CN110848458A - Buried pipeline installation method - Google Patents

Buried pipeline installation method Download PDF

Info

Publication number
CN110848458A
CN110848458A CN201911164752.0A CN201911164752A CN110848458A CN 110848458 A CN110848458 A CN 110848458A CN 201911164752 A CN201911164752 A CN 201911164752A CN 110848458 A CN110848458 A CN 110848458A
Authority
CN
China
Prior art keywords
buried
buried pipeline
installing
pipelines
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911164752.0A
Other languages
Chinese (zh)
Inventor
杨贵柏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
China 19th Metallurgical Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Corp filed Critical China 19th Metallurgical Corp
Priority to CN201911164752.0A priority Critical patent/CN110848458A/en
Publication of CN110848458A publication Critical patent/CN110848458A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • F16L1/036Laying or reclaiming pipes on land, e.g. above the ground in the ground the pipes being composed of sections of short length
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Abstract

The invention relates to the technical field of pipeline installation, in particular to a buried pipeline installation method, which comprises the following steps: a. a plurality of concave roller bed frame bodies are arranged on the ground; b. placing all the sections of buried pipelines on a concave roller way frame body, and sequentially connecting all the sections of buried pipelines together; c. and installing and fixing the connected buried pipelines underground. According to the invention, the buried pipelines are connected in sequence on the ground, so that the connecting operation space of the buried pipelines is remarkably increased, the connecting efficiency and quality can be improved, and the mounting efficiency and quality of the buried pipelines are improved.

Description

Buried pipeline installation method
Technical Field
The invention relates to the technical field of pipeline installation, in particular to a buried pipeline installation method.
Background
The existing buried pipeline installation procedures are as follows: digging out a foundation pit on the ground, then placing the buried pipelines into the foundation pit through a crane, connecting the buried pipelines together in the foundation pit through hot melting or welding, and finally backfilling earthwork of the foundation pit so as to finish the installation of the buried pipelines. Because the operation space in the foundation pit is small, the operation difficulty of connecting each section of buried pipelines in the foundation pit is high, the connection quality of the buried pipelines cannot be guaranteed, the connection efficiency is low, and the installation efficiency of the buried pipelines is reduced.
Disclosure of Invention
The invention aims to provide a buried pipeline installation method which is high in installation efficiency and good in quality.
The technical scheme adopted by the invention for solving the technical problems is as follows: the buried pipeline installation method comprises the following steps:
a. a plurality of concave roller bed frame bodies are arranged on the ground;
b. placing all the sections of buried pipelines on a concave roller way frame body, and sequentially connecting all the sections of buried pipelines together;
c. and installing and fixing the connected buried pipelines underground.
Further, in the step a, the centers of all the concave roller bed frame bodies are on the same straight line.
Further, in the step b, the buried pipelines are connected together by means of hot melting or welding.
Furthermore, in the step b, the buried pipelines are connected by arranging a winch device and a pipe support sleeve, the pipe support sleeve is arranged on the buried pipeline on the outermost side, and the winch device is detachably connected with the pipe support sleeve.
Further, in the step c, the process of installing and fixing the buried pipeline in the ground comprises the following steps: firstly, digging a foundation pit on the ground, and enabling the buried pipelines connected together to be parallel to the foundation pit; then, the buried pipelines connected together are placed into the foundation pit through a power device; then fixing the buried pipeline in the foundation pit through a fastener; finally, backfilling the foundation pit.
Further, the power device comprises a plurality of single-arm cranes.
Further, the fastener is a flat steel hoop and a steel chisel.
Further, in the step c, the buried pipeline installation and fixation process for the underground of the river comprises the following steps: the method comprises the steps of firstly connecting a shield drilling machine with a buried pipeline, then driving the buried pipeline to move along the underground of a river through the shield drilling machine, installing the buried pipeline under the ground of the river, and finally separating the shield drilling machine from the buried pipeline.
Further, the shield drilling machine is connected with the buried pipeline through screw threads, and the screw threads are reinforced through bolts.
Furthermore, a clamping ring is sleeved at the joint of the shield drilling machine and the buried pipeline.
The invention has the beneficial effects that: the buried pipeline connecting device is characterized in that a plurality of concave roller way frame bodies are arranged on the ground, then all sections of buried pipelines are sequentially connected together on the concave roller way frame bodies, and finally the connected buried pipelines are installed and fixed underground. Therefore, the buried pipeline connecting device completes the sequential connection work of all the buried pipelines on the ground, the connecting work space of the buried pipelines is obviously enlarged, and the connecting efficiency and the connecting quality can be improved, so that the mounting efficiency and the mounting quality of the buried pipelines are improved.
Drawings
FIG. 1 is a schematic plan view of an underground buried pipeline installation on land;
FIG. 2 is a schematic elevation view of a buried pipeline installation in the ground of a land;
FIG. 3 is an enlarged view at A in FIG. 2;
FIG. 4 is a schematic elevation view of the underground of a river for buried pipeline installation;
FIG. 5 is a schematic structural view of the junction of a buried pipeline and a shield drilling rig;
labeled as: the device comprises the ground 1, a concave roller bed frame body 2, a buried pipeline 3, a winch device 4, a pipe support sleeve 5, a foundation pit 6, a power device 7, a fastener 8, a flat steel hoop 9, a steel chisel 10, a river 11, a clamping sleeve ring 12, a shield drilling machine 13 and a bolt 14.
Detailed Description
The invention is further described with reference to the following figures and detailed description.
As shown in fig. 1, 2, 3 and 4, the buried pipeline installation method comprises the following steps:
a. a plurality of concave roller bed frame bodies 2 are arranged on the ground 1;
b. placing the buried pipelines 3 on the concave roller bed frame body 2, and sequentially connecting the buried pipelines 3 together;
the connection mode is hot melting or welding;
c. and installing and fixing the buried pipelines 3 connected together underground.
In step a, in order to ensure that the buried pipes 3 connected together are on the same straight line, the centers of all the concave roller bed frame bodies 2 are on the same straight line.
In step b, the buried pipelines 3 are connected together by means of hot melting or welding. In order to facilitate the connection operation of the buried pipelines 3, the invention connects the buried pipelines 3 by arranging a winch device 4, a pipe bracket sleeve 5 and a pulley block. During connection, the pipe support sleeve 5 is arranged on the buried pipeline 3 on the outermost side, the winch device 4 penetrates through the pulley block to be connected with the pipe support sleeve 5, and the connected buried pipeline 3 is lifted by the winch device 4 and pushed by the winch device, so that connection work is facilitated.
In step c, the procedure of installing and fixing the underground buried pipeline 3 on the ground comprises the following steps: firstly, digging a foundation pit 6 on the ground 1, and enabling the buried pipelines 3 connected together to be parallel to the foundation pit 6; then the buried pipelines 3 connected together are placed into a foundation pit 6 through a power device 7; then fixing the buried pipeline 3 in the foundation pit 6 through a fastener 8; and finally, backfilling earthwork of the foundation pit 6. The power device 7 is a plurality of single-arm cranes which simultaneously lift the buried pipelines 3 connected together and place the buried pipelines into the foundation pit 6. The fastener 8 is a flat steel hoop 9 and a steel chisel 10, the flat steel hoop 9 is firstly clamped on the buried pipeline 3, and the steel chisel 10 penetrates through the flat steel hoop 9 to be fixed in the foundation pit 6, so that the buried pipeline 3 is fixed in the foundation pit 6.
When the existing underground buried pipeline 3 of the river 11 is installed, water in the river 11 needs to be drained firstly, then the foundation pit 6 needs to be dug out, finally, after the buried pipeline 3 is installed in the foundation pit 6, earthwork backfilling is carried out on the foundation pit 6, the number of processes is large, and the efficiency is low. In step c, the process of installing and fixing the buried pipeline 3 under the river 11 comprises the following steps: as shown in fig. 4, the shield drilling machine 13 is firstly connected with the buried pipeline 3, then the buried pipeline 3 is driven to move along the underground of the river 11 by the shield drilling machine 13, the buried pipeline 3 is installed in the underground of the river 11, and finally the shield drilling machine 13 is separated from the buried pipeline 3. The shield drilling machine 13 is used for drilling a foundation hole under the river 11 and installing the buried pipeline 3 in the foundation hole, so that water in the river 11 does not need to be pumped out, the working procedures are obviously reduced, and the installation efficiency is obviously improved. In order to ensure the connection strength of the shield drilling machine 13 and the buried pipeline 3, as shown in fig. 5, the shield drilling machine 13 is connected with the buried pipeline 3 through screw threads, and is reinforced at the screw threads through bolts 14, the number of the bolts 14 is 2-6, and the size of the connection end of the shield drilling machine 13 is large outside and small inside, so that the buried pipeline 3 can be connected conveniently. In order to further improve the connection strength between the shield drilling machine 13 and the buried pipeline 3, a clamping sleeve ring 12 is sleeved at the joint of the shield drilling machine 13 and the buried pipeline 3, and the clamping sleeve ring 12 can also protect the connection position between the shield drilling machine 13 and the buried pipeline 3.
In conclusion, the buried pipelines 3 are connected in sequence on the ground 1, so that the connecting operation space of the buried pipelines 3 is remarkably increased, the connecting efficiency and the connecting quality can be improved, and the installation efficiency and the installation quality of the buried pipelines 3 are improved.

Claims (10)

1. The buried pipeline installation method is characterized by comprising the following steps:
a. a plurality of concave roller bed frame bodies (2) are arranged on the ground (1);
b. placing the buried pipelines (3) on the concave roller way frame body (2), and connecting the buried pipelines (3) together in sequence;
c. and installing and fixing the buried pipelines (3) which are connected together underground.
2. A method of installing a buried pipeline according to claim 1, wherein: in the step a, the centers of all the concave roller way frame bodies (2) are on the same straight line.
3. A method of installing a buried pipeline according to claim 1, wherein: in the step b, the buried pipelines (3) are connected together in a hot melting or welding mode.
4. A method of installing a buried pipeline according to claim 1, wherein: in the step b, the buried pipelines (3) are connected by arranging the winch device (4) and the pipe support sleeve (5), the pipe support sleeve (5) is arranged on the buried pipeline (3) on the outermost side, and the winch device (4) is detachably connected with the pipe support sleeve (5).
5. A method of installing a buried pipeline according to claim 1, wherein: in the step c, the procedure of installing and fixing the underground buried pipeline (3) on the land comprises the following steps: firstly, digging a foundation pit (6) on the ground (1), and enabling the buried pipelines (3) connected together to be parallel to the foundation pit (6); then the buried pipelines (3) which are connected together are placed into the foundation pit (6) through a power device (7); then the buried pipeline (3) is fixed in the foundation pit (6) through a fastener (8); finally, backfilling the foundation pit (6).
6. A method of installing a buried pipeline according to claim 5, wherein: the power device (7) comprises a plurality of single-arm cranes.
7. A method of installing a buried pipeline according to claim 5, wherein: the fastener (8) is a flat steel hoop (9) and a steel chisel (10).
8. A method of installing a buried pipeline according to claim 1, wherein: in the step c, the process of installing and fixing the buried pipeline (3) under the river (11) comprises the following steps: firstly, a shield drilling machine (13) is connected with a buried pipeline (3) through a clamping sleeve ring (12), then the buried pipeline (3) is driven to move along the underground of a river (11) through the shield drilling machine (13), the buried pipeline (3) is installed underground of the river (11), and finally the shield drilling machine (13) is separated from the buried pipeline (3).
9. A method of installing a buried pipeline according to claim 8, wherein: the shield drilling machine (13) is connected with the buried pipeline (3) through screw threads, and the screw threads are reinforced through bolts (14).
10. A method of installing a buried pipeline according to claim 9, wherein: a clamping sleeve ring (12) is sleeved at the joint of the shield drilling machine and the buried pipeline.
CN201911164752.0A 2019-11-25 2019-11-25 Buried pipeline installation method Pending CN110848458A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911164752.0A CN110848458A (en) 2019-11-25 2019-11-25 Buried pipeline installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911164752.0A CN110848458A (en) 2019-11-25 2019-11-25 Buried pipeline installation method

Publications (1)

Publication Number Publication Date
CN110848458A true CN110848458A (en) 2020-02-28

Family

ID=69603999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911164752.0A Pending CN110848458A (en) 2019-11-25 2019-11-25 Buried pipeline installation method

Country Status (1)

Country Link
CN (1) CN110848458A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155585A (en) * 2011-04-12 2011-08-17 中国十九冶集团有限公司 Method for laying mine slurry pipeline in long and narrow section
CN107191676A (en) * 2017-07-11 2017-09-22 中国十九冶集团有限公司 Buried pipeline construction method
CN108758081A (en) * 2018-06-13 2018-11-06 云南建投第十建设有限公司 Heavy caliber PE pipe installation methods
US10344892B2 (en) * 2014-04-17 2019-07-09 Lavalley Industries, Llc Pipe processing tool with pipe deformation members
US20190249800A1 (en) * 2018-02-13 2019-08-15 Zilper Trenchless, Inc. Systems and methods for underground pipe installation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155585A (en) * 2011-04-12 2011-08-17 中国十九冶集团有限公司 Method for laying mine slurry pipeline in long and narrow section
US10344892B2 (en) * 2014-04-17 2019-07-09 Lavalley Industries, Llc Pipe processing tool with pipe deformation members
CN107191676A (en) * 2017-07-11 2017-09-22 中国十九冶集团有限公司 Buried pipeline construction method
US20190249800A1 (en) * 2018-02-13 2019-08-15 Zilper Trenchless, Inc. Systems and methods for underground pipe installation
CN108758081A (en) * 2018-06-13 2018-11-06 云南建投第十建设有限公司 Heavy caliber PE pipe installation methods

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋成贵: "《油气田地面工程实用施工技术-安装篇》", 28 February 2010, 中国石油大学出版社 *

Similar Documents

Publication Publication Date Title
CN202852194U (en) Device and system of under ground pipeline repair without excavation of pneumatic burst pipe
CN107255188B (en) A kind of lifting pipeline method suitable at pipe gallery intersection node
CN108915582B (en) A kind of drilling machine for rotary digging drill bit and impactor switching construction
CN110848458A (en) Buried pipeline installation method
CN210266161U (en) Vertical jacking device in horizontal steel jacking pipe
CN109185558B (en) Method for underwater installation of large-diameter GRP pipeline
CN215518799U (en) Slope unearthing mouth PC worker method stake reinforcing apparatus
CN103382842B (en) A kind of construction method preventing push-bench and tube coupling from rotating
CN213685544U (en) Installation device for underground water conduit
CN211735679U (en) Urban sewage pipeline treatment device
CN210610245U (en) Mine land reclamation is with device of digging
CN103924603A (en) Tool for preventing pole pit soil collapse and method for using same to dig pole pit
CN210440668U (en) Quick clamping device of pipe jacking slip casting
CN203729310U (en) Tool for preventing soil collapse of bar pits
CN103388479B (en) The construction equipment preventing push-bench and tube coupling from rotating with drag-line and construction method
CN107269282B (en) Integrated pushing system of mud-water push bench
CN215172749U (en) Large-diameter jacking pipe guide structure with adjustable universality is strong
CN102052517A (en) Horizontal connecting system for regional underground vertical pipes and connecting construction method thereof
CN105135054B (en) The pipe jacking construction method of super-long pipeline
CN114396070B (en) Electric power transmission tower mounting base
CN107060843B (en) The method that shield tail is separated with molding section of jurisdiction when shield receives
CN217151949U (en) Slurry pipe extension device for slurry shield split starting stage
CN220453009U (en) Hydraulic pipeline for hydraulic engineering
CN220847627U (en) Pile casing device
CN213775276U (en) Casing pipe introducing device for petroleum operation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200228