CN110826885A - Electric power engineering cost budget establishing method - Google Patents

Electric power engineering cost budget establishing method Download PDF

Info

Publication number
CN110826885A
CN110826885A CN201911032947.XA CN201911032947A CN110826885A CN 110826885 A CN110826885 A CN 110826885A CN 201911032947 A CN201911032947 A CN 201911032947A CN 110826885 A CN110826885 A CN 110826885A
Authority
CN
China
Prior art keywords
information
module
data
budget
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911032947.XA
Other languages
Chinese (zh)
Inventor
陈贞辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201911032947.XA priority Critical patent/CN110826885A/en
Publication of CN110826885A publication Critical patent/CN110826885A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method for establishing budget of electric power engineering construction cost, and particularly relates to the field of electric power engineering construction cost budget. The invention sets up the correction module, revise it with the self-correcting function of the correction unit, is used for revising, changing through the relevant aspects of data correction procedure construction scale, structural property, apparatus type, the rough calculation of preliminary design is adjusted correspondingly, facilitate users meet the problem can change rapidly in the consulting service of the project cost, make the project cost control more accurate and rational, thus has improved its practicability, compared with prior art, the design is more superior, have better correction function.

Description

Electric power engineering cost budget establishing method
Technical Field
The invention relates to the technical field of electric power engineering cost budgeting, in particular to a method for establishing budget for electric power engineering cost.
Background
The use of electric energy has penetrated all fields of national economy and people's life, becomes the main power form of industry, agriculture, transportation and national defense and the indispensable energy in people's family life, and has been widely applied in aspects such as dragging, lighting, electric heating, electrochemistry and communication. Electrical energy is a product that differs from other types of products in that it cannot be stored. Therefore, the electric energy produced and transmitted by the electric power system consisting of the power plant, the transmission line, the substation and the distribution network at every moment must be consistent with the consumption of the electric energy of the user. This makes power production closely related to national economy and people's life. Even if the power failure occurs in a short time, great harm is brought, and large-area power failure causes great loss to national economy and inconvenience to people's lives. Therefore, care must be taken to ensure a high degree of reliability in the supply of electricity in the planning, design, construction and operation of electrical power engineering, i.e. the engineering involved in the production, transportation, distribution of electrical energy, and in a broad sense also the engineering of electricity as a power and energy source in a variety of fields. Meanwhile, the construction cost budget can be understood when the power transmission and transformation business expansion project is carried out.
However, when the existing electric power engineering cost budget scheme is actually used, since the budget directly processes and analyzes various engineering data, budget data and material quotations, once unexpected data has deviation, the final budget result is affected, and the final budget result cannot be directly modified in the budget process, so that the practicability is reduced.
Disclosure of Invention
In order to overcome the above-mentioned defects in the prior art, embodiments of the present invention provide a method for establishing budget for electric power engineering cost, in which a feedback unit in a correction module is configured to function, and the feedback unit is corrected by using a self-correction function of the correction unit, so as to modify and change the construction scale, structural properties, and device types of the data correction program, and the preliminary design approximate calculation is correspondingly adjusted, thereby facilitating quick modification of problems encountered in the engineering cost consultation service by a user, and enabling the engineering cost to be controlled more accurately and reasonably, thereby improving the practicability thereof.
In order to achieve the purpose, the invention provides the following technical scheme: a method for establishing budget for electric power engineering cost comprises a central processing module, wherein the input end of the central processing module is respectively connected with an information loading module and a market price module, the connecting end of the central processing module is connected with a big data module, the output end of the central processing module is respectively connected with a correction module, a regulation and control module and a display module, the output end of the display module is connected with a printing module, the information loading module comprises an information extraction unit, an information comparison unit and an information classification unit, the correction module comprises a feedback unit and a correction unit, the regulation and control module comprises an upper limit regulation and control unit and a lower limit regulation and control unit, the display module comprises a display unit, and the printing module comprises a printing unit;
the method for establishing budget for the construction cost of the electric power project further comprises the following steps:
s1: loading of data information: storing electronic information generated in the power engineering construction process in a U disk, butting the U disk with a central processing module, and extracting input power engineering construction information by an information loading module;
s2: extracting the information of the material price, wherein the central processing module is in butt joint with the market price module, so that the price information of the material required in the construction cost process of the electric power engineering is extracted;
s3: extracting information of historical data, wherein a large amount of project data, correction data, budget data and settlement data in the cost of the electric power project are stored in a big data module, and a central processing module performs comparison analysis by using the information in the big data module;
s4: correction information: the central processing module is connected with the data correction program and is used for modifying and changing the relevant aspects of the construction scale, the structural property and the equipment type of the data correction program, and the preliminary design approximate calculation is also correspondingly adjusted;
s5: and (3) regulating and controlling the upper limit and the lower limit of the cost budget: setting a deviation threshold value of the construction cost, and generating another two groups of budget results when the deviation value of the construction cost data and the set target data at a certain stage exceeds or is lower than the set deviation threshold value, so as to realize the construction cost management and control of the project;
s6: and displaying the budget information and printing a result, directly displaying the intermediate process data information and the final data information generated according to the steps in the whole process of the electric power engineering cost budget, and printing the result.
In a preferred embodiment, the first step is specifically: when the electronic file information is transmitted to the inside of the information loading module, the information extraction unit can extract a large amount of data information in one step to extract key data information, after the data is extracted, the data is compared by the information comparison unit to remove repeated data information, and then the repeated data information is classified by the information classification unit, so that the information is processed more regularly.
In a preferred embodiment, the second step is specifically: through the regulation and control of the central processing module, the price information of the market price module is directly extracted, and therefore price clearing is carried out.
In a preferred embodiment, the step three is specifically: and the information stored in the big data module is called and contrasted and analyzed through the regulation and control of the central processing module.
In a preferred embodiment, the step four is specifically: when information error occurs, the feedback unit in the correction module can play a role, the operation process is fed back to the previous section, and the self-correction function of the correction unit is utilized to correct the operation process.
In a preferred embodiment, the step five is specifically: when the cost of the electric power project is estimated, a threshold value is set on the standard price, which is respectively an upper limit regulation unit and a lower limit regulation unit, so that another two groups of cost estimation results are formed.
In a preferred embodiment, the display unit in the sixth step is a display screen, and the printing unit is a printer.
The invention has the technical effects and advantages that:
1. according to the invention, the correction module is arranged, the feedback unit in the correction module can play a role, the self-correction function of the correction unit is utilized to correct the correction module, and the correction module is used for modifying and changing the relevant aspects of construction scale, structural property and equipment type through a data correction program, and primary design approximate calculation is also correspondingly adjusted, so that a user can rapidly change problems encountered in engineering cost consultation service, the engineering cost control is more accurate and reasonable, the practicability is improved, and compared with the prior art that the error data cannot be corrected in time, the design is more superior and has a better correction function;
2. according to the invention, the regulation module is arranged, the regulation module is used for setting a threshold value on the standard price, and the threshold value is respectively an upper limit regulation unit and a lower limit regulation unit, so that another two groups of cost budget results are formed, the cost budget results are compared with the cost budget of the middle relative standard, an active guiding function is played on the budget of the power engineering cost, the construction cost can be effectively controlled, and compared with the single budget result in the prior art, the design has comparability.
Drawings
Fig. 1 is an overall block diagram of the present invention.
FIG. 2 is a schematic diagram of the unit of the present invention.
The reference signs are: the system comprises a central processing module 1, an information loading module 2, an information extracting unit 21, an information comparing unit 22, an information classifying unit 23, a market price module 3, a big data module 4, a correcting module 5, a feedback unit 51, a correcting unit 52, a regulating and controlling module 6, an upper limit regulating and controlling unit 61, a lower limit regulating and controlling unit 62, a display module 7, a display unit 71, a printing module 8 and a printing unit 81.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The method for establishing budget according to the construction cost of the electric power engineering shown in the attached figures 1 and 2 comprises a central processing module 1, an information loading module 2, a market price module 3, a big data module 4, a correcting module 5, a regulating module 6, a display module 7 and a printing module 8, wherein the input end of the central processing module 1 is respectively connected with the information loading module 2 and the market price module 3, the connecting end of the central processing module 1 is connected with the big data module 4, the output end of the central processing module 1 is respectively connected with the correcting module 5, the regulating module 6 and the display module 7, the output end of the display module 7 is connected with the printing module 8, the information loading module 2 comprises an information extracting unit 21, an information comparing unit 22 and an information classifying unit 23, the correcting module 5 comprises a feedback unit 51 and a correcting unit 52, the regulating module 6 comprises an upper limit regulating unit 61 and a lower limit regulating unit 62, the display module 7 comprises a display unit 71, and the printing module 8 comprises a printing unit 81;
the method for establishing budget for the construction cost of the electric power project further comprises the following steps:
s1: loading of data information: electronic information generated in the process of electric power engineering construction is stored in a U disk, the U disk is in butt joint with a central processing module 1, and an information loading module 2 is used for extracting input electric power engineering construction information;
s2: extracting the information of the material price, wherein the central processing module 1 is in butt joint with the market price module 3, so that the price information of the material required in the construction cost process of the electric power engineering is extracted;
s3: extracting information of historical data, wherein a large amount of project data, correction data, budget data and settlement data in the cost of the electric power project are stored in the big data module 4, and the central processing module 1 performs comparison analysis by using the information in the big data module;
s4: correction information: the central processing module 1 is connected with the data correction program, and is used for modifying and changing the relevant aspects of the construction scale, the structural property and the equipment type through the data correction program, and the preliminary design approximate calculation is also correspondingly adjusted;
s5: and (3) regulating and controlling the upper limit and the lower limit of the cost budget: setting a deviation threshold value of the construction cost, and generating another two groups of budget results when the deviation value of the construction cost data and the set target data at a certain stage exceeds or is lower than the set deviation threshold value, so as to realize the construction cost management and control of the project;
s6: displaying the budget information and printing a result, directly displaying the intermediate process data information and the final data information generated according to the steps in the whole process of the electric power engineering cost budget, and printing the result;
the first step is specifically as follows: when the electronic file information is transmitted to the information loading module 2, the information extraction unit 21 therein extracts a large amount of data information in one step to extract key data information, after the data is extracted, the information comparison unit 22 is used to compare the extracted data information, so as to remove repeated data information, and then the information is classified by the information classification unit 23, so that the information processing is completed, and the information is more regular;
the second step is specifically as follows: through the regulation and control of the central processing module 1, the price information of the market price module 3 is directly extracted, so that price clearing is carried out;
the third step is specifically as follows: the information stored in the big data module 4 is called and contrasted and analyzed through the regulation and control of the central processing module 1;
the fourth step is specifically as follows: when an information error occurs, the feedback unit 51 in the correction module 5 functions to feed back the calculation process to the previous stage, and the self-correction function of the correction unit 52 is used to correct the calculation process.
The implementation mode is specifically as follows: when the invention is implemented, electronic information generated in the process of electric power engineering construction is stored in the U disk, the U disk is in butt joint with the central processing module 1, when electronic file information is transmitted to the information loading module 2, the information extraction unit 21 extracts a large amount of data information in one step, so that key data information is extracted, after the data is extracted, the data is compared by the information comparison unit 22, so that repeated data information is removed, and then the information is classified by the information classification unit 23, so that the information is processed, and is more regular; then extracting the information of the material price and the information of the historical data;
secondly, the correction module 5 is connected with the central processing module 1, when information error occurs, the feedback unit 51 in the correction module 5 will play a role, the operation process is fed back to the previous section, the correction is carried out by utilizing the self-correction function of the correction unit 52, and the correction is used for carrying out modification and change on the relevant aspects of construction scale, structural property and equipment type through a data correction program, the rough calculation of the primary design is also correspondingly adjusted, so that a user can rapidly change the problem encountered in the engineering cost consultation service, the engineering cost is controlled more accurately and reasonably, and the practicability is improved.
The method for establishing budget according to the construction cost of the electric power engineering shown in the attached drawings 1 and 2 further comprises a regulation and control module 6, wherein the connection end of the regulation and control module 6 is connected with a central processing module 1, and the regulation and control module 6 comprises an upper limit regulation and control unit 61 and a lower limit regulation and control unit 62;
the fifth step is specifically as follows: when the cost of the electric power project is estimated, a threshold value is set on the standard price, namely an upper limit regulation unit 61 and a lower limit regulation unit 62, so that another two groups of cost estimation results are formed;
in the sixth step, the display unit 71 is a display screen, and the printing unit 81 is a printer.
The implementation mode is specifically as follows: in the implementation of the invention, when the regulation and control module 6 carries out the cost budget of the electric power project, a threshold value is set on the standard price, which is respectively the upper limit regulation and control unit 61 and the lower limit regulation and control unit 62, so as to form another two groups of cost budget results, which are compared with the cost budget of the middle relative standard, thereby playing an active guiding role in the cost budget of the electric power project, and effectively controlling the construction cost.
The working principle of the invention is as follows:
referring to the accompanying drawings 1 and 2 of the specification, by arranging the correction module 5, a feedback unit 51 in the correction module 5 can play a role, the operation process is fed back to the previous section, the correction module is corrected by using the self-correction function of the correction unit 52 and is used for modifying and changing the relevant aspects of the construction scale, the structural property and the equipment type through a data correction program, the rough calculation of the primary design is correspondingly adjusted, the problem encountered by a user in the engineering cost consultation service can be rapidly changed, the engineering cost control is more accurate and reasonable, and the practicability of the engineering cost control is improved;
referring to the attached drawings 1 and 2 of the specification, by arranging the regulation and control module 6, the regulation and control module 6 sets a threshold value on the standard price, namely the upper limit regulation and control unit 61 and the lower limit regulation and control unit 62, so that another two groups of cost budget results are formed, and compared with the cost budget of the middle relative standard, the cost budget of the electric power project is guided actively, the construction cost can be controlled effectively, and the embodiment specifically solves the problem that the budget result is single in the prior art.
The points to be finally explained are: first, in the description of the present application, it should be noted that, unless otherwise specified and limited, the terms "mounted," "connected," and "connected" should be understood broadly, and may be a mechanical connection or an electrical connection, or a communication between two elements, and may be a direct connection, and "upper," "lower," "left," and "right" are only used to indicate a relative positional relationship, and when the absolute position of the object to be described is changed, the relative positional relationship may be changed;
secondly, the method comprises the following steps: in the drawings of the disclosed embodiments of the invention, only the structures related to the disclosed embodiments are referred to, other structures can refer to common designs, and the same embodiment and different embodiments of the invention can be combined with each other without conflict;
and finally: the above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that are within the spirit and principle of the present invention are intended to be included in the scope of the present invention.

Claims (7)

1. A method for establishing budget for electric power engineering construction cost comprises a central processing module (1), and is characterized in that: the input end of the central processing module (1) is respectively connected with an information loading module (2) and a market price module (3), the connecting end of the central processing module (1) is connected with a big data module (4), the output end of the central processing module (1) is respectively connected with a correction module (5), a regulation and control module (6) and a display module (7), the output end of the display module (7) is connected with a printing module (8), the information loading module (2) comprises an information extraction unit (21), an information comparison unit (22) and an information classification unit (23), the correction module (5) comprises a feedback unit (51) and a correction unit (52), the regulation and control module (6) comprises an upper limit regulation and control unit (61) and a lower limit regulation and control unit (62), and the display module (7) comprises a display unit (71), the printing module (8) comprises a printing unit (81);
the method for establishing budget for the construction cost of the electric power project further comprises the following steps:
s1: loading of data information: electronic information generated in the power engineering construction process is stored in a U disk, the U disk is in butt joint with a central processing module (1), and an information loading module (2) extracts input power engineering construction information;
s2: extracting material price information, wherein the central processing module (1) is in butt joint with the market price module (3), so that the price information of the material required in the construction cost process of the electric power engineering is extracted;
s3: extracting information of historical data, wherein a large amount of project data, correction data, budget data and settlement data in the cost of the electric power project are stored in the big data module (4), and the central processing module (1) performs comparison analysis by using the information in the big data module;
s4: correction information: the central processing module (1) is connected with the central processing module and is used for modifying and changing related aspects of construction scale, structural properties and equipment types through a data correction program, and the preliminary design approximate calculation is also correspondingly adjusted;
s5: and (3) regulating and controlling the upper limit and the lower limit of the cost budget: setting a deviation threshold value of the construction cost, and generating another two groups of budget results when the deviation value of the construction cost data and the set target data at a certain stage exceeds or is lower than the set deviation threshold value, so as to realize the construction cost management and control of the project;
s6: and displaying the budget information and printing a result, directly displaying the intermediate process data information and the final data information generated according to the steps in the whole process of the electric power engineering cost budget, and printing the result.
2. The method for establishing budget for electric power engineering cost according to claim 1, wherein: the first step is specifically as follows: when the electronic file information is transmitted to the inside of the information loading module (2), the information extraction unit (21) extracts a large amount of data information in one step to extract key data information, after the data is extracted, the data is compared by the information comparison unit (22) to remove repeated data information, and then the repeated data information is classified by the information classification unit (23), so that the information is processed and is more regular.
3. The method for establishing budget for electric power engineering cost according to claim 1, wherein: the second step is specifically as follows: through the regulation and control of the central processing module (1), the price information of the market price module (3) is directly extracted, and therefore price clearing is carried out.
4. The method for establishing budget for electric power engineering cost according to claim 1, wherein: the third step is specifically as follows: and the information stored in the big data module (4) is called and contrasted and analyzed through the regulation and control of the central processing module (1).
5. The method for establishing budget for electric power engineering cost according to claim 1, wherein: the fourth step is specifically as follows: when information error occurs, a feedback unit (51) in the correction module (5) acts to feed back the operation process to the previous stage, and the operation process is corrected by using the self-correction function of the correction unit (52).
6. The method for establishing budget for electric power engineering cost according to claim 1, wherein: the fifth step is specifically as follows: when the electric power project cost is budgeted, a threshold value is set on the standard price, namely an upper limit regulation unit (61) and a lower limit regulation unit (62), so that another two groups of cost budgeted results are formed.
7. The method for establishing budget for electric power engineering cost according to claim 1, wherein: and the display unit (71) in the sixth step is a display screen, and the printing unit (81) is a printer.
CN201911032947.XA 2019-10-28 2019-10-28 Electric power engineering cost budget establishing method Pending CN110826885A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911032947.XA CN110826885A (en) 2019-10-28 2019-10-28 Electric power engineering cost budget establishing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911032947.XA CN110826885A (en) 2019-10-28 2019-10-28 Electric power engineering cost budget establishing method

Publications (1)

Publication Number Publication Date
CN110826885A true CN110826885A (en) 2020-02-21

Family

ID=69550922

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911032947.XA Pending CN110826885A (en) 2019-10-28 2019-10-28 Electric power engineering cost budget establishing method

Country Status (1)

Country Link
CN (1) CN110826885A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111626788A (en) * 2020-05-30 2020-09-04 阶梯项目咨询有限公司 Engineering cost management system
CN114116756A (en) * 2022-01-26 2022-03-01 四川野马科技有限公司 Engineering cost data correction system and method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105930931A (en) * 2016-04-22 2016-09-07 国网浙江省电力公司经济技术研究院 Electric power engineering cost management method
CN105956788A (en) * 2016-05-24 2016-09-21 国家电网公司 Dynamic management control method for cost of power transmission and transformation project
KR101761686B1 (en) * 2017-03-31 2017-07-31 (주)하모니앤유나이티드 Real time predicting system for energy management system using machine learning
CN109118069A (en) * 2018-07-27 2019-01-01 重庆工程职业技术学院 A kind of management method of project progress and cost management system
CN109858706A (en) * 2019-02-21 2019-06-07 蔡小青 A kind of project cost data management system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105930931A (en) * 2016-04-22 2016-09-07 国网浙江省电力公司经济技术研究院 Electric power engineering cost management method
CN105956788A (en) * 2016-05-24 2016-09-21 国家电网公司 Dynamic management control method for cost of power transmission and transformation project
KR101761686B1 (en) * 2017-03-31 2017-07-31 (주)하모니앤유나이티드 Real time predicting system for energy management system using machine learning
CN109118069A (en) * 2018-07-27 2019-01-01 重庆工程职业技术学院 A kind of management method of project progress and cost management system
CN109858706A (en) * 2019-02-21 2019-06-07 蔡小青 A kind of project cost data management system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
赫桂梅: "《建筑工程估价》", 3 February 2019 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111626788A (en) * 2020-05-30 2020-09-04 阶梯项目咨询有限公司 Engineering cost management system
CN114116756A (en) * 2022-01-26 2022-03-01 四川野马科技有限公司 Engineering cost data correction system and method thereof

Similar Documents

Publication Publication Date Title
CN110826885A (en) Electric power engineering cost budget establishing method
CN111612412A (en) Intelligent processing method device and system for reinforcing steel bar
Berredo et al. Decision making in fuzzy environment and multicriteria power engineering problems
CN103678447A (en) Multivariate transaction classification
TWI266999B (en) Production system and production method
Hinojosa et al. Improving the mathematical formulation of security-constrained generation capacity expansion planning using power transmission distribution factors and line outage distribution factors
Giannelos et al. Option value of Soft Open Points in distribution networks
Fathi et al. Mathematical modeling of sustainable supply chain networks under uncertainty and solving it using metaheuristic algorithms
Nunes et al. Multi‐stage co‐planning framework for electricity and natural gas under high renewable energy penetration
CN107146165B (en) Distribution network planning data management method and system
Yang et al. Analysis of batch ordering inventory models with setup cost and capacity constraint
Branch et al. Optimum network reconfiguration to improve power quality and reliability in distribution system
Wang et al. On Nash equilibria in duopolistic power markets subject to make-whole uplift
CN111340312A (en) RNN (radio network) -based method for predicting material purchasing demand
CN109754162A (en) Single data processing method and device are enabled for generating industrial part work
CN115358821A (en) Intelligent recommendation method and system for improving conversion rate of scientific and technological achievements
Wang et al. Blockchain-Based Distributed Reputation for a Cap-and-Trade Carbon Emission System
CN103903193A (en) Power supporting system and method
CN104766179A (en) Maintenance method and system for substitute materials
CN102541856B (en) BOM (bill of material) batch sending method and device
Peng et al. Comparative research on operation models of reverse logistics
Jin et al. Research on allocation of gross electromagnetic pollution emission right in power quality markets
Ejeh et al. A flexible energy storage dispatch strategy for day-ahead market trading
Viñán et al. Optimization of the implementation design of distributed energy resources in micro-grids
Gaston et al. How an export boom affects unemployment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200221