CN110748171A - Construction method of steel-concrete assembled building - Google Patents

Construction method of steel-concrete assembled building Download PDF

Info

Publication number
CN110748171A
CN110748171A CN201910978692.XA CN201910978692A CN110748171A CN 110748171 A CN110748171 A CN 110748171A CN 201910978692 A CN201910978692 A CN 201910978692A CN 110748171 A CN110748171 A CN 110748171A
Authority
CN
China
Prior art keywords
steel pipe
steel
pipe column
concrete
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910978692.XA
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Tianbang Jucheng Technology Co Ltd
Original Assignee
Beijing Tianbang Jucheng Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Tianbang Jucheng Technology Co Ltd filed Critical Beijing Tianbang Jucheng Technology Co Ltd
Priority to CN201910978692.XA priority Critical patent/CN110748171A/en
Publication of CN110748171A publication Critical patent/CN110748171A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2406Connection nodes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a construction method of a steel-concrete assembly type building, which comprises the following steps: pre-installing a connecting piece on the steel pipe column; constructing a foundation, namely excavating an independent foundation on a flat field; constructing a main body structure; hoisting the steel pipe beam and connecting the steel pipe beam with the connecting piece; repeating the steps until the assembly of the first layer of the steel pipe beam and the frame of the steel pipe column is completed; laying a mounting floor slab on the upper surface of the steel pipe beam, and pouring concrete of the steel pipe beam, the floor slab and the steel pipe column after the laying is finished; and repeating the process to complete the construction of the multilayer main body structure. According to the construction method of the steel-concrete assembly type building, the construction efficiency is improved, and the bearing capacity and the seismic performance of the building can be improved. Moreover, by adopting the construction method of the steel-concrete assembly type building, the waste materials of a construction site can be reduced, and the energy is saved and the environment is protected.

Description

Construction method of steel-concrete assembled building
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a construction method of a steel-concrete assembly type building.
Background
The construction mode of the construction industry at the present stage still takes the site operation as the main thing to lead to that intensity of labour is high, the job site is in disorder, rubbish waste material is many, the big scheduling problem of environmental injury, and current building is reinforced concrete structure mostly, and the bearing capacity is relatively poor and the shock resistance is lower.
Disclosure of Invention
The present invention is directed to solving at least one of the problems of the prior art. Therefore, one object of the present invention is to provide a construction method for a steel-concrete assembly type building, which enables the building to have higher bearing capacity and strong seismic performance, facilitates the installation of columns and beams, and greatly improves the construction efficiency.
The construction method of the steel-concrete assembly type building comprises the following steps: step one, preassembling a connecting piece on a steel pipe column; step two, constructing a foundation, namely excavating an independent foundation on a flat field, reserving a hole in the foundation, wherein the shape of the hole is matched with that of the steel pipe column, and the size of the hole is larger than that of the steel pipe column; thirdly, constructing a main body structure, namely placing the steel pipe column into the hole, and pouring concrete around the steel pipe column; hoisting the steel pipe beam and connecting the steel pipe beam with the connecting piece; step five, repeating the step one to the step four until the assembly of the first layer of the steel pipe beam and the frame of the steel pipe column is completed; step six, laying and installing a floor slab on the upper surface of the steel pipe beam, and pouring concrete of the steel pipe beam, the floor slab and the steel pipe column after laying is finished; seventhly, repeating the process to complete the construction of the multilayer main body structure; in the main structure construction process, an inner plate and an outer plate of a cement reinforced plate are respectively arranged between an upper layer and a lower layer of adjacent steel pipe beams, door and window openings are reserved, and then outer wall foamed concrete pouring is carried out.
According to the construction method of the steel-concrete assembly type building, disclosed by the embodiment of the invention, the connecting piece is preassembled on the steel pipe column, and then foundation construction and main structure construction are carried out, so that the site construction is simple, convenient and quick, the influence of a construction site is small, the construction period is shortened, the construction efficiency is improved, and the bearing capacity and the anti-seismic performance of the building can be improved. Moreover, by adopting the construction method of the steel-concrete assembly type building, the waste materials of a construction site can be reduced, and the energy is saved and the environment is protected.
According to some embodiments of the invention, the connectors comprise a primary beam connector and a secondary beam connector, and when pre-installing the connectors on the steel pipe column, the method comprises the steps of: cutting notches and machining reinforcing holes in the steel pipe column and the main beam connecting piece; the main beam connecting piece penetrates through the notch and is fixed on the steel pipe column; the secondary beam connecting piece penetrates through the notch in the steel pipe column and the notch in the main beam connecting piece and is fixed on the steel pipe column.
According to some embodiments of the invention, the slots are located on the sides of the steel pipe column, and two slots are formed on each side of the steel pipe column.
According to some embodiments of the invention, the steel pipe column is formed with an operation hole to extend the secondary beam connection into the notch of the primary beam connection.
According to some embodiments of the invention, the handling hole is a round hole, an oblong hole or an elliptical hole.
According to some embodiments of the invention, the notch is a C-shaped notch, and the primary beam connection and the secondary beam connection are both C-shaped plates.
According to some embodiments of the invention, the steel tubular beam is riveted, welded or bolted to the connection piece.
According to some embodiments of the invention, after the first layer of the steel pipe girders and the frame of the steel pipe column are assembled, the reinforcing ribs are inserted into the reinforcing holes, and then the floor slab is laid and installed on the upper surface of the steel pipe girders, so that the reinforcing ribs are located between the steel pipe girders and the floor slab.
According to some embodiments of the present invention, the steel pipe girder has a casting hole formed on an upper surface thereof, and the concrete is poured into the steel pipe girder from the casting hole.
According to some embodiments of the invention, an expanding agent is added to the concrete.
Additional aspects and advantages of the invention will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the invention.
Drawings
The above and/or additional aspects and advantages of the present invention will become apparent and readily appreciated from the following description of the embodiments, taken in conjunction with the accompanying drawings of which:
FIG. 1 is a schematic structural view of a steel pipe column and a connector according to an embodiment of the present invention;
FIG. 2 is a schematic view of a steel tubular beam according to an embodiment of the present invention;
FIG. 3 is a front view of an assembly of a steel pipe column and a steel pipe beam according to an embodiment of the present invention;
FIG. 4 is a top view of the assembly of the steel pipe column and the steel pipe beam shown in FIG. 3;
FIG. 5 is a front view showing the assembly of a steel pipe column and a steel pipe beam according to another embodiment of the present invention;
FIG. 6 is a plan view of the assembly of the steel pipe column and the steel pipe beam shown in FIG. 5;
FIG. 7 is a front view of an assembly of a steel pipe column and a steel pipe beam according to still another embodiment of the present invention;
fig. 8 is a plan view of the steel pipe column and the steel pipe beam shown in fig. 7 assembled together.
Reference numerals:
1: steel pipe columns; 11: reinforcing holes; 12: an operation hole;
2: a steel tubular beam; 21: pouring holes; 3: a connecting member; 4: a notch.
Detailed Description
Embodiments of the present invention will be described in detail below, the embodiments described with reference to the drawings being illustrative, and the embodiments of the present invention will be described in detail below.
A construction method of a steel-concrete fabricated building according to an embodiment of the present invention will be described with reference to fig. 1 to 8.
As shown in fig. 1 to 8, a construction method of a steel-concrete assembly type building according to an embodiment of the present invention includes the steps of:
step one, preassembling a connecting piece 3 on the steel pipe column 1. This step is generally performed in a factory, whereby the prefabricated steel pipe column 1 and the coupling 3 can be directly installed at the time of on-site construction, thereby greatly improving the construction efficiency of the entire fabricated building.
And step two, constructing a foundation, namely excavating an independent foundation on a flat site, reserving a hole in the foundation, wherein the shape of the hole is matched with that of the steel pipe column 1, and the size of the hole is larger than that of the steel pipe column 1.
And step three, constructing a main structure, namely placing the steel pipe column 1 into the hole, and pouring concrete around the steel pipe column 1. Through this step, the steel pipe column 1 can be fixed and installed.
And step four, hoisting the steel pipe beam 2 and connecting the steel pipe beam with the connecting piece 3. For example, referring to fig. 3 to 8 in combination with fig. 1, after the steel pipe column 1 is fixedly installed, the steel pipe beam 2 is hoisted by a tool such as a crane, and both ends of the steel pipe beam 2 are connected to the connectors 3 of the two steel pipe columns 1, respectively. This procedure can connect the steel-pipe column 1 and the steel-pipe beam 2.
And step five, repeating the step one to the step four until the assembly of the first layer of steel pipe beam 2 and the frame of the steel pipe column 1 is completed.
And sixthly, laying and installing a floor slab on the upper surface of the steel pipe beam 2, and pouring concrete of the steel pipe beam 2, the floor slab and the steel pipe column 1 after laying is finished.
And seventhly, repeating the process to complete the construction of the multilayer main body structure. Through the steps S6 and S7, after the concrete pouring of the first layer of steel pipe beam 2, the floor slab and the steel pipe column 1 is completed, the construction of the multi-layer main body structure can be performed in a short time without waiting for the concrete to be poured to solidify, so that the construction efficiency is further improved, and the construction period is shortened.
In the main structure construction process, an inner plate and an outer plate of the cement reinforced plate are respectively arranged between the upper layer and the lower layer of the steel pipe beam 2 which are adjacent to each other, a door and window opening is reserved, and then outer wall foaming concrete pouring is carried out. Therefore, the integrity of the concrete outer wall can be ensured, and the concrete outer wall has the advantages of light dead weight and good heat insulation performance.
According to the construction method of the steel-concrete assembly type building, the connecting piece 3 is preassembled on the steel pipe column 1, and then foundation construction and main structure construction are carried out, so that the site construction is simple, convenient and quick, the influence of a construction site is small, the construction period is shortened, the construction efficiency is improved, and the bearing capacity and the seismic performance of the building can be improved. Moreover, by adopting the construction method of the steel-concrete assembly type building, the waste materials of a construction site can be reduced, and the energy is saved and the environment is protected.
In some embodiments of the invention, referring to fig. 1, the connections 3 comprise primary beam connections and secondary beam connections. The main beam connecting piece can connect the main steel pipe beam 2 with the steel pipe column 1, and the secondary beam connecting piece can connect the secondary steel pipe beam 2 with the main steel pipe beam 2 and the secondary steel pipe beam 2 with the steel pipe column 1. The width of the main steel pipe beam 2 is larger than that of the secondary steel pipe beam 2, the secondary steel pipe beam 2 transmits load to the main steel pipe beam 2, and the main steel pipe beam 2 plays a role in bearing and transmitting load.
When the connecting piece 3 is preassembled on the steel pipe column 1, the method comprises the following steps:
and S1, cutting notches 4 on the steel pipe column 1 and the main beam connector and machining a reinforcing hole 11.
S2, the main beam connecting piece passes through the notch 4 and is fixed on the steel pipe column 1. In this step, when the main beam connector is located at a predetermined position, the main beam connector and the edge of the notch 4 may be welded, so as to fix the main beam connector to the steel pipe column 1.
And S3, the secondary beam connecting piece penetrates through the notch 4 on the steel pipe column 1 and the notch 4 on the main beam connecting piece to be fixed on the steel pipe column 1.
In the above process, the size of the notch 4 and the mounting accuracy of the connector 3 can be ensured by the master form. Thus, the preassembly of the steel pipe column 1 and the connector 3 can be achieved and the structural stability of the steel pipe column 1 and the connector 3 can be ensured by the steps S1, S2, and S3.
Further, referring to fig. 1, 3-8, the notches 4 are located at the sides of the steel pipe column 1, and two notches 4 are formed at each side of the steel pipe column 1. From this, through above-mentioned setting, can realize firm fixed of girder connecting piece and secondary beam connecting piece to can increase the structural stability of whole steel reinforced concrete assembly type structure.
Optionally, as shown in fig. 1, the steel pipe column 1 is formed with an operation hole 12 to extend the secondary beam connection into the notch 4 of the primary beam connection. For example, when cutting the notch 4 on the steel pipe column 1, the position of the notch 4 on the steel pipe column 1 is specifically calculated according to actual conditions, when the distance between the notch 4 on the steel pipe column 1 and the two ends of the steel pipe column 1 is short, an operator can weld the notch 4 on the secondary beam connecting piece and the main beam connecting piece through the upper end and the lower end of the steel pipe column 1, when the distance between the notch 4 on the steel pipe column 1 and the two ends of the steel pipe column 1 is long, the operator can operate the hole 12 on the steel pipe column 1, so that the operator can weld the notch 4 on the secondary beam connecting piece and the main beam connecting piece through the operation hole 12. So set up, simple structure, convenient operation.
Alternatively, the operation hole 12 may be a circular hole (not shown), an oblong hole (shown in fig. 1), an elliptical hole (not shown), or the like. Therefore, the structural strength of the steel pipe column 1 can be ensured while the condition that the working personnel conveniently weld the notches 4 on the secondary beam connecting piece and the main beam connecting piece is ensured.
Alternatively, referring to fig. 1, 3-8, the notch 4 is a C-shaped notch and the primary and secondary beam connections are both C-shaped plates. From this, through making girder connection spare and secondary beam connection spare be the C template, girder connection spare and secondary beam connection spare's simple structure, and be C type notch through making notch 4, when making connecting piece 3 can pass notch 4, guaranteed steel-pipe column 1's structural strength.
Alternatively, the tubular steel girders 2 are riveted, welded or bolted with the connecting pieces 3. Therefore, the structure is simple, and the firm connection between the steel pipe beam 2 and the connecting piece 3 can be realized.
In some embodiments of the present invention, referring to fig. 3, 5 and 7, after the first-layer steel pipe girders 2 are assembled with the frame of the steel pipe column 1, the reinforcing bars are inserted into the reinforcing holes 11, and then the floor slab is installed on the upper surface of the steel pipe girders 2 such that the reinforcing bars are located between the steel pipe girders 2 and the floor slab. From this, can further guarantee the structural strength and the structural stability of steel tubular beams 2 and steel-pipe column 1's frame, make the structure of whole steel reinforced concrete assembly type building more stable, the anti-seismic performance is better.
In some embodiments of the present invention, referring to fig. 2, 4, 6 and 8, the steel tubular girder 2 is formed with a casting hole 21 on an upper surface thereof, and concrete is poured into the steel tubular girder 2 from the casting hole 21. From this, through setting up pouring hole 21, can realize the concrete placement of steel tubular beam 2, make steel tubular beam 2 can bear bigger load, improve the structural strength of whole steel reinforced concrete prefabricated building.
Optionally, an expanding agent is added to the concrete. Therefore, gaps can be prevented from being generated between the steel pipe column 1 or the steel pipe beam 2 and the concrete structure after concrete is solidified, and the structural strength of the steel pipe column 1 and the steel pipe beam 2 is guaranteed.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "axial", "radial", "circumferential", and the like, indicate orientations and positional relationships based on the orientations and positional relationships shown in the drawings, and are used merely for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the device or element so referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the description herein, references to the description of the term "one embodiment," "some embodiments," "an illustrative embodiment," "an example," "a specific example," or "some examples" or the like mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example.
While embodiments of the invention have been shown and described, it will be understood by those of ordinary skill in the art that: various changes, modifications, substitutions and alterations can be made to the embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the claims and their equivalents.

Claims (10)

1. The construction method of the steel-concrete assembly type building is characterized by comprising the following steps of:
step one, preassembling a connecting piece on a steel pipe column;
step two, constructing a foundation, namely excavating an independent foundation on a flat field, reserving a hole in the foundation, wherein the shape of the hole is matched with that of the steel pipe column, and the size of the hole is larger than that of the steel pipe column;
thirdly, constructing a main body structure, namely placing the steel pipe column into the hole, and pouring concrete around the steel pipe column;
hoisting the steel pipe beam and connecting the steel pipe beam with the connecting piece;
step five, repeating the step one to the step four until the assembly of the first layer of the steel pipe beam and the frame of the steel pipe column is completed;
step six, laying and installing a floor slab on the upper surface of the steel pipe beam, and pouring concrete of the steel pipe beam, the floor slab and the steel pipe column after laying is finished;
seventhly, repeating the process to complete the construction of the multilayer main body structure;
in the main structure construction process, an inner plate and an outer plate of a cement reinforced plate are respectively arranged between an upper layer and a lower layer of adjacent steel pipe beams, door and window openings are reserved, and then outer wall foamed concrete pouring is carried out.
2. The construction method of a steel-concrete assembly type building according to claim 1, wherein the connection members include a main beam connection member and a sub beam connection member,
when the connecting piece is preassembled on the steel pipe column, the method comprises the following steps:
cutting notches and machining reinforcing holes in the steel pipe column and the main beam connecting piece;
the main beam connecting piece penetrates through the notch and is fixed on the steel pipe column;
the secondary beam connecting piece penetrates through the notch in the steel pipe column and the notch in the main beam connecting piece and is fixed on the steel pipe column.
3. The construction method of a steel-concrete fabricated building according to claim 2, wherein the notches are formed at side surfaces of the steel pipe column, and two notches are formed at each of the side surfaces of the steel pipe column.
4. The construction method of the steel-concrete assembly type building according to claim 2, wherein an operation hole is formed in the steel pipe column to extend the secondary beam connection member into the notch of the primary beam connection member.
5. The construction method of the steel-concrete assembly building according to claim 4, wherein the operation hole is a circular hole, an oblong hole or an elliptical hole.
6. The construction method of the steel-concrete assembly building according to any one of claims 2 to 5, wherein the notch is a C-shaped notch, and the main beam connection member and the secondary beam connection member are both C-shaped plates.
7. The construction method of the steel-concrete assembly type building according to claim 1, wherein the steel pipe girder is riveted, welded or bolted to the connecting member.
8. The method of constructing a steel-concrete assembly building according to claim 2, wherein after the first floor of the steel pipe girders is assembled with the frame of the steel pipe column, reinforcing bars are inserted into the reinforcing holes, and then the floor slab is installed by being laid on the upper surface of the steel pipe girders so that the reinforcing bars are positioned between the steel pipe girders and the floor slab.
9. The construction method of the steel-concrete fabricated building according to claim 1, wherein a casting hole is formed on an upper surface of the steel tubular beam, and the concrete is injected into the steel tubular beam from the casting hole.
10. The method of constructing a steel-concrete fabricated building according to claim 1, wherein an expansive agent is added to the concrete.
CN201910978692.XA 2019-10-15 2019-10-15 Construction method of steel-concrete assembled building Pending CN110748171A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910978692.XA CN110748171A (en) 2019-10-15 2019-10-15 Construction method of steel-concrete assembled building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910978692.XA CN110748171A (en) 2019-10-15 2019-10-15 Construction method of steel-concrete assembled building

Publications (1)

Publication Number Publication Date
CN110748171A true CN110748171A (en) 2020-02-04

Family

ID=69278377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910978692.XA Pending CN110748171A (en) 2019-10-15 2019-10-15 Construction method of steel-concrete assembled building

Country Status (1)

Country Link
CN (1) CN110748171A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112064786A (en) * 2020-07-31 2020-12-11 浙江双友物流器械股份有限公司 Frame structure building
CN112064779A (en) * 2020-07-31 2020-12-11 浙江双友物流器械股份有限公司 Frame structure building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013204306A (en) * 2012-03-28 2013-10-07 Ohbayashi Corp Column-beam joining structure
CN105569191A (en) * 2016-01-23 2016-05-11 安徽鸿路钢结构(集团)股份有限公司 Steel-encased concrete composite beam-steel pipe column connection joint
CN105649360A (en) * 2015-12-29 2016-06-08 山东远博建筑科技有限公司 Integral assembling type building system and installing method
CN105756198A (en) * 2016-03-28 2016-07-13 文登蓝岛建筑工程有限公司 Beam and center post connecting piece for prefabricated building
CN205476071U (en) * 2016-02-04 2016-08-17 李新华 Steel structure support structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013204306A (en) * 2012-03-28 2013-10-07 Ohbayashi Corp Column-beam joining structure
CN105649360A (en) * 2015-12-29 2016-06-08 山东远博建筑科技有限公司 Integral assembling type building system and installing method
CN105569191A (en) * 2016-01-23 2016-05-11 安徽鸿路钢结构(集团)股份有限公司 Steel-encased concrete composite beam-steel pipe column connection joint
CN205476071U (en) * 2016-02-04 2016-08-17 李新华 Steel structure support structure
CN105756198A (en) * 2016-03-28 2016-07-13 文登蓝岛建筑工程有限公司 Beam and center post connecting piece for prefabricated building

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112064786A (en) * 2020-07-31 2020-12-11 浙江双友物流器械股份有限公司 Frame structure building
CN112064779A (en) * 2020-07-31 2020-12-11 浙江双友物流器械股份有限公司 Frame structure building

Similar Documents

Publication Publication Date Title
CN107989227B (en) Assembled steel reinforced concrete shear wall structure and preparation and installation methods thereof
CN211037273U (en) Steel joint is connected to assembled concrete structure primary and secondary roof beam
CN108678220B (en) Concrete shear wall with integrally installed reinforcing steel bar templates
CN107989228B (en) Prefabricated steel reinforced concrete shear wall structure and preparation and installation methods thereof
CN110173076B (en) Structural system comprising high-seismic-resistance welding-free concrete filled steel tube column and construction method thereof
CN109403545B (en) High-assembly-rate steel pipe concrete frame structure system and connection method
CN111535498B (en) Prefabricated stiff concrete shear wall plate with steel beam connecting keys, assembled stiff concrete shear wall and manufacturing method
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
CN110748171A (en) Construction method of steel-concrete assembled building
CN107447873B (en) Device for connecting prefabricated laminated connecting beam and prefabricated shear wall and installation method
CN106894544B (en) Embedded single-layer steel plate-concrete combined shear wall and construction method thereof
KR100939970B1 (en) A method of constructing a complex girder and its structure
CN106592821B (en) Side-standing type integral forming structure and method of shear steel plate and one side reinforcing mesh
CN214364235U (en) Assembled steel sheet compound shear wall body structure
CN114108808B (en) PVC-FRP pipe concrete column and concrete superposed beam combined structure with adjustable connecting node and installation method thereof
CN105804262A (en) Energy consumption support and assembly type concrete framework dual energy consumption node and assembly method
CN210508035U (en) Assembly type combination beam secondary beam structure
CN212053436U (en) Strenghthened type precast concrete wallboard and connection structure with from structure of taking one's place
CN210288825U (en) Assembled and cast-in-situ combined beam plate structure
CN110029729B (en) Splicing joint of prefabricated reinforced concrete main beam and secondary beam and construction method
CN210713245U (en) Connecting mechanism of beam-column joint in RCS combined structure
CN112726942A (en) Concrete prefabricated shear wall structure with sandwich steel plates and construction method
CN217175198U (en) Connecting structure of steel bar truss floor bearing plate and reinforced concrete wall
CN219508818U (en) Prefabricated girder component with secondary girder connection node
CN210685159U (en) Assembled stride no post structure arched plate greatly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200204