CN110714481B - Construction method for prefabricated assembly type power pipe gallery - Google Patents
Construction method for prefabricated assembly type power pipe gallery Download PDFInfo
- Publication number
- CN110714481B CN110714481B CN201910758202.5A CN201910758202A CN110714481B CN 110714481 B CN110714481 B CN 110714481B CN 201910758202 A CN201910758202 A CN 201910758202A CN 110714481 B CN110714481 B CN 110714481B
- Authority
- CN
- China
- Prior art keywords
- pipe gallery
- power pipe
- template
- waterproof
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/08—Producing shaped prefabricated articles from the material by vibrating or jolting
- B28B1/087—Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B1/00—Producing shaped prefabricated articles from the material
- B28B1/08—Producing shaped prefabricated articles from the material by vibrating or jolting
- B28B1/093—Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
- B28B7/38—Treating surfaces of moulds, cores, or mandrels to prevent sticking
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/08—Sinking workpieces into water or soil inasmuch as not provided for elsewhere
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G9/00—Installations of electric cables or lines in or on the ground or water
- H02G9/02—Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention relates to the technical field of infrastructure engineering, in particular to a construction method of a prefabricated assembly type power pipe gallery. The method comprises the following steps: binding a power pipe gallery steel frame; step two, pedestal construction; step three, installing a template; step four, pouring concrete; fifthly, transporting the power pipe gallery; sixthly, installing the power pipe gallery; seventhly, performing waterproof construction outside the power pipe gallery; and step eight, backfilling the pipe gallery. The construction method effectively accelerates the turnover efficiency of the pipe culvert prefabricating and shaping steel die and accelerates the prefabrication efficiency of the pipe culvert. Effectively quickening the installation efficiency of the pipe culvert and ensuring the installation quality of two adjacent pipe galleries.
Description
The invention relates to the technical field of infrastructure engineering, in particular to a prefabricated assembly type power pipe gallery
A construction method.
Background art the construction of the existing comprehensive power pipe gallery is realized by adopting a traditional cast-in-place construction mode, and the construction process is carried out in the prior art
Needs more manpower cooperation for constructors, and has high construction cost of projects due to more manpower construction links,
The construction efficiency is low, and the uncontrollable factors of the construction quality are more. But in today's society, efficiency and quality are critical to businesses. In mechanization and self
Under the dynamic development trend, the traditional cast-in-place construction mode has the problems of high construction cost, high labor intensity and low construction efficiency, and cannot better adapt to the requirements of modern construction.
The invention provides a construction method of a prefabricated assembly type power pipe gallery, which aims to solve the problem that the power pipe gallery is constructed in the traditional mode
The construction cost is high, the labor intensity is high and the construction efficiency is low in the construction process.
The invention discloses a construction method of a prefabricated assembly type power pipe gallery, which adopts the following technical scheme: a construction method for a prefabricated assembly type power pipe gallery comprises the following steps:
step one, binding a steel frame of the power pipe gallery: binding reinforcing steel bars of the power pipe gallery by using galvanized steel pipes as a framework and using deformed steel bars as a support;
step two, pedestal construction: the electric power pipe gallery construction adopts a pedestal and mould separated design, combines the existing templates, arranges pedestals, the pedestals are arranged in two rows, the two rows of pedestals are transversely arranged at intervals, a steel template is installed when the pedestals are poured, a leveling instrument is used for leveling the top elevation of the template, counter pull rods and inclined struts are arranged on the template, steel plates are placed on the surface of the pedestals, and the welding is firm by electric welding;
step three, template installation: after the on-site mold is qualified, the mold is firstly polished by a steel wire brush, then is coated with cement mortar for polishing, and then is coated with the cement mortar for polishing, and then is circularly polished in sequence, and is subjected to oxidation treatment after polishing, the template is assembled according to a drawing, double-sided sponge rubber strips are adhered to joints of the template, and a layer of special release agent needs to be uniformly coated on a steel template; the template is installed by lifting the template by a gantry crane and manually matching the template in place; the template connection adopts bolt fixation, the top and the bottom of the inner template and the outer template adopt high-strength pull rods to fix the inner support and the template truss for positioning, after the templates are installed and formed, the longitudinal and transverse axes are used for correcting the position of the templates, the plumb of the templates is corrected by a plumb bob, and a lifting appliance is reserved at the position of a template lifting hole;
step four, pouring concrete: adopting a gantry crane to lift a hopper for layered pouring, stopping pouring after pouring of bottom concrete is finished, adopting an inserted vibrator for vibrating, and installing a bottom template when the bottom concrete surface is flat and has slurry, does not sink and has no bubbles; after the bottom formwork is installed, pouring the side surface and the top plate, wherein the two ends are symmetrical, layered pouring is carried out, the thin layer of the inclined surface is pushed, an attached high-frequency vibrator and an inserted vibrating rod are combined, the lower layer concrete is inserted for 50-100 mm during vibrating, and each vibrating part needs to be vibrated until the concrete at the vibrating part is compact, namely no air bubble is generated;
step five, transporting the power pipe gallery: hoisting the power pipe gallery by using a crawler crane, before hoisting, performing waterproof treatment on a socket by using the power pipe gallery, fixing a hoisting tool firstly during hoisting, slowly hoisting, stopping dropping at a position 200mm away from the ground, standing for two minutes after the power pipe gallery is stable, slowly moving to a position right above the center of a waterproof base plane of the power pipe gallery, standing for two minutes, vertically dropping a component after the power pipe gallery is stable, stopping dropping at a position 200mm away from the waterproof base plane on the bottom surface of the power pipe gallery, adjusting the direction of the power pipe gallery, and after ensuring that bell sockets of the power pipe gallery are aligned, finely adjusting the power pipe gallery by using a manual hoist, and controlling the central line and the inner bottom elevation of a box culvert; the method comprises the following steps of ensuring that tensioning channels reserved at four corners of the power pipe gallery are aligned, and after the tensioning channels reserved at the four corners are aligned, additionally arranging temporary supports on the inner walls of joints of adjacent power pipe galleries to be tensioned to fix the inner walls of the adjacent power pipe galleries to be tensioned, so that the inner walls of the two adjacent power pipe galleries are smooth; then tensioning pore channels at four corners of the power pipe gallery to perform steel strand penetrating and anchoring the front end in advance;
step six, installing the power pipe gallery: after the power pipe gallery is hoisted in place, firstly, tensioning the power pipe gallery for the first time after tensioning pore channels at four corners of the power pipe gallery are aligned, and detaching a lifting appliance after the four corners of the power pipe gallery are aligned and the bell and spigot are orthogonal; performing secondary tensioning, and when the gap width of the tensioning bell and spigot of the power pipe gallery reaches 20mm, performing locking treatment on the rear end of the anchorage device to cut off redundant steel strands;
seventhly, waterproof construction outside the power pipe gallery: waterproof introduction of anti-freezing waterproof mortar outside the power pipe gallery, waterproof construction of a surface layer by adopting the waterproof mortar, construction of a tensioning groove on the inner side of the power pipe gallery in three times, sealing mortar, namely the waterproof mortar is mixed with water and cannot leak to be sealed, and polysulfide sealant is filled in a joint of a bell and spigot by adopting a glue dispenser;
step eight, backfilling the pipe gallery: the foam board is pasted on the waterproof layer surface, the bilateral symmetry is backfilled, the box culvert is guaranteed not to displace, and the connection of adjacent sections leaves steps to guarantee that the pipe culvert is backfilled in place.
In the second step, 30 pedestals are arranged in the prefabricating area, and the distance between two adjacent rows of pedestals is two meters. In the third step, the slump of the concrete of the pipe gallery needs to be controlled between 140mm and 180 mm. The thickness of the layers is
300 mm-400 mm. With a phi 50-insertion vibrator, the vibration spacing not exceeding the action radius of the vibrator
1.5 times, and the distance between the die and the side die is kept between 50mm and 100 mm.
In the fourth step, the ST water stop adhesive tape stuck on the socket has the top width of 20mm, the bottom width of 22mm, the thickness of 20mm, the width of the micro-expansion rubber strip of 15mm and the thickness of 20 mm.
In the fifth step, the length of the handle rod is selected to be 35.6m and the working radius is selected to be 26m in the first-stage slope section and the second-stage slope section, so that the single-machine crawler crane with the lifting capacity of 20.1t is adopted, and the length of the handle rod in the first-stage groove and the second-stage groove is selected to be 41.2m and the working radius is selected to be 36m, so that the single-machine crawler crane with the lifting capacity of 21t is adopted.
In the seventh step, the waterproof mortar is doped with water in the following proportion: cement: river sand: the alloy powder is 1.04: 1: 2.5:0.05, adhering small stainless steel hooks on two sides of the joint by 107 glue, paving a galvanized steel wire mesh with the width of 50cm and the mesh size of 800, increasing the bonding strength and preventing settlement and cracking.
The invention has the beneficial effects that: the standard and specification of the binding of the steel bars of the pipe culvert are ensured. Effectively quickening the turnover efficiency of the pipe culvert prefabricating and shaping steel die and quickening the prefabricating efficiency of the pipe culvert. Effectively quickening the installation efficiency of the pipe culvert and ensuring the installation quality of two adjacent pipe galleries. The construction of the external water-proof of the pipe culvert is efficiently finished, a better effect is obtained, and the construction method is approved by all parties involved in construction. The timing of the backfilling of the pipe culvert is mastered, the machines and tools which are beneficial to the backfilling of the pipe culvert are summarized, and the water resistance outside the constructed pipe culvert is effectively protected.
Drawings
To more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following embodiments will be made to
The drawings that are required for use in the description of the embodiments or the prior art are briefly described, and it is apparent that
The drawings in the description are only some embodiments of the invention and it is obvious to a person skilled in the art that other drawings can be derived from them without inventive exercise.
Fig. 1 is a flow chart of a prefabricated assembled power pipe gallery construction method of the present invention;
FIG. 2 is a schematic of an engineering project with two levels of side slopes;
in the figure: 1. a crawler crane; 2. a spreader; 3. a first grade slope section; 4. a second grade slope section; 5. a transport vehicle.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The embodiment of the invention relates to a construction method of a prefabricated assembly type power pipe gallery, which comprises the following steps:
step one, binding a steel frame of the power pipe gallery: binding reinforcing steel bars of the power pipe gallery by using galvanized steel pipes as a framework and using deformed steel bars as a support; the deformed steel bar adopts deformed steel bar with the diameter of 16, and the standard, quick and accurate manufacturing effect of the binding of the pipe culvert steel bars is realized.
Step two, pedestal construction: the electric power pipe gallery construction adopts a pedestal and mould separated design, combines the existing templates, arranges pedestals, the pedestals are arranged in two rows, the two rows of pedestals are transversely arranged at intervals, a steel template is installed when the pedestals are poured, a leveling instrument is used for leveling the top elevation of the template, counter pull rods and inclined struts are arranged on the template, steel plates are placed on the surface of the pedestals, and the welding is firm by electric welding; the steps optimize the template through analyzing the advantages and the disadvantages of the integral steel mould with the base and the base separating template, improve the turnover work efficiency of the template and accelerate the prefabrication progress of the pipe culvert.
Step three, template installation: after the on-site mold is qualified, the mold is firstly polished by a steel wire brush, then is coated with cement mortar for polishing, and then is coated with the cement mortar for polishing, and then is circularly polished in sequence, and is subjected to oxidation treatment after polishing, the template is assembled according to a drawing, double-sided sponge rubber strips are adhered to joints of the template, and a layer of special release agent needs to be uniformly coated on a steel template; the template is installed by lifting the template by a gantry crane and manually matching the template in place; the template connection adopts bolt fixation, the top and the bottom of the inner template and the outer template adopt high-strength pull rods to fix the inner support and the template truss for positioning, after the templates are installed and formed, the longitudinal and transverse axes are used for correcting the position of the templates, the plumb of the templates is corrected by a plumb bob, and a lifting appliance is reserved at the position of a template lifting hole; the high-strength pull rod adopts a T20 high-strength pull rod. The lifting appliance adopts four lifting appliances 2 with the weight of five tons.
Step four, pouring concrete: adopting a gantry crane to lift a hopper for layered pouring, stopping pouring after pouring of bottom concrete is finished, adopting an inserted vibrator for vibrating, and installing a bottom template when the bottom concrete surface is flat and has slurry, does not sink and has no bubbles; after the bottom formwork is installed, pouring the side surface and the top plate, wherein the two ends are symmetrical, layered pouring is carried out, the thin layer of the inclined surface is pushed, an attached high-frequency vibrator and an inserted vibrating rod are combined, the lower layer concrete is inserted for 50-100 mm during vibrating, and each vibrating part needs to be vibrated until the concrete at the vibrating part is compact, namely no air bubble is generated;
step five, transporting the power pipe gallery: hoisting the power pipe gallery by using a crawler crane, before hoisting, performing waterproof treatment on a socket by using the power pipe gallery, fixing a hoisting tool firstly during hoisting, slowly hoisting, stopping dropping at a position 200mm away from the ground, standing for two minutes after the power pipe gallery is stable, slowly moving to a position right above the center of a waterproof base plane of the power pipe gallery, standing for two minutes, vertically dropping a component after the power pipe gallery is stable, stopping dropping at a position 200mm away from the waterproof base plane on the bottom surface of the power pipe gallery, adjusting the direction of the power pipe gallery, and after ensuring that bell sockets of the power pipe gallery are aligned, finely adjusting the power pipe gallery by using a manual hoist, and controlling the central line and the inner bottom elevation of a box culvert; the method comprises the following steps of ensuring that tensioning channels reserved at four corners of the power pipe gallery are aligned, and after the tensioning channels reserved at the four corners are aligned, additionally arranging temporary supports on the inner walls of joints of adjacent power pipe galleries to be tensioned to fix the inner walls of the adjacent power pipe galleries to be tensioned, so that the inner walls of the two adjacent power pipe galleries are smooth; then tensioning pore channels at four corners of the power pipe gallery to perform steel strand penetrating and anchoring the front end in advance;
step six, installing the power pipe gallery: after the power pipe gallery is hoisted in place, firstly, tensioning the power pipe gallery for the first time after tensioning pore channels at four corners of the power pipe gallery are aligned, and detaching a lifting appliance after the four corners of the power pipe gallery are aligned and the bell and spigot are orthogonal; performing secondary tensioning, and when the gap width of the tensioning bell and spigot of the power pipe gallery reaches 20mm, performing locking treatment on the rear end of the anchorage device to cut off redundant steel strands;
seventhly, waterproof construction outside the power pipe gallery: waterproof introduction of anti-freezing waterproof mortar outside the power pipe gallery, waterproof construction of a surface layer by adopting the waterproof mortar, construction of a tensioning groove on the inner side of the power pipe gallery in three times, sealing mortar, namely the waterproof mortar is mixed with water and cannot leak to be sealed, and polysulfide sealant is filled in a joint of a bell and spigot by adopting a glue dispenser;
step eight, backfilling the pipe gallery: the foam board is pasted on the waterproof layer surface, the bilateral symmetry is backfilled, the box culvert is guaranteed not to displace, and the connection of adjacent sections leaves steps to guarantee that the pipe culvert is backfilled in place.
Further, in the second step, 30 pedestals are arranged in the prefabricating area, and the distance between two adjacent rows of pedestals is two meters.
Furthermore, in the third step, the concrete slump of the pipe gallery is controlled to be 140 mm-180 mm. The thickness of the layered layer is 300 mm-400 mm. The phi 50 inserted vibrator is adopted, the vibration interval does not exceed 1.5 times of the action radius of the vibrating spear, and the distance between the vibrator and the side die is kept between 50mm and 100 mm.
Furthermore, in the fourth step, the width of the top of the ST water stop adhesive tape stuck on the socket is 20mm, the width of the bottom of the ST water stop adhesive tape is 22mm, the thickness of the ST water stop adhesive tape is 20mm, the width of the micro-expansion rubber strip is 15mm, and the thickness of the ST water stop adhesive tape is 20 mm.
Further, in the fifth step, the length of the rod of the crawler crane with the single crane lifting capacity of 20.1t is selected to be 35.6m and the working radius is selected to be 26m in the first-stage slope section 3 and the second-stage slope section 4, the length of the rod of the crawler crane with the single crane lifting capacity of 21t is selected to be 41.2m and the working radius is selected to be 36m in the first-stage slope section 3 and the second-stage slope section 4.
In the seventh step, the waterproof mortar is doped with water in the following proportion: cement: river sand: the alloy powder is 1.04: 1: 2.5:0.05, adhering small stainless steel hooks on two sides of the joint by 107 glue, paving a galvanized steel wire mesh with the width of 50cm and the mesh size of 800, increasing the bonding strength and preventing settlement and cracking.
The transport vehicle 5 is parked on the side opposite to the crawler crane 1. The invention has the beneficial effects that: ensures the standard and specification of the binding of the steel bars of the pipe culvert, and effectively accelerates
The pipe culvert prefabrication shaping steel mould turnover efficiency is improved, and the prefabrication efficiency of the pipe culvert is improved. Effectively quicken the installation of the pipe culvert
Efficiency, guaranteed two adjacent piping lane installation quality. The construction of the external water-proof of the pipe culvert is efficiently finished, a better effect is obtained, and the construction method is approved by all parties involved in construction. The timing of the backfilling of the pipe culvert is mastered, the machines and tools which are beneficial to the backfilling of the pipe culvert are summarized, and the water resistance outside the constructed pipe culvert is effectively protected.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.
Claims (6)
1. A construction method for a prefabricated assembly type power pipe gallery comprises the following steps:
step one, binding a steel frame of the power pipe gallery: binding reinforcing steel bars of the power pipe gallery by using galvanized steel pipes as a framework and using deformed steel bars as a bracket;
step two, pedestal construction: the construction of the electric power pipe gallery adopts a pedestal and mould separated design, the existing templates are combined, pedestals are arranged, the pedestals are arranged in two rows, the two rows of pedestals are transversely arranged at intervals, a steel template is installed when the pedestals are poured, the top elevation of the template is leveled by using a level gauge, counter pull rods and inclined struts are arranged on the template, steel plates are placed on the surface of the pedestals, and the welding is firm by using electric welding;
step three, template installation: after the on-site mold is qualified, the mold is firstly polished by a steel wire brush, then is coated with cement mortar for polishing, and then is coated with the cement mortar for polishing, and then is circularly polished in sequence, and is subjected to oxidation treatment after polishing, the template is assembled according to a drawing, double-sided sponge rubber strips are adhered to joints of the template, and a layer of special release agent needs to be uniformly coated on a steel template; the template is installed by lifting the template by a gantry crane and manually matching the template in place; the template connection adopts bolt fixation, the top and the bottom of the inner template and the outer template adopt high-strength pull rods to fix the inner support and the template truss for positioning, after the templates are installed and formed, the position of the templates is corrected by longitudinal and transverse axes, the verticality of the templates is corrected by a plumb bob, and a lifting appliance is reserved at the position of a template lifting hole;
step four, pouring concrete: adopting a gantry crane to lift a hopper for layered pouring, stopping pouring after the bottom concrete pouring is finished, adopting an inserted vibrator for vibrating, and installing a bottom template when the bottom concrete surface is flat and has slurry, does not sink and has no bubbles; after the bottom formwork is installed, pouring the side surface and the top plate, wherein the two ends are symmetrical, layered pouring is carried out, the thin layer of the inclined surface is pushed, an attached high-frequency vibrator and an inserted vibrating rod are combined, the lower layer concrete is inserted for 50-100 mm during vibrating, and each vibrating part needs to be vibrated until the concrete at the vibrating part is compact, namely no air bubble is generated;
step five, transporting the power pipe gallery: hoisting the power pipe gallery by using a crawler crane, before hoisting, performing waterproof treatment on a socket by using the power pipe gallery, fixing a hoisting tool firstly during hoisting, slowly hoisting, standing for two minutes at a position 200mm away from the ground, slowly moving to a position right above the center of a waterproof base plane of the power pipe gallery after the power pipe gallery is stable, standing for two minutes, vertically dropping a component after the power pipe gallery is stable, stopping dropping at a position 200mm away from the waterproof base plane on the bottom surface of the power pipe gallery, adjusting the direction of the power pipe gallery, and after ensuring that bell sockets of the power pipe gallery are aligned, finely adjusting the power pipe gallery by using a manual hoist to control the central line and the elevation of an inner bottom of a box culvert; the method comprises the following steps of ensuring that tensioning channels reserved at four corners of the power pipe gallery are aligned, and after the tensioning channels reserved at the four corners are aligned, additionally arranging temporary supports on the inner walls of joints of adjacent power pipe galleries to be tensioned to fix the inner walls of the adjacent power pipe galleries to be tensioned, so that the inner walls of the two adjacent power pipe galleries are smooth; then tensioning pore channels at four corners of the power pipe gallery to perform steel strand penetrating and anchoring the front end in advance;
step six, installing the power pipe gallery: after the power pipe gallery is hoisted in place, firstly, tensioning the power pipe gallery for the first time after tensioning pore channels at four corners of the power pipe gallery are aligned, and detaching a lifting appliance after the four corners of the power pipe gallery are aligned and the bell and spigot are orthogonal; performing secondary tensioning, and when the width of a gap at the tensioning socket of the power pipe gallery reaches 20mm, performing locking treatment on the rear end of the anchorage device to cut off redundant steel strands;
seventhly, waterproof construction outside the power pipe gallery: waterproof introduction of anti-freezing waterproof mortar outside the power pipe gallery, waterproof construction of a surface layer by adopting the waterproof mortar, construction of a tensioning groove on the inner side of the power pipe gallery in three times, sealing mortar, namely the waterproof mortar is mixed with water and cannot leak to be sealed, and polysulfide sealant is filled in a joint of a bell and spigot by adopting a glue dispenser;
step eight, backfilling the pipe gallery: the foam board is pasted on the waterproof layer surface, the bilateral symmetry is backfilled, the box culvert is guaranteed not to displace, and the connection of adjacent sections leaves steps to guarantee that the pipe culvert is backfilled in place.
2. The prefabricated assembled power pipe gallery construction method according to claim 1, wherein: in the second step, 30 pedestals are arranged in the prefabricating area, and the distance between two adjacent rows of pedestals is two meters.
3. The prefabricated assembled power pipe gallery construction method according to claim 2, wherein: in the third step, the slump of the pipe gallery concrete is controlled to be 140-180 mm, the layering thickness is 300-400 mm, a phi 50 inserted vibrator is adopted, the vibration interval does not exceed 1.5 times of the action radius of a vibrating rod, and the distance between the pipe gallery concrete and the side mold is kept to be 50-100 mm.
4. The prefabricated assembled power pipe gallery construction method according to claim 3, wherein: in the fourth step, the ST water stop adhesive tape stuck on the socket has the top width of 20mm, the bottom width of 22mm, the thickness of 20mm, the width of the micro-expansion rubber strip of 15mm and the thickness of 20 mm.
5. The prefabricated assembled power pipe gallery construction method according to claim 4, wherein: in the fifth step, the length of the rod is selected to be 35.6m and the working radius is selected to be 26m in the first-stage slope-releasing section and the second-stage slope-releasing section, so that the single-machine crawler crane with the lifting capacity of 20.1t is adopted, the length of the rod is selected to be 41.2m and the working radius is selected to be 36m in the first-stage groove and the second-stage groove, and the single-machine crawler crane with the lifting capacity of 21t is adopted.
6. The prefabricated assembled power pipe gallery construction method according to claim 5, wherein: in the seventh step, the waterproof mortar is doped with water in the following proportion: cement: river sand: the alloy powder is 1.04: 1: 2.5:0.05, adhering small stainless steel hooks on two sides of the joint by 107 glue, paving a galvanized steel wire mesh with the width of 50cm and the mesh size of 800, increasing the bonding strength and preventing settlement and cracking.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910758202.5A CN110714481B (en) | 2019-08-16 | 2019-08-16 | Construction method for prefabricated assembly type power pipe gallery |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910758202.5A CN110714481B (en) | 2019-08-16 | 2019-08-16 | Construction method for prefabricated assembly type power pipe gallery |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110714481A CN110714481A (en) | 2020-01-21 |
CN110714481B true CN110714481B (en) | 2021-05-18 |
Family
ID=69209426
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910758202.5A Active CN110714481B (en) | 2019-08-16 | 2019-08-16 | Construction method for prefabricated assembly type power pipe gallery |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110714481B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112248211A (en) * | 2020-10-22 | 2021-01-22 | 杨华生 | Underground culvert pipe processing method |
CN113172754A (en) * | 2021-04-22 | 2021-07-27 | 中电建十一局工程有限公司 | Method for manufacturing prefabricated pedestal of pipe gallery |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149709A (en) * | 2017-12-28 | 2018-06-12 | 中铁十局集团第五工程有限公司 | Underground pipe gallery precast assembly construction method |
CN107989070A (en) * | 2017-12-30 | 2018-05-04 | 中建四局第五建筑工程有限公司 | A kind of prefabricated piping lane device and its construction method |
CN108643228A (en) * | 2018-05-21 | 2018-10-12 | 南通路桥工程有限公司 | A kind of logical construction technology of prefabricated car case |
CN109972656A (en) * | 2018-08-09 | 2019-07-05 | 中铁二十二局集团第三工程有限公司 | A kind of overlapping fabricated construction pipe gallery and its construction method |
CN108678010A (en) * | 2018-08-15 | 2018-10-19 | 屠娟 | Prefabricated pipe gallery construction method |
CN109056815B (en) * | 2018-10-22 | 2021-05-18 | 中建科技有限公司 | Comprehensive pipe gallery construction method |
CN109958143A (en) * | 2019-03-08 | 2019-07-02 | 厦门三航混凝土有限公司 | A kind of piping lane prefabricated mould and piping lane construction method |
-
2019
- 2019-08-16 CN CN201910758202.5A patent/CN110714481B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN110714481A (en) | 2020-01-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107059917B (en) | Split component prefabricated comprehensive pipe gallery and construction method thereof | |
CN110714481B (en) | Construction method for prefabricated assembly type power pipe gallery | |
CN105569224A (en) | Concrete-filled steel tube edge restraint overlapping integrated shear wall and preparing and installation methods thereof | |
CN110552370A (en) | Reverse construction method based annular lining wall integral single-side formwork construction method | |
CN105134009A (en) | Sill coping concrete structure of frame structure infilled wall and construction method | |
CN110145124A (en) | A kind of control shear wall level connects the reinforcement tools and its construction method of batch quality | |
CN109648696A (en) | Side slope precast lattice beam of reinforcing bar connection and preparation method thereof and construction method | |
CN110158645A (en) | Prefabricated components Hybrid connections assembly concrete pipe gallery | |
CN113216252A (en) | Expansion joint reinforcing device and method for multi-section continuous casting of underground pipe gallery | |
CN207660136U (en) | A kind of assembly concrete frame-shear wall keyway connection structure | |
CN110607805A (en) | Cable tunnel construction method | |
CN106759563A (en) | A kind of device for pile foundation repairing and reinforcing and the construction method using the device | |
CN206706844U (en) | A kind of alter-pouring strips mould plate installs construction | |
CN210263131U (en) | Assembled is from stagnant water underground pipe gallery structure | |
CN103866982A (en) | Petal artistic framework construction method | |
CN115890877A (en) | Adjustable diaphragm plate template and construction method thereof | |
CN216787229U (en) | Basement outer wall post-cast strip assembled shutoff steel sheet structure | |
CN215857879U (en) | Post-cast strip for bottom plate of underground chamber | |
CN110306398B (en) | Sectional beam-setting pretensioning staggered symmetrical tensioning prestressed tendon superposed assembly road and construction method thereof | |
CN108590316A (en) | A kind of assembly concrete tower piece construction method | |
CN212388856U (en) | Cast-in-place clear water concrete batter post structure of prestressing force | |
CN209816832U (en) | General prefabricated reinforced concrete guide wall for underground continuous wall | |
CN109826186B (en) | General prefabricated reinforced concrete guide wall for underground diaphragm wall and implementation method | |
CN211900603U (en) | Face combination shield structure hole of hoist enclosed construction forever | |
CN112983465A (en) | Fully-prefabricated internal structure of shield tunnel and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |