CN110847911A - Vertical shaft tunneling construction method for passing through thin quicksand layer - Google Patents

Vertical shaft tunneling construction method for passing through thin quicksand layer Download PDF

Info

Publication number
CN110847911A
CN110847911A CN201910984022.9A CN201910984022A CN110847911A CN 110847911 A CN110847911 A CN 110847911A CN 201910984022 A CN201910984022 A CN 201910984022A CN 110847911 A CN110847911 A CN 110847911A
Authority
CN
China
Prior art keywords
shaft
quicksand
layer
sand
sand blocking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201910984022.9A
Other languages
Chinese (zh)
Inventor
罗业民
蒋文利
吴永强
于志明
王宝文
孙艳秋
庞博
杨闯
李成斌
刘进铭
雷发根
吴大川
赵振江
刘彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Iron and Steel Group Mining Co Ltd
HBIS Co Ltd
Original Assignee
HBIS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HBIS Co Ltd filed Critical HBIS Co Ltd
Priority to CN201910984022.9A priority Critical patent/CN110847911A/en
Publication of CN110847911A publication Critical patent/CN110847911A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • E21D1/105Preparation of the ground by water level modification
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/06Lining shafts; Linings therefor with iron or steel

Abstract

The invention discloses a vertical shaft tunneling construction method for passing through a thin quicksand layer, which comprises the following steps: a. digging a water pit, collecting water gushing from a working surface and discharging the water outside by using a pump; b. a plurality of sand blocking piles arranged around a shaft of the vertical shaft are driven into a quicksand layer in a direction deviating to the outer side of the shaft, so that the plurality of sand blocking piles form a cylindrical shaft wall with a thin upper part and a thick lower part; c. excavating quicksand on the inner side of a cylindrical well wall formed by a plurality of sand blocking piles to form a well shaft with a certain height; d. processing a permanent support on the inner side of the sand blocking pile by adopting concrete; e. and (d) repeating the steps a to d below the processed permanent support until the construction of the shaft in the quicksand layer is completed. The invention utilizes the sand blocking piles and the concrete to construct supports layer by layer, prevents the sand outside the shaft from flowing into the shaft, and compared with the traditional freezing method and the drilling method, the invention not only can ensure the normal operation of shaft construction, but also can greatly improve the construction efficiency and reduce the construction cost, and is particularly suitable for excavating the shaft in a thin sand layer.

Description

Vertical shaft tunneling construction method for passing through thin quicksand layer
Technical Field
The invention relates to a method capable of quickly excavating a vertical shaft in a thin flowing sand layer, and belongs to the technical field of mining.
Background
In the construction process of the vertical shaft, a quicksand layer is often encountered, if the quicksand in the vertical shaft is excavated by using a common method, the quicksand outside the vertical shaft flows into the vertical shaft, and the more the quicksand is collapsed, the more the quicksand is collapsed, the construction task can not be smoothly completed. For thick or super-thick flowing sand layers, the freezing method or the drilling method is generally adopted for construction at present; for the thin quicksand layer, if the freezing method or the drilling method is used for construction, the construction cost can be greatly increased, and the construction period is prolonged, so that an economic, rapid and safe vertical shaft construction method suitable for the thin quicksand layer is very necessary.
Disclosure of Invention
The invention aims to provide a vertical shaft tunneling construction method for passing through a thin quicksand layer aiming at the defects of the prior art so as to improve the construction efficiency of a vertical shaft and reduce the construction cost.
In order to achieve the purpose, the invention adopts the following technical scheme:
a shaft tunneling construction method for passing through a thin quicksand layer comprises the following steps:
a. digging a water pit at a construction site, collecting water gushing from a working surface in a centralized manner, and discharging the water gushing out by using a pump to reduce the water level of the working surface;
b. a plurality of sand blocking piles arranged around a shaft of the vertical shaft are driven into a quicksand layer in a direction deviating to the outer side of the shaft, so that the plurality of sand blocking piles form a cylindrical shaft wall with a thin upper part and a thick lower part;
c. excavating quicksand on the inner side of a cylindrical well wall formed by a plurality of sand blocking piles to form a well shaft with a certain height;
d. processing a permanent support on the inner side of the sand blocking pile by adopting concrete;
e. and (d) repeating the steps a to d below the processed permanent support until the construction of the shaft in the quicksand layer is completed.
In the shaft tunneling construction method for the over-thin quicksand layer, in the process of excavating quicksand in the shaft, if the quicksand outside the shaft flows into the shaft from the gap between the adjacent sand blocking piles, sand blocking objects are filled in the gap between the adjacent sand blocking piles to prevent the quicksand outside the shaft from flowing into the shaft.
In the shaft tunneling construction method for the over-thin quicksand layer, the included angle between the sand blocking pile and the shaft axis is 5 degrees.
In the shaft tunneling construction method for the thin quicksand layer, the sand blocking object is straw.
According to the shaft tunneling construction method for the over-thin quicksand layer, the sand blocking pile is a channel steel.
The invention utilizes the sand blocking piles and the concrete to construct supports on the well wall layer by layer, prevents the sand flowing out of the well from flowing into the well, and compared with the traditional freezing method and the drilling method, the invention not only can ensure the normal operation of the shaft construction, but also can greatly improve the construction efficiency and reduce the construction cost, and is particularly suitable for excavating the shaft in a thin sand flowing layer.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
Figure 1 is a cross-sectional view of a shaft excavated by the present method;
fig. 2 is a sectional view a-a.
The reference numbers in the figures are as follows: 1. concrete, 2, sand blocking piles, 3 and a well wall.
Detailed Description
The invention provides a shaft tunneling construction method for passing through a thin flowing sand layer. The method comprises the steps of excavating a water pit to collect water gushing from a working surface in a centralized manner, discharging the water gushing by a pump to reduce the water level, driving sand blocking piles 2 made of channel steel into a sand layer at a certain angle deviated from the outside of a shaft of the shaft, forming a circular shaft wall by the channel steel connected with each other to form a forepoling, excavating sand flowing in the shaft, filling partial gaps in the channel steel connected with each other by straws in the excavating process to prevent the sand flowing out of the shaft from flowing into the shaft, and adopting concrete (concrete) to carry out permanent shoring in time after the shaft with a certain height is formed.
The method comprises the following specific steps:
1. when the construction is carried out on a quicksand layer, firstly, a water pit is dug to collect water gushing from the working surface in a centralized way, and the water gushing is discharged by a pump to reduce the water level.
2. And then, along the contour line of the shaft of the vertical shaft, a plurality of sand blocking piles 2 formed by 16 a-shaped channel steel with the length of 2.0m are obliquely and outwards driven into a sand layer, the included angle between the sand blocking piles 2 and the shaft axis of the vertical shaft is 5 degrees, and 200-300 mm outcrops are left at the upper ends of the channel steel to play a role in supporting the wall of the concrete supporting shaft. The lower end of the 16a channel steel is pointed, so that a flowing sand layer can be effectively tamped.
3. And after the first channel steel is constructed, excavating is started, partial gaps in the middle of the adjacent channel steels are filled with straws, the excavating and the filling are carried out simultaneously, and the excavating is stopped when the excavating depth reaches 1.5 m.
4. And after a shaft with the depth of 1.5m is formed, concrete is adopted for permanent support in time.
The above construction process is a cycle. This cycle is repeated until the wellbore has penetrated the quicksand layer.
Compared with a freezing method or a drilling method, the method can simplify the construction process, shorten the construction period, greatly reduce the construction cost and realize economic, quick and safe construction under the condition of the thin quicksand stratum.

Claims (5)

1. A vertical shaft tunneling construction method for passing through a thin quicksand layer is characterized by comprising the following steps:
a. digging a water pit at a construction site, collecting water gushing from a working surface in a centralized manner, and discharging the water gushing out by using a pump to reduce the water level of the working surface;
b. a plurality of sand blocking piles (2) arranged around a shaft of a vertical shaft are driven into a flowing sand layer in a direction deviating from the outer side of the shaft, so that the plurality of sand blocking piles (2) form a cylindrical shaft wall with a thin upper part and a thick lower part;
c. excavating the quicksand on the inner side of a cylindrical well wall formed by a plurality of sand blocking piles (2) to form a shaft with a certain height;
d. processing a permanent support on the inner side of the sand blocking pile (2) by adopting concrete (1);
e. and (d) repeating the steps a to d below the processed permanent support until the construction of the shaft in the quicksand layer is completed.
2. A shaft excavation construction method for a through-thin quicksand layer as claimed in claim 1, characterized in that during excavation of quicksand in the shaft, if the quicksand outside the shaft flows into the shaft from the gap between the adjacent sand blocking piles (2), the gap between the adjacent sand blocking piles (2) is filled with sand blocking objects to prevent the flowing sand outside the shaft from flowing into the shaft.
3. A shaft driving construction method for passing through a thin quicksand layer according to claim 1 or 2, characterized in that the angle between the sand blocking pile (2) and the shaft axis is 5 degrees.
4. A method as claimed in claim 3 wherein the sand guard is straw.
5. A shaft excavation construction method for a thin quicksand layer as claimed in claim 4, characterized in that the sand blocking piles (2) are channel steel.
CN201910984022.9A 2019-10-16 2019-10-16 Vertical shaft tunneling construction method for passing through thin quicksand layer Withdrawn CN110847911A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910984022.9A CN110847911A (en) 2019-10-16 2019-10-16 Vertical shaft tunneling construction method for passing through thin quicksand layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910984022.9A CN110847911A (en) 2019-10-16 2019-10-16 Vertical shaft tunneling construction method for passing through thin quicksand layer

Publications (1)

Publication Number Publication Date
CN110847911A true CN110847911A (en) 2020-02-28

Family

ID=69596460

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910984022.9A Withdrawn CN110847911A (en) 2019-10-16 2019-10-16 Vertical shaft tunneling construction method for passing through thin quicksand layer

Country Status (1)

Country Link
CN (1) CN110847911A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111594176A (en) * 2020-07-20 2020-08-28 中国铁建重工集团股份有限公司 Vertical shaft tunneling construction method and vertical shaft structure aiming at gobi geological environment
CN112780279A (en) * 2021-02-26 2021-05-11 兰州有色冶金设计研究院有限公司 Construction method for over-thick large gravel layer of vertical shaft

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1051226A (en) * 1990-12-18 1991-05-08 鹤壁矿务局工程处 Displacement grouting process for aven shaft sinking through quick sand layer
CN201687480U (en) * 2010-08-19 2010-12-29 李明 Vertical shaft penetrating thick soft soil layer integral butting steel protecting tube
JP2016180215A (en) * 2015-03-23 2016-10-13 大成建設株式会社 Water cut-off structure at entrance
JP6432865B2 (en) * 2015-04-27 2018-12-05 株式会社推研 How to collect excavators

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1051226A (en) * 1990-12-18 1991-05-08 鹤壁矿务局工程处 Displacement grouting process for aven shaft sinking through quick sand layer
CN201687480U (en) * 2010-08-19 2010-12-29 李明 Vertical shaft penetrating thick soft soil layer integral butting steel protecting tube
JP2016180215A (en) * 2015-03-23 2016-10-13 大成建設株式会社 Water cut-off structure at entrance
JP6432865B2 (en) * 2015-04-27 2018-12-05 株式会社推研 How to collect excavators

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111594176A (en) * 2020-07-20 2020-08-28 中国铁建重工集团股份有限公司 Vertical shaft tunneling construction method and vertical shaft structure aiming at gobi geological environment
CN112780279A (en) * 2021-02-26 2021-05-11 兰州有色冶金设计研究院有限公司 Construction method for over-thick large gravel layer of vertical shaft

Similar Documents

Publication Publication Date Title
CN106121657B (en) A kind of multifunctional numerical control shaft sinking device and construction method
CN104264689B (en) The construction method that grooving, pore-forming and large diameter pile are replaced by multiple Small Diameter Pile
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN111335306A (en) Rapid construction method for deep and thick hard rock section drilled pile
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN102116028B (en) Method and structure for excavating soil in core tube region based on raft pile supporting
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN110847911A (en) Vertical shaft tunneling construction method for passing through thin quicksand layer
CN1718942A (en) Ground caisson construction technology and ground caisson
CN107524141B (en) Construction method of cast-in-situ bored pile of rock soil foundation
CN114108675B (en) Pile forming method for pile foundation in karst area
CN113216148B (en) Construction method for pile foundation of pressure-bearing underground air-raid shelter collapse section
CN104481408A (en) Pick cylindrical drill suitable for construction of super-large diameter swivel-driven piles and application method thereof
CN105909262B (en) A kind of bored tunnel driving method
CN103334449A (en) Square hole girdling cutter and method for performing holing construction of deep cutting stab-pile wall by utilizing same
CN204225100U (en) The construction equipment of concrete pile
CN215629910U (en) Steel upright pile with reinforced structure
CN108221966A (en) The mountain area deep pile foundation construction method that manually digging hole is combined with impact holing
CN110529042B (en) Pore-forming method for dewatering well
CN210766939U (en) Hydraulic flushing, digging, reaming and sucking equipment for inner support foundation pit engineering
KR101237749B1 (en) Propulsion unit head that is used in shield method
CN210163888U (en) Quick construction structure of major diameter socketed pile
JP4428888B2 (en) Method of draining pressurized water in the ground on the tunnel planning line
KR101337223B1 (en) Apparatus Equipped with Double Casing for Inserting Plastic Drain Board and Process thereof
CN111472804A (en) Construction method for tunnel entrance of river-crossing tunnel with upper soft and lower hard strata in foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20200228