CN110677976A - Cavity structure for picking up beam phase signals based on inductance probe - Google Patents
Cavity structure for picking up beam phase signals based on inductance probe Download PDFInfo
- Publication number
- CN110677976A CN110677976A CN201911123385.XA CN201911123385A CN110677976A CN 110677976 A CN110677976 A CN 110677976A CN 201911123385 A CN201911123385 A CN 201911123385A CN 110677976 A CN110677976 A CN 110677976A
- Authority
- CN
- China
- Prior art keywords
- cavity
- outer conductor
- inner conductor
- conductor
- picking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000000523 sample Substances 0.000 title claims abstract description 38
- 239000004020 conductor Substances 0.000 claims abstract description 148
- 230000001939 inductive effect Effects 0.000 claims description 10
- 230000007613 environmental effect Effects 0.000 abstract description 5
- 230000000903 blocking effect Effects 0.000 abstract description 4
- 238000011160 research Methods 0.000 description 6
- 230000005684 electric field Effects 0.000 description 5
- 238000000605 extraction Methods 0.000 description 4
- 230000006698 induction Effects 0.000 description 4
- 238000013461 design Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 239000002245 particle Substances 0.000 description 3
- 238000004088 simulation Methods 0.000 description 3
- 230000005672 electromagnetic field Effects 0.000 description 2
- 230000005284 excitation Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 230000006641 stabilisation Effects 0.000 description 2
- 238000011105 stabilization Methods 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000013401 experimental design Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000001959 radiotherapy Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 238000005070 sampling Methods 0.000 description 1
Images
Classifications
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05H—PLASMA TECHNIQUE; PRODUCTION OF ACCELERATED ELECTRICALLY-CHARGED PARTICLES OR OF NEUTRONS; PRODUCTION OR ACCELERATION OF NEUTRAL MOLECULAR OR ATOMIC BEAMS
- H05H13/00—Magnetic resonance accelerators; Cyclotrons
- H05H13/005—Cyclotrons
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05H—PLASMA TECHNIQUE; PRODUCTION OF ACCELERATED ELECTRICALLY-CHARGED PARTICLES OR OF NEUTRONS; PRODUCTION OR ACCELERATION OF NEUTRAL MOLECULAR OR ATOMIC BEAMS
- H05H7/00—Details of devices of the types covered by groups H05H9/00, H05H11/00, H05H13/00
- H05H7/001—Arrangements for beam delivery or irradiation
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05H—PLASMA TECHNIQUE; PRODUCTION OF ACCELERATED ELECTRICALLY-CHARGED PARTICLES OR OF NEUTRONS; PRODUCTION OR ACCELERATION OF NEUTRAL MOLECULAR OR ATOMIC BEAMS
- H05H7/00—Details of devices of the types covered by groups H05H9/00, H05H11/00, H05H13/00
- H05H7/001—Arrangements for beam delivery or irradiation
- H05H2007/008—Arrangements for beam delivery or irradiation for measuring beam parameters
Landscapes
- Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Plasma & Fusion (AREA)
- Spectroscopy & Molecular Physics (AREA)
- Particle Accelerators (AREA)
Abstract
The invention relates to a cavity structure for picking up beam phase signals based on an inductance probe, which comprises a cylindrical cavity outer conductor and a cylindrical cavity inner conductor, wherein a left end cover and a right end cover of the cavity outer conductor are communicated with a beam flow conveying pipeline, the left end and the right end of the cavity inner conductor correspond to the beam flow conveying pipeline communicated with two ends of the cavity outer conductor respectively, the right end surface of the cavity inner conductor is contacted with the right end cover of the cavity outer conductor to form a short-circuit end, a horizontal space is formed between the left end surface of the cavity inner conductor and the left end cover of the cavity outer conductor to form an open-circuit end, and the inductance probe extends into an annular cavity between the cavity outer conductor and the cavity inner conductor and is connected with the right end cover of the cavity. The non-blocking cavity structure can pick up the phase information of the beam in real time, greatly reduce the environmental dose around the accelerator equipment, overcome the problem of limited space of the accelerator equipment and improve the signal-to-noise ratio of the beam phase signal pick-up device.
Description
Technical Field
The invention relates to the technical field of cyclotrons, in particular to a cavity structure for picking up beam phase signals based on an inductance probe.
Background
In the application of the cyclotron for proton treatment, the requirements of the treatment process on the intensity, the stability and the extraction efficiency of beams are higher. In the actual operation process of the cyclotron, factors such as heat loss of a high-frequency system, external temperature change, instability of a power supply and the like can affect the magnetic field strength of the cyclotron, cause detuning of the magnetic field, and affect the stability and extraction efficiency of the beam current, which are adverse factors for cyclotron equipment, startup operators for daily maintenance and patients needing radiotherapy.
Therefore, in order to study beam phase stabilization control of the isochronous accelerator, an auto-tuning beam phase stabilization system was realized. It is necessary to develop and design a cavity structure for picking up a beam phase signal, and to consider the problems of reducing the environmental dose around the accelerator device, and the limited space of the accelerator device.
Disclosure of Invention
The invention aims to provide a cavity structure for picking up beam phase signals based on an inductance probe, the non-blocked cavity structure can pick up the phase information of beams in real time, greatly reduce the environmental dose around accelerator equipment, overcome the problem of limited space of the accelerator equipment, and improve the signal-to-noise ratio of a beam phase signal picking device.
The above object of the present invention is achieved by the following technical solutions:
a cavity structure based on an inductance probe for picking up beam phase signals comprises a cylindrical cavity outer conductor and a cylindrical cavity inner conductor, wherein a left end cover and a right end cover of the cavity outer conductor are communicated with a beam transport pipeline, the left end and the right end of the cavity inner conductor correspond to the beam transport pipeline communicated with the two ends of the cavity outer conductor respectively, the right end face of the cavity inner conductor is in contact with the right end cover of the cavity outer conductor to form a short-circuit end, a horizontal distance is reserved between the left end face of the cavity inner conductor and the left end cover of the cavity outer conductor to form an open-circuit end, and an inductance type induction probe extends into an annular cavity between the cavity outer conductor and the cavity inner conductor and is connected with the right end cover of the cavity outer conductor.
By adopting the technical scheme, the cavity structure for picking up the beam phase signal is arranged on a beam transport pipeline of the cyclotron, the specific size parameters of the cavity outer conductor and the cavity inner conductor of the cavity structure adopt the optimized design, when the beam passes through the cavity structure, the resonance of the cavity structure can be excited, the inductive induction probe at the short-circuit end of the cavity structure can pick up the beam phase signal, the beam phase signal is subjected to phase discrimination with the reference phase signal of the high-frequency accelerating electric field, the exciting current of a main magnet power supply is adjusted through the output result curve of the phase discrimination, so that the magnetic field intensity of the cyclotron is stabilized, the condition that the extracted beam particles are accelerated every time when passing through the accelerating electric field is ensured, and the stability and the extraction efficiency of the beam extracted by the cyclotron are improved. The cavity structure for picking up the beam phase signals is used for picking up high-precision beam phase signals, belongs to research equipment of a beam phase stability control system, and provides necessary conditions for picking up beams with different energy.
The invention is further configured to: the beam transport pipeline and the inner conductor of the cavity have the same diameter, and the axial leads of the outer conductor of the cavity, the inner conductor of the cavity and the beam transport pipeline are coincided.
By adopting the technical scheme, the diameters of the inner conductor of the cavity structure and the beam transport pipeline are kept consistent, so that when the extracted beam passes through the cavity structure for picking up the beam phase signal, the resonance of the cavity of the beam phase probe can be excited, the beam phase signal is picked up, and conditions are provided for the research of beam phase stability control of the isochronous accelerator.
The invention is further configured to: the diameters of the beam transport pipeline and the conductor in the cavity are 190-210 mm, and the wall thickness is 4-6 mm.
By adopting the technical scheme, the diameters of the conductor in the cavity and the beam transportation pipeline are kept consistent, so that when the extracted beam passes through the cavity structure for picking up the beam phase signal, the resonance of the cavity of the beam phase probe can be excited, and the beam phase signal is picked up.
The invention is further configured to: the diameters of the beam transport pipeline and the conductor in the cavity are both 200mm, and the wall thickness is both 5 mm.
By adopting the technical scheme, the diameters of the beam transport pipeline and the inner conductor of the cavity are limited to 200mm, and the wall thickness is 5mm, so that when the extracted beam passes through the cavity structure for picking up the beam phase signal, the resonance of the cavity structure can be excited, and the beam phase signal can be picked up.
The invention is further configured to: the vertical distance between the cavity outer conductor and the cavity inner conductor is 46-48 mm, the horizontal distance between the left end cover of the cavity outer conductor and the left end face of the cavity inner conductor is 8.5-9.5 mm, the length of the cavity outer conductor is 260-264 mm, and the length of the cavity inner conductor is 250-254 mm.
By adopting the technical scheme, the vertical distance, the horizontal distance and the length of the outer conductor of the cavity structure for picking up the beam phase signal influence the eigen frequency of the cavity structure, the larger the vertical distance between the outer conductor of the cavity and the inner conductor of the cavity is, the smaller the eigen frequency of the cavity structure for picking up the beam phase signal is, the larger the horizontal distance between the outer conductor of the cavity and the inner conductor of the cavity is, namely, the larger the capacitance at the open end is, the larger the eigen frequency of the cavity structure for picking up the beam phase signal is, the longer the lengths of the outer conductor of the cavity and the inner conductor of the cavity are, and the smaller the eigen frequency of the cavity structure for picking up the beam phase signal.
The invention is further configured to: the vertical distance between the cavity outer conductor and the cavity inner conductor is 47mm, the horizontal distance between the left end cover of the cavity outer conductor and the left end face of the cavity inner conductor is 10mm, the length of the cavity outer conductor is 262mm, and the length of the cavity inner conductor is 252 mm.
By adopting the technical scheme, the cavity structure for picking up the beam phase signals limits the size parameters, and the eigenfrequency of the cavity structure for picking up the beam phase signals is ensured to be 142.4 MHz.
The invention is further configured to: the eigenfrequency of the cavity structure is 142.4 MHz.
By adopting the technical scheme, the eigenfrequency of the cavity structure for picking up the beam phase signals is 142.4MHz, the non-blocking cavity structure can realize real-time beam phase measurement, the environmental dose level around the accelerator equipment is ensured, and the cavity structure is particularly suitable for the research of the beam phase stability control of the isochronous accelerator.
The invention is further configured to: the side wall of the cavity outer conductor is communicated with a probe guide pipe close to the right end cover of the cavity outer conductor, and the inductive sensing probe is positioned in the probe guide pipe.
By adopting the technical scheme, the inductive induction probe at the short-circuit end of the cavity structure can pick up a beam phase signal, phase discrimination is carried out on the beam phase signal and a reference phase signal of a high-frequency accelerating electric field, and the exciting current of the main magnet power supply is adjusted through an output result curve of the phase discrimination.
In conclusion, the beneficial technical effects of the invention are as follows:
1. the cavity structure for picking up the beam phase signal is arranged on a beam transport pipeline of the cyclotron, the specific size parameters of the cavity outer conductor and the cavity inner conductor of the cavity structure adopt the optimal design, when the beam passes through the cavity structure, the resonance of the cavity structure can be excited, the beam phase signal can be picked up by an inductive induction probe at the short-circuit end of the cavity structure, the beam phase signal and the reference phase signal of the high-frequency accelerating electric field are subjected to phase discrimination, the exciting current of a main magnet power supply is regulated through the output result curve of the phase discrimination, the magnetic field intensity of the cyclotron is stabilized, the condition that the extracted beam particles are accelerated every time when passing through the accelerating electric field is ensured, and the stability and the extraction efficiency of the beam extracted by the cyclotron are improved. The cavity structure for picking up the beam phase signals is used for picking up high-precision beam phase signals, belongs to research equipment of a beam phase stability control system, and provides necessary conditions for picking up beams with different energy.
2. The diameters of the inner conductor of the cavity structure and the beam transport pipeline are kept consistent, so that when the extracted beam passes through the cavity structure for picking up the beam phase signal, the resonance of the cavity of the beam phase probe can be excited, the beam phase signal is picked up, and conditions are provided for the research of the beam phase stability control of the isochronous accelerator; compared with the traditional picking mode, the cavity structure has small space structure, the signal-to-noise ratio is greatly improved, the non-blocking cavity structure can realize real-time measurement of beam phase signals, the environmental dose level around accelerator equipment is ensured, and the cavity structure is particularly suitable for research on beam phase stability control of an isochronous accelerator.
3. According to the invention, the larger the vertical distance between the outer conductor of the cavity and the inner conductor of the cavity is, the smaller the eigenfrequency of the cavity structure for picking up the beam phase signal is, the larger the horizontal distance between the outer conductor of the cavity and the inner conductor of the cavity is, namely, the larger the capacitance at the open end is, the larger the eigenfrequency of the cavity structure for picking up the beam phase signal is, the longer the lengths of the outer conductor of the cavity and the inner conductor of the cavity are, and the smaller the eigenfrequency of the cavity structure for picking up the beam phase signal is. The vertical distance, the horizontal distance and the length of the conductor outside the cavity between the conductor outside the cavity and the conductor inside the cavity have influence on the eigenfrequency of the cavity structure, and the eigenfrequency of the cavity structure for picking up the beam phase signals is 142.4 MHz.
Drawings
Fig. 1 is a schematic diagram of the structure of the chamber of the present invention.
Fig. 2 is an electromagnetic field profile of the cavity structure of the present invention.
Fig. 3 is a magnetic field distribution diagram of the cavity structure of the present invention.
Fig. 4 is a diagram showing the pickup end voltage of the cavity structure for picking up the beam phase signal when the 230MeV and 300nA beam lines are used as excitation.
The reference signs are: 1. a conductor within the cavity; 11. a left end face; 12. a right end face; 2. a cavity outer conductor; 21. a left end cap; 22. a right end cap; 23. a probe catheter; 3. a beam transport pipeline; 4. an inductive sensing probe; 5. an annular cavity; 6. opening a circuit end; 7. and (4) short-circuit ends.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, the invention discloses a cavity structure for picking up beam phase signals based on an inductance probe, comprising a cylindrical cavity outer conductor 2 and a cylindrical cavity inner conductor 1, wherein a left end cover 21 and a right end cover 22 of the cavity outer conductor 2 are both communicated with a beam transport pipeline 3, the left end and the right end of the cavity inner conductor 1 are respectively corresponding to the beam transport pipelines 3 communicated with two ends of the cavity outer conductor 2, a right end face 12 of the cavity inner conductor 1 is contacted with the right end cover 22 of the cavity outer conductor 2 to form a short circuit end 7, a horizontal distance is arranged between a left end face 11 of the cavity inner conductor 1 and the left end cover 21 of the cavity outer conductor 2 to form an open circuit end 6, the inductance probe 4 extends into an annular cavity 5 between the cavity outer conductor 2 and the cavity inner conductor 1 and is connected with the right end cover 22 of the cavity outer conductor 2, the side wall of the cavity outer conductor 2 is communicated with a probe conduit 23 close to, an inductive sensing probe 4 is located within the probe guide 23;
the eigenfrequency of the cavity structure is 142.4MHz, the diameter of the beam transport pipeline 3 is the same as that of the conductor 1 in the cavity, and the axial leads of the outer conductor 2 of the cavity, the conductor 1 in the cavity and the beam transport pipeline 3 are coincident; the diameters of the beam transport pipeline 3 and the conductor 1 in the cavity are both 200mm, and the wall thickness is both 5 mm; the vertical distance between the cavity outer conductor 2 and the cavity inner conductor 1 is 47mm, the horizontal distance between the left end cover 21 of the cavity outer conductor 2 and the left end face 11 of the cavity inner conductor 1 is 10mm, the length of the cavity outer conductor 2 is 262mm, and the length of the cavity inner conductor 1 is 252 mm.
The experimental design steps of the specific dimensional parameters of the cavity structure in this embodiment are as follows:
a) as shown in fig. 1, a model of a cavity structure for picking up beam phase signals is established through CST software, the diameter of a beam transport pipeline of an accelerator and a conductor 1 in the cavity are kept consistent, the diameter is 200mm, the wall thickness reaches 5mm, and the vertical distance, the horizontal distance and the length of the outer conductor 2 between the outer conductor 2 of the cavity and the conductor 1 in the cavity have influence on the eigenfrequency of the cavity structure;
b) the influence of a certain specific variable on the eigenfrequency of the cavity structure is researched by CST software by adopting a control variable method;
c) fixing the horizontal distance between the cavity outer conductor 2 and the cavity inner conductor 1 and the length of the cavity outer conductor 2, changing the vertical distance between the cavity outer conductor 2 and the cavity inner conductor 1, and obtaining the experimental conclusion: the larger the vertical distance between the cavity outer conductor 2 and the cavity inner conductor 1 is, the smaller the eigenfrequency of the cavity structure for picking up the beam phase signal is;
d) the horizontal distance between the cavity outer conductor 2 of the cavity structure open end 6 and the cavity inner conductor 1 determines the capacitance of the open end 6, the length of the cavity inner conductor 1 is fixed, and then the change of the eigenfrequency of the cavity structure is observed by changing the length of the cavity outer conductor 2, and the obtained experimental conclusion is as follows: the larger the horizontal distance between the cavity outer conductor 2 and the cavity inner conductor 1 is, namely the larger the capacitance of the open end 6 is, the larger the eigenfrequency of the cavity structure for picking up the beam phase signal is;
e) the capacitance of the open end 6 of the cavity structure is fixed, the length of the outer conductor 2 of the cavity and the length of the inner conductor 1 of the cavity are changed, and the obtained experimental conclusion is as follows: the longer the lengths of the cavity outer conductor 2 and the cavity inner conductor 1 are, the smaller the eigenfrequency of the cavity structure for picking up the beam phase signal is;
f) through simulation experiments of the influence of the three variables on the eigenfrequency of the cavity structure, the size close to the eigenfrequency of 142.4MHz is preferably selected, namely the vertical distance between the cavity outer conductor 2 and the cavity inner conductor 1 is 47mm, the horizontal distance between the left end cover 21 of the cavity outer conductor 2 and the left end face 11 of the cavity inner conductor 1 is 10mm, the length of the cavity outer conductor 2 is 262mm, the length of the cavity inner conductor 1 is 252mm, and the electromagnetic field distribution of the cavity structure for picking up beam phase signals after simulation is shown in FIG. 2;
g) in a Particle Wakefield mode of CST software, a beam line of 230MeV and 300nA is set as excitation, and the velocity of the beam is calculated by the following formula:wherein W is the beam energy in eV,beta is calculated to be about 0.7, and assuming that the length of the beam line is 30mm, the charge amount is calculated to be about 7.95E-10C. The sampling end of the inductive sensing probe 4 is connected to a 500hm load, the voltage value of the inductive sensing probe is observed at the load end, and the simulation result is shown in fig. 4. As can be seen from fig. 4, the CST voltage of the cavity structure for picking up the beam phase signal can be simulated by using the CST software, which illustrates that the non-blocking cavity structure can be used for measuring the beam phase signal.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.
Claims (8)
1. The utility model provides a cavity structure based on inductance probe picks up beam phase signal, includes cavity outer conductor (2), cavity inner conductor (1) of barrel form, its characterized in that: the left end cover (21) and the right end cover (22) of the cavity outer conductor (2) are communicated with the beam flow conveying pipeline (3), the left end and the right end of the cavity inner conductor (1) correspond to the beam flow conveying pipeline (3) communicated with the two ends of the cavity outer conductor (2) respectively, a short circuit end (7) is formed by the contact between the right end face (12) of the cavity inner conductor (1) and the right end cover (22) of the cavity outer conductor (2), a horizontal distance is formed between the left end face (11) of the cavity inner conductor (1) and the left end cover (21) of the cavity outer conductor (2) to form an open circuit end (6), and the inductive sensing probe (4) stretches into an annular cavity (5) between the cavity outer conductor (2) and the cavity inner conductor (1) and is connected with the right end cover (22) of the cavity outer conductor (2).
2. The cavity structure for picking up the beam phase signal based on the inductance probe according to claim 1, wherein: the beam transport pipeline (3) and the cavity inner conductor (1) are the same in diameter, and the cavity outer conductor (2) and the cavity inner conductor (1) are coincident with the axis of the beam transport pipeline (3).
3. The cavity structure for picking up the beam phase signal based on the inductance probe as claimed in claim 2, wherein: the diameters of the beam transport pipeline (3) and the inner conductor (1) of the cavity are 190-210 mm, and the wall thickness is 4-6 mm.
4. The cavity structure for picking up the beam phase signal based on the inductance probe as claimed in claim 3, wherein: the diameters of the beam transport pipeline (3) and the conductor (1) in the cavity are both 200mm, and the wall thickness is both 5 mm.
5. The cavity structure for picking up the beam phase signal based on the inductance probe according to claim 1, wherein: the vertical distance between the cavity outer conductor (2) and the cavity inner conductor (1) is 46-48 mm, the horizontal distance between the left end cover (21) of the cavity outer conductor (2) and the left end face (11) of the cavity inner conductor (1) is 8.5-9.5 mm, the length of the cavity outer conductor (2) is 260-264 mm, and the length of the cavity inner conductor (1) is 250-254 mm.
6. The cavity structure for picking up the beam phase signal based on the inductance probe as claimed in claim 5, wherein: the vertical distance between the cavity outer conductor (2) and the cavity inner conductor (1) is 47mm, the horizontal distance between the left end cover (21) of the cavity outer conductor (2) and the left end face (11) of the cavity inner conductor (1) is 10mm, the length of the cavity outer conductor (2) is 262mm, and the length of the cavity inner conductor (1) is 252 mm.
7. The cavity structure for picking up the beam phase signal based on the inductance probe as claimed in claims 5 to 6, wherein: the eigenfrequency of the cavity structure is 142.4 MHz.
8. The cavity structure for picking up the beam phase signal based on the inductance probe according to the claims 1 to 6, characterized in that: the side wall of the cavity outer conductor (2) is communicated with a probe guide pipe (23) close to a right end cover (22), and the inductive sensing probe (4) is positioned in the probe guide pipe (23).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911123385.XA CN110677976B (en) | 2019-11-16 | 2019-11-16 | Cavity structure for picking up beam phase signals based on inductance probe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911123385.XA CN110677976B (en) | 2019-11-16 | 2019-11-16 | Cavity structure for picking up beam phase signals based on inductance probe |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110677976A true CN110677976A (en) | 2020-01-10 |
CN110677976B CN110677976B (en) | 2024-10-18 |
Family
ID=69087505
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911123385.XA Active CN110677976B (en) | 2019-11-16 | 2019-11-16 | Cavity structure for picking up beam phase signals based on inductance probe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110677976B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111896993A (en) * | 2020-07-23 | 2020-11-06 | 苏州核道核能技术有限公司 | Ion ray angular distribution ionization chamber detector |
CN112240993A (en) * | 2020-10-14 | 2021-01-19 | 中国原子能科学研究院 | Evaluation system and method for compact cyclotron magnetic field stability measurement |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090140671A1 (en) * | 2007-11-30 | 2009-06-04 | O'neal Iii Charles D | Matching a resonant frequency of a resonant cavity to a frequency of an input voltage |
US8358186B1 (en) * | 2010-05-14 | 2013-01-22 | Christos Tsironis | Impedance tuners with resonant probes |
US20130113503A1 (en) * | 2009-11-20 | 2013-05-09 | Marcel Ruf | Method and device for measuring the location of a particle beam present in packets in a linear accelerator |
CN106211539A (en) * | 2016-07-29 | 2016-12-07 | 中国原子能科学研究院 | A kind of cyclotron digital stabilising arrangement of ejected beam phase place and method thereof |
CN109413833A (en) * | 2018-12-10 | 2019-03-01 | 合肥中科离子医学技术装备有限公司 | A kind of system and method for realizing that the self feed back of accelerator line is adjusted based on phase probe |
CN109893777A (en) * | 2019-02-26 | 2019-06-18 | 中国原子能科学研究院 | Phase detector and proton beam phase stabilization device comprising the phase detector |
CN209448962U (en) * | 2018-12-10 | 2019-09-27 | 合肥中科离子医学技术装备有限公司 | A kind of system for realizing that the self feed back of accelerator line is adjusted based on phase probe |
CN211656498U (en) * | 2019-11-16 | 2020-10-09 | 中国原子能科学研究院 | Cavity structure for picking up beam phase signals based on inductance probe |
-
2019
- 2019-11-16 CN CN201911123385.XA patent/CN110677976B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090140671A1 (en) * | 2007-11-30 | 2009-06-04 | O'neal Iii Charles D | Matching a resonant frequency of a resonant cavity to a frequency of an input voltage |
US20130113503A1 (en) * | 2009-11-20 | 2013-05-09 | Marcel Ruf | Method and device for measuring the location of a particle beam present in packets in a linear accelerator |
US8358186B1 (en) * | 2010-05-14 | 2013-01-22 | Christos Tsironis | Impedance tuners with resonant probes |
CN106211539A (en) * | 2016-07-29 | 2016-12-07 | 中国原子能科学研究院 | A kind of cyclotron digital stabilising arrangement of ejected beam phase place and method thereof |
CN109413833A (en) * | 2018-12-10 | 2019-03-01 | 合肥中科离子医学技术装备有限公司 | A kind of system and method for realizing that the self feed back of accelerator line is adjusted based on phase probe |
CN209448962U (en) * | 2018-12-10 | 2019-09-27 | 合肥中科离子医学技术装备有限公司 | A kind of system for realizing that the self feed back of accelerator line is adjusted based on phase probe |
CN109893777A (en) * | 2019-02-26 | 2019-06-18 | 中国原子能科学研究院 | Phase detector and proton beam phase stabilization device comprising the phase detector |
CN211656498U (en) * | 2019-11-16 | 2020-10-09 | 中国原子能科学研究院 | Cavity structure for picking up beam phase signals based on inductance probe |
Non-Patent Citations (3)
Title |
---|
郑建华, 赵晓岩, 王延谋, 董金梅, 尹炎: "基于容性感应探针测量方法的研究", 核电子学与探测技术, no. 06, 20 November 2004 (2004-11-20) * |
郑建华;刘巍;王义芳;王延谋;马维年;尹炎;宋海宏;: "高灵敏度等时性回旋加速器束流相位测量系统", 高能物理与核物理, no. 03, 15 March 2007 (2007-03-15) * |
郭娟娟;殷治国;纪彬;宋国芳;: "质子治疗回旋加速器束流相位探测器的仿真设计", 中国原子能科学研究院年报, no. 00, 31 August 2017 (2017-08-31) * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111896993A (en) * | 2020-07-23 | 2020-11-06 | 苏州核道核能技术有限公司 | Ion ray angular distribution ionization chamber detector |
CN112240993A (en) * | 2020-10-14 | 2021-01-19 | 中国原子能科学研究院 | Evaluation system and method for compact cyclotron magnetic field stability measurement |
CN112240993B (en) * | 2020-10-14 | 2021-07-20 | 中国原子能科学研究院 | Evaluation system and method for compact cyclotron magnetic field stability measurement |
Also Published As
Publication number | Publication date |
---|---|
CN110677976B (en) | 2024-10-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110677976A (en) | Cavity structure for picking up beam phase signals based on inductance probe | |
WO2012020476A1 (en) | Impedance matching device, and control method | |
CN211656498U (en) | Cavity structure for picking up beam phase signals based on inductance probe | |
Zhang et al. | Detection of metal obstacles in wireless charging system of electric vehicle | |
EP1118254A2 (en) | Method of reducing axial beam focusing | |
CN103996591B (en) | Microwave ion source and starting method thereof | |
Zhang et al. | Preliminary study of a niobium quarter-wave prototype cavity for a heavy-ion superconducting linac | |
US8169167B2 (en) | Methods for diagnosing and automatically controlling the operation of a particle accelerator | |
Marti et al. | Commissioning of the coupled cyclotron system at NSCL | |
CN208903782U (en) | A kind of transformer case with quick temperature-reducing function | |
Li et al. | Improved particle swarm optimization algorithm for adaptive frequency-tracking control in wireless power transfer systems | |
CN207166844U (en) | Radio-frequency acceleration cavity | |
CN109271718A (en) | A kind of design method for the spiral inductance being wound on tubulose magnetic core | |
CN108521709A (en) | The method that high stream forceful electric power accelerates is realized based on tokamak device | |
CN207731730U (en) | Induction type cable pendency degree online monitoring method system | |
Mulhayatiah et al. | Analysis effect of winding on radiation-electromagnetic field on the tesla coil | |
CN110039383A (en) | A kind of radio-frequency ion source | |
Li et al. | Influence of Coil Radius, Distance and Working Frequency on Efficiency in Two-Coil Magnetically Coupled Resonant Wireless Power Transmission System | |
CN208969226U (en) | A kind of MRI scan transmitter | |
CN202975154U (en) | Electromagnetic coupling resonance coil parameter measuring system | |
Zhang et al. | Comprehensive test stand for high-intensity cyclotron development | |
Tian-Jue et al. | Design and construction progress of BRIF | |
WO2009097536A1 (en) | Methods for diagnosing and automatically controlling the operation of a particle accelerator | |
Ferrand et al. | Final design of the fully equipped HWR cavities for SARAF | |
CN109860010A (en) | A method of applying internal field and inhibits electron beam radial oscillation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant |