CN110689313A - Method for establishing overall-planning-method table-mode project reverse control multi-level plan system - Google Patents

Method for establishing overall-planning-method table-mode project reverse control multi-level plan system Download PDF

Info

Publication number
CN110689313A
CN110689313A CN201910231706.1A CN201910231706A CN110689313A CN 110689313 A CN110689313 A CN 110689313A CN 201910231706 A CN201910231706 A CN 201910231706A CN 110689313 A CN110689313 A CN 110689313A
Authority
CN
China
Prior art keywords
project
projects
organization
target control
sub
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910231706.1A
Other languages
Chinese (zh)
Inventor
吴茜龄
吴开平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Senkun Enterprise Management Consulting Co Ltd
Original Assignee
Jinan Senkun Enterprise Management Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Senkun Enterprise Management Consulting Co Ltd filed Critical Jinan Senkun Enterprise Management Consulting Co Ltd
Priority to CN201910231706.1A priority Critical patent/CN110689313A/en
Publication of CN110689313A publication Critical patent/CN110689313A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a method for establishing a project reverse control multi-level plan system in a form mode of an overall planning method, which can fully apply a computer technology, control and make various project all-level organization management and target control plans and establish a multi-level plan system in a form mode by adopting a reverse step-by-step construction period, and belongs to the technical field of the overall planning method; the method comprises the following steps: (1) decomposing the project in any order step by step and establishing a main work list of each stage in any order; (2) determining main parameters of each stage and each item of work in any sequence; (3) determining the organization relation among all levels of work in any sequence, and determining the organization mode and method among the work in any sequence; (4) performing logical conversion of the organization relation of each level of work; (5) sequencing the organization sequence of all levels of work; (6) and calculating the time parameters of the multi-stage planning system.

Description

Method for establishing overall-planning-method table-mode project reverse control multi-level plan system
Technical Field
The invention belongs to the technical field of a comprehensive method, and relates to one of main components of a project or task organization management and target control technology of the comprehensive method, in particular to a method for replacing the method for establishing a project or task organization management and target control plan by establishing a network model, gradually decomposing various projects or tasks, respectively establishing an organization management and target control plan by each level in a table mode, and establishing a project or task organization management and target control multi-level plan system by reverse gradual construction period control.
Background
In the beginning of the fifties of the last century, in order to meet the requirements of scientific research with complex relationships and technical development work organization management, advanced industrial countries in the world have been researched on new plan management technologies in sequence, wherein the U.S. has firstly researched CPM (critical line method) and PERT (plan review technology) successfully, and the methods are established on the basis of a working relationship network model and organically combine the formulation, coordination, optimization and control of a plan, so the method is called as a network planning technology abroad.
The PERT (plan review technology) invented in 1956 in the United states is applied to compiling a research plan of a North Star missile, and more than three thousand enterprises are coordinated, so that the plan is completed two years ahead of time according to preset time; the method is applied to the management and control of Apollo space planning which costs more than four billion dollars and mobilizes more than forty thousand manpower, and achieves good effects.
According to the statistics of the former Soviet Union government, the construction period of a building installation enterprise applying the network planning technology can be shortened by 20%, and the engineering cost can be reduced by about 10%.
In 3 1978, the american society for civil engineering and engineers journal commentary states that this method is currently the only new method for project management and that no new method will appear to replace it in the foreseeable future, and therefore we should enjoy it, use it, and improve it.
At present, network planning techniques are popularized and applied in various advanced industrial countries in the world, such as the United states, the Russia, the English, the Japanese, the French, the Germany, and the like.
The professor of Hualuo heptyl, a famous mathematic scientist in China, sets up a scientific system of an overall method on the basis of absorbing the technical theory of foreign network planning from the national situation of China, and is popularized and applied in production practice from the beginning of sixty years in the last century to obtain great economic benefits.
The network planning technology has the following defects and shortcomings, which influence and restrict the implementation, popularization and application of the network planning technology.
(1) Establishing the restriction of the network model rule of project or task organization management and target control plan and the restriction of the expression mode of the plane network model, so that most of project or task organization management and target controllers cannot complete, especially large or complex projects;
(2) the method is not beneficial to the restriction of the application of the computer technology, the application of the technology depends on the support of the computer technology, the establishment and modification of a network model, the calculation of time parameters, the optimization control of a construction period target, the optimization control of a resource target and the like, and the method is difficult to complete only by manpower;
(3) due to the restriction of application range, the CPM is only suitable for organization management and target control of a series of specific work directly decomposed from positive projects or tasks; PERT is only applicable to the review of non-affirmative project or task milestone targets; with the overall and rapid development of scientific technology, not only most projects or tasks have mixed characteristics, but also the organization method has mixed characteristics;
(4) the necessary functional technologies are lacked, and the main functional technologies are only: construction period-cost optimization technology; the construction period is unchanged, and the resource demand is balanced and optimized; the resources are limited, and the construction period is the shortest optimization technology; and non-affirmative project or task milestone target review techniques;
(5) the main functional technologies all have obvious defects and shortcomings, such as:
1) the construction period-cost optimization technology comprises the following steps: the critical line can be judged only after time parameter calculation is carried out on each line consisting of the critical work, and the project period-cost optimization can be carried out only by calculating the charge rate of each critical work, which is difficult or even impossible in the actual work;
2) the construction period is unchanged, and the resource balance optimization technology comprises the following steps: the optimization method does not consider the dynamic condition of resource demand of non-key work in the local (or maneuvering) time difference range, and is obviously unreasonable;
3) the optimization technology has the advantages of limited resources and shortest construction period: arranging the work started before the optimization time period at the most important head, and not considering the influence of the optimization of the non-critical work started before the optimization time period on the construction period;
4) the evaluation technology of the non-affirmed project or task milestone target does not consider the non-key milestone target interval Lagi-jThe impact on the estimated variance, etc.
The network planning technology is free of a method for establishing a project or task organization management and target control multi-level plan system by adopting reverse step-by-step construction period control, wherein step-by-step decomposition is adopted for various projects or tasks, and organization management and target control plans are respectively formulated at all levels.
The network planning technology belongs to a coordination method, and is one of application technologies of the coordination method; it can be said that the network planning technique is a orchestration method, and not vice versa.
Disclosure of Invention
The invention is an important component of another application technology different from a comprehensive planning method of a network planning technology, and is a method which adopts various projects or tasks which are beneficial to the application of a computer technology to make an organization management and target control plan by adopting a step-by-step decomposition mode, adopts a table mode to make the organization management and target control plan at each stage, adopts a reverse step-by-step construction period control to establish a project or task organization management and target control multi-stage plan system, and organically combines the plan making with the establishment, coordination, optimization and control of the plan system.
The method of the present invention is described below by taking various projects or tasks, adopting three-level decomposition of project, single project and specific work, respectively making an organization management and target control plan at each level, and taking the established project or task organization management and target control multi-level plan system as an example.
The invention divides the project or task into two types of positive type work and non-positive type work according to the requirements of organization management and target control:
(1) positive finalization "work": time t required for completing "worki(or T)i) Is positive;
(2) non-affirmative type "work": the time required for completing the work is not positive, and a three-point estimation method is adopted for estimating the time for completing the work:
at、mt、bt,Dt=(at+4mt+bt)÷6,σt 2=[(bt-at)÷6]2
aT、mT、bT,DT=(aT+4mT+bT)÷6,
aT、at-optimistic completion "work" time;
mT、mtpossible "work" time to complete;
bT、bt-pessimistic completion "work" time;
DT、Dt-estimating a weighted average of the time to complete the "work";
σt 2-an estimated deviation of the completion time.
According to the type of work decomposed by the project, the project is divided into a positive type, a non-positive type and a mixed type:
(1) positive type item: according to the requirements of organization management and target control, the decomposed 'work' is positive type 'work';
(2) non-affirmative type item: according to the requirements of organization management and target control, the decomposed 'work' is 'work' of a non-positive type;
(3) and (3) mixing type items: according to the requirements of organization management and target control, the decomposed 'work' is both positive type 'work' and non-positive type 'work'.
The project of the invention is divided into an organization mode and an organization method between 'works' according to the requirements of organization management and target control, and the invention comprises the following seven types:
the project is according to organization management and target control requirement, the organization mode and organization method between the decomposed 'works': taking i "work" and j "work" as examples, i "work" is the "work" immediately before j "work", or j "work" is the "work" immediately after i "work", the organization method and organization method between i "work" and j "work" are:
(1) fys (lt): i 'work' ends LT day, j 'work' begins;
(2)STS(LTi): i "work" Start LTiDay, j "work" begins;
(3)FTF(LTj): i "work" end LTjDay, j "work" ends;
(4)STF(LTi,LTj): i "work" Start LTiLT for daily and reusejDay, j "work" ends, i.e. j "work" starts LT at i "workiAfter a day, with LTjFinishing the day;
(5) STS and FTF (LT)i,LTj): i "work" Start LTiThe day, j 'work' starts, i 'work' ends LTjFinishing the day and j work;
(6) STS and STF (LT)i,LTi’,LTj): i "work" start LTi days, j "work" start, i "work" start LTi'LT for daily and reusejDay, j "work" ends, i.e. j "work" starts LT at i "worki’After a day, with LTjFinishing the day;
(7) FTS and STF (LT, LT)i,LTj): i 'work' ends LT day, j 'work' starts, i 'work' starts LTiLT for daily and reusejDay, j "work" ends, i.e. j "work" is to start LT at I "workiAfter a day, with LTjThe day is over.
The invention divides the organization management and target control modes between 'work' into two types of affirmation type and non-affirmation type:
(1) the positive type organization management and target control mode is as follows: the lapping relation and the lapping time interval are both positive organization management and target control modes;
(2) non-positive type organization management and target control mode: the lap relationship is positive; however, the lap time interval is not certain, and a three-point estimation method is adopted to estimate the lap time interval:
1)LTa、LTm、LTb,DLT=(LTa+4LTm+LTb)÷6,σLT 2=[(LTb-LTa)÷6]2
2)LTia、LTim、LTib,DiLT=(LTia+4LTim+LTib)÷6,σiLT 2=[(LTib-LTia)÷6]2
3)LTja、LTjm、LTjb,DjLT=(LTja+4LTjm+LTjb)÷6,σjLT 2=[(LTjb-LTja)÷6]2
4)LTi'a、LTi'm、LTi'b,Di'LT=(LTi'a+4LTi'm+LTi'b)÷6,σi'LT 2=[(LTi'b-LTi'a)÷6]2
according to the method, project organization management and target control modes are divided into positive type, non-positive type and mixed type according to the difference between the project organization management and the target control modes:
(1) the positive project organization management and target control mode comprises the following steps: the organization management and target control modes between the work decomposed by the project are positive organization management and target control modes;
(2) non-positive project organization management and target control mode: the organization management and target control modes between the work decomposed by the project are both non-affirmatively set organization management and target control modes;
(3) the mixed project organization management and target control mode comprises the following steps: the organization management and target control modes between the work decomposed by the project are both positive type organization management and target control modes and non-positive type organization management and target control modes.
The project organization management and the target control plan of the invention are divided into three categories:
(1) positive project organization management and goal control plan: the positive type project adopts a project organization management and target control plan in a positive type organization management and target control mode;
(2) the non-affirmative project organization management and target control plan comprises the following three types:
1) the positive project adopts a project organization management and target control plan of a non-positive organization management and target control mode;
2) a non-affirmative project adopts a project organization management and target control plan of a positive organization management and target control mode;
3) the non-positive project adopts a project organization management and target control plan of a non-positive organization management and target control mode;
(3) the mixed project organization management and target control plan comprises the following five types:
1) a mixed project adopts a project organization management and target control plan of a positive type organization management and target control mode;
2) the mixed project adopts a project organization management and target control plan of a non-positive organization management and target control mode;
3) the mixed project adopts a project organization management and target control plan of a mixed organization management and target control mode;
4) a non-affirmative project, which adopts a project organization management and target control plan of a hybrid organization management and target control mode;
5) the positive project adopts a project organization management and target control plan of a hybrid organization management and target control mode.
The method comprises the steps of decomposing projects or tasks step by step, respectively making organization management and target control plans at all levels, and establishing a project organization management and target control multi-level plan system, as shown in figure 1.
Method for establishing reverse progressive construction period control, project organization management and target control multi-level planning system
The method for making the first-level decomposition, organization management and target control plan comprises the following steps:
(1) according to the requirements of organization management and target control, the project is decomposed in any order and is decomposed into a series of sub-projects; and a main project list is established according to any sequence;
(2) the main parameters of each main sub item are transferred in any sequence:
1) organizing the construction period of the management and target control plan by corresponding second-level project division as the construction period of the project division;
2) the total resource requirement of the management and target control plan is organized according to the corresponding second-level sub-projects, and the total resource requirement is divided by the construction period of the sub-projects and is used as the resource requirement of the sub-projects in unit time;
(3) determining the sub items immediately before and (or) immediately after each sub item in the main sub item list according to any sequence;
(4) determining an organization mode (overlapping relation) between each sub-project and the sub-projects immediately before and/or after according to any sequence;
(5) determining or estimating the organization method (lap time interval) of the determined organization mode (lap relation) according to any sequence;
(6) and (3) carrying out the conversion of the organization logic relation among the sub-projects, as determined by project organization management and a target control plan maker: the next sub-project before the sub-project B is the sub-project A, and the next sub-project converted into the sub-project A is the sub-project B; or the next sub-project of the sub-project A is the sub-project B, and the next sub-project converted into the sub-project B is the sub-project A;
(7) organizing logical relationship arrangement
Figure RE-GDA0002170834160000041
(8) Sorting of the organization order of the items in the main item list: in order from ST: taking ST as a sub-project of an immediately preceding sub-project; taking the sorted sub-items as sub-items of the immediately previous sub-items; … …, respectively; until FIN; starting from FIN, the following are in sequence: using FIN as a sub-project of the 'sub-project' after the FIN is closed; taking the sorted sub-items as sub-items of the next sub-items; … …, respectively; until ST;
note: decomposing the items and establishing a main project list; calculating or determining or estimating main parameters of each sub-project; determining the sub-items immediately before and (or) immediately after each sub-item; determining an organization mode between each sub-project and the immediately preceding and/or immediately following sub-projects; determining or estimating the organizational method between each sub-project and the immediately preceding and/or immediately following sub-projects, etc., may be performed crosswise.
To this end, project level organizational management and target control plan planning is complete, as shown in the following table:
Figure RE-GDA0002170834160000051
wherein:
A. positive type item division:
aT=mT=bT=DT=T;σT 2=0;
B. positive fixed lap joint time interval:
a.LTa=LTm=LTb=DLT=LT,σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi,σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj,σjLT 2=0;
d.LTi'a=LTi'm=LTi'b=Di'LT=LTi',σi'LT 2=0。
the project level organization manages the target construction period of the target control plan, and the target construction period is required to meet the requirements of contracts or preset construction periods.
One of the two-level decomposition, the organization management and the target control plan making method:
(1) decomposing the sub-projects in any order according to the requirements of organization management and target control, and decomposing the sub-projects into a series of single projects; and a main single item list is established according to any sequence;
(2) and transferring main parameters of each main single item in any order:
1) organizing the construction period of the management and target control plan by using the corresponding three levels of single projects as the construction period of the single project;
2) organizing the total resource demand of management and target control plan by corresponding three levels of single projects, and dividing the total resource demand by the construction period of the single project to be used as the resource demand of the single project in unit time;
(3) determining single items immediately before and (or) immediately after each single item in the main single item list according to any sequence;
(4) determining the organization mode (overlapping relation) between each single item and the single item immediately before and/or after according to any sequence;
(5) determining or estimating the organization method (lap time interval) of the determined organization mode (lap relation) according to any sequence;
(6) and (3) performing the conversion of the organization logic relationship between the single projects, as determined by project organization management and a target control planner: the single item immediately before the B single item is the A single item, and the single item immediately after the A single item is converted into the B single item; or the single item immediately after the A single item is the B single item, and the single item immediately before the A single item is converted into the B single item is the A single item;
(7) organizing logical relationship arrangement
Figure RE-GDA0002170834160000052
Figure RE-GDA0002170834160000061
(8) Ordering of the organization order of the individual items in the main list of individual items: in order from ST: taking ST as a single item of the 'single item' immediately before; taking the sorted single item as a single item of an immediately previous single item; … …, respectively; until FIN; starting from FIN, the following are in sequence: taking FIN as a single item of the 'single item' after the FIN is closed; taking the sorted single items as the single items of the next single items; … …, respectively; until ST;
note: decomposing the sub items and establishing a main single item list; calculating or determining or estimating main parameters of each single item; determining the single item immediately before and/or after each single item; determining an organization mode between each single item and the single items immediately before and/or after; determining or estimating the organizational method between each individual item and the immediately preceding and/or immediately following individual items, etc., may be performed across.
To this end, one of the project levels, organization management and goal control planning, is accomplished as shown in the following table:
Figure RE-GDA0002170834160000062
wherein:
A. positive type list item:
aT=mT=bT=DT=T;σT 2=0;
B. positive fixed lap joint time interval:
a.LTa=LTm=LTb=DLT=LT,σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi,σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj,σjLT 2=0;
d.LTi'a=LTi'm=LTi'b=Di'LT=LTi',σi'LT 2=0。
and organizing the target construction period of the management and target control plan of each project of the project secondary level as the construction period of the corresponding project in the primary management and target control plan.
One of three levels of decomposition, a method for establishing an organization management and target control plan:
(1) according to the requirements of organization management and target control, carrying out the decomposition of the single project in any order, and decomposing the single project into a series of works; and a main work schedule is established according to any sequence;
(2) calculating or determining or estimating the main parameters of each main job in any order;
(3) determining the work immediately before and/or after each work in the main work list according to any sequence;
(4) determining an organization mode (overlapping relation) between each work and the work before and/or after the work in any sequence;
(5) determining or estimating the organization method (lap time interval) of the determined organization mode (lap relation) according to any sequence;
(6) performing a translation of organizational logical relationships between jobs, as determined by project organizational management and the objective control planner: the work before the work B is the work A, and the work after the work A is converted into the work B; or the work immediately after the work A is the work B, and the work immediately before the work A is converted into the work B is the work A;
(7) organizing logical relationship arrangement
Figure RE-GDA0002170834160000063
Figure RE-GDA0002170834160000071
(9) Ordering of work organization order in the Main work List: in order from ST: taking ST as the work of 'work' immediately before; taking the sequenced work as the work of the immediately preceding work; … …, respectively; until FIN; starting from FIN, the following are in sequence: taking FIN as the work of 'working' after tightening; taking the sequenced work as the work of the work after the sequencing; … …, respectively; until ST;
note: the decomposition of the single item and the establishment of a main work list; calculation or determination or estimation of the main parameters of each job; determining the work immediately before and/or after each work; determining an organization mode between each work and the work before and/or after the work; determining or estimating the organization method between each task and the immediately preceding and/or immediately following task, etc., may be performed across tasks.
To this end, one of the project three levels of organizational management and target control planning is accomplished as shown in the following table:
wherein:
A. and (3) performing positive setting work:
at=mt=bt=Dt=t;σt 2=0;
B. positive fixed lap joint time interval:
a.LTa=LTm=LTb=DLT=LT,σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi,σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj,σjLT 2=0;
d.LTi'a=LTi'm=LTi'b=Di'LT=LTi',σi'LT 2=0。
and (4) organizing the target construction period of the management and target control plan of each single project in the project three-level, wherein the target construction period is used as the construction period of the corresponding single project in the second-level organization management and target control plan.
In the project organization management and target control multi-level plan system, the time parameter calculation method of each level and each organization management and target control plan is as follows:
(1) time of earliest possible start of "work
(2) Time of earliest possible end of "work
(3) Interval between "work
(4) Maneuver (local) time differences of "work": FFi=min(Lagi-j);
(5) Total time difference for "work": TFi=min(TFj+Lagi-j);
(6) Time at which "work" must start at the latest: LS (least squares)i=ESi+TFi
(7) Time at which "work" must be ended at the latest: LF (Low frequency)i=EFi+TFi
In the project organization management and target control multi-level plan system, the method for calculating the estimated variance of each level and each organization management and target control plan is as follows:
in the project organization management and target control plan system, after time parameters of each level, each organization management and target control plan are calculated, the influence of the deviation on the implementation process of the next work is estimated according to the completion time of each main work, and the deviation sigma is carried out2After the adjustment of (2), the calculation of the estimated variance thereof is performed.
For discontinuously completed work (namely discontinuous work), the adjustment of the estimated deviation of the time for completing the work is carried out;
the method for adjusting the time deviation of the completion of each item of 'main work' estimation 'work' comprises the following steps:
Figure RE-GDA0002170834160000091
note:
(1)*σi 2for adjusted sigmai 2
(2)σi 2Variance, σ, of estimated completion time deviation for "primary job" ii 2=[(bit-ait)÷6]2Wherein:
1)bit-a pessimistic (longest) value of estimated completion time for "primary work" i;
2)ait-an optimistic (shortest) value of estimated completion time for "primary job" i;
(3)Dit-is a weighted average of the estimated completion times of the "main jobs" i: dit=(ait+4mit+bit) 6, wherein:
1)mit-the most probable (time) value of estimated completion time for "primary job" i;
(4)Dit' -limit of estimated completion time for "primary job" i.
By normal distribution of parameters
Figure RE-GDA0002170834160000092
When lambda isiP (D) is more than or equal to 3.5it') approximately equal to 100%, therefore
Figure RE-GDA0002170834160000093
The estimated deviation of the "work" completion time, the effect on the "work" immediately after, is to consider the actual lap time span (EF)i-ESj) The influence of (1), namely the influence of the adjustment on the work after the tightening according to the actual lap joint time interval;
the variance is estimated by the actual overlap time between the main 'working' and the influence value upsilon of the 'working' after fastening2 j(LT)The calculation method of (a) is shown in the following table:
in the project organization management plan, each item of 'work' organization arrangement (lap time interval) estimation variance ((υ 2 j(LT)Taking the maximum of the following calculation results)
The estimated variance of "work" in tissue management and target control plans, the impact on the "work" immediately after, taking into account the interval time (ES) between "workj-EFi) The influence factors of (a) are as follows:
various 'main work' accumulated estimation 'work' completion time deviation value variance upsilon2 j(t)Is calculated by
Note:
(1)EFi' As the ' main job ' i, the time which can be completed at the latest due to the influence of the estimated ' job ' completion time deviation is determined by the normal distribution parameter
Figure RE-GDA0002170834160000103
Figure RE-GDA0002170834160000104
λiP is more than or equal to 3.5(iEF’)≈100%,
Therefore, it is not only easy to use
Figure RE-GDA0002170834160000105
(2) In the project organization management and target control plan, the variance of the time deviation of the completion of each 'main work' estimation 'work' is composed of two parts: i.e. upsilon2 j(t)(excluding*σj 2) And*σj 2;υ2 j(t)also comprising two parts, i.e. v2 i(t)And*σi 2the effect on j "work". Upsilon is2 j(t)(excluding*σj 2) -an estimated variance for the j job start time; upsilon is2 i(t)(excluding*σi 2) -estimated variance for i job start time.
The invention calculates ES by the table one and the table two of the immediate organization relation in the project organization management and target control schedulei、EFi、υi 2(ii) a Calculating the Lag according to the first table and the third table of the organization relationship after tighteningi-jAnd determining FFiThen calculating TFi、LSi、LFi
The estimated variance of the three-level single project organization management and target control planning time limit is used as the corresponding two-level project organization management and target control
The estimated variance of the starting time of each project in the primary organization management and target control plan is the estimated variance of the starting time of the corresponding secondary project organization management and target control plan; similarly, in the second-level project organization management and target control plan, the estimation variance of the starting time of each single project is the estimation variance of the starting time of the corresponding third-level project organization management and target control plan.
The resource requirement of the unit time of the single project is equal to the sum of the resource requirements of the organization management and the target control plan of the single project divided by the construction period of the single project; similarly, the resource requirement per time unit of project is equal to the sum of the resource requirements of project organization management and target control plan divided by the project time limit of project.
Drawings
FIG. 1 is a diagram: the project or task is decomposed step by step, and the organizational management and target control plan is respectively made at each level, so as to establish a project organizational management and target control multi-level plan system.

Claims (9)

1. A method for establishing a reverse control multi-level planning system by a tabular mode project of a planning method is characterized by comprising the following steps of: the complete scheme for performing project organization management and target control is realized by fully applying a computer technology to perform step-by-step decomposition of various projects or tasks, respectively making organization management and target control plans at all levels, reversely establishing a project organization management and target control multi-level plan system by step-by-step construction period control, and performing the project organization management and the target control, and is realized by the following steps:
the following explains the specific method of the present invention by taking the three-level decomposition of the project or task by adopting the step-by-step project division, the single project division and the specific work as an example:
establishing a project organization management and target control multi-level plan system by making various levels, organization management and target control plans through the following steps and methods:
(1) first-level decomposition, namely making a first-level organization management and target control plan of the project:
(1-1) decomposing the project or task into a series of sub-projects in any sequence according to the requirements of organization management and target control, and establishing a main sub-project list in any sequence;
(1-2) switching the construction period of the organization management and target control plan of each project into any sequence to be used as the construction period of each project; dividing the total resource requirement of the organization management and target control plan of the sub-project by the project period of the sub-project to be used as the main resource quantity required by unit time of the sub-project;
(1-3) determining the organization logic relationship among the sub-projects in any order according to the process logic relationship among the sub-projects and the requirements of organization management and target control, and carrying out the conversion of the organization logic relationship among the sub-projects;
(1-4) determining the overlapping relation among the sub-projects in any sequence according to the process logic relation among the sub-projects, the organization and management requirements and the economic, scientific, reasonable and feasible principle;
(1-5) determining or estimating lap joint time distances among the sub-projects in any sequence according to organization and management requirements and the economic, scientific, reasonable and feasible principle;
(1-6) performing project organization sequence ordering in the step (6) to form a first-level organization management and target control schedule integrating calculation of an immediately-before organization logic relationship, an immediately-after organization logic relationship and a time parameter;
(1-7) performing primary organization management and target control plan time parameter calculation, namely finishing the formulation of the primary organization management and the target control plan;
(2) and (3) secondary decomposition, namely respectively making a secondary organization management and target control plan of the project:
the decomposition of the sub-items is also performed separately, taking the decomposition of one sub-item as an example:
(2-1) decomposing the sub-items into a series of single items in any order according to the requirements of organization management and target control, and establishing a main single item list in any order;
(2-2) transferring the construction period of the organization management and target control plan of each single project to be used as the construction period of the single project in any sequence; dividing the total resource requirement of the organization management and target control plan of the single project by the construction period of the single project to serve as the main resource requirement of the unit time of the single project;
(2-3) determining the organization logic relationship among the single projects in any order according to the process logic relationship among the single projects and the requirements of organization management and target control, and carrying out the conversion of the organization logic relationship among the single projects;
(2-4) determining the lapping relation among the single projects in any sequence according to the process logic relation among the single projects, the organization and management requirements and the economic, scientific, reasonable and feasible principle;
(2-5) determining or estimating the lap joint time distance between the single projects in any sequence according to the organization and management requirements and the economic, scientific, reasonable and feasible principle;
(2-6) performing single item organization sequence ordering to form one of a two-level organization management and target control schedule table which integrates calculation of an immediately-before organization logic relationship, an immediately-after organization logic relationship and a time parameter;
(2-7) performing secondary organization management and target control plan time parameter calculation, namely finishing the formulation of one of the secondary organization management and the target control plan;
(3) and (3) three-level decomposition, wherein the decomposition of each single item is also carried out respectively, and the decomposition of one single item is taken as an example:
(3-1) decomposing a single project into a series of specific works in any sequence according to the requirements of organization management and target control, and establishing a main work list in any sequence;
(3-2) determining or estimating the time required by each work and the main resource amount required by unit time in any sequence according to the economic, scientific, reasonable and feasible principle in the step (2);
(3-3) determining the organization logic relationship between the works in any order according to the process logic relationship between the works and the requirements of organization management and target control, and carrying out the conversion of the organization logic relationship between the works;
(3-4) determining the lapping relation between the works in any sequence according to the process logic relation between the works, the organization and management requirement and the economic, scientific, reasonable and feasible principle;
(3-5) determining or estimating the lap time interval between works in any sequence according to the organization and management requirements and the economic, scientific, reasonable and feasible principle;
(3-6) sequencing the work organization sequence, so as to form an organization management and target control schedule which integrates the calculation of an immediately-before organization logic relationship, an immediately-after organization logic relationship and a time parameter;
(3-7) calculating the time parameters and the estimated variances of the organization management and target control plan in step (7), and then calculating the estimated variances of the organization management and the target control plan of each secondary project by taking the variances of each stage of the construction period of each organization management and target control plan of each stage as the estimated variances of the construction period of each single project; taking the variances of all levels of the organization management and the target control plan construction period of each project as the estimated variances of the construction period of each project, and calculating the estimated variances of the first-level organization management and the target control plan; namely, the project or task organization management and the establishment of the target control multi-level plan are completed.
2. The method according to claim 1, wherein the various types of projects organize a multi-level planning system by:
(1) the items or tasks, the sub-items and the single items are classified into positive type, non-positive type and mixed type according to the types of the sub-items, the single items and the specific work which are decomposed step by step of the items or the tasks;
(2) according to the types of the lap joint time distances among the sub-projects, the single projects and the specific works which are decomposed by the projects or tasks, the project or task, the sub-project and the single project are organized into a positive type, a non-positive type and a mixed type;
(3) various projects organize multiple levels of plan systems, various organizational management and target control plans, including:
1) positive type projects, sub-projects and single projects, and adopts an organization management and target control plan formulated by a positive type organization method;
2) positive type projects, sub-projects and single projects, and adopts a non-positive type organization method to make an organization management and target control plan;
3) affirming the type project, the sub-project and the single project, and adopting a mixed type organization method to make an organization management and target control plan;
4) non-positive projects, sub-projects and single projects, and adopts positive organization methods to make organization management and target control plans;
5) the system comprises non-positive projects, sub-projects and single projects, and an organization management and target control plan made by adopting a non-positive organization method;
6) the organization management and target control plan is made by adopting a mixed stereotype organization method for non-positive projects, sub-projects and single projects;
7) mixed projects, sub-projects and single projects, and adopts an organization management and target control plan formulated by a positive organization method;
8) mixed projects, sub-projects and single projects, and an organization management and target control plan formulated by adopting a non-affirmative organization method;
9) mixed projects, sub-projects and single projects, and an organization management and target control plan made by adopting a mixed organization method.
3. The overall planning method table-mode project reverse control multi-level planning system establishment method according to claim 1, wherein the steps (1-3), (2-3) and (3-3): determining the organization logic relationship among the sub-projects (single project and work), and performing the organization logic relationship conversion among the sub-projects (single project and work), wherein the method comprises the following three methods:
(1) determining an organization logic relationship before and after the sub-projects (single project and work) are converted into an organization logic relationship after and before the sub-projects (single project and work);
(2) determining the organization logic relationship after the sub-projects (single projects and works) are organized, and converting the organization logic relationship into the organization logic relationship before the sub-projects (single projects and works) are organized;
(3) determining the organization logic relationship before or (and) after the sub-projects (single projects and works), and converting the organization logic relationship before the sub-projects (single projects and works) into the organization logic relationship after the sub-projects (single projects and works); and organizing the logical relationship between the sub-projects (single project and work) after the sub-projects are organized, and converting the logical relationship into the logical relationship between the sub-projects (single project and work) before the sub-projects are organized.
4. The overall planning method table-mode project reverse control multi-level planning system establishment method according to claim 1, wherein the steps (1-4), (2-4) and (3-4): determining the lapping relation between the sub-projects (single project and work), according to the process logic relation between the sub-projects (single project and work), according to the organization management requirement and the principle of economy, science, reasonability and feasibility, except that according to the process logic relation requirement and the lapping relation between the sub-projects (single project and work), one of STS, FTF, STF, STS and FTF, STS and STF, FTS and STF is adopted, and the lapping relation between other sub-projects (single project and work) is FTS.
5. The overall planning method table-mode project reverse control multi-level planning system establishment method according to claim 1, wherein the steps (1-5), (2-5) and (3-5): determining or estimating the lap time interval between the sub-projects (single project and work), estimating the lap time interval by using a three-point estimation method for the non-positive lap time interval, and calculating the estimation deviation of the lap time interval.
6. The overall planning method table-mode project reverse control multi-level planning system establishment method according to claim 1, wherein the steps (1-6), (2-6) and (3-6): the method for organizing and sequencing the projects (single project and work) comprises the following steps:
(1) the ordering method for organizing the logical relationship immediately before the project (single project and work) comprises the following steps: 1) sub-projects (single project, work) with ST as the "work" immediately before; 2) taking the sorted sub-projects (single project and work) as the sub-projects (single project and work) of the previous sub-projects (single project and work); … …, respectively; until FIN;
(2) the ordering method for organizing the logical relationship after the sub-projects (single project and work) comprises the following steps: 1) sub-projects (single project, work) with FIN as the next work; 2) taking the sorted sub-projects (single project and work) as the sub-projects (single project and work) of the next sub-project (single project and work); … …, respectively; up to ST.
7. The method for establishing the overall planning table-mode project reverse control multi-stage planning system according to claim 1, wherein the time parameter calculation in the steps (1-7), (2-7) and (3-7); the calculation was performed in the following order:
(1) three levels of organization management and target control plans:
1) computing ES with project organization management and target control plans expressed with immediately prior organizational logical relationshipsi、EFi、υi 2
2) Computing lags for project organization management and target control plans expressed by closely organized logical relationshipsi-jAfter that, FF is determinediThen calculating TFi、LSiAnd LFi
(2) And taking the estimated variances of the construction period and the construction period of each single project in the three-level organization management and target control plan as the estimated variances of the construction period and the construction period of each single project in the two-level organization management and target control plan:
1) computing ES with project organization management and target control plans expressed with immediately prior organizational logical relationshipsi、EFi、υi 2
2) Computing lags for project organization management and target control plans expressed by closely organized logical relationshipsi-jAfter that, FF is determinediThen calculating TFi、LSiAnd LFi
(3) And taking the estimated variance of the construction period and the construction period of the organization management and target control plan of each secondary project as the estimated variance of the construction period and the construction period of each project in the primary organization management and target control plan:
1) computing ES with project organization management and target control plans expressed with immediately prior organizational logical relationshipsi、EFi、υi 2
2) Computing lags for project organization management and target control plans expressed by closely organized logical relationshipsi-jAfter that, FF is determinediThen calculating TFi、LSiAnd LFi
8. The method for establishing the multi-level planning system for various project organizations in the integrated planning table mode according to claim 1, wherein the steps (1-7), (2-7) and (3-7): an estimated variance calculation comprising:
(1) adjusting the estimation deviation of the non-affirmation type project (single project, work) completion time and the estimation deviation of the non-affirmation type project (single project, work) completion time which are carried out discontinuously;
(2) the estimated deviation of the non-positive type lap time interval;
(3) interval ESj between sub-projects (single project, work)-EFiFactors, and the like.
9. The method for establishing the overall planning table-mode project reverse control multi-stage planning system according to claim 1, wherein the steps (1-7), (2-7) and (3-7) are to estimate variance calculation:
(1) ES in project in primary organization management and target control planiThe estimated variance of (1) is the estimated variance of the starting time of project organization management and target control plan in the secondary organization management and target control plan;
(2) single item management at two levels of organizationAnd ES in the target control planiThe estimated variance of the target control plan is the estimated variance of the starting time of the single-project organization management and the target control plan in the three-level organization management and the target control plan;
(3) in the three-level organization management and target control plan, the estimation variance of the completion time of the organization management and target control plan of a single project is the estimation variance of the completion time of the single project in the two-level organization management and target control plan;
(4) in the secondary organization management and target control plan, the estimation variance of the completion time of the organization management and target control plan of each project is the estimation variance of the completion time of each project in the primary organization management and target control plan.
CN201910231706.1A 2019-03-26 2019-03-26 Method for establishing overall-planning-method table-mode project reverse control multi-level plan system Pending CN110689313A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910231706.1A CN110689313A (en) 2019-03-26 2019-03-26 Method for establishing overall-planning-method table-mode project reverse control multi-level plan system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910231706.1A CN110689313A (en) 2019-03-26 2019-03-26 Method for establishing overall-planning-method table-mode project reverse control multi-level plan system

Publications (1)

Publication Number Publication Date
CN110689313A true CN110689313A (en) 2020-01-14

Family

ID=69107548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910231706.1A Pending CN110689313A (en) 2019-03-26 2019-03-26 Method for establishing overall-planning-method table-mode project reverse control multi-level plan system

Country Status (1)

Country Link
CN (1) CN110689313A (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴开平: "《替代、且显著领先于具有国际先进水平的网络计划技术的统筹法—JQ、JH、(JQ-JH)》", 《"企业创新与知识管理成果征集及评选活动"优秀成果论文集》 *

Similar Documents

Publication Publication Date Title
CN103839114A (en) Timing sequence plan automatic making system for steelmaking workshop
CN109189094A (en) It is a kind of to have man-machine and multiple no-manned plane composite formation resource regulating method more
CN109345135B (en) Method for determining key process in flow construction progress control
CN110334830B (en) Cost optimization application method for qualitative construction period of various project organization plans by overall planning method
CN110689313A (en) Method for establishing overall-planning-method table-mode project reverse control multi-level plan system
CN110334831B (en) Qualitative construction period optimization method for multi-level plan system of step-by-step control project organization
CN110689314A (en) Method for establishing forward and backward step-by-step control multi-stage planning system for overall planning project
CN110689215A (en) Method for establishing defect inspection and modification by overall planning method project organization multi-level plan system
CN110334834B (en) Method for optimizing qualitative construction period cost of various project organization plans by overall planning method
CN110633832A (en) Optimization method for relatively-minimum technical route of project organization plan resources by overall planning method
CN110633825A (en) Resource-limited optimization scheme comparison method for project combination construction period restriction by overall planning method
CN109034551A (en) Equilibrium of stock method for construction plan establishment
CN110659764A (en) Overall planning method project combination construction period restriction resource and construction period dynamic review method
CN110633823A (en) Method for optimizing minimum organization plan resources in any project combination by overall planning method
CN103679404A (en) Multi-project resource balancing and optimizing method
CN110633834A (en) Optimization method for multi-level organization plan resource relative minimum technical route by overall planning method
CN110659765A (en) Optimization method for restricting resource limitation in any project combination construction period by overall planning method
CN110717613A (en) Overall planning method multi-level organization plan resource limited optimization scheme comparison method
CN110633833A (en) Overall planning method project organization multi-level plan resource limited technology route optimization method
CN110633885A (en) Optimization method for one-level resource minimum of any project combination multi-level plan by overall planning method
CN110717612A (en) Method for comparing multi-level organization plan resource minimum optimization schemes by overall planning method
CN110633822A (en) Optimization method for minimum and relative minimum of arbitrary project combination resources by overall planning method
CN110717614A (en) Resource combination optimization method for various project organization multi-level plan system by overall planning method
CN110633828A (en) Route optimization method for multi-level plan resource balancing technology of overall planning project organization
CN110633835A (en) Optimization method for multi-level plan resource minimum technology route of project organization by overall planning method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 250014 11-2-501, No.7 Zhuanshan West Road, Lixia District, Jinan City, Shandong Province

Applicant after: Jinan senkun Technology Co.,Ltd.

Address before: 250014 11-2-501, No.7 Zhuanshan West Road, Lixia District, Jinan City, Shandong Province

Applicant before: Jinan Senkun Enterprise Management Consulting Co.,Ltd.

CB02 Change of applicant information