CN110747878A - Construction method of tire template system - Google Patents

Construction method of tire template system Download PDF

Info

Publication number
CN110747878A
CN110747878A CN201910969288.6A CN201910969288A CN110747878A CN 110747878 A CN110747878 A CN 110747878A CN 201910969288 A CN201910969288 A CN 201910969288A CN 110747878 A CN110747878 A CN 110747878A
Authority
CN
China
Prior art keywords
steel bar
concrete
square frame
reinforcing
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910969288.6A
Other languages
Chinese (zh)
Inventor
周学军
王维才
王维金
庞一鸣
吕志鹏
杨玉飞
王伟
王俊
张星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Huajian Construction Co Ltd
Original Assignee
Jiangsu Huajian Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huajian Construction Co Ltd filed Critical Jiangsu Huajian Construction Co Ltd
Priority to CN201910969288.6A priority Critical patent/CN110747878A/en
Publication of CN110747878A publication Critical patent/CN110747878A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

The invention provides a construction method of a tire template system, which comprises 10 steps of prefabricating a tire template and the like, wherein the prefabricating of the tire template comprises the step S11 of respectively taking four steel bars with preset lengths and welding the four steel bars into a second rectangular square frame; step S12, taking the first steel bar and the second steel bar, and welding the first steel bar and the second steel bar to form a steel bar mesh; step S13, welding a steel bar mesh inside the second rectangular square frame; step S14, pouring concrete into the second rectangular square frame; step S15, vibrating and tamping the concrete; step S16, rubbing and pressing the surface of the concrete after the concrete is initially set; and step S17, after the concrete is finally set, covering and curing the concrete. According to the method, the required tire template can be directly prefabricated on site, then the prefabricated tire template is welded to form the first rectangular square frame, and then the first rectangular square frame is lifted to the preset position by using the lifting equipment, so that the cost of manual carrying is saved.

Description

Construction method of tire template system
Technical Field
The invention relates to the technical field of buildings, in particular to a construction method of a template system.
Background
In the construction of foundation formwork engineering, brick moulding beds, light batten moulding beds and the like are mainly used at home and abroad. The brick masonry is used as a foundation tire template, which is an early and traditional construction technology, the material loss is serious in the construction process, the labor intensity of workers is high, the production efficiency is low, and the construction period is not guaranteed. Later, a construction technology of taking an aerated concrete strip as a basic tire template appears, the aerated concrete strip can be prefabricated in a processing factory, and the problems of heavy mass and inconvenient carrying of a single aerated concrete strip exist. Meanwhile, the aerated concrete batten needs to be cut in the installation process, so that waste and infirm splicing joints are easily caused.
Disclosure of Invention
The invention aims to provide a construction method of a tire template system, which can perform on-site prefabrication of a tire template.
In order to achieve the above object, the construction method provided by the present invention comprises the steps of:
step S1: prefabricating a tire template;
step S2: assembling the tire templates into a first rectangular square frame;
step S3: respectively arranging a lifting ring on four outer corners of the first rectangular frame;
step S4: hanging four lifting hooks on a lifting appliance on corresponding lifting rings respectively;
step S5: hoisting the first rectangular square frame by using a hoisting device;
step S6: marking a marking line on the concrete cushion layer;
step S7: placing the first rectangular box on the concrete cushion layer so that the first rectangular box is overlapped with the marking line;
step S8: inserting a wood purlin into the first rectangular square frame, and fixing the wood purlin by using a support;
step S9: backfilling earthwork around the first rectangular frame;
step S10: after the earthwork backfilling is completed, the supporting pieces and the wood purlin are removed, and waterproof materials are paved inside the first rectangular square frame.
Wherein, step S1 includes the following steps:
step S11: taking four steel bars with preset lengths respectively, and welding the four steel bars into a second rectangular square frame;
step S12: taking a first reinforcing steel bar and a second reinforcing steel bar, and welding the first reinforcing steel bar and the second reinforcing steel bar to form a reinforcing steel bar mesh;
step S13: welding a steel bar mesh inside the second rectangular frame;
step S14: pouring concrete into the second rectangular square frame;
step S15: vibrating and tamping the concrete;
step S16: rubbing and pressing the surface of the concrete after the initial setting of the concrete;
step S17: and after the concrete is finally set, covering and curing the concrete.
According to the scheme, the tire templates can be prefabricated on a construction site. The bed mould board adopts the concrete to make, and bed mould board inside still is provided with the reinforcing bar net piece, has guaranteed the intensity of bed mould board. In the process of earth backfilling, the supporting piece plays a role in stabilizing the forming die plate, so that the forming die plate cannot deform due to overlarge lateral pressure caused by backfilling earth. The forming die plate does not need to be prefabricated in a processing factory, the second rectangular square frame meeting the requirements can be manufactured according to the required specification, and then the required forming die plate can be directly manufactured on site without cutting. Meanwhile, after the tire templates meeting the requirements are prefabricated, the prefabricated tire templates are directly welded to form a first rectangular square frame, and then the first rectangular square frame is lifted to a preset position by using lifting equipment, so that the cost of manual carrying is saved.
Preferably, in the process of performing the step S11, the specification of the steel bar is 50 × 50 × 3mm square steel tube and 50 × 50 × 3mm angle steel, the shape of the steel bar is a straight quadrangular prism, the bottom surface of the straight quadrangular prism is isosceles trapezoid, the width of the steel bar is 1.5mm, the height of the steel bar is 50mm, and the number of base angles of the isosceles trapezoid is 45 °.
Further, in the process of performing the step S11, among the four steel bars, two steel bars have a length equal to the length of the long side of the template, and the other two steel bars have a length equal to the length of the short side of the template.
In the above solution, the length of the steel bar is determined according to the specification of the template to be manufactured. The shape of the moulding bed is rectangular, wherein the length of two steel bars is equal to the length of the short side of the rectangle, and the length of the other two steel bars is equal to the length of the long side of the rectangle.
A further scheme is that in the process of executing the step S12, the specifications of the selected first steel bars and the second steel bars are both Φ 6 mm, the number of the first steel bars and the number of the second steel bars are both more than two, the axes of the first steel bars and the axes of the second steel bars are perpendicular to each other, the distance between every two adjacent first steel bars in the first steel bars is 200mm, and the distance between every two adjacent second steel bars in the second steel bars is 200 mm.
Further, in the step of S13, the mesh of reinforcing bars is welded at an intermediate position inside the second rectangular block, and the distance between the axis of the first reinforcing bar and the bottom surface of the bar is 25 mm.
Still further, in the step of performing S14, the concrete includes water, cement, coarse sand, stone chips, polystyrene particles, and a foaming agent.
Further, in the step of performing S16, the flatness of the concrete surface does not exceed 5 mm.
Further, in the step of S17, the concrete is maintained for at least seven days.
According to a further scheme, before the step S7 is executed, blind holes are formed in the concrete cushion layer on the inner side of the marking line through electric drills, then third steel bars are embedded in the blind holes, the number of the blind holes is more than two, the inner diameter of each blind hole is not smaller than 14mm, the depth of each blind hole is 50-60 mm, the length of each third steel bar is not smaller than 100mm, and the distance between every two adjacent blind holes is 1000 mm.
In the above scheme, the number of the marking lines is four, and the four marking lines enclose a rectangle. The tire template system is formed by welding four tire templates, and the tire templates are arranged in one-to-one correspondence with the marking lines. The blind holes are formed in the inner sides of the marking lines, the third steel bars are embedded into the blind holes and welded at the bottoms of the corresponding tire templates, and the bottom of each tire template is positioned.
In a further scheme, in the process of executing the step S8, the support head on the support member abuts against the middle of the wood balk, so that the wood balk is tightly attached to the inner side wall of the tire template.
In the above scheme, the support member comprises a connecting steel pipe and two support heads, wherein the two support heads are respectively arranged at two ends of the connecting steel pipe along the axial direction. The supporting head is abutted against the middle part of the wood purlin, and pressure is applied to the middle position of the tire template through the wood purlin. When earth backfilling is carried out around the tire template system, the supporting head can offset the lateral pressure of a part of backfill soil to the tire template, and the phenomenon that the mounting quality of the tire template system is influenced due to the fact that the pressure of the backfill soil to the side wall of the tire template is too large is prevented.
Drawings
FIG. 1 is a flow chart of an embodiment of the construction method of the present invention.
FIG. 2 is a flow chart of the present invention for preforming a tire form.
Fig. 3 is a top view of a rectangular box and rebar mesh embodiment of the present invention.
FIG. 4 is a schematic diagram of a prefabricated tire template of the present invention.
FIG. 5 is a schematic structural view of the tire template system of the present invention.
FIG. 6 is a schematic diagram of the lift tire template system of the present invention.
FIG. 7 is a schematic diagram of the tire template mounting system of the present invention.
Fig. 8 is a schematic view of the present invention in which waterproof material is installed.
The invention is further explained with reference to the drawings and the embodiments.
Detailed Description
Referring to fig. 1, the construction method provided by this embodiment includes the following steps: firstly, step S1 is executed to prepare a tire template; then, step S2 is executed to assemble the tire mold plates into a first rectangular block; then, step S3 is executed, and a hanging ring is respectively disposed on four outer corners of the first rectangular box; then, step S4 is executed, and four lifting hooks on the lifting appliance are respectively hung on the corresponding lifting rings; then, step S5 is executed to hoist the first rectangular box by using the hoisting device; then, step S6 is executed to mark a marking line on the concrete cushion; then, step S7 is executed to place the first rectangular box on the concrete cushion layer so that the first rectangular box coincides with the marking line; then, step S8 is executed, a wood purlin is inserted into the first rectangular square block, and the wood purlin is fixed by using a support; next, step S9 is executed to backfill the earth around the first rectangular box; finally, step S10 is executed, and after the earth backfilling is completed, the support and the wood brace are removed, and the waterproof material is laid inside the first rectangular box.
Referring to fig. 2, step S1 includes the steps of: firstly, step S11 is executed, and four steel bars with preset lengths are respectively taken and welded into a second rectangular square frame; then, step S12 is executed, the first steel bar and the second steel bar are taken, and the first steel bar and the second steel bar are welded to form a steel bar mesh; then, step S13 is executed, and a steel mesh is welded inside the second rectangular box; then, step S14 is executed to cast concrete into the second rectangular box; then, step S15 is executed to vibrate and tap the concrete; next, step S16 is executed, and after the concrete is initially set, the surface of the concrete is rubbed and pressed; finally, step S17 is executed, and after the concrete is finally set, the concrete is covered and cured.
Referring to fig. 3 and 4, the second rectangular block 1 is formed by welding four steel bars 11. The steel bar 11 is a square steel pipe of 50X 3mm or an angle steel of 50X 3 mm. The cross section of the square steel pipe is 50 multiplied by 50mm square, and the thickness of the pipe wall is 3 mm. The steel bar can also be formed by welding two pieces of angle steel with the same shape, size and length. Each angle steel comprises two plate bodies which are perpendicular to each other, the width of each plate body is 50mm, and the thickness of each plate body is 3 mm. Each steel bar 11 is in the shape of a straight quadrangular prism, the bottom surface of the straight quadrangular prism is in the shape of an isosceles trapezoid, the width of each steel bar is 1.5mm, the height of each steel bar is 50mm, and the degree of the base angle of each isosceles trapezoid is 45 degrees. Of the four steel bars 11, two steel bars 11 have a length equal to the length of the long side of the template 2, and the other two steel bars 11 have a length equal to the length of the short side of the template 2. The reason why the steel bars 11 are designed in the shape of an isosceles trapezoid is to improve the welding strength between the steel bars 11. When four steel bars 11 are welded to form the second rectangular frame 1, the inclined surfaces between the two steel bars 11 are welded together, so that the strength of the second rectangular frame 1 obtained by welding is higher. And a steel bar mesh is arranged in the second rectangular square frame 1, and comprises a first steel bar 12 and a second steel bar 13 which are perpendicular to each other. The specifications of the first reinforcing steel bar 12 and the second reinforcing steel bar 13 are both phi 6 mm. The number of the first reinforcing bars 12 and the second reinforcing bars 13 is more than two. The distance between every two adjacent first reinforcing steel bars 12 is 200mm, and the distance between every two adjacent second reinforcing steel bars 13 is 200 mm. After the inner frame of the template 2 is prefabricated, concrete is poured into the inner frame to be vibrated, and then the template 2 is manufactured.
In this embodiment, the length of the steel bar 11 is determined according to the specification of the template 2 to be manufactured. The form 2 has a rectangular shape, wherein the lengths of two bars 11 are equal to the length of the short side of the rectangle, and the lengths of the other two bars 11 are equal to the length of the long side of the rectangle. The steel bar net sheet is welded at the middle position inside the second rectangular square frame 1, and the distance between the axis of the first steel bar 12 and the bottom surface of the steel bar 11 is 25 mm. The concrete used to prepare the form 2 includes water, cement, grit, stone chips, polystyrene particles and a foaming agent. In the process of manufacturing the tire formwork 2, the concrete needs to be vibrated and compacted, after the concrete is initially set, the surface of the concrete is pressed, and the flatness of the surface of the concrete is required to be not more than 5mm in the pressing process. And after the concrete is finally set, covering and curing the concrete for at least seven days.
Referring to fig. 5 and 6, the number of the tire mold plates 2 to be prefabricated is four. Firstly, the four tire templates 2 are put into a shaping and fixing assembly mold 3 for assembly, so that the four tire templates 2 are assembled into a rectangular square frame. Then, the intersection of two mutually perpendicular tire templates 2 is welded, and the length of the welding seam is 100 mm. In this way, all the intersections of the four panels 2 are welded, so that the four panels 2 can be assembled into a first rectangular frame. And the four outer corners of the first rectangular frame are respectively provided with a lifting ring 4 with the specification of phi 48.3 multiplied by 3mm and the length of 100mm, and the lifting ring 4 is welded on the outer corners of the first rectangular frame. When the first rectangular box needs to be hoisted, a hoist 5 needs to be used. The spreader 5 includes a fourth steel bar 51 and two fifth steel bars 52, and a lifting ring 53 is provided at the middle of the fourth steel bar 51. Two fifth reinforcing bars 52 are respectively provided at both ends of the fourth reinforcing bar 51, and the middle portion of each fifth reinforcing bar 52 is welded to one end of the fourth reinforcing bar. The two ends of each fifth steel bar 52 are respectively provided with a hook 54, when the first rectangular square frame needs to be lifted, the four hooks 54 are respectively hung on the corresponding lifting rings 4, and then the lifting rings 53 are lifted through the lifting equipment, so that the whole first rectangular square frame can be lifted.
Referring to fig. 7, the concrete pad 6 is marked with four marking lines 7, and the four marking lines 7 form a rectangle. Four tire templates 2 in the tire template system are arranged in one-to-one correspondence with the marking lines 7. The inner side of each marking line 7 is provided with a blind hole (not shown in the figure), and the blind hole is formed by arranging an electric drill on the concrete cushion 6. And a third steel bar 8 is embedded in each blind hole, and the third steel bars 8 are welded at the bottom of the corresponding tire template 2 to play a role in positioning the bottom of the tire template 2. The quantity of the blind hole on each sign line 7 is more than two, and the internal diameter of blind hole is not less than 14mm, and the degree of depth of blind hole is 50 to 60mm, and the length of third reinforcing bar 8 is not less than 100mm, and the distance between two adjacent blind holes is 1000 mm. If the length of the template 2 is within 1000mm, only one third reinforcing steel bar 8 needs to be welded at the bottom of each template 2. If the length of the core plate 2 exceeds 1000mm, two or more third reinforcing bars 8 need to be welded to the bottom of each core plate 2 in order to fix the bottom of the core plate 2 better.
In this embodiment, a wood purlin 9 and a support 10 are further disposed inside the first rectangular square block, and the wood purlin 9 is a wood purlin with a specification of 50 × 100 mm. The support member 10 includes a connecting steel pipe 101 of a diameter of 48.3 mm and two support heads 102, and the two support heads 102 are respectively disposed at both ends of the connecting steel pipe 101. In fig. 7, two wood purlins 9 are arranged on each tire template 2, and the two wood purlins 9 are respectively arranged at positions close to two ends of the tire template 2. Two support heads 102 on the same support 10 abut against the wood balms 9 on the two opposite tire formworks 2 respectively. The supporting head 102 abuts against the middle of the wood purlin 9, so that the wood purlin 9 is tightly attached to the inner side wall of the tire template 2. In order to prevent the mutual interference between the steel connecting pipes 101, the steel connecting pipes 101 of different supporting members 10 are located at different heights. The support head 102 applies pressure to the middle position of the tire mold plate 2 through the wood balk 9. When earth backfilling is performed around the first rectangular frame, the supporting head 102 can counteract the lateral pressure of a part of backfilled soil on the tire template 2, so that the situation that the installation quality of the tire template system is affected due to the fact that the pressure of the backfilled soil on the lateral wall of the tire template 2 is too high is prevented.
Referring to fig. 8, after the earth backfilling is completed around the first rectangular square frame, the supporting members 10 and the wood beams 9 are removed, and the waterproof material 14 is laid inside the tire template system. The waterproof material 14 may be a waterproof paint, and is coated on the inner surface of the tire template system by painting. The waterproofing material 14 may also be a waterproofing membrane that may be applied to the inner surface of the tire template system. The waterproof material 14 can prevent water leakage due to the occurrence of fine cracks inside concrete after the concrete in the form system is molded.
While the present invention has been particularly shown and described with reference to the present embodiments and preferred versions thereof, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (10)

1. A construction method of a tire template system comprises the following steps:
step S1: prefabricating a tire template;
step S2: assembling the tire templates into a first rectangular square frame;
step S3: the four outer corners of the first rectangular square frame are respectively provided with a hanging ring;
step S4: hanging four lifting hooks on a lifting appliance on the corresponding lifting rings respectively;
step S5: hoisting the first rectangular square frame by using a hoisting device;
step S6: marking a marking line on the concrete cushion layer;
step S7: placing the first rectangular box on the concrete pad such that the first rectangular box coincides with the marking line;
step S8: inserting a wood purlin into the first rectangular square frame, and fixing the wood purlin by using a support;
step S9: backfilling earthwork around the first rectangular square frame;
step S10: after earth backfilling is completed, removing the supporting piece and the wood purlin, and paving a waterproof material inside the first rectangular square frame;
characterized in that, the step S1 includes the following steps:
step S11: taking four steel bars with preset lengths respectively, and welding the four steel bars into a second rectangular square frame;
step S12: taking a first steel bar and a second steel bar, and welding the first steel bar and the second steel bar to form a steel bar mesh;
step S13: welding the reinforcing mesh inside the second rectangular square frame;
step S14: pouring concrete into the second rectangular square frame;
step S15: vibrating and tamping the concrete;
step S16: rubbing and pressing the surface of the concrete after the concrete is initially set;
step S17: and after the concrete is finally set, covering and curing the concrete.
2. The construction method according to claim 1, characterized in that:
in the process of executing the step S11, the specifications of the selected steel bar are a square steel tube with a thickness of 50 × 50 × 3mm and an angle steel with a thickness of 50 × 50 × 3mm, the steel bar is in the shape of a straight quadrangular prism, the bottom surface of the straight quadrangular prism is in the shape of an isosceles trapezoid, the width of the steel bar is 1.5mm, the height of the steel bar is 50mm, and the degree of the bottom angle of the isosceles trapezoid is 45 °.
3. The construction method according to claim 2, characterized in that:
in the process of performing the step S11, among the four steel bars, two of the steel bars have a length equal to that of the long side of the match plate, and the other two of the steel bars have a length equal to that of the short side of the match plate.
4. The construction method according to claim 3, wherein:
in the process of executing the step S12, the specifications of the first reinforcing steel bar and the second reinforcing steel bar are both Φ 6 mm, the number of the first reinforcing steel bar and the second reinforcing steel bar is two or more, the axis of the first reinforcing steel bar and the axis of the second reinforcing steel bar are perpendicular to each other, the distance between every two adjacent first reinforcing steel bars in the first reinforcing steel bar is 200mm, and the distance between every two adjacent second reinforcing steel bars in the second reinforcing steel bar is 200 mm.
5. The construction method according to claim 4, wherein:
in the process of performing the step S13, the mesh of reinforcing bars is welded at an intermediate position inside the rectangular box, and the distance between the axis of the first reinforcing bar and the bottom surface of the steel bar is 25 mm.
6. The construction method according to claim 5, wherein:
in the course of performing the S14 step, the concrete includes water, cement, coarse sand, stone chips, polystyrene particles, and a foaming agent.
7. The construction method according to claim 6, wherein:
in the course of performing the step S16, the flatness of the concrete surface does not exceed 5 mm.
8. The construction method according to claim 7, wherein:
in the process of executing the step S17, the time for covering and curing the concrete is not less than seven days.
9. The construction method according to claim 8, wherein:
executing before the S7 step, mark the inboard electric drill of line and set up the blind hole on the concrete cushion, then again the third reinforcing bar is buried to the inside of blind hole, the quantity of blind hole is more than two, the internal diameter of blind hole is not less than 14mm, the degree of depth of blind hole is 50 to 60mm, the length of third reinforcing bar is not less than 100mm, adjacent two distance between the blind hole is 1000 mm.
10. The construction method according to any one of claims 1 to 9, characterized in that:
in the process of executing the step S8, the support head on the support member is abutted against the middle of the wood balk, so that the wood balk is tightly attached to the inner side wall of the tire template.
CN201910969288.6A 2019-10-12 2019-10-12 Construction method of tire template system Pending CN110747878A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910969288.6A CN110747878A (en) 2019-10-12 2019-10-12 Construction method of tire template system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910969288.6A CN110747878A (en) 2019-10-12 2019-10-12 Construction method of tire template system

Publications (1)

Publication Number Publication Date
CN110747878A true CN110747878A (en) 2020-02-04

Family

ID=69278114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910969288.6A Pending CN110747878A (en) 2019-10-12 2019-10-12 Construction method of tire template system

Country Status (1)

Country Link
CN (1) CN110747878A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035354A (en) * 2017-11-30 2018-05-15 中国冶集团有限公司 A kind of construction method of GRC cement plates brick mold
CN109944265A (en) * 2019-04-08 2019-06-28 中冶东北建设(沈阳)工程技术有限公司 The method for carrying out foundation construction using concrete light scutum

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035354A (en) * 2017-11-30 2018-05-15 中国冶集团有限公司 A kind of construction method of GRC cement plates brick mold
CN109944265A (en) * 2019-04-08 2019-06-28 中冶东北建设(沈阳)工程技术有限公司 The method for carrying out foundation construction using concrete light scutum

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马荣全: "《海岛建筑工程绿色建造关键技术》", 31 August 2016, 海洋出版社 *

Similar Documents

Publication Publication Date Title
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN106592426A (en) Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method
CN1952288A (en) Shuttering component for filling concrete
CN105113706A (en) Reinforced truss gypsum plate with insulation layer, novel dismantling-free formwork and their construction method
CN110004974B (en) Prefabricated waterproof retaining wall plate structure and construction method thereof
CN110593321B (en) Construction method of basement outer wall post-cast strip advanced sealing prefabricated clamping groove formwork-free system
US4131405A (en) Apparatus for producing structural panels
CN211714001U (en) Inner supporting device for prefabricated plate moulding bed
CN112112295A (en) Reinforcing construction method for post-cast strip of post-sealed outer wall
KR100726111B1 (en) Bathroom bottom manufacture method using precast concreat slab
CN109811613B (en) Temporary ground facility and integrated construction method thereof
CN110747878A (en) Construction method of tire template system
CN215630069U (en) Waterproof integrated prefabricated component for independent basement foundation
CN214364434U (en) Assembled constructional column suitable for prefabricated wallboard of frame construction
CN211312571U (en) A bed mould system for pouring smash concrete
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN209759116U (en) Filter plate for denitrification filter tank
CN209975560U (en) Prefabricated waterproof retaining wall plate structure
CN210507502U (en) Prefabricated assembled concrete slab bed structure
CN210288465U (en) Assembled retaining wall post-cast strip plugging member
CN105839824B (en) Shed deckhead construction method
JPS60129326A (en) Coupling metal for building concrete wall body
JPH045331A (en) Method for constructing foundation
KR101530601B1 (en) Method for a patterned concrete pannel and method for manufacturing a retaining wall including the same, and patterned concrete pannel
CN217353538U (en) Disposable integral molding construction structure for sunken well and reversed ridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200204

RJ01 Rejection of invention patent application after publication