a line switching system in the air-to-rail system is saved, and the flexibility of the whole line switching system is improved.
It should be noted that the multi-track-turnout-structure-based multi-track beam of the present invention can be used at the turnout of a linear track beam and the turnout of a curved track beam, and is suitable for both an internal suspension type air-rail track beam and an external suspension type air-rail track beam.
The invention is further described with reference to the following detailed description of embodiments with reference to the accompanying drawings.
Referring to fig. 1, the multi-track beam based on the multi-track branching structure provided by the present invention includes a first main track 1, a second main track 2, a third main track 3, a fourth main track 4, a first track-changing device 5, a second track-changing device 6, a third track-changing device 7, a first branching track beam 8, a second branching track beam 9, a third branching track beam 10, a fourth branching track beam 11, a fifth branching track beam 12, a sixth branching track beam 13, a first connecting track segment 14, a second connecting track segment 15, a third connecting track segment 16, and a fourth connecting track segment 17, in this embodiment, the first branching track beam, the second branching track beam, the third branching track beam, the fourth branching track beam, the fifth branching track beam, and the sixth branching track beam are track beams disposed between the four main track beams for changing direction at a branch point of the multi-track structure, the six forked track beams and the corresponding main line track beams which are connected form acute angles and are arranged in a tangent mode; the first branch track beam 8, the second branch track beam 9, and the third branch track beam 10 are sequentially disposed between the first main track 1 and the fourth main track 4 from the left end to the right end of the multi-line track beam, and are used to realize cross-line communication from the first main track to the fourth main track; the fourth diverging track beam 11, the fifth diverging track beam 12, and the sixth diverging track beam 13 are sequentially disposed between the fourth main track and the first main track from the left end to the right end of the multi-line track beam, and are configured to implement cross-line communication from the fourth main track to the first main track; at the same time, the second diverging track beam 9 and the fifth diverging track beam 12
In this embodiment, the first connection track section 14, the second connection track section 15, the third connection track section 16, and the fourth connection track section 17 are respectively disposed at two ends of the first mainline track and the fourth mainline track, and are used for smooth connection with a traveling track beam after track change, so as to ensure smooth and safe operation, it should be noted that specific arrangement positions of the first connection track section, the second connection track section, the third connection track section, and the fourth connection track section do not limit the protection scope of the present invention, that is, if the tracks at two ends of the multi-line track beam are at two ends of the second mainline track and the third mainline track after track change, the corresponding connection track sections are disposed at two ends of the second mainline track and the third mainline track for smooth connection after track change, each connection track beam and the main track beam can be integrally formed or fixedly connected, so that other structural designs are not described in detail herein.
The first branch track beam 8 and the sixth branch track beam 13 are disposed between the first main track 1 and the second main track 2, and from a left end to a right end of the multi-track beam, the first branch track beam is configured to switch tracks from the first main track to the second main track, and the sixth branch track beam is configured to switch tracks from the second main track to the first main track, that is, the first branch track beam and the sixth branch track beam respectively realize track switching in different directions between the first main track and the second main track.
The second branch track beam 9 and the fifth branch track beam 12 are provided between the second main track 2 and the third main track 3, and are configured to switch tracks from the second main track to the third main track from a left end to a right end of the multi-track beam, and the fifth branch track beam is configured to switch tracks from the third main track to the second main track, that is, the second branch track beam and the fifth branch track beam respectively realize track switching in different directions between the second main track and the third main track.
The third branch track beam 10 and the fourth branch track beam 11 are disposed between the third main track 3 and the fourth main track 4, and are configured to change a track from the third main track to the fourth main track from a left end to a right end of the multi-track beam, and the fourth branch track beam is configured to change a track from the fourth main track to the third main track, that is, the third branch track beam and the fourth branch track beam respectively realize track changes in different directions between the third main track and the fourth main track.
Further, a first crossroad composed of the first branch track beam 8, the second branch track beam 9, and the third branch track beam 10 may implement interconnection from the first mainline track to the fourth mainline track; a second jumper channel composed of the fourth branch track beam 11, the fifth branch track beam 12, and the sixth branch track beam 13 may implement interconnection and intercommunication from the fourth main track to the first main track, so as to implement jumper communication from the fourth main track beam to the first main track; the forked track beams in the first overline passage and the corresponding main track form a right-side single-opening turnout structure, and the forked track beams in the second overline passage and the corresponding main track form a left-side single-opening turnout structure.
In this embodiment, the first track transfer device 5 and the second track transfer device 6 are six in number, and are respectively arranged at the corresponding left single-open turnout structure and right single-open turnout structure in a lifting manner, so as to be used for track change of a train at a turnout intersection, that is, the first track transfer device and the second track transfer device are arranged at a connecting part of a forked track beam and a main track, and communication of the corresponding track beams is realized through lifting change; and the third track-changing device 7 is arranged at the intersection of the second branch track beam and the fifth branch track beam and controls the communication of the corresponding track beams through a rotary structure.
Furthermore, the first branch track beam, the second branch track beam, the third branch track beam, the fourth branch track beam, the fifth branch track beam and the sixth branch track beam are all S-shaped curved track beams, and the curve radius of each curved track beam is a set turning radius value, so that turning operation and reversing smoothness between the train and the main track beam are facilitated.
Referring to fig. 2 and 3, fig. 2 is a schematic structural diagram of the first track-changing device, and fig. 3 is a schematic perspective structural diagram of the second track-changing device; the first rail transfer device comprises a first communicating member 51, a second communicating member 52 and a first driving mechanism (not shown), wherein the first communicating member 51 is used for controlling the communication of the main line track beam, the second communicating member is used for controlling the communication between the main line track beam and the branch track beam, the first communicating member and the second communicating member can move in a lifting manner under the driving of the first driving mechanism, namely when the main line track beam needs to realize the state of the self-passage, the first communicating member moves downwards to a lower limit point under the driving of the first driving mechanism to be in butt joint with a fracture at a fork of the corresponding main line track beam so as to realize the passage of the main line track beam, and at the moment, the second communicating member moves upwards to an upper limit point under the driving of the first driving mechanism to be far away from the track plate without interfering the running of a train, wherein, the two actions of moving downwards to the lower limit locus and moving upwards to the upper limit locus are synchronous and opposite; that is, when it is necessary to switch tracks at a track switch structure switch, a first set of actions is performed, the first set of actions including: a first communication component in the first track transfer device moves upwards to an upper limit point, and a second communication component in the first track transfer device moves downwards to a lower limit point in the same time period, wherein the upward movement to the upper limit point and the downward movement to the lower limit point are synchronous reverse motions, and the first action set completes the closing of a straight section of a corresponding main line track beam and communicates with a corresponding forked track beam, so that the purpose of changing tracks at a fork of a vehicle is realized; after the vehicle passes through the turnout, implementing a second action set, wherein the second action set and the first action set perform opposite actions, and recovering to a default state before the first action set is implemented, namely corresponding to respective own paths of the main line track beam; the first driving mechanism is connected with the first track transfer device through an electric signal, and the lifting hydraulic control can quickly realize track transfer of vehicles and operation of double-line vehicles, improve the overall operation efficiency and save track transfer time.
The first communication component comprises a first mainline track part and a first connecting part, the first mainline track part is horizontally arranged and is used for being butted with a track traveling plate of a corresponding mainline track beam, the first connecting part is vertically and fixedly connected with the first mainline track part and is used for being butted with a track web plate of the corresponding mainline track beam, and two ends of the first communication component formed by the first connecting part and the first mainline track part are matched with positions, to be butted, of the track traveling plate and the track web plate of the corresponding mainline track beam; the second communicating member includes a second main line track portion and a second connecting portion 522, the second main line track portion is horizontally arranged and used for being abutted with a track traveling plate of a corresponding forked track beam, the second connecting portion is vertically and fixedly connected with the second main line track portion and used for being abutted with a track web of the corresponding forked track beam, and two ends of the second communicating member formed by the second connecting portion and the second main line track portion are matched with positions to be abutted of the track traveling plate and the track web of the corresponding forked track beam.
With continued reference to fig. 3, the second track-changing device 6 includes a third communicating member 61, a fourth communicating member 62 and a second driving mechanism (not shown), the third communicating member 61 is used for controlling the communication of the main track itself, the fourth communicating member is used for controlling the communication between the main track and the branch track beam, the third communicating member and the fourth communicating member can move up and down under the driving of the second driving mechanism, that is, when the main track needs to realize the state of its own channel, the third communicating member moves down to the lower limit locus under the driving of the second driving mechanism to be butted with the fracture at the intersection of the corresponding main track, so as to realize the channel of the main track itself, at this time, the fourth communicating member moves up to the upper limit locus under the driving of the second driving mechanism, and is far away from the track slab, so as not to interfere with the running of the train, wherein, the two actions of moving downwards to the lower limit locus and moving upwards to the upper limit locus are synchronous and opposite; that is, when it is necessary to switch tracks at a track switch structure switch, a first set of actions is performed, the first set of actions including: a third communication component in the second track transfer device moves upwards to an upper limit point, and a fourth communication component in the second track transfer device moves downwards to a lower limit point in the same time period, wherein the upward movement to the upper limit point and the downward movement to the lower limit point are synchronous reverse motions, the first action set completes the closing of a straight section of a corresponding main line track and communicates with a corresponding forked track beam, and the purpose of changing tracks at a fork of a vehicle is further realized; after the vehicle passes through the turnout, implementing a second action set, wherein the second action set and the first action set perform opposite actions, and recovering to a default state before the first action set is implemented, namely corresponding to the own paths of the mainline tracks; the second driving mechanism is connected with the second track switching device through an electric signal, and the lifting hydraulic control can quickly realize the track switching of the vehicle and the operation of the double-track vehicle, improve the overall operation efficiency and save the track switching time.
The third communicating member 61 comprises a third rail part and a third connecting part, the third rail part is horizontally arranged and is used for being butted with a rail travelling plate of a corresponding mainline rail, the third connecting part is vertically and fixedly connected with the third rail part and is used for being butted with a rail web plate of the corresponding mainline rail, and two ends of the third communicating member formed by the third connecting part and the third rail part are matched with the positions, to be butted, of the rail travelling plate of the corresponding mainline rail beam and the rail web plate; the fourth communicating member 62 includes a fourth track portion and a fourth connecting portion, the fourth track portion is horizontally disposed and is used for being abutted with the track running plate of the corresponding diverging track beam, the fourth connecting portion is vertically and fixedly connected with the fourth track portion and is used for being abutted with the track web of the corresponding diverging track beam, and two ends of the fourth communicating member formed by the fourth connecting portion and the fourth track portion are matched with the positions to be abutted of the track running plate of the corresponding diverging track beam and the track web.
Furthermore, the first rail-changing devices also comprise support rods and lifting parts, the support rods are fixedly arranged on the turnout track beam, the lifting parts are connected with the support rods, each lifting part comprises a first part and a second part, the second part can be arranged in a vertical sliding mode relative to the first part, the second parts are fixedly connected with the rail-changing devices, the first rail-changing devices are driven by the driving mechanisms to lift up and down to achieve communication of the corresponding track beam, the first driving mechanisms can be hydraulic driving mechanisms, pneumatic driving mechanisms, linear motor driving mechanisms, rotating motor driving mechanisms, gear rack mechanisms and the like, and the purpose of driving the rail-changing devices to lift up and down can be achieved, and the description is omitted; it is understood by those skilled in the art that the above structure provided on the first track-changing device is also applicable to the second track-changing device, and therefore, the detailed description thereof is omitted.
In the invention, the first track-changing device and the second track-changing device control the main track and the forked track beam to have one and only one path at the same time, so that a train can continuously pass through the turnout junction, and track line change can be rapidly carried out without stopping at the forked track junction to wait for track communication; when the train is positioned on the main line track and needs to continuously run along the main line track, the first track transfer device and the second track transfer device are in a state that the corresponding main line track is communicated per se in a default state, and track changing is not needed, namely, the driving mechanism does not need to act to finish the rapid passing of the train at the track fork.
Preferably, a reinforcing rib (not shown) can be additionally arranged between the first connecting part and the first track part in the first rail transfer device to improve the bearing capacity of the first track part, a stress monitoring device can be further arranged between the first connecting part and the first track part, when the stress is detected to exceed a preset value, a system finds an alarm signal, so that personnel can monitor the structural strength of the switching part in time, and the safety of the rail transfer device is enhanced; similarly, the second connecting portion and the second rail portion, the third connecting portion and the third rail portion of the second rail transfer device, and the fourth connecting portion and the fourth rail portion may be disposed in the same manner.
Preferably, a notch is reserved at each structure position where the first communicating member and the second communicating member theoretically coincide with each other, and the third communicating member and the fourth communicating member theoretically coincide with each other, so that the first communicating member and the second communicating member, and the third communicating member and the fourth communicating member do not interfere with each other when moving in opposite directions.
Further, in the first track transfer device, the first connecting portion of the first communicating member, which is butted against the web, may carry a static load and a moving load of the first communicating member; when the main track beam is in a self-communicating state, that is, when the first communicating member descends to a lower limit point and is in butt joint with the notch on the corresponding main track beam, and when a bogie of a train passes through the first track part of the first communicating member, the first main track part transmits pressure to the first connecting part through a vertical limiting member (not shown) between the first connecting part and the first connecting part, and because the width of the first connecting part is greater than that of the first track part, the pressure on the first connecting part can transmit force to the first main track through the connecting part and the self structure; meanwhile, the side of the first connecting part facing the train bogie can bear the load from the transverse direction of the train bogie and transmit the transverse load to the main line track beam main body through a transverse limiting component (not shown) arranged on the main line track beam; in the invention, the load pressure borne by the first track transfer device in a working state can be transmitted to the main line track beam main body through the arranged vertical limiting members and the transverse limiting members, so that the structural safety performance of the first track transfer device is further improved; similarly, the second communicating member in the first rail transfer device is also provided with a vertical member and a transverse member which play the same role as the first communicating member, namely when the rail parts in different communicating members are in a state of being overlapped and butted with the rail surface, the load force from the train bogie is transmitted to the rail beam main body through the limiting members by the rail parts and the connecting parts, the load bearing of the rail transfer device is dispersed, and therefore the more reliable structural safety of the rail transfer device is realized.
Further, when the first track part is positioned at the lower limit point and is superposed and butted with the track surface of the main line track beam, the main line track beam is in a passage state, and a train can pass along the main line track beam; at the moment, the main line track locks the first track part through the first locking device, so that the stability and the safety performance of a butt joint are further ensured, and after a train passes through the main line track, the first locking device releases the main line track surface; similarly, the second communicating member in the first track-changing device is also provided with a locking device which has the same function as that of the first communicating member, namely when the track parts in different communicating members are in a state of being overlapped and butted with the track surface, the corresponding locking device locks the corresponding track parts, so that the structural safety performance of a butted area is further guaranteed; the first action set, the second action set, the locking and the releasing of the multi-line track beam are all controlled by an operation management system in the suspension type air-rail system.
Referring to fig. 4, there is shown a schematic perspective view of a third track-changing device 7, which is disposed between the second diverging track beam 9 and the fifth diverging track beam 12 and is used for communication with the diverging track beams themselves; the third rail transfer device comprises a fifth communication component, an arc-shaped closing plate, a rack and a connecting component, wherein the fifth communication component is a transition track beam which can be butted with the forked track beam, two ends of the transition track beam are matched with a fracture of the forked track beam to be butted, the transition track beam is an arc surface in the embodiment, and the third rail transfer device is driven by the driving device to rotate; in this embodiment, the third rail transfer device is in a state of being butted with the fifth diverging track beam, that is, a communication state of the fifth diverging track beam itself is realized, at this time, the second diverging track beam is in a disconnected state, and one pair of the arc-shaped closing plates arranged on both sides of the transition track beam closes two fractures of the corresponding second diverging track beam, so that birds and animals are prevented from entering the diverging track beam in a broken state; the outer side of the arc-shaped closing plate is further provided with a positioning locking device, when the third track transfer device rotates to the position locking device is positioned on a web of the track beam, the rotating motor stops rotating, the third track transfer device rotates in place, and meanwhile the positioning locking device locks the third track transfer device, so that the third track transfer device is fixed in the butt joint position with the corresponding forked track beam, and the butt joint precision is guaranteed.
Furthermore, the third orbital transfer device realizes the rotation of the third orbital transfer device through the matching of two arc-shaped tooth tracks arranged on the third orbital transfer device and a gear of the driving device; the connecting member is rotatably connected with a track top plate arranged above a cross area of the forked track beam, so that the third track transfer device is borne and rotated; the connecting component can be a pivoting support, so that the structural strength of the third rail transfer device and the bearing of the train are guaranteed.
Furthermore, a supporting device which can be relatively rotatably connected with the rail transfer device can be arranged below the third rail transfer device, so as to assist in bearing the rail transfer device.
In order to describe the present invention more clearly, the protection content of the present invention is further explained below with reference to the specific partial structural schematic diagram.
Referring to fig. 5, there is shown a partial structural schematic view of a connection portion between the first main line track 1 and the first diverging track beam 8, where the first main line track 1 and the first diverging track beam 8 form a right-side single-open turnout structure, and the second track-changing device 6 is disposed at the turnout structure and is configured to control communication between the first main line track itself and communication between the first main line track and the first diverging track beam; the first connecting track section 14 is disposed at a to-be-butted position of the turnout structure and the traveling track beam, and is used for smoothly butting with the traveling track beam.
Referring to fig. 6, there is shown a partial structural schematic view of a connection portion between the first main line track 1 and the sixth diverging track beam 13, where the first main line track 1 and the sixth diverging track beam 13 constitute a left-side single-open turnout structure, and the first track transfer device 5 is disposed at the turnout structure and is configured to control communication of the first main line track itself and communication of the first main line track and the sixth diverging track beam; the second connection track section 15 is arranged at a to-be-butted position of the turnout structure and the running track beam and is used for smoothly butting with the running track beam.
Referring to fig. 7, a partial structure diagram of a connection portion between the second main line rail 2 and the first branch rail beam 8 is shown, the second main line rail and the first branch rail beam are formed into a right-side single-open turnout structure, and the second rail changer 6 is disposed at the turnout structure and is configured to control communication of the second main line rail itself and communication of the second main line rail and the first branch rail beam.
Referring to fig. 8, there is shown a partial structural view of a connection portion between the second main line track 2 and the sixth diverging track beam 13, which constitutes a right-side single-open turnout structure, where the first track-changing device 5 is provided for controlling the communication of the second main line track itself and the communication of the second main line track and the sixth diverging track beam.
Referring to fig. 9, a partial structure diagram of a connection portion between the second main line rail 2 and the second branch rail beam 9 is shown, where the second main line rail and the second branch rail beam form a left single turnout structure, and the second track changer 6 is disposed at the turnout structure and is configured to control communication between the second main line rail and the second branch rail beam.
Referring to fig. 10, a schematic diagram of a partial structure of a connection portion between the second main line track 2 and the fifth branch track beam 12 is shown, where the second main line track and the fifth branch track beam form a left single-open turnout structure, and the first track changer 5 is disposed at the turnout structure and is configured to control communication between the second main line track and the fifth branch track beam.
Referring to fig. 11, a schematic partial structure diagram of a connection portion between the third main line track 3 and the fifth branch rail beam 12 is shown, where the third main line track and the fifth branch rail beam form a right single-open turnout structure, and the first rail changer 5 is disposed at the turnout structure and is configured to control communication between the third main line track and the fifth branch rail beam.
Referring to fig. 12, a partial structure diagram of a connection portion between the third main line rail 3 and the second branch rail beam 9 is shown, the third main line rail and the second branch rail beam form a right single-open turnout structure, and the second rail changer 6 is disposed at the turnout structure and is configured to control communication of the third main line rail itself and communication of the third main line rail and the second branch rail beam.
Referring to fig. 13, a partial structure diagram of a connection portion between the third main line rail 3 and the fourth branch rail beam 11 is shown, where the third main line rail and the fourth branch rail beam form a left-side single-open turnout structure, and the first rail changer 5 is disposed at the turnout structure and is configured to control communication between the third main line rail itself and communication between the third main line rail and the fourth branch rail beam.
Referring to fig. 14, a partial structure diagram of a connection portion between the third main line rail 3 and the third branch rail beam 10 is shown, the third main line rail and the third branch rail beam constitute a left-side single-open switch structure, and the second track changer 6 is disposed at the switch structure and is configured to control communication of the third main line rail itself and communication of the third main line rail and the third branch rail beam.
Referring to fig. 15, a schematic partial structure of a connection portion between the fourth main line rail 4 and the fourth branch rail beam 11 is shown, where the fourth main line rail and the fourth branch rail beam form a right single turnout structure, and the first rail changer 5 is disposed at the turnout structure and is configured to control communication between the fourth main line rail and the fourth branch rail beam.
Referring to fig. 16, a partial structure diagram of a connection portion between the fourth main line track 4 and the third branch track beam 10 is shown, the fourth main line track and the third branch track beam constitute a left-side single-open switch structure, and the second track changer 6 is disposed at the switch structure and is configured to control communication of the fourth main line track itself and communication of the fourth main line track and the third branch track beam.
It should be noted that, in the specific embodiment of the multi-track beam of the present invention, each main track beam includes four sections of standard track beams, that is, the unification of track specifications such as length, width, and the like is achieved, which is convenient for the standardized formulation in the technical field of suspended air-rail transportation, when the multi-track beam has a fault in a complex staggered track system, only the section track beam of the corresponding section needs to be replaced, so as to achieve the rapid emergency treatment of the faulty line, without affecting the operation of the whole line; no matter the track beam is a forked track beam or a section of track beam in a main track beam, when a fault occurs, the track beam can be quickly replaced by a standard linear track beam, and the straight-going or return dispatching of a train track and the cross-line running are realized.
When the train needs to realize cross-track running from a single running track beam through the multi-track beam system, the train enters a communication interaction section after passing through a turnout identification plate and completes clock synchronization with a set clock synchronizer; establishing a continuous communication connection relationship between a train-mounted controller and a turnout controller; the train-mounted controller rechecks turnout profile distribution information according to the operation diagram and sends an access application request number to the turnout controller; the turnout controller is in a release state (a non-interlocked standby state), receives the route request, establishes an interlocking relationship with the train controller, and feeds back a route permission signal to the train-mounted controller after finishing a corresponding numbering action; or when the turnout controller is in an interlocking state (other train occupation states), feeding back a waiting signal to the train-mounted controller and keeping a communication relation; after the turnout controller obtains the access request of the vehicle-mounted controller, the train passes through and clears the turnout, the communication responder sends a locking releasing instruction to the turnout controller, the turnout controller releases the interlocking state, and other trains are admitted and received to establish the interlocking relationship in sequence; when the train-mounted controller does not obtain the access request, the train-mounted controller applies for obtaining the access sequence number in the safety waiting area, and when the turnout finishes other preorder numbering work, the train-mounted controller feeds back a monarch access permission signal.
In the multiple rail beams which are staggered with each other, when different train route requests do not interfere with each other, the turnout controller can complete corresponding actions and then issue route admission signals to corresponding train vehicle-mounted controllers, so that higher passing efficiency is realized; when different trains send access requests to the turnout controllers at the same time, the corresponding turnout controllers are aligned and sequenced according to the sequence of the operation diagram; the multi-line track beam can realize the bidirectional composite track reversing of a plurality of trains; the vehicle-mounted controller is in communication connection with the turnout controller.
The invention also provides a suspension type air-rail system which comprises a plurality of running track beams, wherein one or more multi-line track beams based on the multi-turnout structure are arranged among the running track beams, and the multi-line track beams are fixedly connected with the running track beams and used for realizing the track change of trains on staggered complex lines and controlling the trains to construct unique paths at turnout parts.
It should be noted that, in the embodiment of the present invention, the first branch track beam 7, the third branch track beam 9, and the fifth branch track beam 11 are respectively and symmetrically disposed with respect to the second branch track beam 8, the fourth branch track beam 10, and the sixth branch track beam 12, so as to form track intercommunication between four main tracks, in the present invention, the transverse median plane of the multi-line track beam is a median plane perpendicular to the longitudinal direction of the main tracks, and by the symmetrical design of the plurality of branch track beams, track transformation that forms a plurality of staggered lines within the shortest distance range of the main track beams is realized, that is, in this embodiment, each main track only includes three sections of standard track beams, so as to realize intercommunication between four main tracks, so as to realize track transformation in the shortest time, however, the present embodiment does not limit the protection scope of the present invention, and does not limit the scheme for implementing interconnection and intercommunication between multiple main line tracks, each branch track beam may also be asymmetrically arranged, as long as the branch track beams are sequentially arranged in a specified direction to implement communication, as understood by those skilled in the art, the multi-track beam may also be configured to detach a group of main line tracks according to actual needs, change into a three-track beam system formed by combining three main line tracks and four branch track beams, and also implement reversing and transit between multiple traveling track beams, therefore, the present invention does not limit the number of specific main line tracks, that is, the number of main lines in the present invention includes three or more, and is not described herein; in addition, the description of other structural embodiments which are asymmetrically arranged is omitted.
While the invention has been described with reference to a preferred embodiment, various changes may be made and equivalents may be substituted for elements thereof without departing from the scope of the invention, and particularly, features shown in the various embodiments may be combined in any suitable manner without departing from the scope of the invention. It is intended that the invention not be limited to the particular embodiments disclosed, but that the invention will include all embodiments falling within the scope of the appended claims.
In the description of the present invention, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like, which indicate directions or positional relationships, are based on the directions or positional relationships shown in the drawings, which are for convenience of description only, and do not indicate or imply that the devices or elements must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
Furthermore, it should be noted that, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
The terms "comprises," "comprising," or any other similar term are intended to cover a non-exclusive inclusion, such that a process, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, article, or apparatus.
So far, the technical solutions of the present invention have been described in connection with the preferred embodiments shown in the drawings, but it is easily understood by those skilled in the art that the scope of the present invention is obviously not limited to these specific embodiments. Equivalent changes or substitutions of related technical features can be made by those skilled in the art without departing from the principle of the invention, and the technical scheme after the changes or substitutions can fall into the protection scope of the invention.
Claims (10)
1. The multi-track-branch-structure-based multi-track beam is characterized by comprising a first main track, a second main track, a third main track, a fourth main track, a guide track and a track changing device for switching the track communication direction; the first, second, third, and fourth main line tracks do not cross each other; the guide track comprises a first bifurcation track beam, a second bifurcation track beam, a third bifurcation track beam, a fourth bifurcation track beam, a fifth bifurcation track beam and a sixth bifurcation track beam;
from a first end to a second end of the multi-track beam, the first branch track beam, the second branch track beam, and the third branch track beam are sequentially disposed between the first main track and the fourth main track, the fourth branch track beam, the fifth branch track beam, and the sixth branch track beam are sequentially disposed between the fourth main track and the first main track, and the second branch track beam and the fifth branch track beam are disposed in a crossing manner;
the rail transfer device comprises a fork rail transfer device and a fork rail transfer device, the fork rail transfer device is arranged at a connecting part of the fork track beam and the main track beam, and the fork rail transfer device is arranged at a crossing part of the second fork track beam and the fifth fork track beam.
2. The multi-track-branch-structure-based multi-track beam according to claim 1, wherein the first branch track beam and the sixth branch track beam are disposed between the first main track and the second main track and are tangentially disposed at an acute angle to both the first main track and the second main track; the second branch track beam and the fifth branch track beam are arranged between the second main track and the third main track and are tangentially arranged at acute angles with the second main track and the third main track; the third branch track beam and the fourth branch track beam are disposed between the third main track and the fourth main track, and are tangentially disposed at acute angles to the third main track and the fourth main track;
the first bifurcated track beam, the second bifurcated track beam, and the third bifurcated track beam, which are sequentially disposed between the first mainline track and the fourth mainline track, are sequentially disposed to form a first cross track line; the fourth branch track beam, the fifth branch track beam and the sixth branch track beam which are sequentially arranged between the fourth mainline track and the first mainline track are sequentially arranged to form a second cross track line;
the fork track-changing device is arranged at the connecting parts of the first track-crossing line, the second track-crossing line and the corresponding main track in a lifting manner; the fork track-changing device is arranged at the intersection part of the second branch track beam and the fifth branch track beam so as to switch a first passage and a second passage; the first path is communication of the first track crossing line, and the second path is communication of the second track crossing line.
3. The multi-track-branch-structure-based multi-track beam as claimed in claim 2, wherein the branch track-changing device comprises a first track-changing device and a second track-changing device, the first track-changing device being elevatably disposed at a connecting portion of the first branch track beam and the first main track and the second main track, and/or at a connecting portion of the second branch track beam and the second main track and the third main track, and/or at a connecting portion of the third branch track beam and the third main track and the fourth main track;
the second track transfer device is arranged at a connecting part of the sixth diverging track beam and the first main track and the second main track in a liftable and lowerable manner, and/or a connecting part of the fifth diverging track beam and the second main track and the third main track, and/or a connecting part of the fourth diverging track beam and the third main track and the fourth main track.
4. The multi-track girder based on a multi-track turnout structure according to claim 3, wherein the first track transfer device comprises a first communicating member, a second communicating member and a first driving mechanism; the first connecting component comprises a first connecting part and a first track part, and the first track part is fixedly connected with the first connecting part and is connected with the driving mechanism through the first connecting part; the second communicating member comprises a second connecting part and a second track part, and the second track part is fixedly connected with the second connecting part and is connected with the driving mechanism through the second connecting part;
the first driving mechanism drives one of the first communicating member and the second communicating member to move downwards to be in butt joint with the running track beam, and simultaneously drives the other communicating member to ascend to a set height so as to construct a unique passage at the turnout part.
5. The multi-track girder based on a multi-track turnout structure according to claim 3, wherein the second track transfer device comprises a third communicating member, a fourth communicating member and a second driving mechanism; the third communicating member comprises a third connecting part and a third track part, and the third track part is fixedly connected with the third connecting part and is connected with the second driving mechanism through the third connecting part; the fourth communicating member comprises a fourth connecting part and a fourth track part, and the fourth track part is fixedly connected with the fourth connecting part and is connected with the second driving mechanism through the fourth connecting part;
the second driving mechanism drives one of the third communicating member and the fourth communicating member to move downwards to be in butt joint with the running track beam, and simultaneously drives the other communicating member to ascend to a set height so as to construct a unique passage at the turnout part.
6. The multi-track turnout structure based multi-track beam of claim 2, wherein the fork derailment apparatus comprises a third derailment apparatus, the third derailment apparatus comprises a transition track beam and a third driving apparatus; both ends of the transition track beam can be butted with the second branch track beam and the fifth branch track beam which establish a passage; the third driving device is used for driving the transition track beam to rotate so as to establish a passage.
7. The multi-track branching structure-based multi-track beam as claimed in claim 2, wherein the first branch track beam, the second branch track beam, the third branch track beam, the fourth branch track beam, the fifth branch track beam and the sixth branch track beam are all curved track beams, and a curve radius of the curved track beams is a set turning radius value.
8. The multi-track turnout structure based multi-track beam according to any one of claims 1-7, further comprising a docking track section comprising a first docking track section, a second docking track section, a third docking track section and a fourth docking track section, wherein one end of the first docking track section, one end of the second docking track section and one end of the first main track are fixedly connected or integrally formed; one end of the third connection track section and one end of the fourth connection track section are fixedly connected with one end of the fourth main line track or are integrally formed;
the other ends of the first connection track section, the second connection track section, the third connection track section and the fourth connection track section are connected with a running track beam.
9. The multi-track turnout structure based multi-track beam of claim 8, wherein the first, second, third and fourth connecting track segments are linear track beams.
10. A suspended air-railway system, which comprises a plurality of running track beams, and is characterized in that the suspended air-railway system is provided with one or more multi-line track beams based on a multi-turnout structure, which are fixedly connected with the running track beams, and are used for realizing the interconnection and intercommunication operation of trains on different complex tracks.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911294917.6A CN110886158A (en) | 2019-12-16 | 2019-12-16 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911294917.6A CN110886158A (en) | 2019-12-16 | 2019-12-16 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110886158A true CN110886158A (en) | 2020-03-17 |
Family
ID=69752095
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911294917.6A Pending CN110886158A (en) | 2019-12-16 | 2019-12-16 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110886158A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110878498A (en) * | 2019-12-16 | 2020-03-13 | 中建空列(北京)科技有限公司 | Rail transfer device for reversing of suspended type air railway, air railway turnout and air railway system |
CN110878497A (en) * | 2019-12-16 | 2020-03-13 | 中建空列(北京)科技有限公司 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
CN110886159A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Double-line double-opening track beam and suspension type air-railway system based on multi-turnout structure |
CN111364298A (en) * | 2020-04-21 | 2020-07-03 | 中国铁建重工集团股份有限公司 | Rail system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010140934A1 (en) * | 2009-06-02 | 2010-12-09 | Beamways Ab | Track and bogie for suspended vehicles |
CN107620230A (en) * | 2017-10-31 | 2018-01-23 | 中铁第四勘察设计院集团有限公司 | A kind of lifting type Riding-type Monorail Switch |
CN109989300A (en) * | 2017-12-29 | 2019-07-09 | 比亚迪股份有限公司 | Crossover turnout and Rail Transit System with it |
CN110878497A (en) * | 2019-12-16 | 2020-03-13 | 中建空列(北京)科技有限公司 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
CN110886160A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Double-track beam and suspension type air-railway system based on double-turnout structure |
CN110886161A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Rail transfer device for suspension type air-rail crossing track and suspension type air-rail system |
CN110886159A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Double-line double-opening track beam and suspension type air-railway system based on multi-turnout structure |
CN211596213U (en) * | 2019-12-16 | 2020-09-29 | 中建空列(北京)科技有限公司 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
-
2019
- 2019-12-16 CN CN201911294917.6A patent/CN110886158A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2010140934A1 (en) * | 2009-06-02 | 2010-12-09 | Beamways Ab | Track and bogie for suspended vehicles |
CN107620230A (en) * | 2017-10-31 | 2018-01-23 | 中铁第四勘察设计院集团有限公司 | A kind of lifting type Riding-type Monorail Switch |
CN109989300A (en) * | 2017-12-29 | 2019-07-09 | 比亚迪股份有限公司 | Crossover turnout and Rail Transit System with it |
CN110878497A (en) * | 2019-12-16 | 2020-03-13 | 中建空列(北京)科技有限公司 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
CN110886160A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Double-track beam and suspension type air-railway system based on double-turnout structure |
CN110886161A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Rail transfer device for suspension type air-rail crossing track and suspension type air-rail system |
CN110886159A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Double-line double-opening track beam and suspension type air-railway system based on multi-turnout structure |
CN211596213U (en) * | 2019-12-16 | 2020-09-29 | 中建空列(北京)科技有限公司 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110878498A (en) * | 2019-12-16 | 2020-03-13 | 中建空列(北京)科技有限公司 | Rail transfer device for reversing of suspended type air railway, air railway turnout and air railway system |
CN110878497A (en) * | 2019-12-16 | 2020-03-13 | 中建空列(北京)科技有限公司 | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system |
CN110886159A (en) * | 2019-12-16 | 2020-03-17 | 中建空列(北京)科技有限公司 | Double-line double-opening track beam and suspension type air-railway system based on multi-turnout structure |
CN111364298A (en) * | 2020-04-21 | 2020-07-03 | 中国铁建重工集团股份有限公司 | Rail system |
CN111364298B (en) * | 2020-04-21 | 2022-05-31 | 中国铁建重工集团股份有限公司 | Rail system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110886158A (en) | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system | |
CN211596214U (en) | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system | |
CN211596213U (en) | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system | |
JP6719389B2 (en) | Large transportation power direct track transportation system | |
AU658579B2 (en) | Transportation system | |
CN110886159A (en) | Double-line double-opening track beam and suspension type air-railway system based on multi-turnout structure | |
CN110878497A (en) | Multi-track-turnout-structure-based multi-line track beam and suspended air-railway system | |
CN110886160A (en) | Double-track beam and suspension type air-railway system based on double-turnout structure | |
CN105040533B (en) | Pivot type turnout structure and turnout switching method | |
CN110983874B (en) | Wheel rail structure suspension type PRT elastic turnout switch structure and switching method | |
WO2021057577A1 (en) | Personal automatically-controlled light maglev rail transit system capable of changing rails | |
CN108454651A (en) | Straddle-type monorail replaces beam list crossover turnout equipment | |
CN211689690U (en) | Double-track beam and suspension type air-railway system based on double-turnout structure | |
CN211547108U (en) | Double-line double-opening track beam and suspension type air-railway system based on multi-turnout structure | |
CN105155366A (en) | Replacing beam turnout structure and turnout switch method | |
CN111172821A (en) | Suspension type single-rail single-shaft single-beam flat-turning turnout | |
CN116142239B (en) | L track system | |
CN211340239U (en) | Rail transfer device for reversing of suspended type air railway, air railway turnout and air railway system | |
CN111321638A (en) | Suspension type monorail vehicle moving platform | |
US6279484B1 (en) | Actuating mechanism for a transit vehicle guide beam switch | |
CN211596215U (en) | Switch device for suspended air-rail cross track and suspended air-rail system | |
CN110878498A (en) | Rail transfer device for reversing of suspended type air railway, air railway turnout and air railway system | |
WO2023033877A1 (en) | Adaptive route rail system with passive switches | |
CN208698792U (en) | Straddle-type monorail replaces beam list crossover turnout equipment | |
CN110886162A (en) | Switch device for suspended air-rail cross track and suspended air-rail system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |